Professional Documents
Culture Documents
Glossary For PMP Exam
Glossary For PMP Exam
AC
(actual cost) The costs incurred to accomplish the work to date.
activity
Any element of project work that requires action to produce a deliverable.
activity dependency
A logical relationship that exists between two project activities.
activity sequencing
A planning method that involves identifying and documenting interactivity dependencies among
project activities for the purpose of creating the project schedule.
actual cost
(AC) The total amount of costs incurred while accomplishing work performed. It may be computed in
terms of the total costs that were incurred during completion of a schedule activity or during the
completion of a work breakdown structure component.
administrative closure
The project management process of verifying and documenting project results to formalize phase or
project completion.
aggregated cost
A method of cost budgeting that requires the adding together of the estimated activity costs to
establish an estimate for a work package, then for each work package, and on an iterative basis until
there is a single estimated cost for the whole WBS. This also produces a baseline for measuring a
project's cost performance.
alternatives identification
The act of generating different plans for achieving project goals.
analogous estimating
A top-down estimating technique using durations of previous similar activities to estimate future
durations.
anticipatory breach
An unavoidable indication that the other party will not be able to produce the performance
necessary to fulfill an agreed-upon contract.
assumptions
The statements that must be taken to be true in order to begin project planning.
audit
see “inspection.”
average
The number that typifies the data in a set. It is calculated by adding the values of a group of numbers
and dividing that total by the number of objects included.
____________________________________________
baseline
An approved time phased plan for a project, work breakdown structure component, work package,
or schedule activity, plus or minus approved scope, cost, schedule, and technical changes.
BCWP
see “earned value.”
BCWS
see “planned value.”
benchmarking
A method of addressing the evaluation of a group’s business or project practices in comparison to
those of other groups. It is used to identify best practices in order to meet or exceed them.
bottom-up estimating
A method of estimating costs that involves estimating the cost for each work package in the WBS;
the estimates are then rolled up (aggregated) for progressively higher levels within the WBS to
compile the total project cost.
breach of contract
Failure to meet some or all of the obligations of a contract. It may result in damages paid to the
injured party, litigation, or other ramifications.
budget at completion
(BAC) Total planned value at completion.
business requirements
The pressing organizational needs that drive decision makers to sponsor projects and to prioritize
competing projects.
business risk
The inherent risk in any business endeavor which carries the potential for either profit or loss.
____________________________________________
capital budgeting
A decision-making process used to evaluate fixed asset purchases.
causes of variance
In a process or item, these are the sources or reasons for deviations from the expected standard.
checklist
A job aid that prompts employees to perform activities according to a consistent quality standard.
co-location
The placing of most or all key team members in the same physical location to make communication
easier and enhance team performance and team spirit.
communications requirements
The project stakeholders' documented communications needs.
communications technology
The technologies used for communications planning.
completion contract
A type of contract that is completed when the seller delivers the product to the buyer and the buyer
accepts the product.
conditional branch
Activities that will be implemented only under specific conditions.
configuration management
A controlling tool for applying technical and administrative direction and surveillance to manage
changes that affect the function or characteristics of the product or service being produced.
conflict management
The application of one or more strategies for dealing with disagreements, struggles, and
compatibility issues that may be detrimental to team performance.
constraints
The factors that limit the way that the project can be approached.
contingency allowances
Additional funds that are sometimes built into cost estimates to allow for unanticipated events, or
known unknowns.
contingency plans
A risk-response strategy developed in advance; it is meant to be used in the event that identified
risks become reality.
contingency reserve
A predetermined amount of additional time, money, or resources set aside in advance to be used to
further the project's objectives in the event that unknown risks or accepted known risks become
reality.
contract
A mutually binding agreement that details the obligations of the buyer and seller.
contract closure
The project management process of ensuring that contractual obligations have been met on both
sides and resolving any outstanding issues.
contract negotiation
The process of bargaining to come to a mutual agreement regarding the terms and conditions of a
contract.
