You are on page 1of 8

Engineering Technical Note

Technical Note
ETN-C-1-13

Economical Reinforced
Concrete Construction
Introduction Use concrete members that provide archi-
Experience has shown that the initial cost of tectural interest and finishes. The extra cost as-
reinforced concrete structures can be reduced sociated with the formwork and related architec-
through planning and detailing in such a way tural details for the desired effect will more than
as to minimize the expenses related to the ma- offset the additional expense if a separate finish
terials and the construction activities associated is eliminated. Panelized concrete structures are
with formwork, reinforcement, and concrete. Fre- routinely constructed with numerous architectural
quently, these cost-reducing techniques are not finishes. Similarly, concrete floors can be stained
obvious to the designer. For example, formwork and sealed rather than carpeted or tiled. Other
costs are generally 40 to 60 percent of the com- examples include the use of flat plate floors as
pleted reinforced concrete structure. Material exposed ceilings and exposed interior walls that
costs for concrete and reinforcement are on the may utilize self-consolidating concrete along with
order of 10 to 30 percent. The labor cost percent- high quality formwork.
age for placing the concrete and the reinforce-
Orient one-way structural members to
ment is the remainder. This technical note ad-
span the same direction throughout the en-
dresses many of the areas that have shown to
tire structure. Experience has shown that struc-
result in overall cost savings.
tures that are detailed with the one-way structural
Formwork members oriented in the same direction through-
out the entire structure tend to be constructed
Select one framing system and use it most efficiently, because there is less confusion
throughout the structure. For each framing and fewer mistakes than similar structures with
system used, a separate forming system will be multiple framing directions.
necessary. This means additional costs associat-
ed with the formwork and its mobilization, as well Use modular formwork. Traditionally, modu-
as a learning curve for the construction person- lar forms have been used to form large areas of
nel will be incurred. As a result, experience has walls or floors where the forms can be moved in
shown that it is difficult to economically justify the large sections and reused many times (often 10
use of more than one framing system. The ex- to 20 times). The use of proprietary forming sys-
ception usually occurs on large structures when tems have become more common and are being
usage changes over the building height, such as used to cast smaller members. Similarly, proprie-
a high-rise with a multiple floor parking garage tary forming systems are increasingly being used
in the lower floors and residences in the upper in more customized applications such as slip
floors. formed elevator and stairway shafts and curved
exterior walls. Generally, more intricate shapes
Arrange and organize structural members can be justified even though additional costs are
to fully utilize structural capacity. The thick- incurred when the forms are used multiple times.
ness of floor slabs may be governed by the re- A unique shape or finish may cost more but can
quired fire rating specified by the building code, be justified if architectural interest is provided.
so span the slab as far as practical (considering
deflection) with the minimum amount of reinforce- Arrange columns in a regular pattern. Ar-
ment. Another basic structural member frequently range columns in a regular pattern throughout
underutilized is the concrete wall. Concrete walls each floor level of the structure as well as verti-
normally have to be of a minimum thickness and cally. This practice enforces consistency on the
provided with a minimum amount of reinforce- other structural members which will dictate that
ment. These walls, whether they are exterior the formwork and reinforcement layout are also
walls or interior partitions, can carry significant consistent. Formwork will be reused and setup
axial loads, provide lateral load resistance to the will become repetitive and efficient. This repeti-
overall structure as shear walls, or act as transfer tiveness and efficiency will also carry over to all
girders when the column layout is changed. aspects related to the reinforcing bars.
Use a consistent column size. Experience has Use beams that are 2-inches wider, on each side,
shown that it is more efficient to use the same size col- than the column. A beam made intentionally wider than
umn throughout a structure’s height. Rather than varying the column will allow the outermost horizontal bars in the
the column size, it is more efficient to vary the number of beam to pass by the vertical longitudinal column bars with
bars, and vary the concrete compressive strength. This minimal interference. Another advantage is that it is easier
approach of using consistent column size will result in to position the beam form if placed on top of the column
less variation in column forms, fewer variations in the form than connecting the beam form to the side of the col-
slab and beam forms, and standardization of the steel umn form.
reinforcement.
Use the same floor-to-floor heights throughout
Use floor framing system with the minimum the structure. If changes in floor-to-floor heights are
depth. The depth of the floor is normally governed by necessary, reduce the heights in the upper stories. Cut-
deflection (serviceability) considerations. However, by ting the column form down in length is easier than adding
minimizing the floor depth, and thereby the floor-to-floor to it.
height, the cost of a structure is minimized because the
overall height of the building is minimized. In certain ar- Use a flat plate floor system for spans up to 25
eas where zoning limits the building height, additional feet. A flat plate is the most economical floor system
floor(s) may be included. Other areas of cost savings in- because the formwork and related construction are all
clude the exterior façade; interior partition walls; vertical based off the same flat formwork. The flat plate is recog-
runs of plumbing, electrical, mechanical, and elevators; nized as being the least expensive, fastest, and shallow-
stairs; formwork height; and shoring. est framing method available.

