Professional negligence — Duty of care - Management contract — Respective
obligations of designer, contractor and supervisor — Buildability - Scope of
duty of supervision.
Department of National Heritage v
Steensen Varming Mulcahy (a firm)
(Balfour Beatty Ltd and another,
third parties)
QUEEN’S BENCH DIVISION (OFFICIAL REFEREES’ BUSINESS)
HIS HONOUR JUDGE PETER BOWSHER QC
26-29 JANUARY, 2-5, 9-12, 16-19, 23-27 FEBRUARY, 2-5, 9-12, 16-19, 23-26, 30, 31 MARCH, 1, 2, 6—
8, 22, 23, 27-30 APRIL, 5-7, 11, 12, 14, 18-21 MAY, 10, 15-18, 22-25, 29, 30 JUNE, 1, 2, 6-9, 13-16, 20-
23, 28, 30 JULY 1998
0. Analysis of liability for design and for supervision.
The plaintiffs (Heritage) were an emanation of the Crown responsible for the
erection of the British Library. They were one of many bodies which had in
succession been so responsible. The defendants, Steensen Varming Mulcahy
(SVM) were mechanical and electrical consulting engineers for the Library
project. The plaintiffs sued the defendants in contract and tort alleging
professional negligence. The defendants joined as third parties Balfour Beatty
Ltd (BB), the electrical contractors for the project and Laing Management Ltd
(LM), engaged as management contractors for the project. The plaintiffs and
the third parties joined forces and were jointly represented. The plaintiffs’
claim was limited to £8.4m which was the sum paid out by the insurers, who
were the effective plaintiffs.
The claim arose out of very extensive damage to the low voltage cabling
installed by BB. BB replaced some of the cabling at their own cost but from
1993 were alleging that the damage was due to design faults for which they
were not responsible. SVM said that the defects were due to bad workmanship
on the part of BB and bad supervision and lack of co-ordination by both LM
and Heritage.
The contract was on a form of construction management. The Crown
entered directly into separate contracts with the designers, construction
manager and the works contractors and the construction manager (LM) was
engaged to manage the works contractors on behalf of the Crown.
Held: (1) SVM’s express design obligations were set out in the contract under
seal dated 15 June 1984. Contrary to the plaintiffs’ arguments, these did not
forbid lid-down trunking which was recognised by the contract as a possible34 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
though not the preferred option. SVM preferred to avoid a mixture of lid-up
and lid-down trunking because this would produce difficulties at the joins.
This choice was obvious to all and no one suggested that lid-down trunking
was forbidden until years later.
(2) SVM were under an express duty to exercise all reasonable skill, care
and diligence. They were under the same duty at common law. This included
a duty to design the work so that it could be built ‘by those likely to be
employed to do it’. BB’s contractual obligation of which they were frequently
in breach was to use ‘directly employed qualified staff? and their contract
further required ‘a high standard of workmanship and finish’ and the bringing
to the attention of LM of any departures in the drawings or specification from
accepted good practice. In the light of these considerations SVM were not in
breach by designing a lid-down system.
(3) SVM did have supervisory duties but in the context of the contract, they
were limited so far as cable damage was concerned to detecting cable damage
after it had occurred and requiring it to be put right. The duty did not extend
to preventing BB doing bad work.
(4) The argument of the plaintiffs that it was inherently unlikely that an
experienced contractor’s workforce would have installed in excess of 3,000
kilometres of cable incorrectly and that therefore there must have been defects
of design was not established. In breach of contract BB did not always use
directly employed staff and not enough supervisors were employed by them.
There was widespread bad workmanship by BB.
Accordingly, there should be judgment for the defendants.
Cases referred to in judgment
Adcock’s Trustee v Bridge RDC (1911) 75 JP 241.
Bolam v Friern Hospital Management Committee [1957] 2 All ER 118,
[1957] 1 WLR 582.
Bonnington Castings Lid v Wardlaw [1956] 1 All ER 615, [1956] AC 613,
[1956] 2 WLR 707, HL.
Brickfield Properties Ltd v Newton, Rosebell Holdings Ltd v Newton [1971]
3 All ER 328, [1971] 1 WLR 862, CA.
British Westinghouse Electric and Manufacturing Co Ltd v Underground
Electric Rlys Co of London Ltd [1912] AC 673, [1911-13] All ER Rep 63,
HL.
Caparo Industries ple v Dickman [1990] BCLC 273, [1990] 1 All ER 568,
{1990] 2 AC 605, [1990] 2 WLR 368, HL.
Chelmsford DC v T J Evers (1984) 25 BLR 99.
Corfield v Grant (1992) 29 ConLR 58.
East Ham BC v Bernard Sunley & Sons Ltd [1965] 3 All ER 619, [1966] AC
406, [1965] 3 WLR 1096, HL.
Elliott Steam Tug Co v Shipping Controller [1922] 1 KB 127.
Equitable Debenture Assets Corp Ltd v William Moss Group Ltd (1984) 2
ConLR 1.
Hutchison v Harris (1978) 10 BLR 19, CA.
Jameson v Simon 1899 1 F (Ct of Sess) 1211.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 35
Livingstone v Rawyards Coal Co (1880) 5 App Cas 25.
McGhee v National Coal Board [1972] 3 All ER 1008, [1973] 1 WLR 1, HL.
Merton London Borough v Lowe (1979) 18 BLR 130, CA.
Nye Saunders and Partners (a firm) v Alan E Bristow (1987) 37 BLR 92, CA.
Robinson v Harman (1848) 1 Exch 850, [1843-60] All ER Rep 383.
South Australia Asset Management Corp v York Montague Ltd, United Bank
of Kuwait plc v Prudential Property Services Ltd, NyKredit Mortgage Bank
ple v Edward Erdman Group Lid [1996] 3 All ER 365, [1997] AC 191,
[1996] 3 WLR 87, HL, rusg sub nom Banque Bruxelles Lambert SA v Eagle
Star Insurance Co Ltd {1995] 2 All ER 769, [1995] QB 375, [1995] 2 WLR
607, CA.
Sutcliffe v Chippendale & Edmundson (1971) 18 BLR 149.
University of Glasgow v Whitfield John Laing Construction Ltd (1988) 19
ConLR 111.
Victoria University of Manchester v Hugh Wilson and Lewis Womersley (a
firm) (1984) 2 ConLR 43.
Yorkshire Dale Steamship'Co Ltd v Minister of War Transport [1942] 2 All
ER 6, [1942] AC 691, HL.
Jobn Slater QC, Peter Hamilton and Simon Henderson (instructed by
Bannisters) for the plaintiffs and the first and second third parties.
Philip Vallance QC, David Evans and John Whitting (instructed by
Berrymans Lace Mawer) for the defendants.
INDEX TO JUDGMENT
CONCLUSION 36
INTRODUCTION 37
ABBREVIATIONS 37
‘THE PARTIES 37
‘THE CLAIMS 38
THE ISSUES 40
OTHER BODIES AND INDIVIDUALS PRINCIPALLY INVOLVED 40
DESCRIPTION OF SITE a2
GENERAL HISTORY OF THE PROJECT 43
DESCRIPTION OF THE ELECTRICAL INSTALLATION 7
THE CONTRACTS 50
Construction management 50
LM’s contract 50
BB's contract 62
SVM’s contract 70
CONSTRUCTION OF THE CONTRACTS AND COMMON LAW DUTIES 80
SVM’s express design obligations under its contract 82
SVM’s duty to exercise all reasonable skill and care 84
SVM’s duty to keep design under review 89
Co-ordinated and comprehensive drawings 90
Selection and approval of equipment and materials 91
SVM’s duty to supervise and inspect 9436 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
BREACHES 99
Was there breach by SVM, BB or LM? 99
The evidence called on behalf of SVM 99
Cause in law 101
Cause in fact 104
‘THE PLAINTIFFS’ GENERAL CASE 110
THE NATURE OF THE DAMAGE TO CABLES 412
DEFECTIVE MATERIALS AND BAD WORKMANSHIP 113
Pulling cables 119
BB’s case on pulling cables and friction burns 123
CRITICISMS OF DESIGN 126
Lid-down trunking 126
Trunking overloaded with cables 131
Routes of cables — long cables — complex trunking 139
Failure to co-ordinate design and late design changes 142
Failure to review the design 144
CRITICISMS OF SUPERVISION 144
CONTRIBUTORY NEGLIGENCE AND CONTRIBUTION 155
DAMAGES 155
Damages - remedial works 156
LM and agency staff costs 163
Consultant staff 164
APPENDIX A 170
HIS HONOUR JUDGE PETER BOWSHER QC.
CONCLUSION
For the following reasons given in this judgment, | find that the plaintiffs
have proved no liability on the part of the defendants. I also find the first
third party primarily to blame for the damage complained of in this action
and the second third party and the plaintiffs secondarily to blame. Since the
plaintiffs have made common cause with the third parties, | accept the
invitation of their counsel to treat them as one and I give judgment for the
defendants against the plaintiffs and the third parties. I also order that the
defendants’ costs be paid by the insurers of the plaintiffs and both third
parties jointly, such costs to be taxed if not agreed.
The taxation of costs is to be on the standard basis save that the costs of
Messrs Thain, Ulyatt and Mullis relating to quantum incurred before trial are
to be taxed on an indemnity basis.
If there should be a taxation of costs of this action, I invite the attention of
the taxing master to the enormous assistance given to me by leading and
junior counsel for all parties by their work both in and out of court. Their
oral submissions have been supported by most helpful written submissions
and schedules with detailed references to the evidence which have been of
enormous assistance to me. I am also grateful to the parties for having
provided me with the assistance of a computerised transcript by Livenote.