control chart
A graph used to analyze and communicate the variability of a process or project activity over time.
cost baseline
A time-phased budget that will monitor and measure cost performance throughout the project life
cycle.
cost budgeting
The process of allocating the overall cost estimates to individual activities or work packages across
the project life cycle.
cost control
The project management process of monitoring cost performance and controlling changes to the
cost baseline.
cost estimating
The process of projecting the cost of resources that are necessary for the completion of your project.
cost of capital
Average after-tax interest rate at which the project investment would be financed. Also called the
hurdle rate.
cost of quality
The total cost of efforts to achieve an acceptable level of quality in the project’s product or service.
cost-benefit analysis
A comparison of the predicted costs versus the predicted benefits of a project.
cost-reimbursable contract
This contract provides sellers a refund of the expenses incurred while providing a service, plus a fee
representing seller profit.
CPI
(cost performance index) A measurement of cost performance used to determine whether the
project is over or under budget. The formula for calculating CPI is CPI = EV/AC.
crashing
A schedule compression method that analyzes cost and schedule trade-offs to determine how to
obtain the greatest amount of schedule compression for the least incremental cost.
creep
A change in scope that will adversely affect cost, time, or quality and that has not been processed
appropriately through the scope change control process.
criteria profiling
A decision model used to evaluate and score alternatives on each criterion.
critical activities
The schedule activities that are on the critical path.
critical path
The network path that has the longest total duration in an activity.
CV
(cost variance) The difference between the earned value and the actual cost incurred to complete
that work. The formula for calculating CV is CV = EV - AC.
____________________________________________
decision tree
A type of screening system decision model that uses a branch diagram to choose among two
different alternatives. Incorporates probabilities of occurrence and the costs or rewards of each
decision.
deliverable
The end result of work; it can be a product, service, or outcome that responds to a business need or
fits the sponsor's requirements.
Delphi technique
A group technique that extracts and summarizes anonymous group input to choose among various
alternatives. Often used to arrive at an estimate or forecast.
Design of Experiments
(DOE) A technique to systematically identify varying levels of independent variables.
____________________________________________
EAC
(estimate at completion) A forecast of what it will cost to complete all of the work required to
produce the product or provide the service of a project.
earned value
A composite measurement of both actual cost and time performance in relation to scheduled or
planned cost and time performance; it was formerly called the budgeted cost of work performed
(BCWP).
effort
The number of person-hours or person-days required for completion of an activity.
elapsed time
The actual calendar time required from start to finish of an activity. May or may not be the same as
duration.
EMV analysis
(expected monetary value analysis) A method of calculating the average outcome when the future is
uncertain.
estimate to complete
(ETC) A forecasting technique, based on a new estimate that is more accurate and comprehensive; it
is independent and non-calculated for all outstanding work.
evaluation criteria
The standards used to rate or score proposals, quotes, or bids.
EVM
(earned value management) A methodology that measures project progress by comparing actual
schedule and cost performance against planned performance as laid out in the schedule and cost
baselines.
expert judgement
Knowledge provided based upon expertise in a knowledge area, an application area, or an industry.
express warranty
A warranty in which the pre-determined standard for quality or performance is specified, either in a
formal warranty or in the manufacturer's description of the product.
____________________________________________
fast tracking
The process of compressing total project duration by performing some activities concurrently that
were originally scheduled sequentially.
feasibility analysis
An analysis that provides technical and operational data to management to help determine if a
project will work for the organization or if an alternative should be pursued.
float
The amount of time an activity can be delayed from its ES without delaying the project finish date; in
some organizations, it is also known as “free float.” In arrow diagramming methods, float is known
as “slack.”
flowchart
A diagram that shows the relationships of various elements in a system or process.
free float
The amount of time an activity can be delayed without delaying the ES of any activity that
immediately follows it.
fundamental breach
A breach of contract so serious that it negates the very foundation of the contract.
funding limit reconciliation
A method of adjusting spending, scheduling, and resource allocation in order to bring expenditures
into alignment with budgetary constraints.