Use beams and joists of the same depth. While Use various techniques to increase shear capac-
using beams and joists of the same depth throughout ity at the column slab connection. Issues concerning
a structure may seem wasteful, just the increased cost shear capacity at the column slab connection are fre-
of shoring—not counting a separate set of forms—will quently resolved by increasing the floor slab thickness,
exceed the minor additional material costs for the con- use of a drop panel, increase in the column size (perim-
crete and reinforcing bars. Using the same depth allows eter), puddling higher strength column concrete around
all the formwork to be the same and assists in reducing the column, increasing the floor slab’s concrete strength,
the interferences between the structure and mechanical or by use of shear stud rails. Column capitals should only
systems. be used as a last resort. Shear stud rails are recognized
as an effective way to increase shear capacity around
Another similar technique is to use relatively wide, the column perimeter and are recognized in ACI 318.
shallow beams that can be up to four to five times wide Alternatively, puddling of high-strength concrete around
as deep. The quantity of steel reinforcement would then the column perimeter a set distance during column con-
be varied rather than the depth of the beam. If this does crete placements is frequently used. The higher-strength
not work, consider limiting the beams to two depths column concrete is then integrated with the concrete
throughout the structure. placement for the floor slab to avoid cold joints and po-
tential load transfer issues. Similarly, stud shear rails and
Use only one, one-way joist pan size throughout puddling can be used together. See Figures 1 and 2 for
the structure. The cost of material saved from optimizing examples of these construction techniques.
pan sizes is likely to be insignificant when compared to ad-
ditional shipping and handling the various pan sizes. Also, Use drop panels for increased shear capacity.
the overall floor depth is established by the deepest pan Rather than using a tapered column capital, a drop panel
or deepest beam and, as such, no building height-related can be formed around columns to increase the shear ca-
savings will be possible. pacity. See Figure 3.

Use available, standard joist form sizes. Specify Use standard lumber dimensions for drop pan-
available standard sizes, for one-way and two-way joists el thickness. Actual lumber dimensions are 1½, 3½,
(waffle slabs). Nonstandard sizes have to be specially 5½, and 7¼ inches for nominal sizes 2x2, 2x4, 2x6, 2x8,
fabricated and the entire cost may need to be charged respectively. Assuming a form thickness of ¾ inches, the
to the specific project rather than amortized over several resulting drop panel height would be 2¼, 4¼, 6¼ and 8
projects. Contact potential suppliers for form size avail- inches, respectively. See Figure 4.
ability.
Specify the time when forms may be stripped for
Use standard shaped forms. Avoid shapes that self-supporting members and strength for others.
have to be either fabricated by the form supplier or cus- Members such as columns and walls can be stripped
tomized by carpenters in the field. Similarly, inordinate based on time, such as 12 hours after concrete place-
field fabrication costs can be incurred when the forms ment. For floors, beams, and slabs, stripping time can
have to be modified for tapering or haunches. be specified by referring to a specific percentage of com-

2 Economical Reinforced Concrete Construction [ETN-C-1-13]


Column concrete
placed in the
nearby slab
section.

