Standard Practice for


Preparing Coal Samples for Analysis 1

This standard is issued under the fixed designation D2013/D2013M; the number immediately following the designation indicates the
year of original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last
reapproval. A superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

This standard has been approved for use by agencies of the U.S. Department of Defense.

1. Scope 2. Referenced Documents


2
1.1 This practice covers the reduction and division of gross 2.1 ASTM Standards:3
or divided samples, and the preparation of composite samples, D121 Terminology of Coal and Coke
up to and including the individual portions for laboratory D2234/D2234M Practice for Collection of a Gross Sample
analysis. of Coal
1.2 Reduction and division procedures are prescribed for D3 l 73/D3 l 73M Test Method for Moisture in the Analysis
coals of the following groups: Sample of Coal and Coke
1.2.1 Group A includes coals that have been cleaned in all D3 1 74 Test Method for Ash in the Analysis S ample of Coal
sizes. and Coke from Coal
1.2.2 Group B includes all other coals. Unknown coals are D3 180 Practice for Calculating Coal and Coke Analyses
to be considered under Group B. from As-Determined to Different Bases
1.2.3 Group A allows smaller weight laboratory samples to D3302/D3302M Test Method for Total Moisture in Coal
be retained than Group B. These lower weights may be used for D4749 Test Method for Performing the Sieve Analysis of
particular coals if they have been shown, by using the Coal and Designating Coal Size
procedures of A l .2, to give a sample preparation and analysis D7430 Practice for Mechanical Sampling of Coal
variance which is no more than 20 % of the total analysis D7582 Test Methods for Proximate Analysis of Coal and
variance. Coke by Macro Thermogravimetric Analysis
Ell Specification for Woven Wire Test Sieve Cloth and Test
1.3 Units-The values stated in either SI units or inch­ Sieves
pound units are to be regarded separately as standard. The El77 Practice for Use of the Terms Precision and Bias in
values stated in each system are not necessarily exact equiva­ ASTM Test Methods
lents; therefore, to ensure conformance with the standard, each E456 Terminology Relating to Quality and Statistics
system shall be used independently of the other, and values
2.2 ISO Standard:4
from the two systems shall not be combined.
ISO 13909 Hard Coal and Coke-Mechanical Sampling
1.4 This standard does not purport to address all of the
safety concerns, if any, associated with its use. It is the 3. Terminology
responsibility of the user of this standard to establish appro­
3 . 1 Definitions of Terms Specific to This Standard-No
priate safety, health, and environmental practices and deter­
terms are used which are specific to this practice. Many terms
mine the applicability of regulatory limitations prior to use.
used in this practice may be found in Terminologies D121 and
1.5 This international standard was developed in accor­
E456 and in Practice E l 77.
dance with internationally recognized principles on standard­
ization established in the Decision on Principles for the
4. Summary of Practice
Development of International Standards, Guides and Recom­
mendations issued by the World Trade Organization Technical 4.1 T hree processes of sample division and reduction are
Barriers to Trade (TBT) Committee. covered as follows:

1 This practice is under the jurisdiction of ASTM Committee D05 on Coal and
Coke and is the direct responsibility of Subcommittee D05.23 on Sampling. 3 For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Current edition approved Oct. I, 2021. Published December 2021. Originally contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
approved in 1962. Last previous edition approved in 2020 as D2013/D2013M - 20. Standards volume information, refer to the standard's Document Summary page on
DOI: I0.1520/D2013_D2013M-21. the ASTM website.
2 For more detailed explanation of this practice, see Keller, G. E., "Determination 4 Available from International Organization for Standardization (ISO), ISO
of Quantities Needed in Coal Sample Preparation and Analysis," Transactions, Vol Central Secretariat, BIBC II, Chemin de Blandonnet 8, CP 401, 1214 Vernier,
232, 1965, pp. 218-226. Geneva, Switzerland, http://www.iso.org.