Without all that help, both from counsel and the shorthand writers, the trial60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 37
of this action would have taken very much longer, and would not have
concluded, as it did, before the formal opening of the Library.
All concerned should be congratulated in preparing this action for trial in
what was for them a very busy period of two years between the issue of the
writ in January 1996 and the commencement of trial in January 1998.
INTRODUCTION
1. By this action a claim is made limited to £8,437,446 plus interest for
damages arising out of alleged breaches of duty in the construction of the
new British Library in London. The delays and rising costs of that project
have been the subject of much public comment which has centred mainly
upon difficulties with mechanically operated shelving in the basement
storage areas and electric cabling. This case has been primarily concerned
with electric cabling.
2. This action is in reality brought by insurers. Normally, that is not a
matter which concerns the court, but in this case it is a matter to be taken
into account particularly because one of the issues is whether certain
payments originating with insurers were in correct legal analysis to be
regarded as discharging obligations of the plaintiff. The claim is limited to
£8.4m because that is the cost to the insurers. From the point of view of the
taxpayer reading this judgment, the involvement of insurers is relevant
because it is important that the taxpayer should appreciate that nothing
decided in this judgment immediately affects the financial position of the
Crown.
3. In view of the notoriety of the British Library construction project, it is
also important that I should stress that, despite the length of this trial, I have
not been conducting a general inquisitorial inquiry into the causes and effects
of delays in that construction project. My task is the limited task of deciding
whether certain insurers are entitled, on the evidence put before me, to
recover from the defendants £8.4m expended by those insurers, and if so,
whether the defendants have rights of recourse over against two of the many
other companies involved in the project. I stress the words, ‘on the evidence
put before me’, because I do not have inquisitorial powers and the evidence
put before me is not complete even in relation to those issues which I have to
decide. I have not, for example, had the benefit of hearing evidence from Mr
Dusan Marcovic, the former partner in the defendant company responsible
as consultant mechanical and electrical engineer for the project during a vital
period from about 1988 to November 1992. Moreover, the evidence
adduced to prove the amount of the claim is incomplete and unsatisfactory.
ABBREVIATIONS
4. A list of abbreviations used in this judgment is attached to this judgment
as App A.
THE PARTIES
5. This action is brought by insurers by subrogation in the name of the
Department of National Heritage, now renamed the Department of Culture
Media and Sport. Many bodies have been concerned with the interest of the38 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
new British Library. When considering the legal effect of what has been done
by and on behalf of the various bodies, it is important to bear in mind that
the plaintiff is the Crown suing in the name of the Department of National
Heritage (DNH): see the Crown Proceedings Act 1947, s 13. DNH is not to
be regarded as if it were a corporation in its own right: it is a manifestation
of the Crown. In the history of the British Library project the Crown also
appears in other manifestations and as acting through various agents. DNH
itself took over responsibilities from the Department of the Environment
upon the creation of DNH in 1992.
6. Although this is an insurance claim, the reputations, professional and
business, of distinguished individuals and bodies are at stake.
7. The defendants, Steensen Varming Mulcahy (SVM), were appointed
mechanical and electrical consulting engineers for the British Library project.
They are sued for alleged professional negligence in breach of contract and
at common law. The defendants are sued as a firm. There were two partners,
Mr Michael Carver and Mr Dusan Marcovic. Since 1992, the practice has
continued through limited liability companies. Until recently, Mr Carver was
managing director of SVM plc, a holding company for SVM Partnership Ltd
and other group companies. Those companies are not concerned with this
action.
8. The defendants in turn joined third parties. The first third party, Balfour
Beatty Ltd (BB), is part of a group which is probably the largest electrical
contracting group in the world. BB were engaged to install (among other
things) the cabling and trunking the subject of this action. Other companies
in the Balfour Group were involved in doing the work and in the remedial
work. It is agreed that no distinction between one Balfour company and
another is relevant for the purposes of this action, and for simplicity I shall
refer to any Balfour company involved as BB.
9. The second third party, Laing Management Ltd (LM), were engaged as
management contractors for the British Library project.
THE CLAIMS
10. The plaintiff alleges that the true loss in fact suffered by DNH as a
result of breaches of obligation on the part of SVM is reasonably calculated
at £16,481,044 excluding interest, but the claim in this action is limited to
the actual amount paid out by insurers in respect of material damage and in
respect of consequential loss under the British Library project policy, in the
sum of £8.4m. The plaintiff alleges that the total cost in fact incurred by
DNH in respect of material damage was £3,881,660 but the claim is limited
to an amount equal to the insurance settlement figure finally agreed for
material damage namely £3,437,446. Ir is this latter figure which forms the
first head of the £8.4m claim. DNH do not make any claim in respect of their
uninsured material loss. The second head of the claim is made in respect of
the costs alleged to be attributable to delays arising from the fact of cable
damage. Under that head, the claim is limited to the policy limit of £5m,
which was paid as the limited payment under an agreed settlement figure for
a claim for consequential damage. That settlement figure was originally
alleged to have been £14,317,682 but the figure was later amended to60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 39
£12,599,384. There were some additional items, again not claimed, which go
to make up the alleged total of £16,481,044 for material damage and delay.
11, The claim arises from the discovery of very extensive damage to low
voltage (240V) cabling installed in the New British Library by the appointed
parcel contractor BB. There is some dispute as to the date when damage to
cabling was first discovered. BB had been awarded the electrical works
package in 1988 and this involved, so far as concerns this action, the
installation of more than 3,000 km of single core low voltage cables in metal
trunking, When items of damage were first discovered, BB replaced damaged
cables at their own cost. By February 1993, BB were alleging that the amount
of damage being discovered was due to design faults for which they were not
responsible. BB claimed payment for their remedial works in respect of
damaged cabling. There followed long delays for reasons which | shall
consider, It was not until early 1995 that work was resumed at a reasonable
pace.
12. Some 300 km of low voltage cabling were reinstated. As an alternative
to the impractical task of replacing the totality of the 3,000 km of cabling,
further mitigating electrical works were carried out in order to eliminate risk
of fire, personal injury or current failure. Those further electrical works,
known as ‘enhanced cable protection’, included the installation of automatic
fuse switches and the redesign of some electrical systems.
13. In such a massive construction project, some defects and damage are
to be expected, and would be put right as part of the ordinary process of
installation at the cost of the contractor. But it is common ground that the
amount of damage discovered in the low voltage cabling of phase 1A of the
British Library project was far in excess of what might be expected in the
ordinary course of events. DNH, BB, and LM now combine in this action to
allege that the excessive damage was caused by bad design and other failings
on the part of SVM, though they did not take that stand in common at the
time. SVM deny those allegations and say that the excessive damage was
caused by a combination of bad workmanship on the part of BB and bad
supervision and lack of co-ordination both on the part of LM and on the part
of DNH and its agents. Moreover, while DNH in this action alleges delays
caused by cable damage, SVM say that delays were caused by many other
matters also, including most importantly, changes in the overall design
dictated by changes in government policy and requirements.
14. As a result of the common cause made by DNH, BB, and LM,
unusually, the plaintiff and both third parties in this action are represented
by the same counsel and solicitors.
15. In considering the allegations made against BB and LM I bear in mind
that although witnesses were called from both companies, those companies
were not in command of these proceedings. BB and LM were represented by
the lawyers instructed by the insurers because they, like DNH, were insured
under the project policy, as was required by the employers, the Crown. If the
Crown had required that the professional advisers, like the contractors,
should be covered by the same policy, this litigation is unlikely to have
occurred,40 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
‘THE ISSUES
16. At the outset of this trial, virtually everything which could be in issue
was stated to be in issue.
The conflicting parties dispute:
A. The nature and extent of SVM’s obligations and duty.
B. The fact, nature and extent of any breaches of obligation and duty on
the part of SVM.
C. The mechanism of causation of cable damage and any consequential
loss in particular whether such damage and consequential loss was caused by
any breach of obligation on the part of SVM.
D. The character and extent of cable damage.
E. The parties responsible for causing cable damage.
F. The quantum of remedial works and the fact and quantum of
consequential loss.
SVM in particular:
A. Deny the obligations alleged against them as to design, co-ordination of
design, production of ‘working drawings', and duties of supervision and
inspection of the works as they proceeded.
B. Deny that any failure in design or co-ordination or detailed working
drawings or inspection occurred at all.
C. Deny any breach of obligation on their part.
D. Deny that they caused any of the damage or loss.
E. Maintain that all the damage is due to failures on the part of BB and
failures on the part of LM and DNH.
F. Maintain that BB’s workforce was primarily responsible for all the
damage because of unsuitable materials, bad workmanship, insufficient
workface supervision and other failures, and maintain that LM are also
responsible for the damage because of failures in co-ordination, supervision
and inspection of the works.
G. Deny that the bulk of the losses alleged have been incurred at all by
DNH.
H. Deny that SVM was in any way responsible for any part of the loss.
OTHER BODIES AND INDIVIDUALS PRINCIPALLY INVOLVED
17. The employing client for the project, to whom everyone was ultimately
responsible was the Crown. The most senior person dealing with the project
in person was the Minister for the time being, assisted by the Permanent
Secretary for the Department, who since 1992 to the end of the period under
consideration was Mr (now Sir) Hayden Phillips.
18. DNH employed a project director who from August 1987 until
17 August 1995 was Mr John Pardey. He played the part normally played in
a commercial venture by the owner’s representative. For ordinary purposes
he was the voice of the plaintiff.
