Doc.No.: ID-ISO/F-122-PR/1 of 7.Rev.

00

Report No. : 41

Report Period : 9-Jun-23 - 15-Jun-23

Date of Created : June 15, 2023

WEEKLY CONSTRUCTION REPORT

OF

YIH QUAN FOOTWEAR INDONESIA PROJECT

CLIENT : PT. YIH QUAN FOOTWEAR INDONESIA

DESIGNED : PT. WAHANACIPTA BANGUNWISMA

CONSTRUCTION PERIOD : 14 November 2022 - 15 March 2023

TOTAL FLOOR AREA : 162,289.02 m2

Ir. Achmad Budi S.


Senior Project Manager

Client Consultant Contractor

COPIES PT.YIH QUAN FOOTWEAR INDONESIA PT. WAHANACIPTA BANGUNWISMA PT. TAKENAKA INDONESIA
DELIVERED (Set)
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

PROJECT VIEW C
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

PHOTO PROGRESS D
Plan Photo

4
1

2 3

1 4

2 3

WORK LOCATION DATE

Project View YIH QUAN SITE PROJECT Tuesday, 13 June 2023


Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

NEW FACTORY BUILDING WORK PHASE - 1 YIH QUAN FOOTWEAR INDONESIA S-CURVE PLAN R.01 (May 11 th,2023)
Month Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-23 Feb-23 Mar-24 Weight
NO WORK ITEM
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 (%)
100,0%

A Preliminary Work 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 18,37%

B Pilling Work 0,00%

C General 0,00%
90,0%
1 Road Plan 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 6,15%

2 Drainage System 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1,27%

3 Rain Water Recycling System 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 1,04%


80,0%
4 Waste Water System 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,16%

5 Utility Trench 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 1,88%

6 Landscape; Water Fountain 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1,14%


70,0%
7 Perimeter Fence 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 1,17%

8 Retaining Wall 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,68%

9 Main Gate Entrance Bridge 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,21%


60,0%
10 Sub Gate Entrance Bridge 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,07%

D Main Production Building 0,00%

1 Workshop B1 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 14,07%
50,0%
2 Workshop B2 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 14,60%

3 Linking Corridor Warehouse-B1 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,29%

4 Linking Corridor B1-B2 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%PLAN


0% 37,2%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,66%
40,0%
5 Warehouse 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 5,98%

E Utility Building 0,00%


ACTUAL 37,2%
1 Power Station B 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 3,65%

2 WWTP 30,0%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2,21%

3 Dry Waste Storage 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2,59%

4 Liquid Chemical Storage 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 3,25%

F Auxiliary Building 20,0% 0,00%

1 Office 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 6,30%

3 Motorbike Parking + Rain Water Tank 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 10,78%

6 Mosque + Clean Water Tank + Hydrant Tank 10,0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2,91%

7 Guard House; Custom Office; Main Gate and Tower 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,48%

8 Subgate 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0,04%

9 Car Parking Canopy (1 Unit) 0,0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0,04%


0,0%
0,0%
0,3%
0,4%
0,7%
0,8%
0,9%
1,0%
1,1%
1,3%
1,4%
1,4%
16,03% 2,4% 10,8% 1,4%
17,96% 1,9% 12,3% 1,5%
19,58% 1,6% 13,9% 1,5%
22,34% 2,8% 15,6% 1,7%
22,34% 0,0% 17,4% 1,8%
25,23% 2,9% 19,7% 2,3%
26,38% 1,1% 22,4% 2,6%
28,48% 2,1% 25,1% 2,7%
30,55% 2,1% 27,9% 2,8%
32,81% 2,3% 30,7% 2,8%
35,42% 2,6% 33,8% 3,1%
1,8% 37,2% 3,4%
0,0% 40,3% 3,1%
0,0% 43,4% 3,0%
0,0% 46,2% 2,8%
0,0% 49,0% 2,8%
0,0% 51,7% 2,7%
0,0% 54,6% 2,9%
0,0% 57,5% 2,9%
0,0% 60,0% 2,5%
0,0% 62,6% 2,6%
0,0% 65,0% 2,5%
0,0% 67,5% 2,4%
0,0% 69,8% 2,3%
0,0% 72,0% 2,2%
0,0% 74,1% 2,0%
0,0% 75,8% 1,7%
0,0% 77,5% 1,7%
0,0% 79,0% 1,5%
0,0% 80,5% 1,5%
0,0% 82,1% 1,6%
0,0% 83,5% 1,5%
0,0% 84,9% 1,4%
0,0% 86,2% 1,3%
0,0% 87,4% 1,2%
0,0% 88,7% 1,2%
0,0% 89,8% 1,2%
0,0% 91,0% 1,2%
0,0% 92,2% 1,2%
0,0% 93,3% 1,1%
0,0% 94,2% 1,0%
0,0% 95,1% 0,9%
0,0% 95,8% 0,8%
0,0% 96,6% 0,8%
0,0% 97,3% 0,7%
0,0% 97,9% 0,5%
0,0% 98,4% 0,5%
0,0% 98,8% 0,5%
0,0% 99,2% 0,4%
0,0% 99,6% 0,4%
0,0% 99,9% 0,3%
0,1%
Weekly Plan Progress

100%
0,0%
0,0%
0,3%
0,7%
1,5%
2,3%
3,2%
4,1%
5,2%
6,5%
7,9%
9,4%

Accumulative Plan Progress


0,0%
0,0%
0,6%
1,2%
0,7%
0,5%
1,1%
2,0%
1,3%
2,3%
11,42% 1,8%
13,63% 2,2%

0,0%
Weekly Actual Progress
6,10%
7,35%
9,65%

37,2%
0,0%
0,0%
0,6%
1,8%
2,5%
3,0%
4,1%

Accumulative Actual Progress

WORK LOCATION DATE

BUILDING CONSTRUCTION YIH QUAN PROJECT Tuesday, 13 June 2023


Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A


PROGRESS MONITORING - WORKSHOP B1 BUILDING R.01 (May 11 th,2023) Monitoring 15/06/2023 10.45

Work Item Duration Start Date Finish Date Weight 2023 2024

Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
Workshop B1 13,339.9 m2 (Period 12 Months) 304 16/01/2023 15/11/2023

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
1
2
3
4
5
6
7
8
9
100%
Steel Structure Shopdrawing Approval 32 16/01/2023 16/02/2023 100,0%
0,00%
Steel Structure Fabrication & Delivery 90 17/02/2023 17/05/2023 0,00%
Structure Shopdrawing Approval 32 16/01/2023 16/02/2023 0,00% 90,0%
Finishing Shopdrawing Approval 175 17/02/2023 10/08/2023 0,00%
Pile Finish 0 31/01/2023 31/01/2023 0,00%
Foundation & Tie Beam Works 105 01/03/2023 14/06/2023 80,0%
17,44% ## ## ## ## ## ## ## ##
Concrete Slab 1st Floor (6.837 m2) 91 01/05/2023 31/07/2023 9,47% ## ## ## ## ## ## ##
Concrete Column 1st Floor (147 Pcs) 90 01/04/2023 30/06/2023 6,30% ## ## ## ## ##
70,0%
Beam & Slab 2nd Floor (6.837 m2) 91 14/04/2023 14/07/2023 18,48% ## ## ## ## ## ## ##
Concrete Column 2nd Floor (109 Pcs) 93 21/04/2023 23/07/2023 2,37% ## ## ## ##
Beam & Roof Slab (2.766 m2) 93 07/05/2023 08/08/2023 5,64% 60,0% ## ## ## ## ## ##
Concrete Column Roof (40 Pcs) 94 14/05/2023 16/08/2023 0,82% ## ## ## ##
Beam & Concrete Roof Slab (266 m2) 24 14/07/2023 07/08/2023 2,36% Plan 44.4%## ## ##
50,0%
Steel Structure (170 Ton) 31 07/07/2023 07/08/2023 9,60% ## ## ## ## ##
Roofing, Flashing & Gutter Works (3.838 m2) 38 07/08/2023 14/09/2023 4,13% ## ## ## ## ##
Downspout Works 29 01/09/2023 30/09/2023 0,84% 40,0% ## ## ## ##
Waterproofing & Cynder Concrete 31 21/07/2023 21/08/2023 2,44% Actual ## ##
ALC Wall & Plaster Works (23.016 m2) 99 14/06/2023 21/09/2023 44.3%
5,43% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
30,0%
Joinery Works 62 14/07/2023 14/09/2023 5,87% ## ## ## ## ## ## ## ## ## ##
Exposed Ceiling w/ Skim Coat Finish (1st & 2nd Floor) 92 14/06/2023 14/09/2023 1,54% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Floor Finishing (Concrete Polished & Ceramic Tile) 91 01/08/2023 31/10/2023 3,81% 20,0% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Toilet Works (1st & 2nd Floor) 92 14/07/2023 14/10/2023 0,31% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Elevator Works 68 07/08/2023 14/10/2023 1,16% ## ## ## ## ## ## ## ## ## ##
10,0%
Stair Works 108 14/06/2023 30/09/2023 0,91% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Painting Works 71 21/08/2023 31/10/2023 1,06% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Inspection 25 21/10/2023 15/11/2023 0,00% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
1,2% 1,2%
2,3% 1,2%
3,5% 1,2%
4,6% 1,2%
6,3% 1,6%
7,9% 1,6%
11,0% 3,1%
14,3% 3,2%
18,2% 3,9%
22,5% 4,3%
26,9% 4,4%
31,2% 4,4%
35,6% 4,4%
40,0% 4,4%
44,4% 4,4%
48,1% 3,8%
51,9% 3,8%
55,2% 3,3%
60,9% 5,7%
66,7% 5,7%
72,9% 6,2%
79,2% 6,3%
82,5% 3,3%
85,3% 2,9%
88,2% 2,8%
90,6% 2,4%
93,2% 2,6%
95,9% 2,6%
97,0% 1,2%
97,8% 0,8%
98,3% 0,5%
98,9% 0,5%
99,2% 0,4%
99,6% 0,4%
100,0% 0,4%
100,0% 0,0%
100,0% 0,0%
Weekly Progress Plan