Copyright ©ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
� D2013/D2013M - 21
4.1.1 Procedure A-Manual riffles are used for division of height with smooth, hard, well-rounded, flint pebbles, or
the sample and mechanical crushing equipment for the reduc­ equivalent, that do not increase ash content of the sample.
tion of the sample. 6.1.4 Bucking Board (Chrome Steel) or Mortar (Agate or
4.1.2 Procedure B-Mechanical sample dividers are used Equivalent) and Pestle-Only for reducing the small fraction
for the division of the sample and mechanical crushing of sample, not passing a 250 µm [No. 60] sieve after pulveri­
equipment for the reduction of the sample. zation.
4.1.3 Combined Procedure A and B-The two procedures 6.2 Sample Dividers:
may be combined at any stage.
6.2.1 Mechanical-A mechanical sample divider using a
reciprocating or rotating cutter, a rotating hopper and spout, a
5. Significance and Use
rotating slotted cone, a reciprocating hopper and fixed cutter,
5.1 Other standards are used to collect the gross sample: bucket cutter with either bottom dump or inverting discharge,
Practice D2234/D2234M allows for one division of the gross slotted belt, rotary disk divider, mechanical stopped or moving
sample before crushing. The mass and top size of the gross or belt sweeper, or other acceptable devices for dividing the
divided sample collected by using these guides and practices sample. Typical mechanical sample dividers are shown in Fig.
are usually too large for chemical or physical testing. Practice 1 . These illustrate various designs, but other acceptable designs
D2013/D2013M provides instructions for reducing and divid­ are available.
ing the gross or divided sample, by on-line or off-line 6. 2.2 Riffle-A manual sample divider that splits the coal
processes, or both, to a top size and mass suitable to the stream into two parts when it is directed through alternating
performance of testing. Any bias in the gross or divided sample slots. Riffle slots shall be at least three times the top size of the
before adherence to this practice will remain in the final sample coal being divided and have an even number of alternating
resulting from use of this practice. Therefore, carefully select slots, in order to achieve similar mass delivered to each catch
the standard to be used to collect the gross sample. pan. Riffles shall be enclosed. The slope of the feed chutes and
riffles shall be at least 60°.
5.2 Division and reduction of a sample may occur at more
than one location. Most often, the sample is collected, reduced, 6.2.2.l Large Riffle-A manual sample divider with at least
and divided (one or more times) by use of a mechanical fourteen 1 2.7 mm [l/2 in.] to 25.4 mm [1 in.] divisions for
sampling system. The remaining sample may be further di­ dividing subsamples of coal passing 2.36 mm [No. 8], and
vided on-site to facilitate transporting it to the laboratory where 4.75 mm [No. 4] sieves. See Fig. 2.
further reduction and division likely occurs before analysis. 6.2.2.2 Small Riffl e-A manual sample divider with at least
twenty-four 6.35 mm [l/4 in.] to 9.52 mm [3/s in.] divisions for
5.3 In places, this practice requires air drying the sample dividing the subsamples of coal passing 250 µm [No. 60]. See
before subsequent reduction. Procedures for air drying and Fig. 3.
air-dry loss determination are provided in Test Method D3302/
6.2.2.3 Feed Scoop-A feed scoop or pan having straight
D3302M.
sides and a width equal to the effective width of the riffle shall
5.4 Most often, samples are reduced and divided to an be used to feed the riffle.
analysis sample. However, some tests may require a sample of 6.2.2.4 Feed Chute-A feed chute shall be used as shown in
different mass or top size. This procedure may be used to Fig. 2. The minimum discharge opening of the feed chute shall
provide a sample of any mass and size consist from the gross be the same width as the riffle slot opening.
or divided sample to, and including, the analysis sample.
6.3 Mixing Wheel-One type of a mechanical device used
5.5 This practice also specifies how to prepare composite for mixing the analysis sample. In this device, the samples are
samples, if required. in closed containers attached to the rim of a wheel at an angle
of 45° with the horizontal wheel shaft. The wheel provides
6. Apparatus space for a number of containers depending on its diameter and
is turned slowly by a small motor and reduction gear. The
6.1 Crushers or Grinders-Jaw, cone, or rotary crusher;
wheel should be rotated at a speed so that the particles fall
hammer mill; roll; or other suitable crusher to reduce the
gently from top to bottom of the container, mixing the sample
sample to pass the sieve designated in 6.4. Hard steel or chilled
thoroughly. The container should be about half full and never
iron plate with tamper, sledge, or hand bar may be used for
more than two-thirds full to obtain good mixing of the sample.
preliminary crushing of any large lumps in the sample before
feeding into the crusher. Crushers should be designed and 6.4 Sieves-A set of sieves whose dimensions are in accor­
operated in a manner to minimize the effect of induced air dance with Specification Ell, of the following sizes, with
circulation and thus the potential for drying the coal. cover and receiver:
6.1.1 Pulverizer or Mill-For final reduction of laboratory No. Size
sample to the 250 µm [No. 60] sieve size, the following
4 4.75 mm
equipment may be used:
8 2.36 mm
6.1.2 Hammer Mill-Completely enclosed to avoid loss of 20 850 µm
dust or moisture. 60 250 µm

6.1.3 Porcelain-Jar Ball Mill-This mill shall be approxi­ 6.5 Laboratory Sample Containers- Heavy vapor­
mately 230 mm [9.0 in.] in diameter and 250 mm [10.0 in.] in impervious bags, properly sealed, or noncorroding cans such as

2
AnT�-,
c!lffifl D2013/D2013M - 21

(a) Reciprocating Cutter (b) Rotary Cutter (s)


MOTOR AND DRIVE
FEED MOTOR AND
MECHANISM
GEAR DRIVE
15 TO
50 RPM

SAMPLE
REJECT

(c) Rotating Hopper and Spout (d) Rotating Cone (s)


FEED � MOTOR DRIVE
60 RPM

REJECT

SAMPLE
REJECT
(a) Reciprocating Cutter-Fig. 1 (a) shows a section of a cutter which is moved across a stream of coal. At regular inteNals, the cutter movement is reversed and a sample
increment is collected on each trip through the coal stream.
(b) Rotating Cutter-Fig. 1 (b) shows two cutters attached to a hollow, rotating shaft. Each cutter is designed to extract increments from the feed and to discharge these
into the hollow shaft. One or more cutters may be used.
(c) Rotating Hopper and Spout- Fig . 1 (c) shows the totaling hopper that receives the crushed sample and discharges it through a spout over one or more stationary
cutters.
(d) Rotating Cone-A sampler developed by the British National Coal Board. Two slotted cones are locked together and rotated on a vertical shaft so that on each
revolution the common slot operating intercepts the falling stream of coal and collects an increment.
FIG. 1 Mechanical Sample Dividers

those with an airtight top, friction top, or screwtop sealed with be checked at intervals by the methods described in Annex A1
a rubber gasket and pressure-sensitive tape for use in storage or Annex A2. It is necessary that the variance of sample
and transport of the laboratory sample. Glass containers, sealed division and analysis Scta2 be not more than 20 % of the total
with rubber gaskets, may be used, but care must be taken to variance of sampling, division, and analysis So2•
avoid breakage in transport. 7 .1.1 The sample preparation operations should be per­
7. Precautions formed in an enclosed space, roofed, cool, and free from
excessive air movements.
7.1 Gen eral-The preparation of the gross or divided
sample, or the composite sample, shall be performed by, or 7.2 Number of Tests-Before preparing the gross or divided
under the direct supervision of, personnel knowledgeable of sample, or the composite sample, consider the number and
proper sample handling practices. Sample preparation should nature of the analysis and tests to be performed. A separate

