Weekly Report Yih Quan Project
Weekly Report Yih Quan Project
00
Report No. : 41
OF
COPIES PT.YIH QUAN FOOTWEAR INDONESIA PT. WAHANACIPTA BANGUNWISMA PT. TAKENAKA INDONESIA
DELIVERED (Set)
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00
PROJECT VIEW C
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00
PHOTO PROGRESS D
Plan Photo
4
1
2 3
1 4
2 3
NEW FACTORY BUILDING WORK PHASE - 1 YIH QUAN FOOTWEAR INDONESIA S-CURVE PLAN R.01 (May 11 th,2023)
Month Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-23 Feb-23 Mar-24 Weight
NO WORK ITEM
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 (%)
100,0%
C General 0,00%
90,0%
1 Road Plan 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 6,15%
1 Workshop B1 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 14,07%
50,0%
2 Workshop B2 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 14,60%
2 WWTP 30,0%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2,21%
1 Office 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 6,30%
8 Subgate 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0,04%
100%
0,0%
0,0%
0,3%
0,7%
1,5%
2,3%
3,2%
4,1%
5,2%
6,5%
7,9%
9,4%
0,0%
Weekly Actual Progress
6,10%
7,35%
9,65%
37,2%
0,0%
0,0%
0,6%
1,8%
2,5%
3,0%
4,1%
Work Item Duration Start Date Finish Date Weight 2023 2024
Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
Workshop B1 13,339.9 m2 (Period 12 Months) 304 16/01/2023 15/11/2023
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
1
2
3
4
5
6
7
8
9
100%
Steel Structure Shopdrawing Approval 32 16/01/2023 16/02/2023 100,0%
0,00%
Steel Structure Fabrication & Delivery 90 17/02/2023 17/05/2023 0,00%
Structure Shopdrawing Approval 32 16/01/2023 16/02/2023 0,00% 90,0%
Finishing Shopdrawing Approval 175 17/02/2023 10/08/2023 0,00%
Pile Finish 0 31/01/2023 31/01/2023 0,00%
Foundation & Tie Beam Works 105 01/03/2023 14/06/2023 80,0%
17,44% ## ## ## ## ## ## ## ##
Concrete Slab 1st Floor (6.837 m2) 91 01/05/2023 31/07/2023 9,47% ## ## ## ## ## ## ##
Concrete Column 1st Floor (147 Pcs) 90 01/04/2023 30/06/2023 6,30% ## ## ## ## ##
70,0%
Beam & Slab 2nd Floor (6.837 m2) 91 14/04/2023 14/07/2023 18,48% ## ## ## ## ## ## ##
Concrete Column 2nd Floor (109 Pcs) 93 21/04/2023 23/07/2023 2,37% ## ## ## ##
Beam & Roof Slab (2.766 m2) 93 07/05/2023 08/08/2023 5,64% 60,0% ## ## ## ## ## ##
Concrete Column Roof (40 Pcs) 94 14/05/2023 16/08/2023 0,82% ## ## ## ##
Beam & Concrete Roof Slab (266 m2) 24 14/07/2023 07/08/2023 2,36% Plan 44.4%## ## ##
50,0%
Steel Structure (170 Ton) 31 07/07/2023 07/08/2023 9,60% ## ## ## ## ##
Roofing, Flashing & Gutter Works (3.838 m2) 38 07/08/2023 14/09/2023 4,13% ## ## ## ## ##
Downspout Works 29 01/09/2023 30/09/2023 0,84% 40,0% ## ## ## ##
Waterproofing & Cynder Concrete 31 21/07/2023 21/08/2023 2,44% Actual ## ##
ALC Wall & Plaster Works (23.016 m2) 99 14/06/2023 21/09/2023 44.3%
5,43% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
30,0%
Joinery Works 62 14/07/2023 14/09/2023 5,87% ## ## ## ## ## ## ## ## ## ##