Accumulative Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,5%
0,7%
1,2%
1,2%
2,6%
2,0%
1,0%
2,2%
3,1%
2,1%
0,0%
2,9%
1,9%
3,3%
3,0%
4,0%
5,0%
7,6%
Weekly Progress Actual
11,4%
14,5%
16,6%
16,6%
19,5%
21,4%
24,6%
27,6%
31,6%
36,7%
44,3%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,5%
1,2%
2,4%
3,7%
6,3%
8,3%
9,2%

Accumulative Progress Actual

WORK LOCATION DATE

WORK PRORGESS WORKSHOP B1 YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B1 - CONCRETE COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Concrete Column
Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.

1 Concrete 138 Pcs 90 48 138 100

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B1 - GF CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Base Course Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Lean Concrete 6570 m2 6466 104 6570 100
1
Concrete 6570 m2 0 0 0 0

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B1 - 2nd FLOOR CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Form work Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Form work 6570 m2 4802,05 0 4802,05 73,091
1
Concrete 6570 m2 2052 181,8 2233,8 34

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B1 - CONCRETE 2nd FLOOR COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Concrete Column
Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.

1 Concrete 100 Pcs 0 18 18 18

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

Plan 42.1%

Actual 41,2%

WORK LOCATION DATE

WORK PRORGESS WORKSHOP B2 YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B2 BUILDING - TIE BEAM

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete

Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 4171 m¹ 4171,1 0 4171,1 100%
Tie Beam

1 Lean Concrete 4171 m¹ 4171 0 4171 100%


Concrete 4171 m¹ 4013,6 157,4 4171 100%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B2 BUILDING - GF CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Lean Concrete Concrete

Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
2
Lean Concrete 6570 m 5769,25 127,37 5896,62 90%
1
Concrete 6570 m2 0 0 0 0%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B2 BUILDING - GF CONCRETE COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Concrete Column
Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.

1 Concrete 96 Pcs 54 6 60 62,50%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WORKSHOP B2 BUILDING - 2nd FLOOR CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Form Work Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.

1 Form Work 6570 m2 3914,50 0,00 3914,50 60%

2 Concrete 6570 m2 1071,00 0,00 1071,00 16,3%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A


PROGRESS MONITORING - OFFICE BUILDING R.01 (May 11 th, 2023) Monitoring 13/06/2023 09.12

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

Des-22

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Office 5,701.5 m2 (Period 12 Months) 357 days 16-Jan-23 21-Jan-24

1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 31 days 16-Jan-23 16-Feb-23 100,0%
0,0%
Steel Structure Fabrication & Delivery 89 days 17-Feb-23 17-May-23 0,0%
Structure Shopdrawing Approval 31 days 16-Jan-23 16-Feb-23 0,0% 90,0%

Finishing Shopdrawing Approval 180 days 17-Feb-23 16-Aug-23 0,0%


Pile Finish 0 days 27-Jan-23 27-Jan-23 0,0%
80,0%
Foundation & Tie Beam Works 115 days 21-Jan-23 16-May-23 8,5% ## ## ## ## ## ##
Concrete Slab 1st Floor (1.620 m2) 36 days 1-Jun-23 7-Jul-23 3,4% ## ## ## ## ## ##
Concrete Column 1st Floor (32 Pcs) 60 days 1-Apr-23 31-May-23 2,1% 70,0% ## ## ## ## ##
Beam & Slab 2nd Floor (1.724 m2) 38 days 7-May-23 14-Jun-23 10,5% ## ## ## ## ## ## ## ## ## ##
Concrete Column 2nd Floor (30 Pcs) 38 days 14-May-23 21-Jun-23 1,4% ## ## ## ## ## ##
60,0%
Beam & Slab 3rd Floor (1.649 m2) 35 days 3-Jun-23 8-Jul-23 10,0% ## ## ## ## ## ##
Concrete Column 3rd Floor (35 Pcs) 44 days 7-Jun-23 21-Jul-23 1,3% ## ## ##
Beam & Concrete Roof Slab (1.828 m2) 38 days 7-Jul-23 14-Aug-23 50,0%
11,1% ## ## ## ## ## ##
Steel Structure (53 Ton) 13 days 14-Aug-23 27-Aug-23 5,5% ## ##
Waterproofing & Cynder Concrete 17 days 21-Aug-23 7-Sep-23 3,4% 40,0% ## ##
Roofing, Flashing & Gutter Works (1.620 m2) 14 days 7-Sep-23 21-Sep-23 4,0% ## ## ##
Plan 28.7%
Downspout Works 51 days 1-Aug-23 21-Sep-23 0,7% ## ## ## ##
30,0%
ALC Wall & Plaster Works (3.277 m2) 140 days 3-Jun-23 21-Oct-23 7,2% ## ## ## ## ## ## ## ## ## ##
Joinery Works 142 days 21-Jun-23 10-Nov-23 9,3% ## ## ## ## ##
Ceiling Gypsum Works 137 days 21-Jul-23 5-Dec-23 6,0% 20,0%
## ## ## ## ## ## ## ## ## ##
Floor Finishing (Floor Tile) 62 days 22-Oct-23 23-Dec-23 12,0% Actual 24.2% ## ## ## ## ## ## ## ## ## ## ##
Toilet Works (1st & 2nd Floor) 127 days 2-Sep-23 7-Jan-24 0,5% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
10,0%
Stair Works 98 days 1-Jun-23 7-Sep-23 1,1% ## ## ## ## ## ## ## ## ## ## ## ## ##
Painting Works 139 days 21-Aug-23 7-Jan-24 2,1% ## ## ## ## ## ## ## ## ## ## ## ## ##
Inspection 28 days 24-Dec-23 21-Jan-24 0,0% 0,0%
0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,5% 0,5%
1,0% 0,5%
1,5% 0,5%
2,0% 0,5%
2,5% 0,5%
3,0% 0,5%
3,5% 0,5%
4,0% 0,5%
4,5% 0,5%
5,0% 0,5%
5,8% 0,7%
6,5% 0,7%
7,2% 0,7%
8,0% 0,7%
8,7% 0,7%
11,2% 2,5%
13,9% 2,7%
16,1% 2,2%
18,3% 2,2%
23,4% 5,1%
28,7% 5,3%
32,3% 3,6%
36,1% 3,8%
39,9% 3,8%
43,2% 3,3%
46,5% 3,3%
49,9% 3,4%
53,4% 3,5%
56,9% 3,5%
60,0% 3,1%
64,3% 4,3%
68,6% 4,3%
71,2% 2,5%
74,5% 3,3%
77,8% 3,3%
79,1% 1,2%
80,3% 1,2%
81,5% 1,2%
82,7% 1,2%
84,8% 2,1%
86,9% 2,1%
89,0% 2,1%
91,0% 2,1%
92,6% 1,6%
94,3% 1,6%
95,9% 1,6%
97,2% 1,3%
98,5% 1,3%
99,9% 1,3%
##### 0,1%
##### 0,0%
##### 0,0%
##### 0,0%
##### 0,0%
##### 0,0%
Weekly Progress Plan