Standard Lumber Dimensions and Drop Panel Height


Lumber Size Drop Panel
Nominal Actual Height*

Figure 1 – Concrete “puddling” around the columns 2x 1½″ 2¼″


to enhance punching shear capacity 4x 3½″ 4¼″
(Photo courtesy of Skidmore, Owings and Merrill LLP)
6x 5½″ 6¼″
8x 7¼″ 8″
* ¾-inch form sheathing
Figure 4 – Drop panel height for economy

sequence the concrete placement. Similarly, the joint it-


self can be located where it is hidden in the completed
structure or detailed in such a way that it becomes part
of the finish.

Consider allowing the use of dowel bar mechani-


cal splices at construction joints. At most construc-
Figure 2 – S
 hear studs at an exterior column used tion joints, the most common detail is to simply extend
to increase punching shear capacity the bars through the joint and lap splice with the bars in
(Photo courtesy of Skidmore, Owings and Merrill LLP) the subsequent pour, without damaging the formwork.
As required, an alternate detail the contractor could use
is a dowel bar mechanical splice shown in Figure 5. This
pressive strength gain (e.g., 75 percent of 28-day com-
splice type contains a flange that can be nailed to the
pressive strength). However, these members have to be
form. After the forms are stripped, the adjoining rein-
reshored until compressive strength has been achieved
forcing bar can be screwed onto the coupler. The me-
to minimize deflection. Appropriate stripping specifica-
chanical splice eliminates the bar or dowel penetration
tions will minimize the quantity of formwork required and
through the forms, and can extend the life of the forms if
result in a decrease in formwork cost.
cutting holes is the only other option. See Figure 5.
Use high-early strength concrete. By using high-
Consider the formwork. Provide designs that retain
early strength concrete, the time necessary to wait for
the general integrity of formwork. Where possible, mini-
stripping the forms can be minimized. If the structure is
mize modifications to the formwork for recesses, protru-
large enough, the faster cycle time may allow for a sig-
sions, haunches, stubs, and the like to extend the ser-
nificantly faster overall construction time, possibly avoid-
vice life of the forms. Alternately, architectural formwork
ing seasons with unfavorable weather.
may have a single-use or multiple re-use depending on
Use predetermined construction joints. Ideally, the member(s) being formed; higher costs can be antici-
the contractor and designer should coordinate the loca- pated for the greater level of detail necessitated with this
tions and details for construction joints. Properly located type of formwork.
construction joints will allow the contractor to efficiently
Reinforcement
Use Grade 60 bars. ASTM A615 Grade 60 bars are
the most widely used and inventoried reinforcing bar.
Grade 40 may require 50 percent more steel than Grade
60. ASTM A615 Grade 75 or 80 bars are readily avail-
able, but not normally inventoried by fabricators. Grade
75 or 80 bars are available at competitive prices only
on mill orders in lots ranging from 25 to 75 tons per bar
size. However, smaller quantities may be obtained from
Figure 3 – M
 eans of increasing shear capacity in
warehouses. If a minimum mill order of one bar size can
flat slabs
be used for column vertical bars in a tall structure, Grade

CRSI Technical Note 3


Use straight bars wherever possible. Fabricating
and placing straight bars is faster and easier than bent
bars.

Use ACI standard bar bend types. See standard bar


shapes and bends provided in ACI 315, Details and De-
tailing of Concrete Reinforcement. Nonstandard bends
disrupt shop routine and cost more to fabricate.

