Professional Documents
Culture Documents
FOR
ELECTROSTATIC PRECIPITATOR
INSTALLED F0R
AT
SUBMITTED BY
ACC LIMITED
ENVIRONMENT & ENERGY CONSERVATION CELL
ACC THANE COMPLEX, LBS MARG,
THANE - 400 604, INDIA.
1
INDEX
ELECTROSTATIC PRECIPITATOR
AUXILLARIES
PRECIPITATOR
2
PART I
FOR
ELECTROSTATIC PRECIPITATOR
3
TABLE OF CONTENTS
4
SECTION - 1
INTRODUCTION
PURPOSE AND CONTENTS OF THIS MANUAL
This manual contains both general and specific information for the safe
operation and maintenance of the precipitation equipment installed at M/S
AMBUJA CEMENTS LTD. BHATAPARA. The warranty is valid
provided the equipment is operated and maintained as per the instructions
given in this manual.
Because the equipment has been custom design, certain specific adjustments
and setting can only be made during operation. Information regarding these
adjustments will be supplied during start-up by ACC-EEG field personnel
who will also:
4. Record data.
DESCRIPTION OF INSTALLATION
PURPOSE
SCOPE
5
SECTION -2
IMPORTANT INSTRUCTIONS
1.1 DONT’S
) Do not enter / touch any internals without grounding the field with
portable grounding sticks after throwing the grounding switch to
‘ground’ position.
1.2 DO’S
) Ensure operation of the ESP above the acid dew point temperature
to avoid corrosion of internals.
) Ensure that the ESP gas inlet temp, do not exceed the designed
Temperature limit.
) Stop / trip the unit if the Hopper level (High) signal stays beyond 1
hour to avoid internal damage/collapse of hopper or structure.
) Ensure seal air system is ON at all time and to be put OFF only
during long shutdown / stoppage.
7
SECTION -3
ESP –OPERATING PRINCIPLE
8
Basically An Electrostatic Precipitator consists of a steel airtight chamber
housing the Collecting & discharge electrodes. The Discharge electrodes are
usually suspended from the top through support insulators. The Collecting
electrodes (plates) are connected to ground & the emitting electrodes are
supplied with a high negative voltage, which is in Kilovolts. Rapping system
periodically cleans the dust collected on the collecting electrodes. The dust
is collected in pyramid or trough type hoppers before they are discharged
pneumatically or through a combination of Rotary Air Lock Valve & dust
conveying system. The inlet & outlet cones ensure gradual drop in velocity
till it retains the design velocity on reaching the collecting are. Gas
Distribution plates at the inlet & outlet ensure uniform gas distribution
across the length & width of the ESP.
The collecting & emitting electrodes are alternately placed across the width
of the ESP, each pair of Collecting Electrodes forming a gas passage, which
is usually spaced at 300 mm or 400 mm. The emitting electrodes are of
various types, each having some type of sharp points, which are the corona
generating sources. These are divided into sections or fields to reduce the
effect of electrical disturbance called sparking. The ESP are usually with 2 –
3 fields in series for treating smaller quantity of gas volumes & can be upto
5 –7 series field for larger capacity Power Plants.
9
protective guard. Usually a grounding switch is provided between the TR set
& the emitting electrodes (field) to isolate the TR set & connect the field to
ground potential during ESP maintenance.
The rapping, which is usually, either top rapping using MIGI rappers or side
rapping using rotating hammers driven by geared motors. The inlet field,
which sees more dust, naturally collects more dust as compared to the outlet
field. Generally for a three field ESP, the inlet field collects around 80%
dust, the second field collects 16% dust & the third field collects 4% dust.
However the collecting depends on the power available for these fields as
well as the process conditions. Accordingly the inlet rappers are cleaned
faster as compared to the outlet rappers.
The higher dust load at the inlet results in lower operating current & requires
a higher operating voltage. Typically the current increases as we go from the
inlet field to the last field. At the same time the voltage reduces as we go
from the inlet field to the outlet field. Unusually high currents at the inlet are
an indication of problems in the ESP.
10
SECTION -4
ELECTROSTATIC PRECIPITATOR DESIGN
SPECIFICATIONS
SPECIFICATIONS OF ESP:
COLLECTING ELECTRODES
Material IS 513
Collecting Surface Height (Mtrs.) 9.754
Width of collecting electrode (Mtrs.) 2.225 + 2.74
Collecting plate spacing 400 mm
No of Electrodes / ESP (20*4F + 20*4F) 80 + 80
DISCHARGE ELECTRODES
Type Rigid Pipe & Spike
Material IS 513
Height (Mtrs.) 9.75
Total No of Electrodes / ESP (171 * 4 F) 684Nos.