Accumulative Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,9%
0,5%
1,9%
1,4%
0,7%
0,4%
0,8%
0,8%
0,4%
0,0%
0,5%
1,3%
2,7%
1,9%
2,4%
2,2%
3,3%
Weekly Progress Actual
10,4%
11,7%
14,4%
16,3%
18,7%
20,9%
24,2%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,9%
3,4%
5,4%
6,7%
7,4%
7,8%
8,6%
9,4%
9,8%
9,8%

Accumulative Progress Actual

6 LOCATION DATE

WORK PRORGESS OFFICE BUILDING YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
nd
PROGRESS OFFICE BUILDING - 2 FLOOR SLAB

PROGRESS MONITORING PROGRESS PHOTO

Steel bar Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Forming 1670 m2 1669,5 0 1669,5 100,00%
Floor
2nd

1
Concrete 1670 m2 900 769,5 1669,5 100,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
nd
PROGRESS OFFICE BUILDING - 2 FLOOR COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Steel bar Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Colum

Steel bar 30 pcs 0 18 18 60,00%


2F

1
n

Concrete 30 pcs 0 18 18 60,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - WAREHOUSE R.01 (May 11 th, 2023) Monitoring


Date:
14/06/2023 08.55

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Warehouse 5,588.6 m2 (Period 11 Months) 342 26-Jan-23 31-Dec-23

1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 29 26-Jan-23 24-Feb-23 0,0% 100,0%

Steel Structure Fabrication & Delivery 109 25-Feb-23 14-Jun-23 0,0%


Structure Shopdrawing Approval 14 26-Jan-23 9-Feb-23 0,0% 90,0%
Finishing Shopdrawing Approval 213 10-Feb-23 11-Sep-23 0,0%
Pile Finish 0 9-Feb-23 9-Feb-23 0,0%
80,0%
Foundation & Tie Beam Works 110 10-Feb-23 31-May-23 15,4% ## ## ## ## ## ## ## ##
Concrete Slab 1st Floor (2.737 m2) 37 7-Jun-23 14-Jul-23 7,3% ## ## ## ## ## ## ##
Concrete Column 1st Floor (51 Pcs) 37 1-May-23 7-Jun-23 7,7%
70,0%
## ## ## ## ##
Beam & Slab 2nd Floor (2.900 m2) 51 7-May-23 27-Jun-23 18,0% ## ## ## ## ## ## ## ## ## ##
Concrete Column 2nd Floor (36 Pcs) 61 14-May-23 14-Jul-23 3,3% ## ## ## ## ##
60,0%

Beam & Roof Slab (1.130 m2) 56 1-Jun-23 27-Jul-23 11,9% ## ## ## ## ## ## ## ##


Concrete Column (13 Pcs) 68 7-Jun-23 14-Aug-23 1,2% Plan 44.3% ## ## ##
50,0%
Steel Structure (105,3 Ton) 17 14-Aug-23 31-Aug-23 5,3% ## ## ##
Roofing, Flashing & Gutter Works (1.290 m2) 20 1-Sep-23 21-Sep-23 6,5% ## ## ## ##
Downspout Works 38 14-Aug-23 21-Sep-23 40,0%
0,3% ## ## ## ##
ALC Wall & Plaster Works (2.150 m2) 103 3-Jun-23 14-Sep-23 7,1% ## ## ## ## ## ## ## ##
Joinery Works 74 21-Jul-23 3-Oct-23 7,8% 30,0% ## ## ## ## ##
Exposed Ceiling w/ Skim Coat Finish 83 9-Jun-23 31-Aug-23 1,3% ## ## ## ## ## ## ##
Actual 33.9%
Floor Finishing (Terrazo Floor, Concrete Polished & Ceramic Tile) 127 9-Jun-23 14-Oct-23 3,7% ## ## ## ## ## ## ## ##
20,0%
Toilet Works (1st & 2nd Floor) 103 20-Jul-23 31-Oct-23 0,4% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
Elevator Works 55 20-Sep-23 14-Nov-23 0,6% ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
10,0%
Stair Works 104 15-Jul-23 27-Oct-23 1,1% ## ## ## ## ## ## ## ## ## ## ## ##
Painting Works 94 18-Sep-23 21-Dec-23 1,2% 3,6% ## ## ## ## ## ## ## ## ## ## ## ##
2,9%
Inspection 17 14-Dec-23 31-Dec-23 0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
0,0% 0,0%
1,0% 1,0%
1,9% 1,0%
2,9% 1,0%
3,9% 1,0%
4,8% 1,0%
5,8% 1,0%
6,8% 1,0%
7,7% 1,0%
8,7% 1,0%
9,7% 1,0%
10,6% 1,0%
12,9% 2,3%
17,4% 4,5%
22,2% 4,9%
27,1% 4,9%
32,0% 4,9%
37,8% 5,9%
44,3% 6,5%
50,8% 6,5%
57,3% 6,5%
61,5% 4,2%
65,7% 4,2%
68,2% 2,5%
71,4% 3,2%
73,1% 1,7%
74,9% 1,7%
78,3% 3,4%
81,7% 3,4%
85,1% 3,4%
88,8% 3,7%
92,4% 3,7%
95,8% 3,4%
97,0% 1,2%
98,1% 1,2%
98,6% 0,4%
98,8% 0,2%
99,0% 0,2%
99,3% 0,2%
99,4% 0,1%
99,6% 0,1%
99,7% 0,1%
99,7% 0,1%
99,8% 0,1%
99,9% 0,1%
100,0% 0,1%
100,0% 0,0%
100,0% 0,0%
Weekly Progress Plan

Accumulative Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,2%
1,4%
1,4%
1,5%
2,0%
1,7%
3,5%
2,3%
0,7%
0,0%
0,8%
1,7%
3,0%
3,1%
3,7%
2,3%
2,6%
Weekly Progress Actual 10,1%
13,6%
15,9%
16,6%
16,6%
17,4%
19,1%
22,1%
25,2%
28,9%
31,2%
33,9%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,2%
3,6%
5,0%
6,5%
8,4%

Accumulative Progress Actual

WORK LOCATION DATE

WORK PRORGESS WAREHOUSE YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS WAREHOUSE - GF SLAB

PROGRESS MONITORING PROGRESS PHOTO

Lean Concrete Steel bar Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete 2633 m2 1966,5 0 1966,5 74,70%
SLAB

1 Steel bar 2633 m2 0 0 0 0,00%


Concrete 2633 m2 0 0 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WAREHOUSE - GF COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Steel bar Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Rebar 42 Pcs 34 0 34 80,95%
CL

1
Concrete 42 Pcs 34 0 34 80,95%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS WAREHOUSE - 2nd FLOOR SLAB

PROGRESS MONITORING PROGRESS PHOTO

Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Forming 2633 m2 1080 270 1350 51,28%
SLAB

1
Concrete 2633 m2 0 0 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A


PROGRESS MONITORING - WWTP Monitoring 15/06/2023 11.47

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
WWTP 3,073.3 m2 (Period 10 Months) 278 10-Feb-23 14-Nov-23