3
� D2013/D2013M - 21

FIG. 2 Large Sample Divider (Riffle)

moisture laboratory sample may be required, and portions may 7.3.3 While awa1tmg preparation, the gross or divided
be required for grindability and other tests. Also, a reserve sample shall be protected from moisture change as a result of
sample may be desired in case a check analysis or test is exposure to rain, snow, wind, and sun on contact with
required. absorbent materials.
7.3 This practice specifies situations when air drying the 7.3.4 Whenever subsamples are stored or transported, the
sample is necessary during sample preparation. Test Method containers and subsample shall be weighed and equilibrated to
D3302/D3302M specifies procedures for air drying and calcu­ the new atmosphere by air drying, and the weight loss or gain
lation of percent air dry loss. shall be used in the calculation of moisture content.
7 .3 .1 Calculate and record air-dry loss determination each
time air drying is performed. 7.4 Whenever a distinct change of humidity occurs during
7.3.2 In handling, reducing, and dividing the sample, all the course of preparation of an air-dried subsample, the
operations shall be done rapidly and in as few operations as subsample shall be weighed and its moisture equilibrated with
possible, since moisture loss depends on several factors other the new atmosphere, and the loss or gain in mass shall be used
than total moisture content, such as time required for crushing, in the calculation of moisture content.
atmospheric temperature and humidity, and type of crushing
equipment.

4
� D2013/D2013M - 21

FIG. 3 Small Sample Divider (Riffle)

TABLE 1 Preparation of Laboratory Sample


8. Sieve Tests
Crush to pass at least 95 % through
Divide to a minimum
8.1 The errors of sample division are sensitive to the top weight of, gA
Group B
sieve
size, and therefore, it is important to make a periodic sieve test Group A
of the product of the sample crusher. Sieve tests shall be made 4.75 mm [No. 4] 2000 4000
and reported in accordance with Test Method D4749. 2.36 mm (No. 8] 500 1000
850 µm [No. 20] 250 500

9.
250 µm [No. 60] 50 50
Procedure (100 % through)

9.1 Mass-The minimum allowable mass of the sample at A If a moisture sample is required, increase the quantity of No. 4 (4.75 mm] or
any stage depends on the top size, the variability of the No. 8 (2.36 mm] sieve subsample by 500 g.

constituent sought, and the degree of precision desired (Table


1 ).
9.2 Reduction and Division (See Fig. 4 for flowchart): 9.2.3.1 Reduce the gross or divided sample to a top size of
9.2.1 It is permissible to air dry the sample before crushing. 4.75 mm [No. 4] or 2.36 mm [No. 8] sieve, taking precautions
Samples may require air drying to feed properly through the in accordance with Section 7 .
reduction and dividing equipment. Sometimes there is an 9. 2.3.2 Determine the number of passes required in the
interest in determining the air-dry loss value before crushing. riffling operation from the total mass of the gross sample and
Air dry in accordance with Test Method D3302/D3302M. the minimum permissible mass in accordance with Table 1 .
9.2.2 In the reduction and division of gross or divided 9.2.3.3 Divide the crushed sample by using a large riffle.
samples for which total moisture content is to be determined, Riffles properly used will reduce sample variability but cannot
the precautions in 7.3 and 7.4 must be followed. eliminate it. A typical enclosed riffle is shown in Fig. 2 and
9.2.3 Procedure A-Manual Riffeing: described in 6.2.2. Pass the coal through the riffle from a feed

5
� D2013/D2013M - 21
Acquire Uncrushed
Gross or Divided
Sample

Air-dry
Yes
Sample

No

Reduce to Topsize of
Yes
4.75-mm (No. 4) Sieve

No
Divide to Minimum Wt.
Reduce to Topsize Specified in Table 1
2.36-mm (No. 8) Sieve

Divide to Minimum Wt. Air-dry


Specified in Table 1

Reduce to Topsize
Air-dry 2.36-mm (No. 8) Sieve

Is Sample
to be Reduced to Reduce to Topsize of
Yes
Topsize of 850-µm 850-µm (No. 20) Sieve
(No. 20) Sieve?

No Divide to Minimum Wt.


"" --- --------1 Specified in Table 1

Reduce to 250-µm
(No. 60) Sieve

Divide to Minimum
50 gr. Sample(s)

FIG. 4 Sample Preparation Flowchart

scoop, feed bucket, or riffle pan having a lip or opening the full coal to build up in or above the riffle slots. If it does not flow
width of the riffle. When using any of the preceding containers freely through the slots, shake or vibrate the riffle to facilitate
to feed the riffle, spread the coal evenly in the container, raise even flow.
the container, and hold it with its front edge resting on top of 9.2.3.4 If the initial crushing was only to 4.75 mm [No. 4]
the feed chute, then slowly tilt it so that the coal flows in a sieve size, reduce to 2.36 mm [No. 8] sieve size after dividing
uniform stream through the hopper straight down over the to no less than the quantity specified in Table 1 for a 4.75 mm
center of the riffle into all the slots, then into the riffle pans, one [No. 4] sieve size.
half of the sample being collected in each pan. Under no 9.2.3.5 After reducing to 2.36 mm [No. 8] sieve size, divide
circumstances shovel the sample into the riffle or dribble into the subsample by riffling to no less than the quantity specified
the riffle from a small-mouthed container. Do not allow the in Table 1 for a 2.36 mm sieve size.