Exposed Ceiling w/ Skim Coat Finish (1st & 2nd Floor) 92 14/06/2023 14/09/2023 1,54% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Floor Finishing (Concrete Polished & Ceramic Tile) 91 01/08/2023 31/10/2023 3,81% 20,0% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Toilet Works (1st & 2nd Floor) 92 14/07/2023 14/10/2023 0,31% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Elevator Works 68 07/08/2023 14/10/2023 1,16% ## ## ## ## ## ## ## ## ## ##
10,0%
Stair Works 108 14/06/2023 30/09/2023 0,91% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Painting Works 71 21/08/2023 31/10/2023 1,06% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Inspection 25 21/10/2023 15/11/2023 0,00% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
1,2% 1,2%
2,3% 1,2%
3,5% 1,2%
4,6% 1,2%
6,3% 1,6%
7,9% 1,6%
11,0% 3,1%
14,3% 3,2%
18,2% 3,9%
22,5% 4,3%
26,9% 4,4%
31,2% 4,4%
35,6% 4,4%
40,0% 4,4%
44,4% 4,4%
48,1% 3,8%
51,9% 3,8%
55,2% 3,3%
60,9% 5,7%
66,7% 5,7%
72,9% 6,2%
79,2% 6,3%
82,5% 3,3%
85,3% 2,9%
88,2% 2,8%
90,6% 2,4%
93,2% 2,6%
95,9% 2,6%
97,0% 1,2%
97,8% 0,8%
98,3% 0,5%
98,9% 0,5%
99,2% 0,4%
99,6% 0,4%
100,0% 0,4%
100,0% 0,0%
100,0% 0,0%
Weekly Progress Plan
Concrete Column
Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Progress
No. Item Qty Unit %
Last Week This Week accum.
Lean Concrete 6570 m2 6466 104 6570 100
1
Concrete 6570 m2 0 0 0 0
Progress
No. Item Qty Unit %
Last Week This Week accum.
Form work 6570 m2 4802,05 0 4802,05 73,091
1
Concrete 6570 m2 2052 181,8 2233,8 34
Concrete Column
Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Plan 42.1%
Actual 41,2%
Until Last Week this Week Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 4171 m¹ 4171,1 0 4171,1 100%
Tie Beam
Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
2
Lean Concrete 6570 m 5769,25 127,37 5896,62 90%
1
Concrete 6570 m2 0 0 0 0%
Concrete Column
Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Progress
No. Item Qty Unit %
Last Week This Week accum.
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
Des-22
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Office 5,701.5 m2 (Period 12 Months) 357 days 16-Jan-23 21-Jan-24
1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 31 days 16-Jan-23 16-Feb-23 100,0%
0,0%
Steel Structure Fabrication & Delivery 89 days 17-Feb-23 17-May-23 0,0%
Structure Shopdrawing Approval 31 days 16-Jan-23 16-Feb-23 0,0% 90,0%
6 LOCATION DATE
WORK PRORGESS OFFICE BUILDING YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
nd
PROGRESS OFFICE BUILDING - 2 FLOOR SLAB
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Forming 1670 m2 1669,5 0 1669,5 100,00%
Floor
2nd
1
Concrete 1670 m2 900 769,5 1669,5 100,00%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Colum
1
n
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Warehouse 5,588.6 m2 (Period 11 Months) 342 26-Jan-23 31-Dec-23
1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 29 26-Jan-23 24-Feb-23 0,0% 100,0%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete 2633 m2 1966,5 0 1966,5 74,70%
SLAB
Progress
No. Item Qty Unit %
Last Week This Week accum.
Rebar 42 Pcs 34 0 34 80,95%
CL
1
Concrete 42 Pcs 34 0 34 80,95%
Progress
No. Item Qty Unit %
Last Week This Week accum.