Use bars in one plane. It is highly recommended


that reinforcing bars be designed so their bends are lo-
cated in one geometric plane. Bars with bends in two
or three planes, i.e. having x, y, and z components, are
Figure 5 – Dowel bar mechanical splice difficult and expensive to fabricate. Moreover, these bars
are difficult to hold to proper field tolerances because
75 or 80 may lower the cost of the column vertical rein- adjustment in one direction can impact the tolerance in
forcement by decreasing the congestion and reducing the remaining one or two directions.
the number of crossties.
Use beams of sufficient width for ease of bar and
Use the largest bar size possible. Placing costs concrete placement. Concrete cover, stirrup thickness,
and fabrication costs are minimized by using the largest radius of stirrup, actual bar diameter, bar lap, number of
practical bar sizes while still meeting the design require- bars, and aggregate size all contribute to the minimum
ments. In most cases, it takes as much time to fabricate beam width. Actual bar size is larger than the nominal
and place one small bar as it does one large bar. Howev- size. For example, even though bar sizes are designated
er, a greater quantity of smaller bars may be required for as #4, #5, #6, the actual dimensions are 9/16, 11/16, and
crack control reinforcement or other serviceability issues. 7/8 inches, respectively. Table 1 shows overall bar diam-
eters for all bar sizes. When bars are spaced too close
Consider using #14 and #18 longitudinal column together, not only is placement of the bars difficult but
bars. Rather than using many smaller longitudinal bars placement of the concrete is hindered as well.
in a heavily loaded column, using a fewer number of #14
or #18 bars may be warranted. The large bars reduce Use repetitive bar sizes and lengths. Standard
steel congestion, placing cost, fabrication cost, and cost reinforcing bar length is 60 feet. However, some fabri-
of splices. However, because a crane may be required to cators stock shorter bar lengths. As a general rule, the
place the heavier bars, consideration should be given to longest available (and possible) bar lengths should be
whether a crane will be on the job site for other reasons. used to reduce fabrication and placing costs. Minimize
Also, large bars almost always have to be mechanically the bar sizes specified in the design. This minimizes the
spliced, which is another design consideration.
Table 1 – Overall Reinforcing Bar Diameter
Use columns with tied transverse reinforcement
rather than spiral. Individual ties are generally pre-
ferred for field fabricated columns in non-seismic areas.
Reasons include the weight per foot of spirals is two to
three times as much as comparable column ties, diffi-
culty of consistently fabricating spirals with the identical
diameter and pitch, and handling and placing spirals in
the field. For shop fabricated columns, there is a trend
towards automated fusion welding machines in which Approximate Diameter Outside
the spirals are wound onto pre-placed longitudinal bars Bar Size
Deformations, in. [mm]
and welded together to make a cage. #3 [#10] 7/16 [11]
In some applications there are significant reasons #4 [#13] 9/16 [14]
to use spirals. These advantages may be sufficient to #5 [#16] 11/16 [18]
offset the increased costs. Structural advantages of spi- #6 [#19] 7/8 [22]
rals over tied transverse reinforcement include an ap- #7 [#22] 1 [25]
proximate 20 percent increase in axial capacity, and #8 [#25] 1-1/8 [28]
a one quarter decrease in development length of bars #9 [#29] 1-1/4 [32]
enclosed with spirals. Spiral reinforcement provides en- #10 [#32] 1-7/16 [36]
hanced confinement, thus it is a preferred lateral rein- #11 [#36] 1-5/8 [40]
forcing type for round members in seismic applications. #14 [#43] 1-7/8 [48]
#18 [#57] 2-1/2 [63]