1
2
3
4
5
6
7
8
9
1,00
100,0%
Steel Structure Shopdrawing Approval 30 10-Feb-23 11-Mar-23 0,00%
Steel Structure Fabrication & Delivery 90 12-Mar-23 9-Jun-23 0,00% 90,0%
Actual
Structure Shopdrawing Approval 15 10-Feb-23 24-Feb-23 0,00% 76.5%
80,0%
Finishing Shopdrawing Approval 150 25-Feb-23 24-Jul-23 0,00%
Pile Finish 0 24-Feb-23 24-Feb-23 0,00% 70,0%
Plan
Open-Cut Works 23 25-Feb-23 19-Mar-23 12,68% ## ## ## ## 76.1%
Concrete Under Ground Slab 15 20-Mar-23 3-Apr-23 60,0%
15,56% ## ## ##
Concrete Column & Wall 30 4-Apr-23 3-May-23 17,26% ## ## ## ## ##
50,0%
Concrete Beam & Upper Slab 20 4-May-23 23-May-23 10,48% ## ## ## ##
Waterproofing 12 24-May-23 4-Jun-23 12,80% 40,0% ## ##
Backfill & Compaction 10 5-Jun-23 14-Jun-23 7,28% ## ##
30,0%
Steel Structure Works (49.4 Ton) 12 26-Jun-23 7-Jul-23 14,51% ## ##
Roofing, Flashing & Gutter Works 30 8-Jul-23 6-Aug-23 8,30% 20,0% ## ## ## ## ##
Downspout Works 20 7-Aug-23 26-Aug-23 0,01% ## ## ## ##
10,0%
Concrete Finishing (Concrete Polished) 65 27-Aug-23 30-Oct-23 1,12% ## ## ## ## ## ## ## ## ## ## ##
Inspection 15 31-Oct-23 14-Nov-23 0,00% 0,0% 0,0%
1 11 21 31 41 51 61
Weekly Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
3,2%
3,2%
3,2%
8,4%
5,2%
8,6%
3,5%
3,5%
3,5%
6,1%
2,6%
2,6%
9,0%
6,4%
3,6%
3,6%
0,0%
7,3%
8,9%
1,7%
1,7%
1,7%
1,7%
0,0%
0,0%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,1%
0,0%
0,0%
100,0%
100,0%
100,0%
17,9%
23,0%
31,7%
35,1%
38,6%
42,0%
48,1%
50,7%
53,4%
62,4%
68,8%
72,4%
76,1%
76,1%
83,3%
92,2%
93,9%
95,5%
97,2%
98,9%
98,9%
98,9%
99,0%
99,1%
99,2%
99,3%
99,4%
99,5%
99,6%
99,7%
99,8%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
3,2%
6,3%
9,5%
10,7%

Weekly Progress Actual


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%

5,3%
4,4%
9,2%
6,0%
6,9%
3,5%
1,9%
3,5%
0,0%
1,3%
4,2%
2,7%
2,7%
7,3%
3,6%
3,3%
10,7%
16,1%
20,5%
29,7%
35,8%
42,7%
46,1%
48,0%
51,5%
51,5%
52,8%
57,0%
59,7%
62,4%
69,7%
73,3%
76,5%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%

WORK LOCATION DATE

WORK PRORGESS WWTP YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS WWTP - UPPER CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Steel Bar Forming Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Steel Bar 500,0 m2 500,0 0,0 500,0 100%
UPPER
SLAB

1 Forming 500,0 m2 500,0 0,0 500,0 100%


Concrete 150,0 m3 0,0 150,0 150,0 100%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - DRY WASTE STORAGE Monitoring


Date:
15/06/2023 11.00

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Dry Waste Storage 2,131.2 m2 (Period 10 Months) 315 days 15-Feb-23 26-Dec-23

1
2
3
4
5
6
7
8
9
0,0%
Steel Structure Shopdrawing Approval 30 days 15-Feb-23 16-Mar-23 100,0%
0,0%
99,6% 100,0%
98,7%
Steel Structure Fabrication & Delivery 45 days 17-Mar-23 30-Apr-23 0,0%
90,0% 93,5%
Structure Shopdrawing Approval 15 days 15-Feb-23 1-Mar-23 0,0% 89,7%

Finishing Shopdrawing Approval 175 days 2-Mar-23 23-Aug-23 0,0% 80,0%


81,8%
Pile Finish 0 days 1-Mar-23 1-Mar-23 0,0%
Foundation & Tie Beam Works 40 days 2-Mar-23 10-Apr-23 43,8% 70,0% 0 0 0 0 0 0
Concrete Slab 1st Floor (2.193 m2) 52 days 11-Apr-23 1-Jun-23 Actual 57.9%
2,6% 0 0 0 0 0 0 0 0
Concrete Column 1st Floor (24 Pcs) 14 days 2-Jun-23 15-Jun-23 60,0%
4,8% 0 0
Ring Beam Works 11 days 16-Jun-23 26-Jun-23 5,2% 0 0
56,5%
50,0%
Steel Structure (77 Ton) 15 days 8-Jul-23 22-Jul-23 20,5% 0 0 0
46,4%
Roofing, Flashing & Gutter Works (2.589 m2) 16 days 23-Jul-23 7-Aug-23 8,3%
44,8% Plan 51.2%0 0
40,0%
Downspout Works 30 days 8-Aug-23 6-Sep-23 0,5% 0 0 0 0 0
ALC Wall & Plaster Works (10.968 m2) 80 days 23-Jul-23 10-Oct-23 7,3% 30,0%
0 0 0 0 0 0 0 0 0 0 0
29,2%
Joinery Works 35 days 21-Sep-23 25-Oct-23 4,3% 0 0 0 0 0 0
20,0%
Ceiling Gypsum Works 50 days 1-Oct-23 19-Nov-23 0,1% 0 0 0 0 0 0 0 0
Floor Finishing (Concrete Trowel Finish & Ceramic Tile) 50 days 16-Oct-23 4-Dec-23 0,6% 0 0 0 0 0 0 0
10,0%
Painting Works 82 days 21-Sep-23 11-Dec-23 1,9% 0 0 0 0 0 0 0 0 0 0 0 0 0
Inspection 15 days 12-Dec-23 26-Dec-23 0,0% 0,0% 0,0% 0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
7,3%
7,3%
7,3%
7,3%
7,3%
7,6%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
2,4%
2,4%
2,6%
2,6%
6,8%
6,8%
6,8%
4,8%
4,8%
0,8%
0,8%
0,8%
0,8%
0,8%
0,7%
0,8%
1,5%
1,5%
0,9%
0,9%
1,0%
1,0%
0,2%
0,2%
0,2%
0,2%
0,2%
0,1%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
100,0%
100,0%
100,0%
100,0%
100,0%
100,0%
100,0%
14,6%
21,9%
29,2%
36,5%
44,1%
44,5%
44,8%
45,1%
45,4%
45,8%
46,1%
46,4%
48,8%
51,2%
53,9%
56,5%
63,3%
70,2%
77,0%
81,8%
86,7%
87,4%
88,2%
89,0%
89,7%
90,5%
91,2%
92,0%
93,5%
95,1%
95,9%
96,8%
97,8%
98,7%
99,0%
99,2%
99,4%
99,6%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
7,3%
11,1%
Weekly Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,4%
4,8%

7,9%
3,6%
6,7%
3,6%
3,1%
0,0%
3,7%
1,2%
3,7%
1,6%
0,7%
1,5%
2,3%
18,3%
26,2%
29,8%
36,5%
40,1%
43,2%
43,2%
46,9%
48,1%
51,8%
53,4%
54,1%
55,6%
57,9%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,4%
7,2%

WORK LOCATION DATE

WORK PRORGESS DRY WASTE STORAGE YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS DRY WASTE STORAGE - TIE BEAM

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 109 Pcs 109 0 109 100%
Tie Beam

1 Lean Concrete 109 Pcs 109 0 109 100%


Concrete 109 Pcs 103 6 109 100%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS DRY WASTE STORAGE - CONCRETE COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Steel bar Form Work Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Steel Bar 24 Pcs 16 0 16 66,67%
Tie Beam

1 Forming 24 Pcs 16 0 16 66,67%


Concrete 24 Pcs 16 0 16 66,67%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS DRY WASTE STORAGE - CONCRETE GF SLAB

PROGRESS MONITORING PROGRESS PHOTO

Form Work Concrete


Until Last Until Last
this Week this Week
Week Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Lean Concrete 162 m2 126 36 162 100%
Slab

1 Steel Bar 162 m2 108 54 162 100%


Slab 162 m2 90 36 126 77,8%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS DRY WASTE STORAGE - CONCRETE RING BEAM

PROGRESS MONITORING PROGRESS PHOTO

Form Work Concrete


Until Last Until Last
this Week this Week
Week Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Ring Beam

Forming 24 Pcs 9 0 9 37,50%


1 Steel Bar 24 Pcs 9 0 9 37,50%
Concrete 24 Pcs 0 0 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - MOTORBIKE PARKING R.01 (May 11 th, 2023) Monitoring