____________________________________________
____________________________________________
hammock activity
See “summary activity.”
hurdle rate
Average after-tax interest rate at which the project investment would be financed. Also called cost
of capital.
____________________________________________
immaterial breach
A breach of contract in which there is no resulting damage to the injured party; since there are no
damages, the injured party is not entitled to receive compensation.
impact scale
The assignment of a value that reflects the magnitude of the impact of a risk event on project
objectives.
implied warranty
A warranty in which the pre-determined standard for quality or performance exists but is not
specified; it takes effect if the buyer depends on the seller's expertise when making a purchasing
decision.
information distribution
The process of getting the right information to the right people at the right time.
information-gathering technique
Any method or approach used to collect data that will assist the project team in identifying risks to
the project.
inputs
Information or data that project managers draw on, create, or gather during the course of the
project; they guide and inform the work that will be done to achieve project goals.
inspection
An official examination of work results to verify requirements are met; it involves measuring,
examining, and verifying results to be sure work and deliverables meet requirements and
acceptance criteria. It may also be referred to as “reviews,” “product reviews,” “audits,” or
“walkthroughs.”
insurable risk
A risk that has only the potential for loss and no potential for profit or gain. An insurable risk is one
for which insurance may be purchased to reduce or offset the possible loss.
interdependent
Projects that are inextricably linked because they rely on each other's success in order to meet a
shared business or stakeholder need.
IRR
(Internal Rate of Return) The discount rate that makes the NPV (net present value) of the future cash
return equal to the initial capital investment.
____________________________________________
____________________________________________
knowledge area
An identified area of project management described in terms of its component processes and
defined by its knowledge requirements.
____________________________________________
L
lease, rent, or buy decision
A business analysis that determines the most cost-effective way to procure the necessary equipment
for a project.
lessons learned
Documented historical information and knowledge base about past projects.
levels of uncertainty
A way of analyzing the risks of a project based on how much is known about them.
loop
Activity sequences that must be revisited or repeated.
____________________________________________
make-or-buy analysis
A technique used to determine whether it would be more cost-effective to produce a product or
service in-house or to procure it from an outside vendor.
material breach
A serious breach of contract that prevents the injured party from benefiting from the contract; the
injured party can claim damages, but is no longer obligated to fulfill any contract commitments.
mean
The sum of the events divided by the number of occurrences.
median
The number that separates the higher half of a probability distribution from the lower half. It is not
the same as the average, although the two terms are often confused.
____________________________________________
organization chart
A visual representation of the project’s organizational structure.
organizational structure
The compositional makeup of an organization that dictates how the various groups and individuals
within the organization interrelate.
outputs
The end results and deliverables achieved during project-management processes.
outsourcing
Moving beyond the organization to secure services and expertise from an outside source on a
contract or short-term basis.
____________________________________________
parametric estimating
A method of activity duration estimating in which some durations can be estimated by multiplying a
productivity rate by the quantities to be performed for a specific work category.
parametric estimating
A technique used to predict total project costs by using the project's characteristics and historical
information in a mathematical model.
Pareto diagram
A bar chart or histogram that illustrates the causes of problems and their relative severity. Used for
prioritizing efforts to solve problems.
performance reporting
The project management process of gathering and communicating information regarding the current
status of a project as well as projections for progress over time.
plan contracting
Process of defining and documenting the products, services, and results requirements while
identifying potential procurement sources.
planned value
(PV) The budgeted portion of the approved cost estimate to be spent during a particular time period
to complete the scheduled project work; also known as the budgeted cost for work scheduled
(BCWS).