19. For most of the period of the project, Mr Pardey was answerable to the
head of the Office of Arts and Libraries, a small government department. The
head of that office answered to the Permanent Secretary. In 1991, the Office
of Arts and Libraries was subsumed into the Department of the60 ConLR Dept of National Heritage v Steensen Varming Muleahy (a firm) 41
Environment, the predecessor of DNH. Throughout, the Office of Arts and
Libraries was a manifestation of the Crown.
20. In 1978, when the project was first authorised, its management was
made the responsibility of the Property Services Agency (PSA). At first, the
PSA had financial responsibility for the project. In 1988, that responsibility
passed to the Office of Arts and Libraries but PSA continued the management
of the project. Having previously acted for other government departments,
the PSA later acted for DNH. PSA itself went through some changes. PSA
made some contracts for the project on behalf of the Secretary of State for
the Environment. In 1992, PSA was to be privatised. For that reason, in
September 1992, DNH entered into a project management agreement with
PSA Projects. By September 1992, all contracts and commissions made on
behalf of the Department of the Environment were transferred to DNH. In
December, 1992, PSA Projects were sold to Tarmac Construction Ltd and a
year later their name was changed to TBV Consult (TBV). At one stage the
same agency was in the hands of Schal. Throughout the period relevant to
this action, the management of the project was in the hands of PSA or TBV
or Schal. In this judgment, I may at times refer to PSA when it would be
strictly correct to refer to TBV or Schal. There is no practical difference for
the purposes under consideration. Throughout, PSA or TBV or Schal was
acting as agent for the Crown. The project manager employed by PSA in its
various forms was, until 1994, Mr B A Brown, and the deputy project
manager was Mr Andrew Housam. In early 1994, DNH appointed Mr Leslie
Rothwell as project manager, and from then on all project managers at TBV
worked under Mr Rothwell’s direction and leadership. Mr Housam
remained deputy project manager. Mr Brown, Mr Rothwell, and Mr
Housam all speak on behalf of the plaintiffs.
21. The ultimate occupier of the library is the British Libraries Board. The
British Library and their engineers were intimately involved in the
construction of the project though they did not have a contractual function.
Understandably, the British Library sought to set high standards, and it was
generally agreed by those who gave evidence before me that their standards
were in many instances impossibly high.
22. PSA employed a design team consisting of architects: Colin $t John
Wilson & Partners Ltd; structural engineers: Ove Arup and Partners;
mechanical and electrical engineers: SVM; and quantity surveyors: Davis
Langdon and Everest.
In 1983, Colin St John Wilson & Partners appointed one of their directors,
Mr John Honer, to be supervising officer for the construction, and in May
1991 he was appointed resident architect. The supervising officer has certain
contractual functions to which I shall return.
23. The main construction programme began in 1983, and it was not until
1984 that PSA appointed LM as construction management contractor with
overall responsibility for formulating the construction programme, for
procuring works parcel contractors and for overseeing the work of those
works parcel contractors.42 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
24, Individual parts of the works were divided between about 180 works
parcel contractors. Among them were BB and Haden Young Ltd. Haden
Young Ltd provided and installed some mechanical services including air and
water systems and controls systems. The air system involved air handling
plant, ductwork and terminal units. The water systems included heating and
chilling water systems. The chilled water and hot water systems included
condenser water systems and associated plant, that is, boilers, chillers,
cooling towers, and pumps. There also, of course, were drain pipes for
sewage and other waste water. The mechanical services included building
energy managements systems which included controls, sensors, actuators,
motorised valves and control panels. This equipment required massive plant
rooms and there was a great deal of ductwork and pipework installed by
Haden Young Ltd both in the plant rooms and above ceilings elsewhere in
the building. There were some clashes between that ductwork and services
provided by BB, Responsibility for those clashes is a matter in issue in this
action.
25. All of the mechanical services to which I have referred, together with
other mechanical services and the electrical services, were designed by SVM.
26. An important part is played by McLaren Dick & Co (later known as
McLaren Topliss) (McLarens), loss adjusters. McLarens adjusted the loss
under a project policy maintained by DNH with the Commercial Union
Assurance Co ple and other insurers in respect of the British Library project.
From time to time, McLarens recommended the insurers to make payments
on claims. Payments were always made by cheque to DNH and to no other
party insured by the policy. DNH would then make payments to some parcel
contractors.
DESCRIPTION OF SITE
27. The library is a very large project indeed. One measurement mentioned
is that the total plan area including all floors and basements, is 26 acres.
28. The site is bounded by Euston Road on the south, Brill Road to the
North, and Midland Road and Ossulton Street to the West and East.
29, The observer from the street sees a large building which is not as high
as it might have been, due to planning restrictions imposed for the benefit of
St Pancras Station on one side and some low level housing on the other. The
observer does not see the massive basements which extend under the building
and out under the extensive piazza in front of the building.
30. There are four deep basements for the storage of books, numbered
downwards, B1, B2, B3, and B4, Above those levels there is BY just below
ground level, predominantly occupied by plant rooms. From ground level
upwards there is what has been described as the superstructure. In the
superstructure are readers’ areas, office areas, and exhibition and meeting
areas.
31. That part of the library which has been built is divided into phase 1A
and the completion phase, or CP3. Originally there were plans for phases 1B,
1C, 2A, 2B and 3, which were not built. A smaller CP3 was substituted for
them.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 43
32. Phase 1A is at the south end of the site and the completion phase is to
the north of phase 1A.
33. Phase 1A (itself divided into stages 1AA and 1AB) is 76,000 square
metres in area and comprises above ground: the main entrance hall and
piazza; reading rooms with desks for 579 readers; 13 linear km of open
access book storage; three exhibition galleries; auditorium and meeting room
complex with over 400 seats, and office accommodation for 600 staff;
together with necessary cloakrooms etc.
And below ground: four basement levels with 290 km of closed access
book storage and facilities for computerised mechanical delivery of books to
readers; and one level of plant rooms.
34. Stage 1AA comprised the basement book storage areas and central and
associated plant rooms on five levels below ground together with, above
ground, the entrance hall, exhibition area, rare books reading rooms and two
levels of offices. Stage 1AB comprised the Science Reference reading rooms,
meeting rooms and associated air-handling plant rooms.
35, The completion phase is 32,000 square metres in area and comprises:
the King’s Library holding 60,000 books in a six storey glass bookcase;
Humanities reading rooms on two levels with 450 readers’ desks; Science and
Business rooms on two levels with 61 desks and 6.5 km of open shelving;
Oriental and India Office reading room with 80 desks and 1 km of open
storage; map reading room with 36 seats; additional closed access storage of
25 km; conservation workshops, photographic and reprographic centres;
restaurant facilities for readers and staff, and accommodation for around
600 staff.
36. It is particularly relevant to this action to note that each reader’s desk
is connected with underfloor cabling to serve desk lighting, power points for
readers’ lap-top computers, connections between readers’ computers and the
library’s computerised index, and communication with the book ordering
system. There are also other refinements in the reading rooms requiring
cabling, such as the electrical motorised adjustment of the desk tops in the
map reading room and the library’s own computers away from the desks
allowing readers’ access to the index as well as other computer equipment for
staff. All parties make points (going in different directions) that there was no
significant problem with that substantial quantity of underfloor wiring: the
problems were with cabling overhead, between the ceiling and the underside
of the floor slab above in those areas where there is a ceiling (reading rooms,
offices etc) and in similar positions in other areas where there is no ceiling
such as plant rooms.
GENERAL HISTORY OF THE PROJECT
37. SVM were involved in the British Library project from about 1962
even before the present site was chosen. The original scheme was for an
extension to the British Museum site in Bloomsbury. Planning permission
was refused and in 1970 the government bought the site of the old goods
depot of St Pancras Station. Planning permission was granted in 1977 with
some restrictions, particularly as to the height of the proposed building,
which dictated the unusual shape of the building above ground.44 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR,
38. The original scheme at St Pancras was to build in a series of phases,
phases 1A, 1B, 1C, 2A, 2B, and 3. A change of government in 1979 resulted
in changes in funding requiring phase 1A to be broken down into stages [AA
and 1AB. In 1989, further financial restrictions caused the Office of Arts and
Libraries to decide that phases 1B, 1C, 2A, 2B, and 3 would not be proceeded
with in the planned form and instead there would be a single smaller phase
known as the completion phase. As a result, although the library is opened,
the site is not yet filled.
39. Changes in the overall size of the total project resulted in design
changes affecting the design of the work already under construction. The
original design was for one building, not a series of independent buildings to
be built one after another. Each phase was designed to fit into the whole
building. When the grand scheme was changed, by removing later phases, the
earlier phases had to be changed to conform with the new shape of the
building as a whole. The use to which individual spaces were to be put
changed, and the routes of corridors and services had to be changed. The
mechanical and electrical services were designed for the building as a whole
and they had to be changed. The changes in the grand design worked their
way down to important but comparatively small points of detail like the
matching of routes of individual cables to the routes of ducts and pipes.
Those changes caused very substantial delays and disruption. The architect
and the PSA were not at fault in causing those changes. Even individuals at
DNH could with justice say that they were not personally responsible
because they were compelled by forces outside the DNH. The Crown
collectively is responsible for those delays and hence the Crown represented
by DNH is responsible. It is impossible to put a figure on those delays.
40. Efficient management of the project was also made more difficult by
its manner of funding. The funds for the project were allocated annually and
also on a stage by stage basis. In any one year only the amount allocated
could be spent whether it was sufficient or more than sufficient. The work
had to be programmed according to the funds available.
41. Construction began in 1982 with the demolition of the remains of the
depot buildings, rail tracks, platforms etc.
42. Until 1982, it was intended that the project should be carried out in a
traditional manner. In that year, PSA put forward the idea of running the
project as a construction management project. As a result, LM was
appointed construction manager in 1984, Construction management was
then a relatively novel form of contract management, particularly in
government contracts.