Date:
13/06/2023 11.28

Work Item Duration Start Date Finish Date Weight Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Motorbike Parking + Rain Water Tank 17,479.44 m2 (Period 12 Months) 370 2-Feb-23 31-Jan-24

1
2
3
4
5
6
7
8
9
100,0%
100,0%
Steel Structure Shopdrawing Approval 29 2-Feb-23 3-Mar-23 0,0% 100,0%
99,3%
Steel Structure Fabrication & Delivery 119 4-Mar-23 1-Jul-23 0,0% 96,4%

Structure Shopdrawing Approval 14 2-Feb-23 16-Feb-23 0,0% 90,0%

Finishing Shopdrawing Approval 256 17-Feb-23 31-Oct-23 0,0% 88,3%

Pile Finish 0 16-Feb-23 16-Feb-23 0,0%


80,0%
Excavation Works 9 17-Feb-23 26-Feb-23 1,6% ## ##
Concrete Under Ground Slab 14 27-Feb-23 13-Mar-23 11,3% ## ## ## ## ## ##
Concrete Column & Wall 16 14-Mar-23 30-Mar-23 2,3% ## ##
70,0% 71,4%
Concrete Beam & Upper Slab 20 1-Apr-23 21-Apr-23 2,7% ## ## ##
Waterproofing 37 14-Apr-23 21-May-23 3,9% ## ## ## ## ##
Backfill & Compaction 10 21-May-23 31-May-23 60,0%
0,3% ## ## 60,6%

Foundation & Tie Beam Works 65 21-May-23 25-Jul-23 12,3% ## ## ## ## ##


Concrete Slab 1st Floor (8.099 m2) 75 7-Jun-23 21-Aug-23 5,2% ## ## ## ## ## ##
50,0%
Concrete Column 1st Floor (176 Pcs) 64 21-Jun-23 24-Aug-23 2,5% ## ## ## ##
Beam & Slab 2nd Floor (8.127 m2) 75 1-Jul-23 14-Sep-23 46,5%
19,6% ## ## ## ## ## ## ##
Ramp Works 35 3-Aug-23 7-Sep-23 0,7%
40,0%
## ## ## ## ## ##
Concrete Column 2nd Floor (176 Pcs) 62 21-Jul-23 21-Sep-23 1,1% Actual 28.5% ## ## ## 0
Ring Beam Works 63 1-Aug-23 3-Oct-23 2,6% ## ## ##
30,0%
31,2%
Steel Structure (312 Ton) 47 14-Sep-23 31-Oct-23 19,9% ## ## ## ## ## ## ## 0
Roofing, Flashing & Gutter Works (2.589 m2) 29 23-Oct-23 21-Nov-23 6,6% ## ## ## ## ##
24,4%
Downspout Works 47 7-Oct-23 23-Nov-23 20,0% Plan 27.4%
0,9% ## ## ##
19,3%
Handrail Works 52 1-Nov-23 23-Dec-23 3,3% ## ## ## ## ## ## ## ##
Stair Works 60 24-Oct-23 23-Dec-23 15,1%
0,8% ## ## ## ## ## ## ## ##
10,0%
Floor Finishing (Concrete Trowel Finish) 54 21-Nov-23 14-Jan-24 0,6% ## ## ## ## ## ## ## ##
Painting Works 86 24-Oct-23 18-Jan-24 1,8% ## ## ## ## ## ## ## ## ## ## ## ## ##
5,3%
Inspection 13 18-Jan-24 31-Jan-24 0,0% 0,0% 0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,7%
2,7%
1,9%
1,9%
3,0%
3,0%
0,9%
0,9%
1,7%
0,8%
0,8%
0,8%
0,8%
1,4%
1,4%
1,2%
1,7%
1,7%
2,0%
3,8%
3,8%
3,8%
3,9%
3,1%
3,1%
3,1%
2,6%
2,3%
2,3%
2,2%
3,2%
3,1%
3,1%
3,0%
3,0%
3,0%
4,8%
2,4%
2,4%
2,4%
0,8%
0,7%
0,7%
0,7%
0,7%
0,2%
0,2%
0,2%
0,0%
0,0%
0,0%
100,0%
100,0%
100,0%
100,0%
12,1%
15,1%
16,0%
16,9%
18,6%
19,3%
20,1%
20,9%
21,7%
23,0%
24,4%
25,6%
27,4%
29,1%
31,2%
35,0%
38,8%
42,6%
46,5%
49,6%
52,7%
55,8%
58,3%
60,6%
62,9%
65,1%
68,3%
71,4%
74,5%
77,5%
80,5%
83,4%
88,3%
90,7%
93,1%
95,5%
96,4%
97,1%
97,8%
98,6%
99,3%
99,5%
99,8%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
2,7%
5,3%
7,2%
9,1%

Weekly Progress Acctual


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,2%
1,0%
1,8%
4,9%
3,8%
2,6%
1,3%
2,0%
0,0%
1,0%
1,5%
1,9%
0,7%
1,7%
3,5%
0,7%
11,6%
14,2%
15,6%
17,5%
17,5%
18,5%
20,0%
21,9%
22,6%
24,3%
27,8%
28,5%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,2%
1,2%
2,9%
7,8%

WORK LOCATION DATE

WORK PRORGESS MOTORBIKE PARKING YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS MOTOR BIKE PARKING - FOUNDATION

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete

Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Excavation 2074 m2 2073,6 0,0 2073,6 100%
Found

Water
Rain

1 Lean Concrete 2074 m2 2073,6 0,0 2073,6 100%


Concrete 2074 m2 2073,6 0,0 2073,6 100%
Motor Bike

Excavation 208 pcs 157,0 0,0 157,0 75%


Found

1 Lean Concrete 208 pcs 157,0 0,0 157,0 75%


Concrete 208 pcs 157,0 0,0 157,0 75%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS MOTOR BIKE PARKING - FOUNDATION

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Motor Bike

Excavation pcs 0,0 423,0 57,63%


Tie Beam

734,0 423,0
1 Lean Concrete 734,0 pcs 423,0 0,0 423,0 57,63%
Concrete 734,0 pcs 384,0 39,0 423,0 57,63%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS MOTOR BIKE PARKING - COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Motor Bike

Steel Bar ### pcs 37,0 88,0 50,00%


Tie Beam

51,0
1 Forming ### pcs 51,0 37,0 88,0 50,00%
Concrete ### pcs 51,0 37,0 88,0 50,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - POWER STATION B R.01 (May 11 th, 2023) Monitoring


Date:
15/06/2023 10.54

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Power Station B 4,717.8 m2 (Period 10 Months) 313 2-Feb-23 21-Dec-23

1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 29 2-Feb-23 3-Mar-23 100,0%
0,0%
99,5% 99,9%
Steel Structure Fabrication & Delivery 89 4-Mar-23 1-Jun-23 0,0% 95,7%
90,0%
Structure Shopdrawing Approval 14 2-Feb-23 16-Feb-23 0,0% 89,6%
Finishing Shopdrawing Approval 196 17-Feb-23 1-Sep-23 0,0%
80,0%
Pile Finish 0 28-Feb-23 28-Feb-23 0,0%
Foundation & Tie Beam Works 99 28-Feb-23 7-Jun-23 25,4% 0 0 0 0 0
70,0%
Concrete Slab 1st Floor (1.422 m2) 28 3-Jul-23 31-Jul-23 6,2% 0 0 0 0 68,5%

Concrete Column 1st Floor (46 Pcs) 86 21-Mar-23 15-Jun-23 9,1% 60,0% 0 0 0
Beam & Slab 2nd Floor (1.569 m2) 43 21-May-23 3-Jul-23 10,0% 0 0 0 0 0 0
Concrete Column 2nd Floor (35 Pcs) 54 22-May-23 15-Jul-23 0,6% 50,0% Actual
0 041.0%
0
Ring Beam Works 54 14-Jun-23 7-Aug-23 14,9% 0 0 47,1%