11
RAPPING ARRANGEMENT
HOPPER
Type Pyramidal
12
HOPPER HEATERS
HOPPER VIBRATORS
13
SECTION -5
SAFETY
The key system controls access any to hinged access openings used during
normal operation and routine maintenance. Bolted access covers and junction
boxes of 415 volts or less are not incorporated in the interlock system.
14
2.0 GROUNDING
The key interlock system will not protect against contact with the
following:
1. High Voltage Bus Duct.
Use extreme caution when removing access covers from the bus duct.
Lock out the T-R associated with the bus, and attach a portable ground
to the bus to bleed off any static charge before touching it. The static
charge in the precipitator can be transferred from energized bus sections
to a de-energized section, so keep a ground on the de-energized section,
so keep a ground on the de-energized bus at all times while working on
it.
15
4) DO not operate the controls with the doors open unless live
1. Securely close and lock out dampers, which could admit flue gas into
the precipitator. Depending on the situation, use blanks.
7. Never close a door unless absolutely certain no one is inside, the best
practice is to close the door you have used as soon as you come out,
before someone has the chance to go in behind you. The use of "vessel
entry permits" or a similar type of system, to account for whoever is
inside the precipitator, is recommended.
16
6.0 POTENTIAL FOR FIRES/EXPLOSIONS IN THE
PRECIPITATOR
When combustible mixture of fuel and oxygen is allowed to enter the
precipitator, a fire or explosion may occur, causing severe damage to
ESP. In the event that a quantity of unburned fuel has been supplied
to the precipitator, minimizing. If a fire hazard is suspected, the
precipitator T-R's should be turned off to eliminate sparking as a
source of ignition. The precipitator should then be rapped clean while
flue gas O2 is kept to a minimum.
17
6.2 OXYGEN SOURCES
The amount of oxygen sufficient to support combustion varies with
the concentration of combustible material present in the dust/ash. In
general, damaging fires cannot occur regardless of combustible
concentration when the oxygen level of the flue gas is below 4%
Oxygen levels exceeding approximately 7% are potentially dangerous.
The following procedures should be followed to minimize flue gas
Oxygen:
1. Do not open flue access doors during operation, and make sure
that all access doors and other openings (such as hopper poke
holes) are fully sealed.
18
6.3 IGNITION SOURCES
19
SECTION -6
PREVENTIVE MAINTENANCE
20
1.0 MAINTENANCE OVERVIEW
21
3. As situations warrant, make visual checks of critical compo-
nents such as rappers, particulate removal equipment, etc.,
rather than relying on alarms alone to detect problems. Check
any equipment that does not generate alarms in the turned-off
state, to ensure that it is switched on.
22
2. Check operation of hopper equipment to ensure that collected
particulate is being removed from the hoppers. Frequent and
thorough emptying of the collected particulate is essential to
avoid hopper pluggage. Particulate removal checks may
include: high-level indicators, hopper heater operation,
particulate conveying system function, and hopper throat
temperatures.
23
3.0 OUTAGE INSPECTIONS
24
DURING AND AFTER COMMISSIONING PERIOD:
Ph:(022) 2583-3035
Fax:(022) 2580 1302/2582-0962
25
3.2.2 SUPPORT INSULATOR REPLACEMENT
In the event it becomes necessary to replace a support insulator, the
high-tension frame must be shored-up at its operational elevation prior
to removal of the old piece. Penetrations of the precipitator hot roof
are provided for installation of frame erection support members. The
new insulator should be installed in accordance with the pertinent
ACC-EEG drawing. After replacement is complete, confirm proper
inter-electrode alignment.
3.3 Check for signs of plugging of gas distribution plates and excessive
floor buildup on inlet and outlet plenum surfaces.
3.5 Check for dust clinkers or abnormal build-ups between high voltage
components and ground in any section where operating records may
indicate abnormally low voltage or high sparking. Remove any such
deposits thoroughly so they cannot serve as the nucleus of future
built-ups.
3.6 Check for signs of air in leakage around access doors and shell seams,
which might cause corrosion or abnormal buildups.
26
precise tolerances as recorded in the construction documents. Any
misalignment found after startup should be investigated closely, as it
is indicative of abnormal conditions. Likely causes of misalignment
are:
1. (Bottom electrode alignment) Loose or broken stabilizer bar
insulators, if provided. High voltage frames should move only
slightly when pushed. Bars should be attached firmly to bottoms of
collecting plates, loosely to high voltage frame.
2. (Bottom electrode alignment) Collecting plat spacer bar connections
to side frames or partition walls may have come loose. This
connection is welded and bolted with a slotted hole to provide vertical
movement during heat expansion, but no horizontal movement.