PMIS
(Project Management Information System) An automated or manual system used by a project team
to gather, analyze, communicate, and store project information.
portfolio management
The grouping and oversight of a collection of projects in alignment with the strategic goals of the
organization.
precedence relationship
The logical relationship between two activities that describes the sequence in which the activities
should be carried out.
predecessor activity
In sequencing two activities, the activity that must take place prior to the other.
probability distribution
The scattering of values assigned to likelihood in a sample population.
probability scale
The assignment of value to the likelihood of a risk occurring.
process
A sequence of activities designed to bring about a specific result in response to a business need.
procurement audit
A formal evaluation of both the supplier's performance of the contract, as well as the effectiveness
of the procurement process itself.
procurement documents
Documents submitted to prospective sellers or service providers to solicit their proposals for the
work needed.
product analysis
An evaluation of the project's end product and what it will take to create this product.
product review
see “inspection.”
program
Ongoing work managed in a series of related projects that may or may not have a definite endpoint.
program management
The centralized, coordinated process of managing all of an organization's projects in accordance with
the business's strategic objectives.
progressive elaboration
A process of development in which additional layers of detail are defined over the course of a
project.
project
A temporary endeavor with a clearly defined beginning and end, resulting in a unique product or
service using progressive elaboration (developed in steps and continued in increments).
project charter
A document that provides a clear, concise description of the business needs that the project is
intended to address.
project deliverables
Any tangible, measurable result or outcome required to complete a project or portion of a project.
project objectives
The measurable success criteria for the project.
project phase
A group of related project activities that results in the completion of a major deliverable.
project resource
Any useful material object or person necessary to complete project work.
project schedule
The project team's plan for starting and finishing activities on specific dates and in a certain
sequence. The schedule also specifies planned dates for meeting project milestones.
project selection
The act of choosing a project from among competing proposals.
project stakeholder
A person who has a business interest in the outcome of a project or who is actively involved in its
work.
PV
see “planned value.”
____________________________________________
Q-sorting
A decision model using groups of people to rate the relative priority of a number of alternatives.
quality
The totality of features and characteristics of a product or services that bear on its ability to satisfy
stated or implied needs.
quality assurance
A method of evaluating overall project performance through planned, systematic activities; it
creates confidence that the project will employ the appropriate processes and satisfy standards for
quality.
quality audit
An independent evaluation, inspection, or review of a project's quality assurance system.
quality control
The project management process of monitoring project work results to determine if they comply
with relevant quality standards, and identifying ways to eliminate causes of unacceptable
performance.
quality planning
The process of putting plans into place to ensure that a project will satisfy its stated objectives or
business needs.
____________________________________________
RAM
see “Responsibility Assignment Matrix.”
regulations
Compliance-mandatory characteristics for specific products, services, or processes.
relative authority
The project manager’s authority relative to the functional manager’s authority over the project and
the project team.
reserve analysis
A method of activity duration estimating in which extra time is added to duration estimates that can
serve as a buffer as recognition of scheduled risk (contingency reserves).
resource cost rates
The per unit cost of each resource.
review
see “inspection.”
risk
An uncertain event that has either a positive or negative effect on the project. Its primary
components are a measure of probability that a risk will occur and the impact of the risk on a
project.
risk acceptance
Any decision not to change the project plan to deal with a risk.
risk analysis
The evaluation of the probability and impact of the occurrence of a risk.
risk register
A document that identifies risks, potential risk responses, and their triggers, or warning signs.
risk tolerance
The level of risk a project manager or key stakeholder is willing to take when the investment is
compared to the potential payoff.
____________________________________________
schedule activity
A discrete scheduled component of work performed during the course of a project; it has an
estimated duration, cost, and resource requirements.
schedule baselines
The management-approved version of the project schedule; it is drawn from the schedule network
analysis and includes baseline start and finish dates.
schedule compression
The act of shortening the project schedule without affecting the project scope.
schedule control
The project management process of monitoring schedule performance and controlling changes to
the schedule baseline.
scope control
The project management process of determining whether changes to project scope are needed and
monitoring and managing the changes when they occur.
scope creep
Allowing the scope to expand inappropriately (without securing customer approval or without
addressing the effect that such expansion will have on the project's cost, time, and resources). (See
also “creep.”)
scope planning
The formulation of the project scope management plan.
scope statement
Defines the project and what it does and does not need to accomplish.
scope verification
The project management process of obtaining formal acceptance of the project scope by the
stakeholders (sponsor, client, customer, and so on).
sensitivity analysis
A method of assessing the relative impact of changing a variable in the project to gain insight into
possible outcomes of one or more potential courses of action.
simulation
A technique that uses computer models and estimates of risk to translate uncertainties at a detailed
level into their potential impact on project objectives at the total project level.
slack
See “float.”
specifications
Descriptions of the work to be done or the service or product to be provided; they define the
requirements that must be met in exacting detail.