Steel Structure (53 Ton) 31 21-Jul-23 21-Aug-23 40,0%


10,4% 0 ##
Roofing & Flashing Works (1.730 m2) 10 21-Aug-23 31-Aug-23 5,7% 0 0 0
30,0% Plan 38.6%
Gutter & Downspout Works 33 21-Aug-23 23-Sep-23 2,9% 31,2%
0 0
ALC Wall & Plaster Works (15.558 m2) 89 26-Jun-23 23-Sep-23 6,8% 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20,0%
Joinery Works 85 7-Aug-23 31-Oct-23 6,3% 0 0 0 0 0 0
18,3%
Floor Finishing (Concrete Polished) 92 3-Jul-23 3-Oct-23 0,3% 0 0 0 0 0 0
10,0%
Painting Works 108 21-Aug-23 7-Dec-23 1,5% 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8,0%

Inspection 20 1-Dec-23 21-Dec-23 0,0% 0,0% 0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,8%
1,8%
1,8%
2,6%
2,6%
2,6%
2,6%
2,6%
2,6%
2,6%
2,6%
2,6%
2,6%
4,6%
2,9%
4,2%
4,2%
6,2%
4,2%
4,2%
6,7%
5,2%
3,6%
3,6%
4,4%
4,4%
1,5%
1,5%
1,5%
1,5%
1,1%
1,0%
0,6%
0,6%
0,6%
0,1%
0,1%
0,1%
0,1%
0,1%
0,0%
0,0%
0,0%
100,0%
100,0%
100,0%
100,0%
10,6%
13,2%
15,8%
18,3%
20,9%
23,5%
26,1%
28,7%
31,2%
35,8%
38,6%
42,9%
47,1%
53,3%
57,5%
61,8%
68,5%
73,7%
77,3%
80,8%
85,2%
89,6%
91,1%
92,6%
94,2%
95,7%
96,7%
97,8%
98,4%
98,9%
99,5%
99,6%
99,7%
99,8%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,8%
3,6%
5,5%
8,0%

Weekly Progress Acctual


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,1%
5,6%
3,1%
3,5%
5,7%
1,5%
0,8%
0,0%
0,6%
2,0%
3,7%
2,9%
2,9%
4,4%
4,1%
12,3%
18,0%
19,5%
20,3%
20,3%
21,0%
23,0%
26,7%
29,6%
32,4%
36,8%
41,0%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,1%
5,7%
8,7%

WORK LOCATION DATE

WORK PRORGESS POWER STATION B YIH QUAN PROJECT Tuesday, 13 June 2023
WORK EXECUTED IN THIS WEEK
PROGRESS POWER STATION B - GF CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete

Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete 1391 m2 1391,2 0 1391,2 100%
SLAB

1 Rebar 1391 m2 0 0 0 0,00%


Concrete 1391 m2 0 0 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS POWER STATION B - 1st FLOOR COLUMN

PROGRESS MONITORING PROGRESS PHOTO

Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Colum

Steel Bar 35 Pts 28 7 35 100,00%


1F

1
n

Concrete 35 Pts 18 17 35 100,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS POWER STATION B - 2F CONCRETE SLAB

PROGRESS MONITORING PROGRESS PHOTO

Form work Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
SL 2FL

Forming 1391 Pts 400 237 636,4 45,74%


1
Concrete 1391 Pts 0 - 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - LIQUID CHEMICAL R.01 (May 11 th, 2023) Monitoring Date: 15/06/2023 11.04

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Liquid Chemical Storage 3,207.09 m2 (Period 10 Months) 317 1-Mar-23 11-Jan-24

1
2
3
4
5
6
7
8
9
100,0%
Steel Structure Shopdrawing Approval 30 1-Mar-23 30-Mar-23 0,0% 100,0%
99,3% 100,0%
Steel Structure Fabrication & Delivery 45 31-Mar-23 14-May-23 0,0% 97,0%

Structure Shopdrawing Approval 15 1-Mar-23 15-Mar-23 0,0%


90,0% 92,5%

Finishing Shopdrawing Approval 175 16-Mar-23 6-Sep-23 0,0%


Pile Finish 0 15-Mar-23 15-Mar-23 80,0%
0,0%
Foundation & Tie Beam Works 95 16-Mar-23 18-Jun-23 14,2% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 76,6%

70,0%
Concrete Slab 1st Floor (1.561 m2) 66 5-May-23 9-Jul-23 9,2% 0 0 0 0 0 0 0 0 0 0
Concrete Column 1st Floor (28 Pcs) 59 28-May-23 25-Jul-23 4,9% 0 0 0 0 0 0 0 0 0
60,0%
Beam & Slab 2nd Floor (1.716 m2) 57 12-Jun-23 7-Aug-23 26,9% 0 0 0 0 0 0 0 0 0
Concrete Column 2nd Floor (28 Pcs) 52 1-Jul-23 21-Aug-23 56,7%
1,0% 0 0 0 0 0 0 0 0
50,0%
Ring Beam Works 51 16-Jul-23 4-Sep-23 3,3% 0 0 0 0 0 0 0 0
Steel Structure (54 Ton) 22 28-Aug-23 18-Sep-23 12,4% 0 0 0 0
40,0%
Roofing, Flashing & Gutter Works (1.836 m2) 20 8-Sep-23 27-Sep-23 8,0% 0 0 0
38,9%
Actual 24.8%
Downspout Works 42 21-Aug-23 1-Oct-23 2,5% 0 0 0 0 0 0
30,0%
ALC Wall & Plaster Works (13.312 m2) 106 9-Jul-23 22-Oct-23 6,5% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Joinery Works 108 1-Aug-23 16-Nov-23 4,1% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20,0%
Ceiling Gypsum Works 123 1-Aug-23 1-Dec-23 4,0% 18,8% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11,9% Plan 24.5%
Floor Finishing (Concrete Trowel Finish & Ceramic Tile) 50 2-Nov-23 21-Dec-23 2,1% 0 0 0 0 0 0 0 0
10,0%
Painting Works 86 3-Oct-23 27-Dec-23 10,0%
0,9% 8,0% 0 0 0 0 0 0 0 0 0 0 0 0 0
Inspection 15 28-Dec-23 11-Jan-24 0,0% 0,0% 0,0% 3,0%
0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,0%
1,0%
1,0%
1,0%
1,0%
1,0%
1,9%
1,9%
1,9%
1,9%
2,5%
2,5%
5,5%
5,5%
4,6%
4,6%
4,5%
4,5%
4,5%
4,4%
4,4%
1,4%
4,8%
4,8%
4,4%
7,1%
4,0%
4,0%
1,0%
1,0%
1,0%
1,0%
0,8%
0,8%
0,8%
0,6%
0,6%
0,3%
0,3%
0,3%
100,0% 0,1%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
100,0% 0,0%
10,0%
11,9%
13,8%
16,3%
18,8%
24,3%
29,7%
34,3%
38,9%
43,4%
47,8%
52,3%
56,7%
61,1%
62,5%
67,3%
72,2%
76,6%
83,6%
87,6%
91,6%
92,5%
93,5%
94,4%
95,4%
96,2%
97,0%
97,8%
98,4%
98,9%
99,3%
99,6%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,0%
2,0%
3,0%
4,1%
5,1%
6,1%
8,0%
Weekly Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,2%
3,0%
1,4%
3,6%
1,3%
0,0%
0,5%
0,9%
0,7%
2,4%
3,1%
3,6%
3,2%
10,5%
10,5%
11,0%
11,9%
12,6%
14,9%
18,0%
21,6%
24,8%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,2%
4,2%
5,6%
9,2%

WORK LOCATION DATE

LIQUID CHEMICAL STORAGE YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS LIQUID CHEMICAL STORAGE - FOUNDATION

PROGRESS MONITORING PROGRESS PHOTO

Excavation Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Excavation 28 Pts 28 0 28 100%
Pile Cap

1 Lean Concrete 28 Pts 28 0 28 100%


Concrete 28 Pts 28 0 28 100%
Excavation m' 1062,4 0 1062,4 100%
Tie Beam

1062
2 Lean Concrete 1062 m' 1062 0 1062,4 100%
Concrete 1062 m' 747,8 314,6 1062,4 100%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS LIQUID CHEMICAL STORAGE - GF SLAB CONCRETE

PROGRESS MONITORING PROGRESS PHOTO

Lean Concrete Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Lean Concrete ### m2 986 0 986 66,60%
Slab

1
Concrete ### m2 0 0 0 0,00%

PT. TAKENAKA INDONESIA


NEW FACTORY BUILDING PHASE 1
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS LIQUID CHEMICAL STORAGE - GF COLUMN CONCRETE

PROGRESS MONITORING PROGRESS PHOTO

Steel bar Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Rebar 28 Pcs 8 11 19 67,86%
CL