4 Economical Reinforced Concrete Construction [ETN-C-1-13]


sizes handled in the shop and placed in the field. Also, the other end are easier to place in the column interior.
lap lengths can exceed the minimum length required by These ties are known as “dog” or “stick” ties, and con-
code so that a minimum of bar lengths can be fabricated form to CRSI typical bar bend Type T9. Eliminating un-
and placed in the field. necessary intermediate ties also serves to simplify con-
crete placement in the column, as illustrated in Figure 7.
Use stock length bars. In some situations reinforc-
ing bars can be sheared to a fixed length, while in other To ensure reinforcing bars will fit, draw details to
situations, stock length bars can be cut and spliced in the scale. Certain locations in a reinforced concrete struc-
field for trapezoidal or irregular-shaped walls and slabs. ture commonly present challenges in making all of the
See Figure 6. Use a minimum number of different bar reinforcement fit. It is in those areas where a scaled, de-
lengths to provide savings in fabrication, handling, and tail drawing will help identify possible problems. These
placing since sorting is reduced. The minor added cost areas include the following as examples:
associated with the extra material used due to variable
length laps is more than offset with the savings due to re- • Narrow beams
duced labor while cutting and sorting the reinforcing bar.
• Slabs with multiple openings, especially near sup-
Use lap splices. Where possible, bars should be lap ports and edges
spliced. Also, specify a consistent lap splice length for a
• Slab-column joints, beam-column joints
given bar size. Lap splices should be considered a mini-
mum length and providing a longer lap is generally not • Columns with more than 2 percent vertical rein-
detrimental, unless congestion is an issue. forcement
Use mechanical splices. For columns with #14 and Designers need to consider the overall dimensions
#18 bars, and for #11 and smaller bars where congestion of the reinforcing bars, as well as hook dimensions and
is an issue, use mechanical splices. bend radii, when making a scaled detail drawing. See
Table 1 for a list of overall bar diameters. Hook dimen-
Use compression mechanical splices where pos-
sions and bending radii for both standard hooks and stir-
sible. When a mechanical splice is needed and the bar is
rup/tie hooks are listed in Chapter 6 of CRSI’s Manual of
always in compression, use a compression mechanical
Standard Practice.
splice. A compression mechanical splice is considered
to be the fastest mechanical splice to install in the field. An example of how a scaled detail drawing can help
identify problems is shown in Figure 8. The top sketch
Provide a 4 to 6-inch gap to place concrete when
shows a conceptual beam detail with the reinforcement
bars are closely spaced. On heavily-reinforced beams
depicted as lines and dots, compared to the same beam
such as transfer girders, where the spacing between
detail drawn to scale in the sketch below. It can be seen
bars is relatively close, provide a gap. Sometimes bars
in the scaled detail that the stirrup hooks will likely in-
may be bundled to provide this gap. Experience has
terfere with the top bars and the minimum clearance
shown that 4-inch slump concrete with ¾ inch aggre-
between the bars (as per Section 7.6.1 of the ACI 318
gate will not flow easily through a 2-inch space between
Building Code) may not be met.
bars. Similarly, vibrator heads are 2 to 3 inches in width
and sometimes become entangled in the reinforcement. Two-way slabs with two layers of reinforcement.
Typical examples of reinforcing bar congestion normally
Use intermediate single leg ties. Closed, interme-
concern heavily-reinforced beams or columns. However,
diate column ties (hoops) are difficult to place and align
reinforcement congestion can also occur in such non-
around the interior, longitudinal column bars. Single
typical cases as slab systems. An opportunity for steel
leg ties with a 135° hook at one end, and a 90° hook at
congestion exists in a two-way slab with two layers of
top and bottom steel, each layer having bars in two per-
pendicular directions. Sometimes, there might even be a

Lap Varies,
≥ Minimum

Top Bars Length “A” Top Bars Length “B”


Bottom Bars Length “C” Bottom Bars Length “C” (a) (b) T9 tie
Elevation of Concrete Wall Figure 7 – ( a) An interior hoop tie is difficult to
Figure 6 – U
 sing stock length of bars cut and place, whereas a (b) column with
spliced in the field intermediate T9 ties is preferred

CRSI Technical Note 5


Detailing Hook Detailing
Dimension A or G Dimension

J D D

A or G
d d
4d, 12d
2½" min.

