Professional Documents
Culture Documents
QLDA - Chapter 13-Progress and Performance Measurement and Evaluation
QLDA - Chapter 13-Progress and Performance Measurement and Evaluation
CHAPTER 13:
PROGRESS AND PERFORMANCE
MEASUREMENT AND EVALUATION
1. Identify the four steps for controlling a project. 1. Structure of a Project Monitoring Information System
2. Utilize a tracking Gantt to monitor time performance. 2. The Project Control Process
1
13/1/2022
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 7 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 8
2
13/1/2022
4. DEVELOPMENT OF AN
3. MONITORING TIME PERFORMANCE
EARNED VALUE COST/SCHEDULE SYSTEM
4. DEVELOPMENT OF AN 4. DEVELOPMENT OF AN
EARNED VALUE COST/SCHEDULE SYSTEM EARNED VALUE COST/SCHEDULE SYSTEM
Key steps ensures that the cost/schedule system: Project Management Information System Overview
1. Define the work using a WBS (see Chapters 4 and 5):
Scope, Work packages, Deliverables, Organization units,
Resources, Budgets for each work package.
2. Develop work and resource schedule
Schedule resources to activities (see Chapter 8).
Time-phase work packages into a network.
3. Develop a time-phase budget using work packages
included in an activity. The cumulative values of these
budgets will become the baseline for the planned
budgeted cost of the work scheduled (PV).
4. At the work package level, collect the Actual Costs (AC)
for the work performed.
5. Compute the Schedule Variance (SV = EV − PV) and
Cost Variance (CV = EV − AC)
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 11 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 12
3
13/1/2022
4. DEVELOPMENT OF AN 4. DEVELOPMENT OF AN
EARNED VALUE COST/SCHEDULE SYSTEM EARNED VALUE COST/SCHEDULE SYSTEM
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 13 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 14
The project network early start times will serve as the basis for
assigning the baseline values.
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 15 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 16
4
13/1/2022
Digital Camera
Prototype Project
Baseline Budget
($320)
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 17 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 18
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 19 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 20
5
13/1/2022
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 21 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 22
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 23 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 24
6
13/1/2022
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 25 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 26
Digital Camera Project-Tracking Gantt Chart Project Rollup End Period 7 ($320)
Showing Status—Through Period 7
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 27 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 28
7
13/1/2022
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 29 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 30
1. Project Percent Complete Indexes 1. First method using EACre to represent revisions made
Percent Complete Index Budgeted costs: PCIB = EV/BAC
by experts and practitioners associated with the project.
Percent Complete Index actual Costs: PCIC = AC/EAC
2. Management Reserve index MRI: MRI = CV/MR EACre = AC + ETCre
3. Software for Project Cost/Schedule Systems
Schedule variance (EV − PV) by cost account and WBS and OBS
where
Cost variance (EV − AC) by cost account and WBS and OBS
EACre = revised estimated cost at completion
Indexes—total percent complete and performance index
Cumulative actual total cost to date (AC) AC = cumulative actual cost of work completed to date
Expected costs at completion (EAC)
Paid and unpaid commitments ETCre = revised estimated cost to complete remaining work
4. Additional Earned Value Rules
0/100 rule
50/50 rule
Percent complete with weighted monitoring gates
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 31 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 32
8
13/1/2022
BAC EV
TCPI
BAC AC
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 33 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 34
CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 35 CHAPTER 13: PROGRESS AND PERFORMANCE MEASUREMENT AND EVALUATION 36
9
13/1/2022
9. CHAPTER SUMMARY
10