Forming 2633 m2 1080 270 1350 51,28%
SLAB
1
Concrete 2633 m2 0 0 0 0,00%
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
WWTP 3,073.3 m2 (Period 10 Months) 278 10-Feb-23 14-Nov-23
1
2
3
4
5
6
7
8
9
1,00
100,0%
Steel Structure Shopdrawing Approval 30 10-Feb-23 11-Mar-23 0,00%
Steel Structure Fabrication & Delivery 90 12-Mar-23 9-Jun-23 0,00% 90,0%
Actual
Structure Shopdrawing Approval 15 10-Feb-23 24-Feb-23 0,00% 76.5%
80,0%
Finishing Shopdrawing Approval 150 25-Feb-23 24-Jul-23 0,00%
Pile Finish 0 24-Feb-23 24-Feb-23 0,00% 70,0%
Plan
Open-Cut Works 23 25-Feb-23 19-Mar-23 12,68% ## ## ## ## 76.1%
Concrete Under Ground Slab 15 20-Mar-23 3-Apr-23 60,0%
15,56% ## ## ##
Concrete Column & Wall 30 4-Apr-23 3-May-23 17,26% ## ## ## ## ##
50,0%
Concrete Beam & Upper Slab 20 4-May-23 23-May-23 10,48% ## ## ## ##
Waterproofing 12 24-May-23 4-Jun-23 12,80% 40,0% ## ##
Backfill & Compaction 10 5-Jun-23 14-Jun-23 7,28% ## ##
30,0%
Steel Structure Works (49.4 Ton) 12 26-Jun-23 7-Jul-23 14,51% ## ##
Roofing, Flashing & Gutter Works 30 8-Jul-23 6-Aug-23 8,30% 20,0% ## ## ## ## ##
Downspout Works 20 7-Aug-23 26-Aug-23 0,01% ## ## ## ##
10,0%
Concrete Finishing (Concrete Polished) 65 27-Aug-23 30-Oct-23 1,12% ## ## ## ## ## ## ## ## ## ## ##
Inspection 15 31-Oct-23 14-Nov-23 0,00% 0,0% 0,0%
1 11 21 31 41 51 61
Weekly Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
3,2%
3,2%
3,2%
8,4%
5,2%
8,6%
3,5%
3,5%
3,5%
6,1%
2,6%
2,6%
9,0%
6,4%
3,6%
3,6%
0,0%
7,3%
8,9%
1,7%
1,7%
1,7%
1,7%
0,0%
0,0%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,0%
0,0%
100,0%
100,0%
100,0%
17,9%
23,0%
31,7%
35,1%
38,6%
42,0%
48,1%
50,7%
53,4%
62,4%
68,8%
72,4%
76,1%
76,1%
83,3%
92,2%
93,9%
95,5%
97,2%
98,9%
98,9%
98,9%
99,0%
99,1%
99,2%
99,3%
99,4%
99,5%
99,6%
99,7%
99,8%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
3,2%
6,3%
9,5%
10,7%
5,3%
4,4%
9,2%
6,0%
6,9%
3,5%
1,9%
3,5%
0,0%
1,3%
4,2%
2,7%
2,7%
7,3%
3,6%
3,3%
10,7%
16,1%
20,5%
29,7%
35,8%
42,7%
46,1%
48,0%
51,5%
51,5%
52,8%
57,0%
59,7%
62,4%
69,7%
73,3%
76,5%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Steel Bar 500,0 m2 500,0 0,0 500,0 100%
UPPER
SLAB
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Dry Waste Storage 2,131.2 m2 (Period 10 Months) 315 days 15-Feb-23 26-Dec-23
1
2
3
4
5
6
7
8
9
0,0%
Steel Structure Shopdrawing Approval 30 days 15-Feb-23 16-Mar-23 100,0%
0,0%
99,6% 100,0%
98,7%
Steel Structure Fabrication & Delivery 45 days 17-Mar-23 30-Apr-23 0,0%
90,0% 93,5%
Structure Shopdrawing Approval 15 days 15-Feb-23 1-Mar-23 0,0% 89,7%
7,9%
3,6%
6,7%
3,6%
3,1%
0,0%
3,7%
1,2%
3,7%
1,6%
0,7%
1,5%
2,3%
18,3%
26,2%
29,8%
36,5%
40,1%
43,2%
43,2%
46,9%
48,1%
51,8%
53,4%
54,1%
55,6%
57,9%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,4%
7,2%
WORK PRORGESS DRY WASTE STORAGE YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS DRY WASTE STORAGE - TIE BEAM
Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 109 Pcs 109 0 109 100%
Tie Beam
Progress
No. Item Qty Unit %
Last Week This Week accum.
Steel Bar 24 Pcs 16 0 16 66,67%
Tie Beam
Progress
No. Item Qty Unit %
Last Week This Week accum.
Lean Concrete 162 m2 126 36 162 100%
Slab
Progress
No. Item Qty Unit %
Last Week This Week accum.