6
� D2013/D2013M - 21
9.2.3.6 With suitable pulverizing equipment (see 6.1 ), re­ percent moisture and other as-received basis data determined
duce the 2.36 mm [No. 8] sieve size subsample to a 250 µm on the composite may differ slightly from the weighted average
[No. 60] sieve size. Divide the ground subsample by riffling, of the individual samples. In addition, errors associated with
using the small riffle (see 6.2.2) until a minimum of 50 g is extraction of increments from multiple samples are unknown
obtained. Quickly pass the subsample through a 250 µm and can vary from sample to sample and with the absolute level
[No. 60] sieve. Reduce the particles retained on the screen, on of each analyte. Taking these and other issues into account
a bucking board or mortar and pestle to pass the sieve, and add leads to the requirement that preparation of composites be
to what passed through the sieve and mix thoroughly. This is performed in accordance with the procedures described below.
the analysis sample. The details pertaining to the preparation of composite samples
9.2.3.7 As an alternative to the procedure of 9.2.3.6, the should be agreed to by all concerned parties.
2.36 mm [No. 8] sieve size subsample may be reduced to pass NOTE 2-As used in this standard, the term represent (together with its
95 % through a 850 µm [No. 20] sieve. Divide this subsample related forms) does not imply that samples satisfy a particular quantitative
or statistical relationship to the coal that was sampled. The term is used
by riffling with the small riffle to not less than the quantity
within Practice D2013/D2013M in the sense of its broad dictionary
specified in Table 1, and then reduce to 250 µm [No. 60] sieve definition, that is, to simply stand for or symbolize larger quantities of
size in accordance with 9.2.3 .6. coal.
9.2.3.8 Thoroughly mix, preferably by mechanical means, NOTE 3-As used in this standard, parameters that are additive are those
the analysis sample, weighing not less than 50 g, before having values not affected by interactions between the physical and
chemical properties of the combined individual samples. Non-additive
extracting portions for analysis (see 6.3). parameters are those for which such interactions may occur or those for
9.2.4 Procedure B-Mechanical Division: which definitive information on interactions is not available.
9.2.4. 1 Reduce the gross or divided sample in stages and 10.2 If two or more samples have been collected by a single
divide by suitable mechanical sample dividers (see 6.2.1) to mechanical coal sampling system operated under constant
quantities not less than those shown in Table 1. settings, prepare the composite by directly combining all of the
9.2.4.2 Mechanical division of the sample consists of auto­ material from all samples. If it is desired to decrease the total
matically collecting a large number of increments of the mass of the composite, it is acceptable to combine equal
properly reduced sample. Distribute this large number of percentages (for example, 75 % or 50 %) of each individual
increments equally throughout the entire discharge from the sample, all of which have been divided in the same manner and
sample crusher because crushers can introduce appreciable according to this standard. Determine whether sample masses
segregation. At each stage of division, take at least 60 have been decreased prior to arrival of samples at the labora­
increments. tory and, if so, by what percentages. Account for that informa­
NOTE I-It is recommended that, in the case of mechanical division in tion when making the composite. The samples may be reduced
which an increment is not thoroughly mixed with other increments before in nominal top size (for example, to pass a 2.36 mm [No. 8]
division, a portion of each increment be collected by the subsequent stage sieve) to facilitate the compositing process. Adhere to the
increment collection process. minimum masses required in Table 1. Observe the precautions
9.2.4.3 Thoroughly mix the analysis sample, 100 % through of Practice D7430 and Test Method D3302/D3302M, as well as
250 µm [No. 60] sieve and weighing not less than 50 g, in those found in this standard, to guard against unaccounted-for
accordance with 9.2.3.8 before extracting portions for analysis. changes in moisture. It is advisable to mix the composite
sample thoroughly, but without altering the moisture content,
10. Preparation of Composite Samples to Represent Lot­ before reducing or dividing to smaller quantities.
Size (or Consignment-Size) Quantities of Coal 10.3 If two or more samples have been collected by multiple
10.1 There are several issues to consider when deciding mechanical coal sampling systems, or if manual sampling
whether to make a physical composite of separate samples practices have been used and only additive parameters are
collected to represent different parts of the same lot (or required for analysis, the individual samples can be tested
consignment). See Note 2. When the analytical parameters of separately and a ton-weighted mathematical average
interest are additive (for example, proximate and ultimate performed, or a composite sample may be prepared. However,
analyses), it is not unusual to test the individual samples and if testing is to be performed for non-additive parameters, a
perform a ton-weighted mathematical average to determine the composite sample must be prepared. Either 250 µm [No. 60]
result for the lot (or consignment) . See Note 3 . On the other sieve size samples or samples with larger particle sizes may be
hand, when the sought-after parameters are non-additive (for used. Minimize the chance for unmeasured changes in mois­
example, ash fusibility, Hardgrove grindability, and rheological ture by working quickly while samples are exposed to the
properties), analysis of a composite sample is the only way to atmosphere during the compositing process.
achieve a meaningful test result. Another consideration is that 10.3.1 If a 250 µm [No. 60] sieve size composite is needed,
since there are no provisions in this standard for dividing proceed as follows.
samples of top size larger than 250 µm [No. 60] by means other 10.3.1.1 Determine the residual moisture content of each
than riffling or mechanically subsampling, the exact masses 250 µm [No. 60] sieve size sample according to Test Methods
needed for preparation of composite samples containing larger D3173/D3173M, D3302/D3302M, or D7582. Designate the
particles are not attainable using those processes alone. It is results R 1, R2 , R3 ... R,,.
also important to realize that making a composite can some­ 10.3.1.2 Ascertain the mass of coal in the lot or sub-lot
times result in unintended moisture changes after which the represented by each sample and designate these values L1, L2 ,