1
Concrete 28 Pcs 0 10 10 35,71%

PT. TAKENAKA INDONESIA


NEW FACTORY BUILDING PHASE 1
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A


PROGRESS MONITORING - MOSQUE R.01 (May 11 th, 2023) Monitoring Date: 13/06/2023 10.21

Work Item Duration Start Date Finish Date Weight Schedule Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Mosque & Clean Water Tank 2,570.2 m2 (Period 10 Months) 315 days 23-Feb-23 3-Jan-24

1
2
3
4
5
6
7
8
9
100%
100,0%
Steel Structure Shopdrawing Approval 29 days 23-Feb-23 24-Mar-23 0,0%
Steel Structure Fabrication & Delivery 89 days 25-Mar-23 22-Jun-23 0,0%
Structure Shopdrawing Approval 14 days 23-Feb-23 9-Mar-23 0,0%
90,0%
Finishing Shopdrawing Approval 189 days 10-Mar-23 15-Sep-23 0,0%
Pile Finish 0 days 9-Mar-23 9-Mar-23 0,0%
Open-Cut Works 17 days 10-Mar-23 27-Mar-23 3,2% 0 0 ###
80,0%
Concrete Under Ground Slab 38 days 28-Mar-23 4-May-23 3,4% 0 0 0 0 0 0
Concrete Column & Wall 27 days 5-May-23 31-May-23 8,8% 0 0 0 0
Concrete Beam & Upper Slab 30 days 1-Jun-23 30-Jun-23 0,9% 0 0 0 0 0
70,0%

Waterproofing 21 days 1-Jul-23 21-Jul-23 3,7% 0 0 0


Backfill & Compaction 14 days 7-Jun-23 20-Jun-23 8,6% 0 0
Foundation & Tie Beam Works 18 days 21-Jun-23 8-Jul-23 9,6% 60,0% 0 0 0
Concrete Slab 1st Floor (1.209 m2) 23 days 30-Jun-23 22-Jul-23 7,3% 0 0 0 0
Concrete Column 1st Floor (40 Pcs) 32 days 7-Jul-23 7-Aug-23 3,0% 0 0 0 0 0
Beam & Slab 2nd Floor (1.129 m2) 39 days 14-Jul-23 21-Aug-23 50,0%
7,7% 0 0 0 0 0 0
Concrete Column 2nd Floor (40 Pcs) 23 days 1-Aug-23 23-Aug-23 0,4% 0 0 0 0
Beam & Concrete Roof Slab (599 m2) 28 days 4-Aug-23 31-Aug-23 6,3% 0 0 0 0
40,0%
Waterproofing & Cynder Concrete 17 days 20-Sep-23 6-Oct-23 2,2% 0 0 0
Steel Structure (12 Ton) 16 days 28-Aug-23 12-Sep-23 3,5% 0 0 0
Roofing, Flashing & Gutter Works (355 m2) 20 days 12-Sep-23 1-Oct-23 4,4% 0 0 0
30,0%
Downspout Works 40 days 27-Aug-23 5-Oct-23 0,7% Plan 0 0 0 0 0 0
ALC Wall, Plaster & Louver Block Works 90 days 30-Jul-23 27-Oct-23 9,8% 21.6% 0 0 0 0 0 0 0 0 0 0 0 0 0
Joinery Works 63 days 13-Sep-23 14-Nov-23 1,9% 0 0 0 0 0 0 0 0 0
20,0%
Ceiling Gypsum Works 57 days 28-Sep-23 23-Nov-23 0,7% 0 0 0 0 0 0 0 0 0
Floor Finishing (Ceramic Tile) 53 days 13-Oct-23 4-Dec-23 10,1% Actual 0 0 0 0 0 0 0 0
Toilet Works 147 days 23-Jun-23 16-Nov-23 0,4% 10,0%
20.1%
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Stair Works 97 days 19-Aug-23 23-Nov-23 2,2% 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Painting Works 69 days 12-Oct-23 19-Dec-23 1,2% 0 0 0 0 0 0 0 0 0 0
Inspection 15 days 20-Dec-23 3-Jan-24 0,0% 0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,1%
1,1%
1,6%
0,6%
0,6%
0,6%
0,6%
2,3%
1,8%
1,8%
1,8%
1,9%
3,0%
3,0%
3,0%
6,1%
7,1%
7,8%
5,4%
8,4%
6,0%
3,5%
1,6%
2,7%
2,5%
2,5%
2,9%
2,9%
1,8%
0,7%
1,9%
1,9%
1,6%
1,6%
1,6%
1,6%
1,5%
1,3%
0,1%
0,1%
100,0% 0,1%
100,0% 0,0%
10,1%
11,8%
13,6%
15,5%
18,5%
21,6%
24,6%
30,7%
37,8%
45,7%
51,1%
59,5%
65,4%
69,0%
70,6%
73,2%
75,8%
78,3%
81,2%
84,2%
85,9%
86,6%
88,5%
90,4%
92,0%
93,7%
95,3%
96,9%
98,4%
99,8%
99,8%
99,9%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
1,1%
2,1%
3,7%
4,3%
4,9%
5,4%
6,0%
8,3%

Weekly Progress Acctual


0,0%
0,0%
0,8%
1,4%
2,7%
2,2%
2,8%
0,0%
0,4%
1,6%
1,5%
2,3%
1,7%
1,6%
1,3%
10,3%
11,9%
13,4%
15,7%
17,3%
18,9%
20,1%
Accumulative Progress Actual
0,0%
0,0%
0,8%
2,1%
4,8%
7,0%
9,9%
9,9%

WORK LOCATION DATE

WORK PRORGESS MOSQUE YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS MOSQUE - CLEAN WATERTANK UPPER SLAB

PROGRESS MONITORING PROGRESS PHOTO

Form Work Concrete


Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week Accum.
Form 696 m2 336 168 504 72%
Upper
Slab

1
Concrete 696 m2 0 0 0 0%

PT. TAKENAKA INDONESIA


NEW FACTORY BUILDING PHASE 1
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
Doc.No.: ID-ISO/F-122-PR/4 of 7.Rev.00

CIVIL CONSTRUCTION PROGRESS OUTLINE A

PROGRESS MONITORING - EXTERNAL R.01 (May 11 th, 2023) Monitoring 13/06/2023 16.39

Weigh Schedul
Work Item Duration Start Date Finish Date Jan-23 Feb-23 Mar-23 Apr-23 Mei-23 Jun-23 Jul-23 Agu-23 Sep-23 Okt-23 Nov-23 Des-23 Jan-24 Feb-24 Mar-24
t e

Des-22

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
External Works 427 days 16-Jan-23 17-Mar-24

1
2
3
4
5
6
7
8
9
100,0%

Permanent Road (Base Course) for Temporary Access 125 days 16-Jan-23 20-May-23 100,00% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0,8%

Guard House, Main Gate,Bridge,Tower,Sub Gate,Sub Bridge261 days 21-May-23 5-Feb-24 90,00% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5,6%

Utility Trench 207 days 15-Jun-23 7-Jan-24 80,00%


0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13,2%

Waste Water System 120 days 15-Jul-23 11-Nov-23 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


1,1% 70,00%

Rain Water Cycling 187 days 9-Jun-23 12-Dec-23 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


7,3% 60,00%

Fountain Water 125 days 15-Aug-23 17-Dec-23 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


0,6%
50,00%

Drainage Works 249 days 18-May-23 21-Jan-24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


8,9%
40,00%
Road Pavement 211 days 1-Jul-23 27-Jan-24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
42,2%
30,00%
Fence 217 days 21-May-23 23-Dec-23 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8,2%
20,00%
Retaining Wall 124 days 1-Mar-23 2-Jul-23 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4,8% Plan 8.0%