43. On 24 May 1988, BB’s tender for the electrical works was accepted.
44, The physical work of installation of the electrical works began on
1 September 1988.
45. As early as Autumn 1989, excessive turnover of labour in BB’s
workforce was seen to be impeding the efficient progress of the work, and a
record was made to that effect by a clerk of the works in his diary on
10 March 1990.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 45
46. By October 1991, the project was already 12 weeks behind
programme, due mainly though not wholly to BB having reduced its
workforce in previous months for various reasons including disputes with
DNH over matters not the subject of this action. Other causes of delay
included changes in design due to changes in client’s requirements. Shortage
of electricians and supervisors remained a continuing problem thereafter,
and delays increased. | shall refer to this problem of shortage of labour in
more detail when I come to consider the supervision of the project.
47. During the early part of the work, BB detected and repaired defects at
their own cost in the ordinary way. By at least as early as October 1992, BB
realised that they faced a massive problem in dealing with repairs to damaged
cables. Whether BB were aware of such cable damage earlier is a contentious
matter to which I shall return later.
48. By October 1992, the work was already substantially behind
programme for reasons not connected with cable delays.
49. To avoid having to pay for the repairs themselves, BB set about
preparing a case for putting the blame on SVM. That case was set out in a
carefully drafted lengthy letter dated 23 February 1993.
50. BB obtained a report from Mr R G Anstee, a consultant engineer. His
report was presented on 17 June 1993. That report laid the blame for cable
damage on SVM.
51. PSA then consulted Mr Terry Hedgeland. He produced a hurried
report on 7 July 1993 followed by reports on 23 July 1993 and 6 August
1993 and then two further reports on 26 August 1993. The reports were
inconsistent.
52. In autumn 1993, DNH consulted Kennedy & Donkin. They gave their
first report in October 1993.
53. In mid-1993, BB followed a policy of non-co-operation, reducing the
pace of remedial work and withdrawing labour. BB was now in dispute
about a number of matters not confined to the cable damage the subject of
this action.
54, On 17 December 1993 Mr Pardey for DNH wrote to BB giving them
notice that they must repair the cable damage at their own cost.
55. In February 1994, BB withdrew their labour. DNH then entered into
what was called a ‘commercial agreement’ allowing BB some payment on
terms.
56. In March 1994, BB returned some labour to site but complaints about
shortage of BB labour continued.
57. A lengthy process of re-inspections uncovered many more defects. It
appeared that there could be no certainty of discovering all the defects. An
unrealistic suggestion, made by the British Library, that all the cables should
be removed and replaced was rejected, and after a great deal of indecision, it
was decided on 20 June 1994, to fit ‘enhanced cable protection’, extra circuit
breakers at the distribution boards which would shut off power if a cable
fault occurred. It had taken almost a year to produce that decision.
58. Meanwhile, other works package contractors whose work had been
disrupted, had stopped work. There was very little activity on site during46 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
1994. That situation had been predicted by LM in their report dated
21 December 1993 addressed to the supervising officer with copies to Mr
Pardey of DNH and others, LM wrote:
‘The uncertainty of direction by the Project Team is having a major
demoralising effect on the project as a whole and unless firm direction is
given by the PSA and the supervising officer we anticipate further
deterioration of progress on site and resistance by contractors to commit
themselves to the work remaining.’
At this point, BB had reduced their workforce from 250 to 70 men and
although they had not abandoned the work they were not regularly and
diligently doing the work and they were causing delay to others. At the
supervising officer’s meetings throughout 1994 the lack of progress was
repeatedly reported. In April 1994, LM reported that BB had refused to
provide power to other contractors and thus prevented progress: that was
done as a flexing of muscles in disputes over refusals to accept their work. At
the May 1994 meeting, it was reported that very little recordable work had
been done in the past month ‘due mainly to the electrical contractors and
How Fire’, and LM complained that the absence of decisions from DNH was
leaving them in an impossible management position.
59. The situation on site throughout 1994 was reflected in a minute of a
supervising officer’s meeting towards the end of that period on 8 September
1994 at which the supervising officer, TBV, Colin St John Wilson &
Partners, David Langton & Everest, SVM, and LM were represented. At that
meeting, LM stressed the need for a decision from DNH on three vital
questions: (a) the end date of the project; (b) the full scope of the work; and
(c) the budget and the funding rate. The others present agreed and mentioned
numerous results of the uncertainty. In particular, the works package
contractors generally were concerned at the financial situation resulting from
the delay in the DNH decision and there were rumours exacerbating the
situation. The supervising officer, Mr Addison, said that he was fairly
confident that he would soon be able to issue an instruction.
60. In November 1994, DNH were given an additional budget for the
project.
61. After November 1994, DNH negotiated supplementary agreements
with the works package contractors to get them back to work. The series of
agreements began with the signature of a completion agreement with BB on
11 January 1995. Agreements with other package contractors followed. Mr
Rothwell, British Library operations director and later project manager, said
that the total value of the resolved disputed contracts was over £100m and
the saving on the budget was £3.25m. The terms of those agreements
included terms that all claims and counterclaims between the contractors and
DNH were extinguished. The progress of work picked up in 1995 after the
supplementary agreements had been signed with other works contractors.
62. Construction of phase 1A had been due to be completed on 22 March
1993. The BB completion agreement extended the completion date to 31 July60 ConLR Dept of National Heritage v Steensen Varming Muleahy (a firm) 47
1995. The completion date was then extended to October, 1995.
Construction of phase 1A was not in fact completed until 22 November
1995, a delay calculated as 31 months from the original completion date. The
‘enhanced cable protection’ was installed after that completion date.
63. A report by the Comptroller and Auditor General (22 April 1996)
attributed that delay to, inter alia, the time taken to identify and resolve
problems with the mechanical bookshelving, to reach a compromise on how
to deal with cable damage, and to decide how to deal with shortcomings in
the fire protection systems. I have heard much evidence not available to the
Comptroller and Auditor General, and it is plain that the causes of delay
were many and complex.
64. Two of the three causes identified by the Comptroller and Auditor
General were not even arguably the fault of SVM. Although SVM designed
the mechanical bookshelving, it is not suggested that they were responsible
for delays relating to the bookshelving: their design was not at fault, the
problem was one of failure to conform with the design. The problem with fire
protection systems was itself in part a result of the passage of time in
completing the project in that safety standards and the expectations of BL
altered after the date of the original design. It is not alleged in this action that
SVM were responsible for the delays associated with either of those two
matters identified by the Comptroller and Auditor General.
65. It is alleged that a substantial part of the delay relating to cable damage
was caused by SVM, but they were not responsible for the excessive amount
of time taken to reach a compromise on how to deal with the cable damage,
the installation of the ‘enhanced cable protection’. Even DNH and BB and
LM do not allege that the 31 months delay was wholly caused by cable
damage. A great deal of delay was due to indecision on the part of DNH. The
DNH/BB/LM case is that SVM caused cable damage which in turn caused 12
or perhaps nine months delay to the project as a whole. SVM’s case is that
there were so many different causes of delay that no critical period of delay
can be attributed specifically to cable damage. SVM also say that in any event
they, SVM, were not responsible for the damage to cables.
66. The writ in this action was issued on 24 January 1996. The trial began
almost precisely two years later, on 26 January 1998.
67. The library was opened to readers on 21 April 1998, and was formally
opened by Her Majesty the Queen in June 1998, in the month following the
conclusion of the trial of this action.
DESCRIPTION OF THE ELECTRICAL INSTALLATION
68. London Electricity Board (LEB) supplied electricity at a voltage of
11 kV to two LEB substations situated at opposite ends of the site at
basement 1 (B1) level.
69. From those substations, power was fed at 11kV by high voltage cabling
resting on ladder rack to 3 substations within B3. High Voltage cabling is
large wire armoured cabling. Ladder rack is steel racking in the shape of a
slim ladder suspended horizontally or vertically.
70. Within the substations are transformers which reduce the power to
415 V.48 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
71. The substations are located to serve particular areas of the building.
Substation 1 serves the East side. Substation 3 serves the West side.
Substation 2 is reserved for the heating, ventilation, and air conditioning
system.
72. From the substations, power is taken at 415V by armoured cabling
resting on ladder rack to 11 risers at various points around the building. The
risers are copper bars extending up to the top and down to the bottom of the
building. There was damage to at least one riser, but that is not complained
of in this action. The damage to the riser is only relevant because it is
evidence of at least one piece of indisputably very bad workmanship on the
part of BB, caused by a workforce for whom high standards of workmanship
are claimed by BB.
73. Each riser connects at each level to a distribution board within a steel
cupboard. Each distribution board contains connections and circuit breakers
and fuses for individual circuits. Those individual circuits supplied power at
240V to individual items of equipment, power sockets, lighting and so forth.
Those individual circuits, or rather some of them (and certainly not those
which run under floors), form the subject matter of this action.
74. Three kinds of circuits run from the distribution boards, to feed small
lighting and power, building energy management system, and emergency and
alarm systems. The small lighting and power circuits were required by BB’s
contract to be wired using single core PVC insulated cables with stranded
copper conductors enclosed in conduit or trunking, with no joints being
permitted in the wiring without written approval of LM. The single wires
were of different dimensions, but the majority of them were required to be
not less than 2.5mm? in section. Wires of more than one size were used, but
90% of the wires were 2.5mm?. Each wire is coloured either red or black or
green/yellow (carth). In phase 1A the PVC was white with the surface only
being dyed the appropriate colour, so that when scratched or scuffed, the
white PVC showed through. In CP3 the colouring extended through the
whole body of the PVC. The wires are bendable but are not classed as
flexible: that is, a short length can be held in the hand by one end without it
bending under its own weight.