Ring Beam
Work Item Duration Start Date Finish Date Weight Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Motorbike Parking + Rain Water Tank 17,479.44 m2 (Period 12 Months) 370 2-Feb-23 31-Jan-24
1
2
3
4
5
6
7
8
9
100,0%
100,0%
Steel Structure Shopdrawing Approval 29 2-Feb-23 3-Mar-23 0,0% 100,0%
99,3%
Steel Structure Fabrication & Delivery 119 4-Mar-23 1-Jul-23 0,0% 96,4%
WORK PRORGESS MOTORBIKE PARKING YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS MOTOR BIKE PARKING - FOUNDATION
Until Last Week this Week Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Excavation 2074 m2 2073,6 0,0 2073,6 100%
Found
Water
Rain
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Motor Bike
734,0 423,0
1 Lean Concrete 734,0 pcs 423,0 0,0 423,0 57,63%
Concrete 734,0 pcs 384,0 39,0 423,0 57,63%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Motor Bike
51,0
1 Forming ### pcs 51,0 37,0 88,0 50,00%
Concrete ### pcs 51,0 37,0 88,0 50,00%
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Power Station B 4,717.8 m2 (Period 10 Months) 313 2-Feb-23 21-Dec-23
1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 29 2-Feb-23 3-Mar-23 100,0%
0,0%
99,5% 99,9%
Steel Structure Fabrication & Delivery 89 4-Mar-23 1-Jun-23 0,0% 95,7%
90,0%
Structure Shopdrawing Approval 14 2-Feb-23 16-Feb-23 0,0% 89,6%
Finishing Shopdrawing Approval 196 17-Feb-23 1-Sep-23 0,0%
80,0%
Pile Finish 0 28-Feb-23 28-Feb-23 0,0%
Foundation & Tie Beam Works 99 28-Feb-23 7-Jun-23 25,4% 0 0 0 0 0
70,0%
Concrete Slab 1st Floor (1.422 m2) 28 3-Jul-23 31-Jul-23 6,2% 0 0 0 0 68,5%
Concrete Column 1st Floor (46 Pcs) 86 21-Mar-23 15-Jun-23 9,1% 60,0% 0 0 0
Beam & Slab 2nd Floor (1.569 m2) 43 21-May-23 3-Jul-23 10,0% 0 0 0 0 0 0
Concrete Column 2nd Floor (35 Pcs) 54 22-May-23 15-Jul-23 0,6% 50,0% Actual
0 041.0%
0
Ring Beam Works 54 14-Jun-23 7-Aug-23 14,9% 0 0 47,1%
WORK PRORGESS POWER STATION B YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS POWER STATION B - GF CONCRETE SLAB
Until Last Week this Week Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete 1391 m2 1391,2 0 1391,2 100%
SLAB
Progress
No. Item Qty Unit %
Last Week This Week accum.
Colum
1
n
Progress
No. Item Qty Unit %
Last Week This Week accum.
SL 2FL
PROGRESS MONITORING - LIQUID CHEMICAL R.01 (May 11 th, 2023) Monitoring Date: 15/06/2023 11.04
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Liquid Chemical Storage 3,207.09 m2 (Period 10 Months) 317 1-Mar-23 11-Jan-24
1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 30 1-Mar-23 30-Mar-23 0,0% 100,0%
99,3% 100,0%
Steel Structure Fabrication & Delivery 45 31-Mar-23 14-May-23 0,0% 97,0%
70,0%
Concrete Slab 1st Floor (1.561 m2) 66 5-May-23 9-Jul-23 9,2% 0 0 0 0 0 0 0 0 0 0
Concrete Column 1st Floor (28 Pcs) 59 28-May-23 25-Jul-23 4,9% 0 0 0 0 0 0 0 0 0
60,0%
Beam & Slab 2nd Floor (1.716 m2) 57 12-Jun-23 7-Aug-23 26,9% 0 0 0 0 0 0 0 0 0
Concrete Column 2nd Floor (28 Pcs) 52 1-Jul-23 21-Aug-23 56,7%
1,0% 0 0 0 0 0 0 0 0
50,0%
Ring Beam Works 51 16-Jul-23 4-Sep-23 3,3% 0 0 0 0 0 0 0 0
Steel Structure (54 Ton) 22 28-Aug-23 18-Sep-23 12,4% 0 0 0 0
