Professional Documents
Culture Documents
Bridge Quality Circular
Bridge Quality Circular
19-Dec-2022
From
Er. Akshaya Kumar Pradhan
EIC-cum-Special Secretary to Govt.,
To
Sir,
In order to overcome such issues, much emphasis have been laid down on strict
adherence of the SOP and several letters / executive instructions have been issued in the
recent past, like -
RD-RW-MISC-0055-2022/1/2022
Chief Secretary, R.D. Department – Proper false work (Centering, Shuttering &
Staging work) in Bridge constructions.
Divisional Engineer while preparing the detailed estimate are including the
provision of cantilever wing wall and executing the same in the field on the plea that it is
provided in the GAD even if it may not be appropriate as per site condition. The
cantilever wing wall is appropriate when the existing bank height of the Nallah is well
above the HFL and the length of the bridge is sufficient enough such that the abutments
are placed very close to the high banks and the C.W.Ws. are anchoring into the high
banks above the HFL. In such situation, C.W.Ws. are to be considered as acceptable in
view of less expenditure involved and no individual foundation is required for such
structure.
In all other situations, use of C.W.W. may be discouraged and appropriate R.C.C.
wing wall to be proposed in the estimate justifying adequately with reference to water
spread limit at HFL of the stream at the proposed bridge location.
In order to address type-2 issue, the wearing coat of the bridge need to be cast
with utmost care ensuring use of water reducing agent i.e. plasticizer, super plasticizer
etc. and under strict supervision of the JE / SDO with low water to cement ratio. For
this, all the post and railing works are to be completed first followed by fixation of
suitable expansion joint beams (preferably single mould strip seal expansion beam
obtained from MoRTH empanelled manufacturers ). The 1.0 mtr panel on either side of
the expansion joint beam is to be provided with closely spaced 8mm dia- reinforcement
@ 75mm on both directions. In rest of the wearing coat, 150mm spacing is to be used.
For more guidance, Section 2702 of MoRTH, 5th Revision may be referred to.
RD-RW-MISC-0055-2022/1/2022
In order to address this type of issue, use of good quality drainage spout covered
with stainless steel grating to be ensured. Stainless steel square bar of 12mmX12mm
section may be used for fabrication of the top jally of the drainage spout arrangement.
The 100mm tabular G.I. pipe / corrosion resistant pipe may be fixed below the grating in
the deck slab such that another 100/150mm length is protrude beyond the bottom of the
slab to keep all discharge away from the deck structure. The entire unit of the drainage
spout must be fixed with profound professional skill and care so that not a drop of water
gets accumulated on the deck slab and all dirt, muds etc. get swept down through this
spout to the river and nallaha (Section 2705 of MoRTH may be referred to).
Sharp curve or steep gradient in the immediate approach road need to be avoided
invariably. As far as possible, the initial 15m straight approach on either side of the
bridge is to be ensured with carriage way width at par with the deck slab supplemented
with 1.5m shoulder on either side of the carriage way. The width of the carriage way
need to be merged with the design carriage way of the approach road beyond 15.0m in a
gradual manner. Similarly, if curve is essential and unavoidable in the immediate
approach road, it should be done with proper Geometric design with provision of extra
width and super elevation as per relevant IRC standard.
6. As large number of well foundation bridge are being adopted, bottom plugging of the
wells must be ensured using concreting through trimme pipe arrangement to ensure
quality of the bottom plug making the well water resistant to the maximum possible
extent.
7. Use of hessian cloth cover to the pier & abutment; arranging sprinkler between the
pair of T-Beam girders & between the individual box of twin box girder slab are to be
ensured for effective curing apart from establishing mandatory field lab with all sieve
sets, concrete cube mould, concrete beam mould, slump cone etc. to bring
professionalism and good practice in the field of bridge engineering.
Please note that these are some of the vital points to be practised which need
further expansion and innovation at field level to up keep the image of the Department at
respectable height.
RD-RW-MISC-0055-2022/1/2022
Yours Faithfully
EIC-cum-Special Secretary
CC to:
1. The EIC, Rural Works, Odisha, Bhubaneswar / all Chief Engineers, Rural Works
Organization for information and necessary action.
2. All CCEs (Civil), Rural Works for information and necessary action.
RD-RW-MISC-0055-2022/1/2022