75. Wiring went from the distribution boards enclosed in trunking or
conduits or a combination of the two. A conduit is simply a metal or plastic
pipe. For present purposes, trunking consists of stecl channels made in
lengths joined together. Some of the trunking is single channel, some is two
channel, and some is three channel. The three channel trunking has attracted
the most attention in this case. The external dimensions of the three channel
trunking are 300mm wide by 100mm deep. When laid on a table, a length of
three channel trunking looks like the cutlery drawer of a kitchen cabinet with
no end pieces. Cables are laid in the channels and then a lid is screwed onto
the open side giving the trunking the property of a duct. Trunking may be so
positioned that the lid goes on the side, or on the top, or on the bottom. In
the present case, we are concerned with a choice between trunking so
positioned that the lid goes on top (lid-up trunking), or trunking so
positioned that the lid goes on the bottom (lid-down trunking). Trunking of60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 49
identical design can be positioned for use either as lid-up or lid-down
trunking. The strongest criticism made of SVM in this case is that they
designed the installation in phase 1A to use lid-down trunking throughout,
with the exception of underfloor trunking.
76. The trunking has to be routed to make T junctions and to turn corners
and go through changes in elevation. For those purposes, accessories are
made in the form of T pieces, bends, and sets (going up or down). Three
channel T pieces have come in for particular attention. When a straight piece
of three channel trunking reaches a T junction, it will often happen that the
wires from more than one channel will be divided so that some wires in one
channel go to the right and some from the same channel go to the left. The
specification required that there should be segregation throughout the
building between (a) lighting and small power, (b) escape lighting, and (c)
building energy management system. The wires in (for example) the left
channel must remain segregated from the wires in the centre channel so a
system of bridges is incorporated in the T piece like a spaghetti junction in
miniature. Special skills are required to cope with a very large number of
cables often in very restricted spaces without damaging the wires and I have
heard much evidence about techniques.
77. By the statement of claim, it is alleged that during the installation,
damage was done to PVC single core general wiring cables and also to
building energy management system cables, security cables, fire alarm cables,
public alarm cables, lift diagnostic cables, lighting data loop cables, fibre
optic cables and data and voice cables. Damage of all those kinds was
reported in a report made by W S Atkins to insurance assessors in 1994.
Damages are only claimed by DNH against SVM in respect of the single core
general wiring cables, the 240V cables. The other damage is relevant and
extremely significant because it was caused by the allegedly skilled and
careful workforce and because the explanations put forward for damage
aimed at laying the blame for damage at the door of SVM largely do not
apply to cables other than the PVC single core cables for lighting and small
power.
78. When the installation is properly done there should be no damage to
cables. In the British Library there was an enormous quantity of damage to
cables.
79, In considering the damage, the following elements of the installation
have been examined: Design of the system, in particular as to the nature of
the trunking and the routing; Specification of materials and method; Quality
of the materials, particularly the trunking; Workmanship; Supervision;
Inspection; Co-ordination of the work and Control of the project.
80. The respective responsibilities of each of the parties for those matters
has to be considered to determine whether any one party or parties has failed
to perform its responsibilities. Above all, there is the question whether any
breach of responsibilities leads to a finding that one party has caused the
damage alleged. The contractual requirements are complex.50 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
THE CONTRACTS
Construction management
81. In construing the contracts entered into by the parties to this action,
and in considering their various duties, it is important to read the contractual
documents within the context of the overall contractual scheme chosen for
the project. In particular, it is important to clarify what is meant by a
contract manager in the context of this project.
82. There are four main forms of management contract.
1. Management contracting where all contractors enter into a contract
with the management contractor. The management contractor is responsible
for procurement and financial control and cach contractor is paid by the
managing contractor. The management contractor is paid a fee by the client
together with the costs of all the contractors.
2. Project management contracting where the project manager provides a
technical service to the client and procures and manages works contracts on
behalf of the client. The project manager has full control of budget and
programme and is paid on a staff reimbursement basis.
3. Design and management is similar to project management with the
addition of design responsibility.
4. Construction management was the scheme adopted with LM in this
case. Under such a scheme, the client (in this case, the Crown) enters directly
into separate contracts with the designers, construction manager and the
Works or trade contractors, and the construction manager manages the
Works contractors on behalf of the client.
83. LM were engaged by PSA on behalf of the Crown in the name of DNH
as construction managers. In the course of the project, LM were referred to
as management contractors and in the course of this judgment, I may also so
refer to them. In the language now used in the construction industry, that
latter designation is wrong, but all concerned in this action are agreed that
LM were construction managers. As construction managers, LM became
responsible for managing works parcel contractors and service parcel
contractors, including BB and Haden Young Ltd. There were about 180
parcels. Particularly relevant to this action are the electrical parcel, parcel
4235, handled by BB; and two mechanical services parcels handled by Haden
Young Ltd, namely, central plant and pipework (parcel 4040), and
airhandling plant and ductwork (parcel 4035).
LM’s contract
84. PSA on behalf of the Secretary of State made two management
contracts with LM, namely, 11 January 1984, for stage 1AA and 9 January
1987 for stage 1AB and together those stages made up phase 1A.
85, The second of LM’s contracts was an extension of the first, which was
contained in various documents. By letter dated 11 January 1984 PSA
accepted LM’s tender ‘for the management of the construction and
completion’ of stage 1A. The tender was dated 21 February 1983 and its
acceptance was expressly made—60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) St
‘in conjunction with your letters dated 21 February, 11 May, 24 June,
16 August and 11 October 1983 and this Department’s letters dated 16th
June, 22 August and 3 October 1983...’
86. The tender contained the following:
‘TENDER...
1. I/We have perused the following documents:-
(1) Contract Book:
Section 1: General Information and Instructions to Tenderers
Section 2: Management Contract Conditions
Section 3: Prescribed Form of Works Contract for use with PSA
[Property Services Agency] Management Contracts
Section 4: Programme Summary, Cost Plan Estimate, Outline
Specification, Method Statement and List of Drawings
(2) the Information Drawings listed in Contract Book Section 4
(3) Supplementary Condition No. 139A, Value Added Tax
(4) Standard Fire precautions PS (available from HMSO Shops) . . .
SECTION 1
GENERAL INFORMATION AND INSTRUCTIONS TO TENDERERS
2. Personnel, November 1982...
(b) Design Team
Architect...
M & EEngineer SVM...
Structural Engineer Ove Arup...
Quantity Surveyor DBE .. . (who later became DLE [David Langdon
& Everest]).
7. Division of Responsibilities
The following table is to be used as a general guide to the performance
of the management contractor’s obligations under the Management
Contract, and his relationship with and the responsibilities of the other
persons shown in the table. The table does not limit the responsibilities
of the management contractor set out in Section 2. It may be amended at
any time by the Authority (but not, of course, so as to extend the
management contractor’s responsibilities under Section 2).
For the purposes of the table “Design Team” includes the supervising
officer.52 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
Activity ‘The Authority/Project | The Design Team Management
Manager Contract
1, Brief Preparation, up-dating
and amendments made
necessary by Client's
requirements
2. Design Approval of design at | Design responsibility | Provision of
each stage as submitted | and design expertise to advise
by the designers co-ordination on construction
techniques,
programme and
cost implications,
etc
3. Production
Information
Production and
revision of all design
information necessary
for the construction of
the Works
Provision of
expertise toadvise
on construction
techniques and
cost implications,
etc
9. Construction
of the works
Consider progress
reports and decide
whether intervention is
necessary.
Issue of design
information and
instructions necessary
for the execution and
completion of the
Works.
Full control and
supervision of
construction of
the whole of the
Works in
accordance with
the direct
Contracts and
Supervising
Officer's
instructions.
Establishment of
standards of quality of
material and
workmanship.
Provision of site
supervision of the
whole of the Works.
Oversight of the
works in accordance
with the standards set
by the Contract
documentation.
Oversight of the
Management
Contractor's
management
operations. Approval
and acceptance of
works to be executed
by others. Receive
progress reports and
pass to the Authority/
Project Manager with
comment.
Ensure
completion of the
entire Works to
programme and
specification and
within budget.
Prepare progress
documents.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 53
SECTION 2
MANAGEMENT CONTRACT CONDITIONS
1. Definitions, Etc.
(1) “The Management Contract” means the documents forming the
tender and acceptance thereof, together with the documents referred to
therein including these Conditions, the Specifications, the Cost Plan and
the Drawings, and all these documents taken together shall be deemed to
form one contract .. .
2. Management Contractor’s Obligations
The management contractor shall, through the provision of
management services as detailed in Conditions 3 and 4, and elsewhere in
the Management Contract, secure the completion of the Works by the
Contractors. He shall control their performance in respect of standards of
workmanship, cost and programme. Subject to the provisions of the
Management Contract, the Management Contractor shall exercise the
powers and duties ascribed to him in each direct contract.
3. Pre-commencement services
The pre-commencement services . . . shall include:
(1) Provision of advice and assistance to the Supervising Officer
When requested to do so, consider alternative construction methods and
technical solutions and the time required for cach alternative. Give
technical advice on the construction techniques proposed for the
“construction method” . . .
(6) Provision of Staff
The Management Contractor shall provide such competent specialists
and support staff who have adequate experience on large and complex
installations to undertake the pre-commencement services as shall be
reasonably required by the Project Manager. All such specialists and staff
shall be in the Management Contractor’s direct employment unless
otherwise approved by the Project Manager. They shall include: . . .
Chartered Mechanical and Electrical Engineers . . .