Figure 9 – 9
 0° and 180° standard hooks, all specific
dimensions recommended by CRSI meet
Beam Detail (Conceptual) Beam Detail (Scaled)
minimum requirements of ACI 318-11.
Figure 8 – Beam detail, conceptual and scaled
For both the 90° and 180° hooked, top flexural rein-
third layer of top and/or bottom bars. A third layer of top forcement, one other option is used depending on the
bars can be especially challenging, particularly at the reinforcement details at the slab edge. Oftentimes, the
slab edge where the bars terminate in hooks. It is like- hooks can be tilted from vertical so they fit in the slab
wise important to label or otherwise designate the di- depth with appropriate clear cover. However, another
rection of slab reinforcement, such as N-S and E-W for transverse bar may be required at the edge within the
north-south and east-west, respectively. To summarize, slab depth to hold the given tilt angle, during concrete
one needs to be wary of the possibility of reinforcement placement operations.
congestion everywhere throughout the structure, not just
the usual areas like heavily-reinforced beams. Table 2 – Minimum Slab Thicknesses

Standard 90° hooks versus 90° stirrup/tie hooks. Minimum Slab Thickness
Top bars in a slab with 90° hooks are easiest to install Bar Size 90° Hook 180° Hook
when there is proper clearance (i.e., cover at the top and #3 7 1/2” 4 1/2”
bottom) for the hooks to hang straight down, as shown in #4 9 1/2” 5 1/2”
the sketch in Figure 9. #5 11 1/2” 6 1/2”
#6 1-1 1/2” 7 1/2”
However, the slab must have a minimum thickness
Notes:
for this condition to apply. Assuming and interior slab
(1) Bar sizes shown are for the common bars used in supported slabs.
with ¾ in. clear cover top and bottom, the minimum slab
(2) Assumes hook is oriented vertically.
thickness required to use a 90° hook vertically is shown
in Table 2. Although a 90° hooked flexural bar may be Tighter limits on column longitudinal reinforce-
easier to place, it does require a slab thickness of nearly ment. Section 10.9.1 of ACI 318 limits the area of lon-
1 ft. for the hook tail to hang vertically. gitudinal reinforcement in compression members to no
For thinner slabs, one alternate is to use 180° hooks more than 0.08 times the gross area of the member (8
at the end of the top flexural reinforcement. The “J” de- percent reinforcement). Figure 11 helps illustrate this
tailing dimension of a 180° hook is ½ the “A or G” dimen- situation of higher steel percentages in a column, as ad-
sion of a 90° hook, as illustrated in Figure 9. Table 2 dressed by Schwinger [2011].
shows the minimum slab thickness when a 180° hook The sketch on the left shows the lap region of a col-
is used. umn with 2 percent steel (8-#11 bars). The sketch on the
Usually a transverse edge or framing bar is placed right shows the lap region of a column with 4 percent
inside the hook. In order to drop the 180° hooked bar steel (16-#11 bars). Note the close bar spacing for the
into position, the transverse edge bar may be temporar- column with 4 percent steel. More longitudinal steel can
ily tied to the adjacent first interior bar. After the hooked require more column ties and heavier reinforcement in
bar is placed, the transverse bar is slid over and tied into a column, thus making placement of floor reinforcement
position, as illustrated in Figure 10. Another option would around the column more difficult. It is clear that limiting
have the bar set on the lower mat of reinforcing steel NOTE
and inserted into the hook interior after the hooked bar
is placed. The installation is dependent on the placing
situation and placing contractor; it is mentioned here to
make the inspector aware of the issue.

In some cases, the engineer may detail or call for the


transverse edge bar to be located on the outside diam- FORMWORK
eter of the hook. This places the bar closer to the slab Slide transverse bar over NOTE: Bottom reinforcement
edge, depending on the 180° hook bar size and hence after 180° hook bar is installed omitted for clarity
the hook diameter. Figure 10 – Top flexural reinforcement at a slab edge

6 Economical Reinforced Concrete Construction [ETN-C-1-13]


column reinforcement to no more than 4 percent would
enhance the constructability of reinforced concrete col-
umns.