40,0%
Roofing, Flashing & Gutter Works (1.836 m2) 20 8-Sep-23 27-Sep-23 8,0% 0 0 0
38,9%
Actual 24.8%
Downspout Works 42 21-Aug-23 1-Oct-23 2,5% 0 0 0 0 0 0
30,0%
ALC Wall & Plaster Works (13.312 m2) 106 9-Jul-23 22-Oct-23 6,5% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Joinery Works 108 1-Aug-23 16-Nov-23 4,1% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20,0%
Ceiling Gypsum Works 123 1-Aug-23 1-Dec-23 4,0% 18,8% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11,9% Plan 24.5%
Floor Finishing (Concrete Trowel Finish & Ceramic Tile) 50 2-Nov-23 21-Dec-23 2,1% 0 0 0 0 0 0 0 0
10,0%
Painting Works 86 3-Oct-23 27-Dec-23 10,0%
0,9% 8,0% 0 0 0 0 0 0 0 0 0 0 0 0 0
Inspection 15 28-Dec-23 11-Jan-24 0,0% 0,0% 0,0% 3,0%
0,0%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Excavation 28 Pts 28 0 28 100%
Pile Cap
1062
2 Lean Concrete 1062 m' 1062 0 1062,4 100%
Concrete 1062 m' 747,8 314,6 1062,4 100%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete ### m2 986 0 986 66,60%
Slab
1
Concrete ### m2 0 0 0 0,00%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Rebar 28 Pcs 8 11 19 67,86%
CL
1
Concrete 28 Pcs 0 10 10 35,71%
Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Mosque & Clean Water Tank 2,570.2 m2 (Period 10 Months) 315 days 23-Feb-23 3-Jan-24
1
2
3
4
5
6
7
8
9
100%
100,0%
Steel Structure Shopdrawing Approval 29 days 23-Feb-23 24-Mar-23 0,0%
Steel Structure Fabrication & Delivery 89 days 25-Mar-23 22-Jun-23 0,0%
Structure Shopdrawing Approval 14 days 23-Feb-23 9-Mar-23 0,0%
90,0%
Finishing Shopdrawing Approval 189 days 10-Mar-23 15-Sep-23 0,0%
Pile Finish 0 days 9-Mar-23 9-Mar-23 0,0%
Open-Cut Works 17 days 10-Mar-23 27-Mar-23 3,2% 0 0 ###
80,0%
Concrete Under Ground Slab 38 days 28-Mar-23 4-May-23 3,4% 0 0 0 0 0 0
Concrete Column & Wall 27 days 5-May-23 31-May-23 8,8% 0 0 0 0
Concrete Beam & Upper Slab 30 days 1-Jun-23 30-Jun-23 0,9% 0 0 0 0 0
70,0%
Progress
No. Item Qty Unit %
Last Week This Week Accum.
Form 696 m2 336 168 504 72%
Upper
Slab
1
Concrete 696 m2 0 0 0 0%
PROGRESS MONITORING - EXTERNAL R.01 (May 11 th, 2023) Monitoring 13/06/2023 16.39
Weigh Schedul
Work Item Duration Start Date Finish Date Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
t e
Des-22
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
External Works 427 days 16-Jan-23 17-Mar-24
1
2
3
4
5
6
7
8
9
100,0%
Permanent Road (Base Course) for Temporary Access 125 days 16-Jan-23 20-May-23 100,00% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0,8%
Guard House, Main Gate,Bridge,Tower,Sub Gate,Sub Bridge261 days 21-May-23 5-Feb-24 90,00% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5,6%
Until Last Week this Week Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 612,3 m 528,627 0 528,627 86,33%
Retaining Wall
Until Last Week this Week Until Last Week this Week Until Last Week this Week Until Last Week this Week
Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 735 Pcs 77 77 10,48%
Fence
1 TAKENAKA STAFF
1,1 Project Manager 2 1 3 4 2 4 4 4 3 2 2 4 35 364 399
