"Claim Methodology ": Time Impact Analysis / Window Analysis
"Claim Methodology ": Time Impact Analysis / Window Analysis
“Claim Methodology “
April 2019
Page 1 of 10
2
CONTACTS
Tel +966-545026272
Mob +966-545026272
Email: New.Modern.Consulting.Engineering@outlook.com
Newmodernconsultingoffice@gmail.com
NMDCE.
Masr Centre
AHM.RATEB Street,Cairo, 6Th October
Page 2 of 10
3
A Time Impact Analysis is a method used to determine extent of impact from potential delay in
construction process. This schedule analysis method involves the insertion or addition of
activities indicating delays or changes into an updated schedule representing progress up to the
point when a delay event occurred to determine the impact of those delay activities.
Types of Delays
Delays can be categorized in two main areas:
• Excusable Delays
• Non-Excusable Delays
Excusable delays occur when the affected party is allowed to claim for a time extension,
compensation or both. Meanwhile, non-excusable delays are delays that the contractor or party
affected will need to bear the responsibility.
We have a simple project with the Planned schedule like this:
Page 3 of 10
4
1st month.
Page 4 of 10
5
2nd month.
We have no delay.
Page 5 of 10
6
3rd month.
We have 2 delays:
And those are concurrent delay. So 14 days charge to owner, and 7 day charge to contractor
Page 6 of 10
7
4th month.
We have 1 delay from Contractor in “Garage Walls” but it was not on the critical path. As long as the delay is within available
float there is no effect on the final completion date.
Page 7 of 10
8
5th month.
We have 1 delay (28 days) from Owner in Garage Doors but it only affect 7 days in the critical path. Other 21 days were absorbed
by available float.
Page 8 of 10
9
Last month.
Page 9 of 10
10
Page 10 of 10