7
� D2013/D2013M - 21
L3 ... L,,. Add the individual lot or sub-lot masses to find the least that shown in Table 1 , if possible, for the composite
total sampled lot (or consignment) mass (L,0,a1). sample. See Note 4. Multiply the desired composite mass by
10.3.1.3 Select an appropriate desired mass (MJ of at least the percentage of the total that each sample represents to find
50 g, if possible, for the composite sample. the exact number of grams for each sample to be used in
10.3 . 1.4 Calculate, according to the following, the mass of making the composite.
each sample (M1, Mb M3 ... M,,) to be combined to make the 10.3.2.2 Using a riffle, divide one sample to obtain approxi­
composite sample. mately the number of grams for that sample as calculated
above. It is acceptable in this instance only to produce riffle
_ (MJ (L,)!(L,0"'1)
MI - (100- R,)IIOO (1) portions that are smaller in mass than stated in Table 1. Select
and combine the riffle portions that yield a close approximation
10.3.1.5 Obtain the calculated mass of each sample to the of the desired mass, and add or subtract particles to obtain the
nearest O.OO l g by adding or subtracting particles as necessary, exact desired mass for that sample to the nearest 0.01 g. See
and combine to form the composite sample. Mix by mechani­ Note 5. Repeat for all samples, then combine the riffled-and­
cal means before extracting portions for analysis. adjusted portions of the original samples to form the compos­
10.3.1.6 Calculation of as-received basis data (see Test ite.
Method D3302/D3302M and Practice D3180) from the as­
analyzed basis data obtained by testing the composite sample
Norn 4-For guidance on minimum sample mass when top sizes are
greater than specified in Table 1 of this standard, it may be of value to
requires the equivalent air-dry loss of the composite (ADLJ. consult Table 1 in Part 4 of ISO 13909.
Compute that value as shown below: NOTE 5-It is highly unlikely that the exact number of grams needed for
each sample can be obtained using a riffle. The user must exercise
ADLc = (ADLi) (L,IL,0tal)+(ADL2) (L,IL,orJ ... +(ADL,,) (L,,IL,0,01) judgment to assess when the riffled mass is sufficiently close to the desired
(2) mass and when to add or subtract sample particles so as to not materially
affect the results of the test(s) for which the composite sample is being
where: prepared.
ADL1 air-dry loss of first sample,
ADL2 air-dry loss of second sample, and 11. Precision and Bias
ADL,, air-dry loss of nth sample. 11.1 The precision of sample preparation (and analysis) can
10.3 .2 If a composite with particles larger than 250 µm be checked by Annex A l and Annex A2. Since this practice
[No. 60] sieve size is needed, proceed as follows. does not produce a numerical result, determination of bias is
10.3.2.1 Ascertain the mass of the sub-lot or lot represented not applicable.
by each sample and the total mass represented by all samples.
Calculate the percentage of the total sub-lot or lot that each 12. Keywords
sample represents. Select an appropriate desired mass of at 12.1 coal; composite; division; reduction

8
� D2013/D2013M - 21

ANNEXES

(Mandatory Information)

Al. METHOD OF CHECKING THE PRECISION OF SAMPLE PREPARATION AND ANALYSIS

Al.1 Scope

A1.1.1 This method covers procedures for checking preci­ A1.2.6.1 Make calculations on the first set of ten samples so
sion of sample preparation and analysis of the various stages. that the variance for each of the stages may be checked and
The data obtained from tests using consistent sample prepara­ corrective action, if needed, may be taken.
tion and analysis methods are used to estimate the random Al.2.6.2 Continue this cycle of tests until three successive
errors in the various stages of sample division and analysis. sets of ten samples are satisfactory.
A1.1.2 Coals used in each series of tests should be of similar
ash content. Al.3 Calculation

A l .3.1 The analysis of variance is based upon the calcula­


Al.2 Procedure
tions of mean squared differences with the eight determinations
Al.2.1 Reduce the gross sample to 95 % through 4.75 mm for each sample taken in different combinations. Calculate the
[No. 4] sieve and divide, using either riffles or mechanical variances of these combinations: VP, the variance of the
sample dividers, into two equal parts. difference between duplicate analyses; VQ, the variance of the
Al.2.1.1 Many laboratories are crushing directly to difference between the averages of duplicate analyses; and VR,
2.36 mm [No. 8] size instead of to No. 4, but for purpose of test the variance of the difference between the average of each four
it is usually best to use both No. 4 and 8 sizes since we can analyses, as follows:
assume that crushing directly to No. 8 would give a variance no
greater, and probably less, than crushing to No. 4 and then to VP=(1/4N) L[(x 1 -x 2)2 +(x 3 -X4)2 +(Y 1 - v2)2 +(Y3
-Y4)2 (AI. 1)
No. 8. If, however, it is desired to crush directly to No. 8,
follow the same procedure as if crushed to No. 4 and then to
where:
No. 8.
N number of tests, and
Al.2.2 Divide each subsample by riffling or mechanically to Xl, X2, X3, X4, Yl, Y2, Y3, Y4 individual ash
no less than weights as outlined in Table 1. determinations.
Al.2.2.1 Individual weights should not vary more than
+ Yl Y2
: 0 % from the weights given in Table 1, and the average of
:::t:2
all tests should be within :::t:: 10 % of the weights.
VQ= ( �) [ ( ;
2
L
x1 x 2 X 3 x4
_
; r ( ;
Y+
3 Y4 2
Al.2.3 Reduce the 4.75 mm [No. 4] sieve laboratory sample _
)]
2
(A.
l 2)
95 % through 2.36 mm [No. 8] sieve and divide, using either
l
x1+x2 x3+X 4 -Y+Y2 Y+
3 Y4
riffles or mechanical sample dividers, into two equal parts
without discarding. Divide each subsample to no less than the
VR=( !l N)L [( ; : rJ
minimum weights as outlined in Table 1. (Al.3)

Al.2.4 Reduce each part of the No. 8 subsample to 100 % Al.3.2 The variances can be resolved further in terms of
through 250 µm [No. 60] sieve and divide to no less than 50 g. variance caused by the first stage of sample preparation, Vl;
variance caused by the second stage of sample preparation, V2;
Al.2.5 Determine ash in accordance with Test Method
and the variance of analysis, Va.
D3 l 74 in duplicate on each analysis sample.
Al.2.5.1 This test can be used for sulfur, Btu, or other where:
determinations, instead of ash, if desired. Va 1/2 VP,
Al.2.5.2 If possible, the duplicate determinations should be V2 1/2 VQ - 1/4 VP, and
made at different times and preferably by different analysts. Vl 1/2 VR - 1/4 VQ.
The purpose of these tests is not to find out how accurate a
Al.3.3 The total variance of sample preparation and
laboratory can be, but to find out actual variances of prepara­
analysis, Scta2, is given by the equation:
tion and analysis in the normal routine of a laboratory
following a prescribed procedure. (A1.4)

Al.2.6 Treat three sets of ten samples each in the preceding Al.3.4 The calculations of the variances of sample prepa­
manner. ration are illustrated in Table A1.1.