[In addition, in a Proposal which formed part of the contract, LM
stated: “. . . qualified mechanical and electrical engineers will be deployed
to implement effective controls over services installations and the
commissioning process.”|
4. Management of the Works
The services which the Management Contractor shall provide after the
Order to Commence is given shall include those services listed in
Condition 3 as appropriate and in addition: . . .
(3) Co-ordination and control of the work
(a) Be responsible for and take all necessary steps to secure progress of
the Works to specification and programme and within the cost plan.
(b) Check progress of the preparatory (including installation and shop
drawings) work of the Contractors; make visits to the premises of
Contractors as necessary, to inspect production.
(c) Report to the Supervising Officer regularly on progress and technical
aspects of all orders placed.54
Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
(d) Co-ordinate and expedite all Works carried out by the Contractors
(see also Condition 25) including making good defects during the
maintenance periods.
(c) Take all possible steps to prevent disputes arising between the
Contractors, and, if arising, assist in settling them.
(f) Supervise the execution of all the Works and maintain the necessary
quality control.
(g) Ensure correct setting out and levels for the Works (see also
Condition 12).
(h) Maintain records of the numbers of all workmen employed on the
site.
(i) Maintain records of all materials, delivered to and removed from the
site, and of all inspections, tests, reports etc; submit copies to the
Supervising Officer . . .
10. Progress of the Works
The Order to Commence shall be given to the Management Contractor
by notice and the Management Contractor shall thereupon arrange for
the execution of the Works to begin. Subsequently he shall arrange and
manage the execution of each direct contract so as to ensure that each is
commenced and completed in accordance with the Master Programme
and that the whole of the Works are completed to the standards specified
and to the satisfaction of the Supervising Officer by the date for
completion . . .
14, Appointment of Resident Engineer or Clerk of Works
The Authority may appoint a Resident Engineer or a Clerk of Works
and the Management Contractor shall admit him and his assistants to the
site. The Resident Engineer or Clerk of Works may exercise the powers of
inspection and testing in direct contracts and such other powers as the
Supervising Officer may give notice of to the Management Contractor.
21. Avoidance of Delay
(1) The Management Contractor shall secure the completion of the
Works to the satisfaction of the Supervising Officer on or before the date
for completion, prevent as far as possible any delay in the completion of
the Works, and minimise delay if it becomes unavoidable.
(2) In the event that delay becomes unavoidable owing to circumstances
beyond the Management Contractor’s control, the date for completion
shall be altered accordingly by the Authority.
24, Management Contractor’s Site Organisation
(1) The Management Contractor shall maintain an adequate site
organisation under the full time control of an experienced site agent who
is conversant with British Standards and Codes of Practice and with the
health, safety and welfare regulations, who is capable of assuming
complete responsibility for the Management Contract and who shall be
designated as the Management Contractor’s site agent to whom directions
may be given by the Supervising Officer. The site agent shall be in
attendance at the site during all working hours except that when required
to do so he shall attend at the office of the Supervising Officer.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) SS
(2) The site organisation shall include staff of adequate status and
experience in mechanical, electrical and public health engineering services
to ensure that compatibility is achieved between service installations one
with another and each in relation to the works generally . . .
(5) The Management Contractor shall employ on the site a sufficient
number of suitably qualified persons for the supervision and management
of the execution of the Works, and the Supervising Officer shall have
power to instruct the Management Contractor to increase or decrease the
number of persons so employed
25. Co-ordination
(1) The Management Contractor shall be responsible for obtaining and
co-ordinating installation details of all builders work drawings and
installation drawings for statutory undertakings, Contractors or others
employed direct in connection with the Works and for ensuring that the
services are installed in accordance with the agreed services co-ordination
drawings. The Management Contractor shall ensure that each service is
installed in such a manner as to ensure proper performance and adequate
fixing to the structure and to avoid conflicts in the positioning of the
various ducts, pipes, cables, other items of service installation and other
like items. He shall arrange for statutory undertakings, Contractors and
others employed direct to attend necessary co-ordination meetings.
(2) The Supervising Officer will provide co-ordination drawings
showing the inter-relation of the services and their relation to the buildi
components in sufficient detail to demonstrate that the services will be
properly separated from each other and can be satisfactorily installed and
maintained. These drawings shall form the basis of the relevant
Contractors’ working drawings and it will only be necessary for
Contractors to prepare installation drawings to show details of fabricated
items and fixing details where site measurement is required. Any proposed
deviations from the co-ordination drawings shall be submitted to the
Supervising Officer for approval; if necessary the Supervising Officer will
amend the co-ordination drawing(s). A deviation in this instance is
considered as a change in the position of a service to such an extent that
one or more other service will require repositioning. Development of
installation details would not constitute a deviation unless this resulted in
additional elbows, bends, offsets, transformation pieces etc.
(3) The Management Contractor shall ensure that Contractors and
others programme their work and provide him with information
regarding builders work in reasonable time relative to the construction
programme.
(4) The Management Contractor shall employ a person on site whose
status in his organisation and experience of engineering services are such
that he can discharge competently all the requirements detailed above.
(5) Acceptance or approval by the Supervising Officer of drawings and
other documents provided by the Management Contractor in respect of
work proposed and/or designed by the Management Contractor will not56
Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
relieve the Management Contractor of responsibility for any
discrepancies, errors or omissions therein, nor for any other of his
contractual and legal obligations.
SECTION 3
PRESCRIBED FORM OF WORKS CONTRACT FOR USE WITH
P.S.A. MANAGEMENT CONTRACTS
1. Definitions, etc.
(1) “the Contract” means the documents forming the tender and
acceptance thereof, together with the documents referred to therein
including these Conditions (except as set out in the Abstract of
Particulars), the Specification, the Bills of Quantities and the Drawings,
and all these documents taken together shall be deemed to form one
contract. When there are no Bills of Quantities all reference to Bills of
Quantities in the Contract shall be treated as cancelled, except that where
the context so admits the Schedule of Rates shall be substituted therefor
4. Specification, Bills of Quantities and Drawings
(1) In case of discrepancy between these Conditions and the
Specification and/or the Bills of Quantities and/or the Drawings, the
provisions of these Conditions shall prevail.
(2) Figured dimensions on the Drawings shall be followed in preference
to the scale.
(3) The Management Contractor shall provide free to the Contractor
three copies of the Contract Drawings and of the Specification and of the
blank Bills of Quantities, and two copies of all further drawings issued
during the progress of the Works. The Contractor shall keep one copy of
all Drawings and of the Specification on the Site and the Supervising
Officer and Management Contractor and their representatives shall at all
reasonable times have access to them . . .
6. Progress of the Works
Possession of the Site or the order to commence shall be given to the
Contractor by notice and the Contractor shall thereupon commence the
execution of the Works and shall under the day-to-day supervision and
control of the Management Contractor proceed with diligence and
expedition in regular progression or as may be directed by the
Management Contractor under Condition 7 so that the whole of the
Works shall be completed by the date for completion.
7. Management Contractor’s instructions
(1) The Contractor shall carry out and complete the execution of the
Works to the satisfaction of the Management Contractor who may from
time to time issue further drawings, details and/or instructions, directions
and explanations (all of which are hereafter referred to as “the
Management Contractor’s instructions”) in regard to: (a) the variation or
modification of the design, quality or quantity of the Works or the
addition or omission or substitution of any work; (b) any discrepancy in
or between the Specification and/or Bills of Quantities and/or Drawings;
...(d) the removal and/or re-execution of any work executed by the60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a fiem) Ss?
Contractor; ... (m) any other matter as to which it is necessary or
expedient for the Management Contractor to issue instructions, directions
or explanations...
(4) The Contractor shall not make any alteration in, addition to or
omission from the Works described in the Specification and/or Bills of
Quantities and/or shown on the Drawings except in pursuance of the
Management Contractor’s instruction issued in accordance with this
Condition and such alterations, additions or omissions shall not
invalidate the Contract...
13. Things for incorporation and workmanship to conform to description
(1) All things for incorporation shall be of the respective kinds described
in the Specification and/or Bills of Quantities and/or Drawings and the
Contractor shall upon the request of the Management Contractor prove
to the Management Contractor’s satisfaction that such things do so
conform.
(4) The Works shall be executed in a workmanlike manner and to the
satisfaction in all respects of the Management Contractor. If any things
for incorporation do not accord with the provisions of the Contract or if
any workmanship does not so accord the same shall at the cost of the
Contractor be replaced, rectified or reconstructed as the case may be, and
all such things which are rejected shall be removed from the Site . . .
25. Precautions against loss or damage
(1) The Contractor shall take all reasonable steps and precautions
{including any steps and precautions expressly required under or by virtue
of the Contract) to prevent and to minimise the extent of loss or damage
to the Works and any things for incorporation on the Site (including
things provided by the Authority) arising from any cause whatsoever
including any of the causes referred to in Condition 26(3) . . .
26. Damage to Works or other things .. .
(2) The Contractor shall (unless the Authority exercises his powers to
determine the Contract) with all possible speed make good any loss or
damage arising from any cause whatsoever occasioned to the Works or to
any things for incorporation on the Site (including any things provided by
the Authority) and shall notwithstanding such Joss or damage proceed
with the execution and completion of the Works in accordance with the
Contract.