1,2 Chief Engineer 3 2 5 5 2 5 5 5 3 3 2 5 45 537 582
1,3 Civil Engineer & Ass. 16 17 22 23 17 23 23 23 17 17 17 23 238 2076 2314
1,4 M&E Engineer 0 0 0
1,5 Administration 3 3 4 4 3 4 4 4 3 3 2 4 41 317 358
1,6 Drafter 6 6 6 6 6 7 7 7 4 4 2 7 68 541 609
1,7 Logistic 3 3 3 3 3 3 3 3 3 3 2 3 35 365 400
1,8 Mechanic 4 4 4 4 4 4 4 4 4 3 3 4 46 493 539
1,9 Safety Officer 4 4 4 4 3 4 4 4 3 3 2 4 43 418 461
1,10 Operator (Heavy Equipment) 0 0 0
1,11 Surveyor + Assistant 4 5 5 5 3 5 5 5 4 4 3 5 53 949 1002
0 0 0
0 0 0 0
2 SUBCONTRACTORS 0 0 0
2,1 Civil Works 0 0 0
2,1 SBP (Soil Work) 37 40 34 23 34 28 34 34 34 34 9 18 359 1883 2242
2,2 Adicon (Fence) 7 6 6 6 6 7 7 7 7 7 7 7 80 435 515
2,3 Putri Tunggal (Daily) 72 52 43 53 50 40 43 46 46 40 40 43 568 2834 3402
2,4 PT. Palam Arta 16 18 16 10 18 18 18 18 18 18 18 17 203 268 471
2,5 PT. GKP (Forming) 122 140 147 198 206 197 192 201 204 200 129 191 2127 1122 3249
2,6 Indokaryatama (cutting pile) 33 32 32 26 32 32 32 31 31 32 29 32 374 26 400
2,7 Aris Wiyatama (Scaffolding) 36 33 37 13 34 38 40 41 39 40 23 39 413 0 413
2,8 Indofab (Steelbar) 265 250 264 239 256 262 259 266 261 139 166 234 2861 1351 4212
2,9 Anisa Jaya Hasanah (Cor) 7 7 7 5 7 7 7 7 7 7 5 7 80 2071 2151
2,10 Mahesa 30 38 48 52 48 53 54 56 61 54 42 50 586 1267 1853
2,11 PT. Intra 15 15 15 15 15 15 15 15 15 15 15 15 180 3577 3757
2,12 Keshun 3 3 3 3 3 0 0 0 0 0 0 0 15 1464 1479
2,13 Dwi Lestari 32 34 36 36 33 35 33 35 32 34 35 34 409 722 1131
0 3938 3938
0 287 287
0 316 316
0
TOTAL 720 713 744 737 785 791 793 816 799 662 553 746 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8859 27305 36164
WEATHER LIST
JUNE 2023
Project : YIH QUAN FOOTWEAR INDONESIA Doc.No.: IMS/F-122-PR/7 of 7.Rev.00
12 12 12 12 12 12 12
12
9 1 3 9 2 3 9 3 3 9 4 3 9 5 3 9 6 3 9 7 3 9 8 3
6 6 6 6 6 6 6 6
12 12
12 12 12 12 12 12
9
9 9 3 10
3
9 11 3 9 12 3 9 13 3 9 14 3 9 15 3 9 16 3
6 6 6 6 6 6 6
6
12 12 12 12 12 12
121 12
9
17
17 3 9 18 3 9 19 3 9 20 3 9 21 3 9 22 3 9 23 3 9 24 3
6 6 6 6 6 6 6
6
12 12 12 12 12 12 Remark :
12
AM
1 PM
9 25 3 9 26 3 9 27 3 9 28 3 9 29 3 9 30 3 9 31 3 Date
Rainy
Drizzle
6 6 6 6 6 6 6 Shinny
IMPORTANT NOTES
Description Remark
Takenaka Information:
1 Progress of CSA work
- Plan : 37.2% Actual : 37.2% (On Schedule)
2 Takenaka have received Site Instruction regarding Steel Structure Design change
that caused by Utility bridge for Dry Waste (June 13th, 2023), but not recieve for WWTP
3 Wika trial mix sample failed to fulfill targeted strenght on compressive strenght test
for 14 days.
5 Takenaka need decision from Wahana and The Owner Regarding color scheme and
material type for Homogenous and Ceramic tile due to ordering process need to start soon
and production process from material maker may takes time.
6 Takenaka has submited the invoice of first progress payment, please confirm
when the payment of PT. Yih Quan will be released.
7 Regarding SLF, Takenaka have received list of data to be prepared, but some detail
need to be clarified.
10 Takenaka need information when pile material at supplier workshop can be delivered.