9
� D2013/D2013M - 21
TABLE A 1.1 Illustrations of the Calculation of the VariancesA of Sample Preparation at the Various Stages and Analysis
Test No. X1 X2 Difference Difference2 X3 X4 Difference Difference2
1 1 2. 1 3 1 2. 1 0 0.03 0.0009 1 2.03 1 2.05 -0.02 0.0004
2 1 0.67 1 0.73 -0.06 0.0036 1 0.69 1 0.78 -0.09 0.0081
3 1 0.93 1 1.10 -0. 1 7 0.0289 11 .36 1 1 .45 -0.09 0.0081
4 1 2.05 12.02 0.03 0.0009 1 2.17 1 2.23 -0.06 0.0036
5 1 2.74 1 2.70 0.04 0.00 1 6 1 2.71 1 2.76 -0.05 0.0025
6 1 2.47 1 2.30 0. 1 7 0.0289 1 2.21 1 2.14 0.07 0.0049
7 1 1 .94 1 1 .99 -0.05 0.0025 1 2.08 1 2.17 -0.09 0.0081
8 1 2.52 12.63 -0. 1 1 0.0 1 2 1 1 2.76 1 2.82 -0.06 0.0036
9 1 2.01 1 2.05 -0.04 0.00 1 6 1 1 .94 1 1 .77 0.17 0.0289
10 1 0.96 1 0.88 0.08 0.0064 11 .37 1 1 .40 -0.03 0.0009
Total 1 1 8.42 1 1 8.50 0.0874 1 1 9.32 1 1 9.57 0.0691
Avera e 1 1 .84 1 1 .85 1 1 .93 1 1 .96
Test No. Y1 Y2 Difference Difference2 Y3 Y4 Difference Difference2
1 1 2.00 1 2.01 -0.01 0.0001 1 2.00 1 2.00 0.00 0.0000
2 1 0.53 1 0.65 -0. 1 2 0.0144 1 0.60 1 0.62 -0.02 0.0004
3 1 1 .37 1 1 .47 -0. 1 0 0.0100 11 .22 1 1 .35 -0. 1 3 0.0169
4 1 2. 1 3 1 2. 1 0 0.03 0.0009 1 2.01 1 2.04 -0.03 0.0009
5 1 2.60 1 2.60 0.00 0.0000 1 2.51 1 2.40 0.11 0.0121
6 1 2.09 1 2. 1 5 -0.06 0.0036 1 2.18 1 2.20 -0.02 0.0004
7 1 1 .93 1 1 .87 0.06 0.0036 1 1 .71 1 1 .73 -0.02 0.0004
8 1 2.57 1 2.57 0.00 0.0000 1 2.58 1 2.61 -0.03 0.0009
9 1 1 .81 1 1 .88 -0.07 0.0049 1 1 .70 1 1 .84 -0. 1 4 0.0196
10 1 1 .57 1 1 .48 0.09 0.0081 11 .54 1 1 .36 0.18 0.0324
Total 1 1 8.60 1 1 8.78 0.0456 1 1 8.05 1 1 8.15 0.0840
Avera e 1 1 .86 1 1 .88 1 1 .81 1 1 .82
Test No. X(1 + 2);2 X(3 + 4);2 Difference Difference2 Y(1 + 2);2 Y(3 + 4);2 Difference Difference2
1 1 2. 1 1 1 2.04 0.07 0.0056 1 2.00 1 2.00 0.00 0.0000
2 1 0.70 1 0.73 -0.03 0.00 1 2 1 0.59 1 0.61 -0.02 0.0004
3 1 1 .01 1 1 .40 -0.39 0.1521 11 .42 1 1 .28 0.13 0.0182
4 1 2.03 1 2.20 -0. 1 6 0.0272 1 2.11 1 2.02 0.09 0.0081
5 1 2.72 12.73 -0.01 0.0002 1 2.60 1 2.45 0.14 0.0210
6 1 2.38 1 2. 1 7 0.21 0.0441 1 2.12 1 2.19 -0.07 0.0049
7 1 1 .96 1 2. 1 2 -0. 1 6 0.0256 1 1 .90 1 1 .72 0.18 0.0324
8 1 2.57 12.79 -0.21 0.0462 1 2.57 1 2.59 -0.02 0.0006
9 1 2.03 1 1 .85 0. 1 7 0.0306 1 1 .84 1 1 .77 0.07 0.0056
10 1 0.92 1 1 .38 -0.46 0.2162 11 .52 1 1 .45 0.07 0.0056
Total 1 1 8.46 1 1 9.44 0.5491 1 1 8.69 1 1 8.10 0.0969
Average 1 1 .85 1 1 .94 11 .87 1 1 .81
Test No. X(1 + 2 + 3 + 4)/4 Y(1 + 2 + 3 + 4)/4 Difference Difference2
1 2.07 1 2.00 0.07 0.0056
2 1 0.71 1 0.60 0.11 0.01 38
3 1 1 .21 1 1 .35 -0.04 0.0203
4 1 2. 1 1 1 2.07 0.04 0.0022
5 1 2.72 1 2.52 0.20 0.0400
6 1 2.28 1 2. 1 5 0.1 2 0.0156
7 1 2.04 1 1 .8 1 0.23 0.0552
8 1 2.68 1 2.58 0.1 0 0.100
9 1 1 .94 1 1 .80 0.1 3 0.0182
10 11.15 1 1 .48 -0.33 0.1122
Total 1 1 8.95 1 1 8.39 0.2932
Avera e 1 1 .90 1 1 .84