(3) The cost of making good any loss or damage falling within
paragraph (2) of this Condition shall be wholly borne by the Contractor,
except that (subject to paragraph (4) of this Condition) where the loss or
damage is wholly or partly caused by (a) the neglect or default of a servant
of the Crown acting in the course of his employment as such; (b) any of
the accepted risks; [sic: for “accepted” read “excepted”] (c) any defect in
the design of the Works or any part of the Works (except insofar as such
design was provided by the Contractor, or any servant, agent or
sub-contractor of his or otherwise on his behalf); (d) any requirement
imposed on the Contractor under or by virtue of the Contract as to the
method of executing the Works or any part of the Works (except insofarDept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
as such requirement was devised by the Contractor, or any servant, agent
or sub-contractor of his or otherwise on his behalf); or (e) the neglect or
default of the Management Contractor the Authority shall pay to the
Contractor (where it is wholly so caused) the Appropriate Sum or (where
it is partly so caused) such proportion of the Appropriate Sum as properly
reflects the share of that cause in causing the loss or damage . . .
28. Date for completion: Extensions of time...
(2) The Contractor shall be allowed by the Authority a reasonable
extension of time for the completion of the Works in respect of any delay
in such completion which has been caused or which the Authority is
satisfied will be caused by any of the following circumstances: (a) the
execution of any modified or additional work; ... (f) any other
circumstance which is wholly beyond the control of the Contractor;
(i) except insofar as the Authority shall otherwise decide, it shall be a
condition upon the observance of which the Contractor’s right to any
such extension of time shall depend that the Contractor shall,
immediately upon becoming aware that any such delay has been or will
be caused, give notice to the Management Contractor specifying therein
the circumstances causing or likely to cause the delay and the actual or
estimated extent of the delay caused or likely to be caused thereby; (ii) the
Contractor shall not be entitled to any extension of time in respect of a
delay caused by any circumstance mentioned in sub-paragraph (2)(f) of
this Condition if he could reasonably be expected to have foreseen at the
date of the Contract that a delay caused by that circumstance would, or
was likely to, occur; . iv) it shall be the duty of the Contractor at all
times to use his best endeavours to prevent any delay being caused by any
of the above mentioned circumstances and to minimise any such delay as
may be caused thereby and to do all that may reasonably be required, to
the satisfaction of the Management Contractor, to proceed with the
Works; and (v) the Contractor shall not be entitled to an extension of time
if any such delay is attributable to any negligence, default or improper
conduct on his part. . .
30. Outline Specification...
(21) Medium Voltage Distribution: .. .
Main cabling shall be carried out using paper and PVC insulated single
and multicore armoured cables supported on tray or racking as
appropriate...
(23) Minor Power Installation:
General purpose switched socket outlets shall be installed throughout
the building, and shall be serviced via a floor duct system installed
throughout all areas except the Basement Bookstack compartments.
(24) Motive Power Installations: .. .
Wiring shall be carried out using PVC armoured cables run on tray or
PVC insulated cables in conduit and/or trunking as appropriate . . .
(33) Automatic Data-processing:
A comprehensive wiring facility shall be provided for the provision of
an ADP installation which shall extend throughout the whole building.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 59
The wiring provision shall take the form of a multi-compartment fully
accessible floor distribution system which in some areas shall be
associated with the Minor Power and Telephone Services. The ADP
system shall interface with a central processing unit and_ local
micro-processor terminals as required. Control and signal (but not power)
wiring shall be carried out during the Contract . . .
Appendix A
Design and Construction Method Statement . . .
1. Introduction
(1) Aim
To inform tenderers of the general principles of structural stability
employed both in the temporary and final condition which are an essential
part of the design, in order that they may incorporate this into their
planning of the Works both for tender and construction purposes. This
description is not to be considered as exhaustive and complete. Detailed
working methods which adhere to the principles stated must be submitted
and agreed prior to construction . . .
THE DEPARTMENT OF THE ENVIRONMENT
PROPERTY SERVICES AGENCY
DIRECTORATE OF CIVIL ACCOMMODATION
PART 1
PROJECT ADMINISTRATION AND CONTROL
RESPONSE TO QUESTIONS 1-12 AND 15-19
A Proposal
by
Laing Management Contracting Limited
1. Management
A very able and experienced management team will be essential on this
project to ensure that progress is maintained at the right level and to
control cost and construction quality...
In addition qualified mechanical and electrical engineers will be
deployed to implement effective controls over services installations and
the commissioning process
5.5 PRODUCTION CONTROL AND CO-ORDINATION
(a) Control
It is essential that all contractors are controlled from the start of the
construction stage and Laing will administer and manage all activities to
ensure that the contracts are efficiently carried out.
Progress will be maintained and contractors managed by the application
of the Laing Management Team to the following:
(i) Ensuring that contractors have adequate supervision, labour
resources, plant and equipment available and that they are aware of the
future needs of the project.
(ii) Identifying the interface activities with other contractors and
establishing in agreement practical working arrangements and clearly
defined responsibilities for work finishing . . .60 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
(b) Co-ordination
(i) Monitor physical progress weekly. Maintain close contact with each
contract management and advise on aspects of work sequencing,
resourcing, work planning and the management of installations.
(ii) Convene and chair contract progress meetings involving consultants
and associated contractors as appropriate to ensure that all co-ordination
aspects with other trades are identified.
(iii) Regularly inspect all installations, plant and equipment for quality,
accuracy and compliance with specification . . .
5.6 QUALITY CONTROL,
(i) Policy
All Laing site management will be responsible for the Quality Control
achieved on this project. . .
Electrical Services...
The timing would also be dependent upon whether the permanent
lighting could be used to assist in achieving the high standard of finishes
that will be required. If this is possible, then the use of insulated boards
will allow progressive connecting and testing.
The installation of the electrical services would be carried out in a
traditional manner. High level cable racking within the plant rooms
would be installed before any pipework to avoid possible access
problems...
Provision of a building management system would require careful
planning, since it would not be possible to completely commission such a
system until the plants being monitored were operational. Early
discussions with the Consulting Engincers would be essential to arrange
the early appointment of this specialist sub-contractor so that all routes
and equipment are known and can be installed as the services proceed.
Commissioning . . .
During the design development stage, testing and commissioning
procedures would be agreed with the Consulting Engineers, taking into
account the PSA documentation requirements.
A detailed programme would be drawn up and agreed with the relevant
parties. This would be reviewed and adjusted as necessary at regular
meetings that would be set up with the specialist contractor. At the same
time procedures, progress and problems would be discussed. Laing believe
that the Consulting Engineers presence would be vital to these meetings
and would welcome their participation . . .
Planning and Design
Planning
The British Library building would be highly serviced and the detailed
planning and control of these installations will be fundamental to the
success of the project . . .
All drawings, specifications and information available would be studied
and discussed with the Consulting Engineer. A detailed master
programme would then be prepared integrated with structural and60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 61
finishings activities, This document would be the key to all future
programme agreements with sub-contractors.
Design
When discussing this subject, particular attention would be paid to the
following point:
(i) An information release schedule would be agreed to ensure that the
appropriate design decisions were taken to allow construction to proceed
while allowing maximum flexibility to the design progress . . .
(iv) Areas requiring detailed co-ordination would be identified.
examples being the main plant areas at basement one and two levels [si
these levels became known as B1 and BY]...
(vi) The formation of economical and practical work packages would be
agreed to ensure financial competition, effective site control and design
flexibility...
Pre-Construction Co-ordination
The successful execution and completion of the contract will depend
upon the controls exercised over the contractors employed...
(iii) A design schedule would be agreed with the Consulting Engineers,
in order that information is released to the contractors to enable them to
achieve the above programmes . . .
(v) Agreement would be reached with the contractors regarding
management communications and the structure of meetings required to
control the contract . . .
Construction Co-ordination
To cover the construction period, controls would be implemented to
ensure that the total installation programme was achieved and that the
required standards of installation were maintained . . .
(i) ... The contractor would be advised on aspects of work sequencing
resourcing, work planning and the management of installations.
(ii) Laing would convene and chair regular meetings with the
contractors and Consulting Engineers to discuss engincering queries and
procedures...
(iii) Regular inspections of the entire works would be carried out to
ensure that all installations conform with the drawings, specifications and
good engineering practice. When sections of work have been completed to
the required standard, the Consulting Engineer would be asked to carry
out his final inspection .. .’
Letter from LM to PSA dated 16 August 1983:
‘AMENDMENTS TO LMC SUBMISSION
These amendments are necessary as a consequence of our accepting the
78 months construction period, our clear understanding of the
contractual relationship between the authority, the design team and
ourselves, and the necessity to appoint an alternative member of our staff
as Resources Manager . . .62 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
3. The diagram indicating the formal relationships between the
authority, the design team and LMC. This diagram will replace the ‘site
organisation’ diagram which was enclosed between pages 7 and 8 of
Part 1 of our original submission.’
87. [have quoted at length those provisions from even longer contractual
documents because they are relied on by the parties and they show the
extensive and deep responsibilities of LM particularly in relation to
co-ordination both of the works and of the design and also with regard to
supervision and inspection and prevention of delay. Those provisions are
important in considering the duties of LM as third parties in this action.
They also form an important part of the contractual scheme and are part of
the context in which the obligations of SVM should be construed.
BB’s contract
88. SVM were responsible for preparing the tender for electrical works
and considering the tenders when they came in. When SVM issued the
tender for the electrical work on 3 November 1987, Haden Young Ltd had
already begun their part of the work on site. Haden Young Ltd’s work
included the installation of metal ducting for air conditioning and that
ducting had to be routed near the routes for electrical installations.
89. Mr Sworder, a chartered engineer employed by SVM as a senior
mechanical engineer with experience of clectrical engineering, gave
evidence about the tenders received. The lowest tender was from BB on 8
February 1988, later revised. The tender was analysed by the SVM in-house
QS team. SVM took the view that the tender was too low. It was 10% to
15% below SVM’s estimated cost and Mr Sworder feared that BB were
seeking to obtain the work by putting in a low price without any profit and
that they would later seek to make their profit by claiming for delay and
disruption at later stages in a lengthy programme. However, BB were able
to respond to all queries about their costings and SVM were required under
PSA rules to recommend acceptance of the tender.