SPI
(schedule performance index) The ratio of work performed to work scheduled. The formula for SPI is
SPI = EV/PV.
stakeholder analysis
The formal process of identifying all of the stakeholders and building coalitions at the onset of a
project by identifying their needs, objectives, goals, and issues.
stakeholder management
The process of controlling communications to adjust to the needs of the stakeholders.
standard deviation
This is the measure of the spread of the data, or the statistical dispersion of the values in your data
set.
standards
Non-mandatory guidelines or characteristics that have been approved by a recognized body of
experts such as the International Organization for Standards (ISO).
statement of work
(SOW) A narrative description of the resources, goods, or services that are being sought from
external sources to fulfill a project's requirements; it is distributed to potential sellers, who will use it
to evaluate their capability to perform this work or provide the services.
statistical sampling
A technique used to determine characteristics of an entire population based on actual measurement
of a representative sample of that population.
subprojects
The smaller, more manageable components of projects.
successor activity
In sequencing two activities, the activity that must take place after the other.
summary activity
A group of related activities that are reported as an aggregate activity.
SV
(schedule variance) The measured difference between the planned or scheduled completion of an
activity and the actual completion of that activity. The formula for calculating SV is EV – PV = SV.
____________________________________________
tailoring
The act of determining which processes are appropriate for any given project.
team development
The on-going effort to develop a cohesive team with good communication in order to enhance their
collective performance so that you increase the likelihood of meeting project objectives.
team-building activities
Specific functions or actions taken to help the team to develop into a mature, productive team.
term contract
A type of contract that engages the seller to deliver a set amount of service—measured in staff-
hours or a similar unit—over a set period of time.
three-point estimates
A method of activity duration estimating in which three types of estimates are incorporated into a
singular duration estimate scenario: most likely, optimistic, and pessimistic.
tolerances
The measurement values that determine if a product or service is acceptable or unacceptable.
top-down estimating
see “analogous estimating.”
total float
The total amount of time that an activity can be delayed without delaying the project finish date
when subtracting an activity's EF from its LF or its ES from its LS.
training
An activity in which team members acquire new or enhanced skills, knowledge, or attitudes.
____________________________________________
____________________________________________
variance
The sources or reasons for differences in a process or item.
virtual team
A team that is distributed across multiple locations. Some virtual teams have occasional physical
meetings, while others may never meet face-to-face.
____________________________________________
waiver
The giving up of a contract right, even inadvertently.
walkthrough
see “inspection.”
warranty
A promise, explicit or implied, that goods or services will meet a pre-determined standard. The
standard may cover reliability, fitness for use, safety, and so on.
warranty of merchantability
Implied warranties that require goods to be fit for ordinary usage.
WBS dictionary
An auxiliary document containing details about each element in the WBS; may contain information
such as code of accounts identification, milestones, contract information, cost, quality requirements,
time estimates, or resource information for measuring performance and completeness.
weighted factor
A decision model that applies a multiplier based on importance to each criterion, which is factored
into the scoring.
weighting system
A method for quantifying qualitative data to minimize the influence of personal bias on source
selection.
what-if scenario
An analysis method that allows you to plan for unexpected issues or problems that will interfere
with the schedule.
work package
The smallest, most granular deliverable that cannot be further subdivided.
work package
The planned work contained in the lowest-level component of the work breakdown structure.
____________________________________________
____________________________________________
____________________________________________
____________________________________________
MISC
360-degree feedback
The collection of performance data from several key sources, including peers, managers, and
subordinates.