VP= 1/40 (0.0874 + 0.0691 + 0.0456 + 0.0840) = 0.0071


VO = 1/2o (0.5491 + 0.0969) = 0.0323
VR = 1/10 (0.2932) = 0.0293
T hen:
Va = 1/2 (0.0071) = 0.0035
V = 1/ 2 (0.0323) - 1/4 (0.007 1 ) = 0.0144
v, = 112 (0.0293) - 1/4 (0.0323) = 0.0066
2

Sda2 = 0.0035 + 0.0144 + 0.0066 = 0.0245

A This table contains data taken from a computer printout with rounding errors that are not involved in the overall calculation. Data taken at intermediate steps are not
consistent within limits of these rounding errors. Thus, the difference 0.072 shows a result of 0.0056 which is correct when all places are carried in the calculation.

10
� D2013/D2013M - 21
A2. METHOD FOR DETERMINING THE OVERALL VARIANCE OF DIV ISION AND ANALYSIS

A2.1 Scope

A2.l .1 Legitimate estimates of the variance of division and where:


analysis, Scta2, can only be made using data obtained from tests s a2 variance of division and analysis,
q
that were run using consistent division and analysis methods. x sum of the squares of the four ash results, and
Coals used in these variance tests should be of similar ash <Dl sum of the ash results, quantity squared.
content. Any gross change in the division and analysis methods
A2.2.3 Make progressive checks as the work is carried out
or in the ash characteristics of the test coal will nullify the test
by using the data in groups of five. In any group of five
results.
estimates of Scta2 based on four subsamples for each estimate,
the ratio of the largest estimate to the average of the group
A2.2 Procedure
should not exceed 2.99, in 19 out of 20 cases. Investigate
A2.2.l The following four-step method uses the regular values in excess of this ratio before proceeding with the test. In
gross or divided samples obtained from normal sampling addition, after completing 30 sets, by groups of five, the ratio
operations: of the largest group average to the overall average should not
A2.2. l .1 Crush the gross sample to the same mesh as that exceed 1.88 in 19 cases out of 20. If these criteria are met, the
normally obtained when preparing the gross sample for variance of division and analysis may be taken as the overall
processing, average Scta2 of the 30 sets of data. If these criteria are not met,
A2.2.l.2 Divide the sample into four equal parts, according follow the procedure described in Practice D2013/D201 3M for
to the normal routine laboratory procedure, the necessary information to improve techniques of division
A2.2.l.3 Reduce the four subsamples to laboratory analysis and analysis.
samples, and A2.2.4 Example-A complete example illustrating the pro­
A2.2. l.4 Analyze each analysis sample for dry ash content. cedure for determining the variance of division and analysis is
given in Table A2. l . In this example, gross sample No. 24, the
A2.2.2 Calculate the variance of division and analysis for
highest individual ash sample in the group (19.28 % ash), has
each gross or divided sample from the "within set sums of
an unusually high variance of division and analysis. The
squares" for the replicate determinations as follows:
behavior of samples 21 to 30 indicates that trouble can be
sda2 = L2> 2 - C2:X)214J13 expected when the ash exceeds 15 % (see Table A2.l).

11
� D2013/D2013M - 21
TABLE A2.1 Determination of Variance of Division and Analysis-Use of Four Analysis Samples for Each Gross Sample