90. Before BB submitted their revised tender for the work, SVM had
already, on 8 April 1988 issued BB with all the design and multi-service
drawings for stage 1AA for the purpose of tendering. Due to changes in
client’s requirements, the architects’ design of the building was changing
and for the purpose of tendering, a moratorium was declared on updating
the electrical drawings, so that the drawings in the hands of BB were not up
to date at the time they entered into the contract. Even those out of date
drawings in the hands of BB at the time of tender related only to stage LAA
of phase 1A. BB were required to tender for stage 1AB of phase 1A on the
basis of provisional sums. This heavy reliance on provisional sums was
itself to cause problems.
91. After the work was begun by BB, a very large number of instructions
(known as management contractor’s instructions) would be issued to bring
the tender scheme up to date with the architect’s scheme as it advanced. BB
were entitled to these management contractor’s instructions to support60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 63
claims for payment above the tendered sum. There were also changes in the
client’s brief which led to more changes in the architect’s scheme and hence
to more changes in SVM’s drawings and more management contractor’s
instructions.
92. By letter dated 5 May 1988 addressed to the Secretary of State for the
Environment via the PSA, BB submitted their revised formal tender for the
work in the electrical installation in phase 1A. That tender was accepted by
letter dated 24 May 1988 from LM writing on behalf of the Secretary of
State.
93. The letter from BB to the Secretary of State dated 5 May 1988
included the following:
‘Further to our tender for the above works dated 8th February 1988
and subsequent meetings we would now confirm the following:—
Our tender letter dated 8th February 1988 is withdrawn and replaced
by this letter...
Organisation and Programme
1. We confirm that the Management Contractor’s restraints
programmes and notes (see Appendix B) will take precedence over our
tender programme and that if awarded the contract, our Works
Programme will be developed in accordance with specification clause
PRE4/351...
At Appendix C to this letter, we have included copies of the following
correspondence with the Management Contractor.
a. Laing Management Contracting Limited’s letter dated the 23rd
February 1988.
b. Balfour Beatty’s letter dated the 2nd March 1988.
c. Laing Management Contracting’s letter dated the 3rd March
1988.
d. Laing Management Contracting’s letter dated the 9th March
1988.
. Balfour Beatty’s letter dated the 17th March 1988.
Laing Management Contracting’s letter dated 17th March 1988.
. Balfour Beatty letter dated the 24th March 1988.
. Balfour Beatty letter dated the 25th March 1988.
(ref: TRH/BK/2413/PTM).
Balfour Beatty letter dated the 25th March 1988
(ref: TRH/BB/2413/JMT).
j. Balfour Beatty letter dated the 25th March 1988.
(ref: TRH/BB/2413/Posttend.1/PJM).
k. Laing Management Contracting letter dated the 14th April 1988.
I. Balfour Beatty letter dated the 18th April 1988.
m. Laing Management Contracting letter dated the 29th April 1988.
n. Balfour Beatty letter dated (Sth) May 1988.
These should be read in full, including accompanying documentation,
and are deemed to be contract documents . . .’
ao ne64 Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
94. The tender form sent with the letter of 5 May 1988 included the
following terms:
“1. [We have perused the following documents:
(1) Prescribed Form of Works Contract for use with PSA
Management Contracts
(2) Abstract of Particulars (Form C1009 Abs-VOP-Formula (T)
(December 1978) BL) (plus Addendum).
(3) Supplementary Conditions Nos. 139A (Form C1953A
(September 1975) BL), 147A(M) (Edition 2) (Form C1961(M) (March
1984)BL), 207 (Form C1992 (May 1980 Amended April 1983) BL), 208
(Form C1993 (May 1980 Amended April 1983) BL), and 213(BL)
(Form C1998 BL).
(4) Specification
(5) Bills of Quantities
(6) Standard Fire precautions PS (available from HMSO Shops).
(7) Drawing Nos all per list at PRE 2/200 of the specification.
(8) The Restraints Programme with conjoined notes, and Concurrent
Works Programme
(9) M&E Schedule 4Z - Addendum to Summary to Tender
(10) Schedule 1 - Standby Generation . . .
ABSTRACT OF PARTICULARS which shall be read in conjunction with
Prescribed Form of Works Contract for use with PSA Management
Contracts.
The Authority shall be The Secretary of State for the
Environment.
The Superintending Officer The Architect, Engineer or Surveyor
(including any person or persons acting
for him) appointed for the time being by
the Secretary of State for the
Environment for that purpose.
NEW BRITISH LIBRARY
METHOD STATEMENT
1.3 All installation and testing will be carried out by or under the
supervision of directly employed qualified staff, and the workmanship
assured by regular inspection by the Manager having responsibility for
this function within the Company . . .
8. Installation method — Cabling
All cable routes will be physically checked and measured and where
necessary steelwork, non standard tray or cleat runs, will be designed
and the drawings submitted for approval.
Prior to cable installation, the route will be checked to ensure that all
steelwork is free from abrasive parts.
Depending on the route length, its configuration and the size of the
cable one of three methods of cable pulling will be employed.60 ConLR Dept of National Heritage v Steensen Varming Mulcahy (a firm) 65
8.1 Hand Pull— The cable gang is spaced over the route and the
cable fed by hand from man to man.
8.2 Bond Pull- Normally employed on heavy non armoured.
cables, this method entails a steel bond being
pulled over the section length by winch and the
cable is tied to this at approximately 2 metre
intervals. When installation is completed ties are
cut and the bond removed. Control would be by
wireless or telephone between drum, winch and
strategic positions along the route.
8.3 Nose Pull- Normally employed on heavy armoured cables
where the leading end has a pulling eye fitted to the
cores and the armour of the cable. A rope or bond
is attached to this pulling eye and the cable is
winched in, This operation would be controlled by
wireless or telephone
[I quote the provisions concerning pulling cables from clause 8 only to
reject them as irrelevant. The plaintiffs relied on them in support of their
case that pulling cables was a proper practice. Evidence showed that
each of those three techniques, 8.1, 8.2, and 8.3, as the words of two of
them expressly indicate, related to heavy cables, not to cables the subject
of this action.]
PRESCRIBED FORM OF WORKS CONTRACT FOR USE WITH
P.S.A, MANAGEMENT CONTRACTS
{This document was not with the copy of BB’s tender, but the terms
are included in the contract. The relevant terms are quoted in the
extracts from LM’s contract above and are not repeated.]
SPECIFICATION
Specification [1b]
PRE 1:
700 THE WORKS generally comprise:—
The provision of working drawings, supply and installation of all
materials and components, testing, commission and setting to work of
Electrical Services and Equipment all as set out and defined in the
technical specification . . .
750 DESIGN RESPONSIBILITY: carry out any design (additional to that
incorporated in the documentation provided by the Authority for tender
purposes) which is necessary to ensure the suitability, compatibility and
correct fixing and location within the system of the components selected
by the Contractor to meet the specified performance of the installation
1150 CO-ORDINATION: together with the Management Contractor
co-ordinate the Works with the work of others employed direct so that
their work and the Contractor’s own work are executed with due regard
to each other and in such a manner that satisfactory construction and
performance of the Works results . . .66
Dept of National Heritage v Steensen Varming Mulcahy (a firm) 60 ConLR
PRE 2:
FORM OF CONTRACT
101 CONDITIONS OF CONTRACT: will be the Prescribed Form of Works
Contract for use with PSA Management Contracts and any amendments
or Supplementary Conditions thereto as defined on the Tender Form...
DRAWINGS
250 FURTHER CO-ORDINATION AND DESIGN: the building consists of
areas of different structures, usages and headrooms thus necessitating
complex structural and services solutions.
The Contract Drawings identify the inter-relation of the services and
their relation to the building components in sufficient detail to
demonstrate that the services can be properly separated from each other
and can be satisfactorily installed and maintained. The Contractor is to
complete the final co-ordination of the Works in conjunction with the
Management Contractor and others employed direct.
The Contract Drawings are not Working Drawings but the Contract
Drawings can be adopted by the Contractor as the basis for the
production of his Installation Drawings . . .
PRE 4:
PROGRAMME...
151 METHOD STATEMENT: the method statement submitted with the
tender shall explain in detail the intentions with regard to all aspects of
the work including staffing, resources, hours of working, sequence and
safe method of working, plant proposals, temporary services, quality
control, protection, inspection, testing, access, unloading, storage and
distribution, etc...
1051 PROGRESS DRAWINGS: keep on site for regular inspection by the
Management Contractor, one set of white prints of the working drawings
to provide a complete record of the Works. Mark-up these drawings at
intervals not exceeding one week to show the progress of work installed.
1052 FURTHER METHOD STATEMENT: when requested by the
Management Contractor elaborate on the method statement submitted
with the tender and update same as necessary. Provide details of safe
methods of working before commencing each part of the Works...
1351 DRAWINGS AND DOCUMENTS TO BE SUPPLIED BY THE CONTRACTOR:
provide drawings, documents and explanatory literature as required by
this specification in adequate time to allow for comment, amendment,
resubmission, approval and general issue to suit the Contractor’s Works
Programme. Normally a period of four weeks shall be allowed between
each submission and return of each drawing, whether approved or not...
Where required obtain approval of drawings and documents from the
Management Contractor before any manufacture or installation is
commenced. Should the Contractor believe during the course of
preparation of such drawings that a variation to the Contract has
occurred then the Management Contractor’s instruction must be obtained