From the standpoint of economics, it can be shown


that increasing a column capacity can be achieved at
less additional cost by increasing the concrete strength,
rather than by increasing the amount of steel reinforce-
ment. Table 3 illustrates an example where a column
with 2 percent steel can have its capacity increased by
about 20 percent by either doubling the amount of rein-
forcement or by increasing the concrete strength by just
30 percent. Factored column capacity was calculated Figure 11 – Column with lap spliced
from Equation 10-2 in ACI 318. longitudinal bars

Table 3 – 24” x 24” Reinforced Concrete • Ease of placement and consolidation without
Column Design Options affecting strength;
• Long-term mechanical properties;
fc΄ Αs ρ ΦΡn Remarks
• Durability in severe environments;
5,000 psi 8-#11 2.2% 1,635 k Initial design
Steel reinforcement • High early strength;
5,000 psi 16-#11 4.3% 1,977 k
doubled
Concrete strength • Toughness;
6,500 psi 8-#11 2.2% 2,008 k
increased 30%
• Volume stability.
Although the costs of reinforcing steel, concrete, and
labor will vary geographically, the most economical re- These properties are usually achieved with special
inforced concrete column design will generally have no admixtures, which alter the plastic properties and work-
more than 2 percent longitudinal reinforcement. ability of the concrete during placement, making it less
viscous (more fluid) than conventional concrete. Long-
Avoid using bundled bars in columns. The points term strength properties are usually unaffected.
raised in the previous discussion concerning increasing
longitudinal reinforcement are also applicable for avoid- Self-consolidating concrete (SCC) is a special type of
ing the bundling column bars. Additional points about high-performance concrete. It is defined by the National
bundled bars: Ready-Mix Concrete Association (NRMCA) as a highly
flowable, non-segregating concrete that can flow into
• T
 he 318 Code requires that bundled bars be stag- place, fill the formwork, and encapsulate the reinforce-
gered, which increases the complexity of placing ment without any mechanical consolidation. In general,
the reinforcement SCC is concrete made with conventional concrete ma-
terials and, in most cases, with a viscosity-modifying
• If mechanical splices are used to join the bars, the admixture (VMA). SCC is also useful in applications
couplers cannot easily be installed on bundled bars where high quality surface finishes are desired without
bugholes or honeycombing. Increased form pressures
Concrete
may be generated when SCC is used, necessitating
Use moderate-strength concrete. 4,000 to 5,000 possible changes in formwork design.
psi compressive strength concrete is usually sufficient.
Exceptions are for columns in high-rises and floor sys- ACI Committee Report 237R indicates that SCC pro-
tems in which there are shear capacity issues. Columns, vides the following features, which are equally applicable
shear walls, and joints may require higher strength con- to general high-performance concrete:
crete to enhance their axial and flexural capacity.
• It is good at replicating architectural form features;
Use high-performance concrete where placement
• Free fall into the formwork can be greater than
and consolidation is expected to be difficult. High-
the conventional limit of 5 ft.;
performance concrete is defined within ACI 116 as con-
crete meeting special combinations of performance and • Less screeding operations are required to ensure
uniformity requirements that cannot always be achieved flat surfaces (self-leveling characteristic);
routinely using conventional constituents and normal
mixing, placing, and curing practices. These require- • It facilitates accelerated construction, through
ments could potentially include the following enhance- higher rate of casting or placing and shorter
ments: construction duration;

CRSI Technical Note 7


• It facilitates and expedites the filling of highly re- Some high-strength column concretes may have com-
inforced sections and complex formwork while pressive strengths ranging from 12,000 psi to 15,000 psi.
ensuring good construction quality which may
lead to increased productivity, reduces the labor re- To make placement easier and avoid potential place-
quirement and cost, or both; ment mistakes on the project, it is usually more economi-
cal to use the column concrete in the puddling zone, and
• Improved flexibility in spreading placing points design for a maximum concrete strength of 10,000 psi; a
during casting. This can reduce the need for fre- separate puddling mix is thus not recommended.
quent movement of transit trucks and the need to
move the pump lines to place concrete (possible Limit coarse aggregate size to ¾ inch. As a matter
reduction in the number of pumps, pump opera- of practice limit the coarse aggregate to ¾ inch since the
tors, and so on). This greater flexibility in scheduling minimum clear bar spacing is normally 1 inch and ACI
construction activities and procuring the required 318 Code requires a clear distance of four-thirds the ag-
resources results in both time and resource savings. gregate size.