NOTE 1-Ten percent ash was subtracted from each of the ash results listed to simplify the calculations.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
Gross Analysis Samples Average
Sample Ix (Ix)2/4 (6)-(7) (8)/3 = Sda2 Sets of
Number 2 3 4 5 Sda2
1 .22 1 .37 1 .56 1 .7 1 5.86 8.7230 8.5849 0.1381 0.0460 1 .312925
2 1 .29 1 .1 7 1 .70 1 .57 5.73 8.3879 8.2082 0.1 797 0.0599 1 .708181
3 1 .56 1 .66 1 .58 1 .64 6.44 1 0.3752 1 0.3684 0.0068 0.0023 0.064648
4 5.63 5.57 5.93 5.52 22.65 1 28.3571 1 28.2556 0. 1 0 1 475 0.033825 0.964729
5 3.90 3.87 3.58 3.56 1 4.91 55.6769 55.5770 0.0999 0.0333 0.94951 8
Average 11.118 0.035062 0.745372
6 0.64 0.42 0.80 0.73 2.59 1 .7589 1 .6770 0.0819 0.0273 1 .12
7 2.47 2.44 2.74 2.68 1 0.33 26.7445 26.6772 0.0673 0.022425 0.9191 2
8 3.70 3.53 3.43 3.43 1 4.09 49.6807 49.6320 0.0487 0.0162 0.66
9 3.59 3.73 4.1 3 3.80 1 5.25 58.2979 58.1 406 0.1573 0.0524 2.15
10 2.1 4 2.17 2.25 2. 1 1 8.67 1 8.8031 1 8.7922 0.0109 0.0036 0.15
Average 1 0. 1 86 0.0244 0.52
11 5.71 5.61 5.61 5.71 22.64 1 28.1 524 1 28.1 424 0.0100 0.0033 0.09
12 3.21 3.40 2.86 2.90 1 2.37 38.4537 38.2542 0.1 995 0.0665 1 .87
13 4.99 4.80 5.51 4.93 20.23 1 02.6051 1 02.3 1 32 0.2919 0.0973 2.74
14 3.26 3.1 5 3.1 7 3.09 1 2.67 40.1471 40.1322 0.0149 0.0050 0.14
15 3.48 3.65 3.59 3.53 1 4.25 50.78 1 9 50.7656 0.0163 0.0054 0.15
Average 1 6.432 0.0355 0.76
16 2.89 2.84 2.85 2.89 1 1 .47 32.8923 32.8902 0.0021 0.0007 0.02
17 2.35 2.48 2.90 2.71 1 0.44 27.4270 27.2484 0.1 786 0.0595 1 .86
18 4.23 3.92 4.1 3 4.05 1 6.33 66.71 87 66.6672 0.0515 0.0172 0.54
19 5.46 5.1 3 5.1 3 5.38 21.10 1 1 1 .3898 1 1 1 .3025 0.0873 0.0291 0.91
20 3.1 5 2.98 3.42 3.47 1 3.02 42.5402 42.3801 0.1601 0.0534 1 .67
Average 1 4.472 0.0320 0.679646
21 2.88 2.81 2.80 2.59 1 1 .08 30.7386 30.69 1 6 0.0470 0.0157 0.17
22 4.94 4.32 4.40 4.39 1 8.05 81 .6981 81 .4506 0.247475 0.0824892 0.916778
23 4.04 4.28 4.47 4.48 1 7.27 74.69 1 3 74.5632 0.1 281 0.0427 0.474457
24 8.38 8.28 8.93 9.28 34.87 304.6461 303.9792 0.6669 0.2223 2.1 40456
25 6.93 6.97 6.37 6.54 26.81 1 79.9543 1 79.6940 0.2603 0.0868 0.964196
Average 21.616 0.08998 1.91 2874c
26 4.52 4.27 3.66 4.07 1 6.52 68.6238 68.2276 0.3962 0.1 321 2.02
27 4.53 4.46 4.54 4.65 1 8. 1 8 82.6466 82.6281 0.0185 0.0062 0.09
28 2.18 2.42 2.45 2.31 9.36 21 .9474 21 .9024 0.0450 0.0150 0.23
29 8.84 9.21 8.69 8.55 35.29 3 1 1 .5883 3 1 1 .3460 0.2423 0.0808 1 .24
30 5.03 4.73 5.47 5.1 1 20.34 1 03.7068 1 03.4289 0.2779 0.0926 1 .42
Average 1 9.938 0.0653 1 .388736
Overall 0.047039
average
Sda2
A "C" for individuals in subgroup. Divide individual Sda2 values (Column 9) by average Sda2 (Column 1 0). Results should be below 2.99 in 19 cases out of 20.
8 "C" for subgroup averages. Divide average Sda2 (Column 1 0) by overall averages Sda2. Result should be below 1.88 in 19 cases out of 20.
c Above limit of 1.88.

APPENDIX

(Nonmandatory Information)

XI. STANDARD PRACTICE FOR REDUCTION AND DIVISION OF UNCRUSHED GROSS SAMPLES UTILIZING LINE DIVI­
SION AND THE ALTERNATING SHOVEL METHOD

Xl.1 Ensure that the surface used for line division is an full) of material deposited evenly on top of the conical peak
impermeable surface that is hard, smooth, clean, and free of will partially flow down all sides of the cone, resulting in a
cracks. The surface must also be free of contaminants and limit well-mixed conical pile once completed. Repeat this step a
exposure to excessive moisture or drying. total of three times to complete the mixing of the gross sample.

Xl.2 Mix the gross sample to be divided. Mixing can be Xl.3 Using a shovel by shovel technique, extract incre­
done by building a conical pile. Building the conical pile ments from the conical pile to form a "division" line. This is
requires taking one increment at a time from the gross sample where "line division" will take place to reduce the mass of the
mass (typically a shovel full) and placing each increment on gross sample. Form the division line by spreading the
top of the preceding increment. Over repeated cycles, this will homogenous, well-mixed gross sample from the conical pile
form a gross sample into a conical pile. Each increment (shovel into a division line extending to a prescribed length and width.

12
� D2013/D2013M - 21
The length and width of the line will be dependent on the other shoveled increment away from the original sample line.
amount of gross sample being divided. Alternate the shoveled This process will create two sample lines derived from the
increments from the pile to opposite ends of the division line. original single sample line. One line will be identified as the
Sample from alternating shovels should be deposited onto the "save" and the other as "reject." Make sure the number of
division line from left to right and alternatively followed by increments for the newly divided lines is equal. For example,
right to left. Ensure the sample division line has a uniform a sample line with ten total increments would have division
height and width before proceeding and starting the final passes of 1 ,3,5,7,9 "save" and division passes of 2,4,6,8,10 as
reduction and division processes. "rej ect."

Xl.4 When line dividing, use a shovel with sides of equal or


Xl.6 If further division is required, continue to evenly
greater height compared to the sample line to be divided.
spread and form the smaller division lines just as was done on
Raised sides will prevent coal "roll-off'' during increment
the original division line. Continue to divide by utilizing the
collection. The shovel width should be at least three times the
Alternating Shovel Method until the desired final sample
sample' s nominal top size (coal -typically 50 mm x 0).
weight has been met for the application.
Xl.5 To begin increment collection and division, place the
increment shovel at one end of the sample line and progress Xl.7 Complete this practice as quickly as possible to
along the line one shovel width at a time. Do this by flipping prevent moisture loss from the sample during the division and
the shovel laterally along the sample line and pushing every reduction of sample mass.

ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 6 10-832-9585 (phone), 610-832-9555 (fax), or service @astm. org (e-mail); or through the ASTM website
(www. astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222
Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http://www.copyright. com/

13

You might also like