Landscape 90 days 13-Dec-23 11-Mar-24 10,00% 0 0 0 0 0 0 0 0 0 0 0 0 0


7,4%
Actual 3.9%
Inspection 15 days 3-Mar-24 17-Mar-24 0,00%
0,0%

Weekly Progress Plan


0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,3%
0,9%
0,9%
0,9%
1,2%
1,6%
3,0%
2,7%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
2,8%
3,3%
3,0%
2,8%
2,8%
2,8%
2,3%
2,3%
0,7%
0,7%
0,6%
0,6%
0,6%
0,6%
0,0%
0,0%
0,0%
100,0%
100,0%
100,0%
100,0%
12,6%
15,3%
18,1%
20,9%
23,7%
26,5%
29,3%
32,1%
34,9%
37,7%
40,6%
43,4%
46,2%
49,0%
51,8%
54,7%
57,5%
60,3%
63,1%
66,0%
68,7%
71,5%
74,2%
77,0%
80,3%
83,4%
86,1%
88,9%
91,6%
94,0%
96,3%
97,0%
97,7%
98,3%
98,9%
99,4%
Accumulative Progress Plan
0,0%
0,0%
0,0%
0,1%
0,1%
0,2%
0,2%
0,3%
0,6%
0,9%
1,2%
1,5%
1,8%
2,1%
2,5%
2,8%
3,1%
3,4%
3,7%
4,0%
4,9%
5,9%
6,8%
8,0%
9,6%
Weekly Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,1%
0,1%
0,1%
0,1%
0,1%
0,7%
0,3%
0,0%
0,3%
0,2%
0,2%
0,6%
0,6%
0,1%
0,3%
Accumulative Progress Actual
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,0%
0,1%
0,2%
0,3%
0,4%
0,5%
1,2%
1,6%
1,6%
1,8%
2,1%
2,2%
2,8%
3,4%
3,6%
3,9%
WORK LOCATION DATE

WORK PRORGESS EXTERNAL YIH QUAN PROJECT Tuesday, 13 June 2023


WORK EXECUTED IN THIS WEEK
PROGRESS EXTERNAL - RETAINING WALL

PROGRESS MONITORING CONCRETE PROGRESS PHOTO

Excavation Lean Concrete Retaining Wall

Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 612,3 m 528,627 0 528,627 86,33%
Retaining Wall

Lean Concrete 89,84 m3 28,75 0 28,75 32,00%


1 Type A 1570 m3 1089,24 0 1089,24 69,37%
Type B 755,7 m3 717,915 0 717,915 95,00%
Type C 89,84 m3 16 0 16 2,12%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
WORK EXECUTED IN THIS WEEK
PROGRESS EXTERNAL - RETAINING WALL

PROGRESS MONITORING CONCRETE PROGRESS PHOTO

Excavation Foundation Column Tie Beam

Until Last Week this Week Until Last Week this Week Until Last Week this Week Until Last Week this Week

Progress
No. Item Qty Unit %
Last Week This Week accum.
Excavation 735 Pcs 77 77 10,48%
Fence

Foundation 735 Pcs 46 46 6,26%


1
Column 735 Pcs 0 0 0,00%
Tie Beam 733 Pcs 0 0 0,00%

NEW FACTORY BUILDING PHASE 1


PT. TAKENAKA INDONESIA
PLANNERS, ARCHITECTS, ENGINEERS AND CONTRACTORS
PT. YIH QUAN FOOTWEAR INDONESIA
MANPOWER REPORT
Project : YIH QUAN FOOTWEAR INDONESIA
JUNE 2023 Total
Manpower Day Up To
This
Last Accum.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Month
Month

1 TAKENAKA STAFF
1,1 Project Manager 2 1 3 4 2 4 4 4 3 2 2 4 35 364 399
1,2 Chief Engineer 3 2 5 5 2 5 5 5 3 3 2 5 45 537 582
1,3 Civil Engineer & Ass. 16 17 22 23 17 23 23 23 17 17 17 23 238 2076 2314
1,4 M&E Engineer 0 0 0
1,5 Administration 3 3 4 4 3 4 4 4 3 3 2 4 41 317 358
1,6 Drafter 6 6 6 6 6 7 7 7 4 4 2 7 68 541 609
1,7 Logistic 3 3 3 3 3 3 3 3 3 3 2 3 35 365 400
1,8 Mechanic 4 4 4 4 4 4 4 4 4 3 3 4 46 493 539
1,9 Safety Officer 4 4 4 4 3 4 4 4 3 3 2 4 43 418 461
1,10 Operator (Heavy Equipment) 0 0 0
1,11 Surveyor + Assistant 4 5 5 5 3 5 5 5 4 4 3 5 53 949 1002
0 0 0
0 0 0 0
2 SUBCONTRACTORS 0 0 0
2,1 Civil Works 0 0 0
2,1 SBP (Soil Work) 37 40 34 23 34 28 34 34 34 34 9 18 359 1883 2242
2,2 Adicon (Fence) 7 6 6 6 6 7 7 7 7 7 7 7 80 435 515
2,3 Putri Tunggal (Daily) 72 52 43 53 50 40 43 46 46 40 40 43 568 2834 3402
2,4 PT. Palam Arta 16 18 16 10 18 18 18 18 18 18 18 17 203 268 471
2,5 PT. GKP (Forming) 122 140 147 198 206 197 192 201 204 200 129 191 2127 1122 3249
2,6 Indokaryatama (cutting pile) 33 32 32 26 32 32 32 31 31 32 29 32 374 26 400
2,7 Aris Wiyatama (Scaffolding) 36 33 37 13 34 38 40 41 39 40 23 39 413 0 413
2,8 Indofab (Steelbar) 265 250 264 239 256 262 259 266 261 139 166 234 2861 1351 4212
2,9 Anisa Jaya Hasanah (Cor) 7 7 7 5 7 7 7 7 7 7 5 7 80 2071 2151
2,10 Mahesa 30 38 48 52 48 53 54 56 61 54 42 50 586 1267 1853
2,11 PT. Intra 15 15 15 15 15 15 15 15 15 15 15 15 180 3577 3757
2,12 Keshun 3 3 3 3 3 0 0 0 0 0 0 0 15 1464 1479
2,13 Dwi Lestari 32 34 36 36 33 35 33 35 32 34 35 34 409 722 1131
0 3938 3938
0 287 287
0 316 316
0
TOTAL 720 713 744 737 785 791 793 816 799 662 553 746 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8859 27305 36164
WEATHER LIST
JUNE 2023
Project : YIH QUAN FOOTWEAR INDONESIA Doc.No.: IMS/F-122-PR/7 of 7.Rev.00
12 12 12 12 12 12 12
12

9 1 3 9 2 3 9 3 3 9 4 3 9 5 3 9 6 3 9 7 3 9 8 3

6 6 6 6 6 6 6 6
12 12
12 12 12 12 12 12

9
9 9 3 10
3
9 11 3 9 12 3 9 13 3 9 14 3 9 15 3 9 16 3

6 6 6 6 6 6 6
6
12 12 12 12 12 12
121 12

9
17
17 3 9 18 3 9 19 3 9 20 3 9 21 3 9 22 3 9 23 3 9 24 3

6 6 6 6 6 6 6
6
12 12 12 12 12 12 Remark :
12
AM
1 PM

9 25 3 9 26 3 9 27 3 9 28 3 9 29 3 9 30 3 9 31 3 Date

Rainy
Drizzle
6 6 6 6 6 6 6 Shinny
IMPORTANT NOTES
Description Remark

Takenaka Information:
1 Progress of CSA work
- Plan : 37.2% Actual : 37.2% (On Schedule)

2 Takenaka have received Site Instruction regarding Steel Structure Design change
that caused by Utility bridge for Dry Waste (June 13th, 2023), but not recieve for WWTP

3 Wika trial mix sample failed to fulfill targeted strenght on compressive strenght test
for 14 days.

4 Takenaka is preparing mock up for road pavement base.

5 Takenaka need decision from Wahana and The Owner Regarding color scheme and
material type for Homogenous and Ceramic tile due to ordering process need to start soon
and production process from material maker may takes time.

6 Takenaka has submited the invoice of first progress payment, please confirm
when the payment of PT. Yih Quan will be released.

7 Regarding SLF, Takenaka have received list of data to be prepared, but some detail
need to be clarified.

8 Information status of VO, Currently we have 25 item with status as follows:


- Construction 100% = 13 item
- On going = 4 item
- Hold= 4 item
- Still open = 6 Item

9 Information status of preboring work at linking corridor A1-A2


June 15th, 2023 = Quotation Approval
June 16th, 2023 = Preparation drill from Jakarta
June 17th~18th, 2023 = Delivery to batang
June 19th, 2023 = Machinery setting and inspection
June 20th, 2023 = Start preboring

10 Takenaka need information when pile material at supplier workshop can be delivered.