SCC may be evaluated in the field using a standard References


slump test; however, the slump cone is often inverted. American Concrete Institute – ACI, Committee 116
Instead of measuring the distance between the top of the [2005], Cement and Concrete Terminology (ACI 116R-
cone and the top of the sample, the puddle of concrete 00, Reapproved 2005), American Concrete Institute,
is measured in 2 orthogonal directions to determine Farmington Hills, MI, 73 pp.
the spread diameter. Standard slump measurements
of highly flowable concrete is practically irrelevant, as it American Concrete Institute – ACI, Committee 237
has no measureable slump (>> 12 in.). Other mixture [2007], Self-Consolidating Concrete (ACI 237R-07),
evaluation tests include the J-ring test, used to evaluate American Concrete Institute, Farmington Hills, MI, 30 pp.
the flow and segregation characteristics of high-perfor-
mance concrete. American Concrete Institute – ACI, Committee 315
[1999], Details and Detailing of Concrete Reinforcement
Use high-strength concrete in columns. High- (ACI 315-99), American Concrete Institute, Farmington
strength concrete can be justified in columns if the use Hills, MI, 44 pp.
of higher strength concrete reduces the amount of lon-
gitudinal reinforcement. Similarly, column sizes can be American Concrete Institute – ACI, Committee 318
reduced or just use one column size on a project. Spec- [2011], Building Code Requirements for Structural Con-
ify the same strength concrete in all columns of a story, crete (ACI 318-11) and Commentary (ACI 318R-11),
to minimize mistakes. American Concrete Institute, Farmington Hills, MI, 473 pp.

Specify few mix designs. On most projects only ASTM International – ASTM [2012], Standard Speci-
two strengths of concrete are necessary, a normal mix fication for Deformed and Plain Carbon-Steel Bars for
(4,000 to 5,000 psi) and a high-strength mix (8,000 psi or Concrete Reinforcement, ASTM A615 / A615M – 12,
greater). Some projects may necessitate three. ASTM International, West Conshohocken, PA.

Consistent with the construction shown in Figure 1, Concrete Reinforcing Steel Institute – CRSI [2009],
it is most economical to use the high-strength column Manual of Standard Practice, 28th Edition, Concrete Re-
concrete in the slab puddling zone. In an effort to opti- inforcing Steel Institute, Schaumburg, IL, 144 pp.
mize concrete mixes on a project, some engineers have
Schwinger, C. S. [2011], “Tips for Designing Construct-
specified a separate puddling mix, because ACI 318 only
ible Concrete Structures - Part 1,” STRUCTURE Maga-
allows a design concrete strength of 10,000 psi in shear.
zine, February, pp. 42-43.

Contributors: Adapted from articles by Russell S. Fling and Clifford W. Schwinger with updates
and revisions by CRSI Staff.

Keywords: Concrete, Economy, Formwork, Reinforcement

Reference: Concrete Reinforcing Steel Institute-CRSI [2013], “Economical Reinforced Concrete


Construction,” CRSI Technical Note ETN-C-1-13, Concrete Reinforcing Steel Institute, Schaum- 933 North Plum Grove Rd.
burg, Illinois, 8 pp.
Schaumburg, IL 60173-4758
Historical: Formerly Engineering Data Report No. 30 p. 847-517-1200 • f. 847-517-1206
www.crsi.org
Note: This publication is intended for the use of professionals competent to evaluate the signifi-
cance and limitations of its contents and who will accept responsibility for the application of the Regional Offices Nationwide
material it contains. The Concrete Reinforcing Steel Institute reports the foregoing material as a
A Service of the Concrete Reinforcing Steel Institute
matter of information and, therefore, disclaims any and all responsibility for application of the stated
©2013 This publication, or any part thereof, may not be
principles or for the accuracy of the sources other than material developed by the Institute.
reproduced without the expressed written consent of CRSI.

Printed in the U.S.A.

You might also like