Check for weld failure at this connection.
3. (Top electrode alignment) If a support bushing insulator needs to be
replaced, care must be taken to reposition the upper frame in the
original position when installing the new insulator. Simple
misalignment of the upper frame indicates improper positioning after
repair.
27
Severe distortion of internal components is a sign of thermal stress
caused by fire in the precipitator. If this condition is suspected, a thorough
inspection by ACC-EEG is recommended. Fires do not occur in
precipitators under normal operating conditions. Any evidence of fire
warrants complete and prompt review of operating procedures to prevent the
occurrence of catastrophic fire causing total equipment loss.
3.8 Make notes of nature and location of all abnormalities found in the
precipitator, whether corrected during the outage or not. Use diagrams to
record locations of failed components. These records are useful for
identifying possible patterns of repetitive component failures and will be the
basis of future outage inspections.
3.9 Welding onto high voltage frames In the event it becomes necessary
to do work involving arc welding onto a precipitator high voltage frame, the
high voltage conductor must be removed from the frame's support insulator
spider (and grounded) to isolate the Transformer-Rectifier. The frame itself
should then be grounded using a dedicated grounding jumper prior to
welding. Remove jumper and re-connect high voltage conductor after
welding is complete.
4.1 WARNING
ACC-EMD has provided an appropriate key interlock system that is
installed on all hinged access doors of the precipitator to protect
persons involved in precipitator operation and maintenance from
accidental contact with energized high voltage components. This
system must be maintained in AS NEW condition, and there should
28
exist no extra or additional keys for the system. Should the interlock
system be modified, removed, or otherwise not maintained in its
proper operating condition, or should the Purchaser, or anyone acting
on behalf of the Purchase obtain additional keys for the interlock
system, a significantly dangerous condition would exist for persons
involved in maintaining the equipment for which ACC-EEG disclaims
responsibility. ACC-EEG disclaims responsibility for damage or
injury resulting from the failure of proper maintenance to the interlock
system.
ACC Ltd.
Environment Energy Conservation Celll
Technical Support Service
ACC Thane Complex
L.B.S. Marg,
Thane – 400604,
Ph. (022) 2583-3035,
Fax (022) 2580-1302/2582-0962
29
DUPLICATE AND/OR REPLACEMENT INTERLOCK KEY
RELEASE
REFERENCE: CUSTOMER -
LOCATION -
JOB NUMBER -
30
ATTACHMENT B
INTERLOCK INDEMNITY
If ACC-EEG previously provided a key interlock system with the original
electrostatic precipitator(s) or is furnishing additions or alterations to the
original system or is providing the initial key interlock system under this
contract, the following shall apply:
31
LOCK MAINTENANCE
Keep protective lock covers in place at all times to prevent dust or other
contaminates from fouling the lock mechanisms.
Never apply excessive force to interlock keys, such as by turning keys with
pliers. They are made of brass, and are easily broken.
32
SECTION -7
OPERATION AND MAINTENANCE OVERVIEW
33
1.0 KEY INTERLOCK SYSTEM
1.1 WARNING
Refer to the SAFETY section of this manual for precautions regarding
use and maintenance of the Key Interlock System. Failure to properly
use and maintain the key interlock system could result in a serious
electrocution hazard. Refer to the MAINTENANCE section of this
manual for lock maintenance procedures and information on
replacement of lost or broken keys.
34
I.D. numbers on the keys and locks. Turn the ground switches to the
Ground position.
4. Take the ground switch keys to the transfer box and insert them
into the locks according to matching I.D. numbers. After all ground
switch keys are inserted, the locks can be rotated simultaneously,
releasing the door keys.
5. Enter penthouse area first and put all safety ground sticks on all
high voltage bus sections as a redundant safety measure. (Note:
Remember to remove ground sticks prior to putting precipitator back
in service!)
10. Always Replace Lock Covers After Using The Key System To
Prevent Dust Or Other Contaminants From Fouling The Lock
Mechanisms.
OPEN CIRCUIT TEST & SHORT CIRCUIT TEST: These checks are
performed to check the healthiness of the TR sets.
36
2.0 AIR LOAD TESTING
37
The equipment is designed such that the secondary current rating of
the transformer-rectifier sets may be achieved without sparking on air
load. If sparking does occur, it is normally caused by close inter-
electrode spacing, foreign matter, or moisture. Certain ambient
conditions, such as excessive moisture, can cause sparking and failure
to attain rated transformer-rectifier current, and may not indicate a
problem.
CAUTION: Before starting Air Load Test, the Seal Air System should
be energized at least 4 hours in advance.
38
sparking during air-load. This step may be skipped if the
precipitator internals are known to be dry.
2. Reduce stack draft or airflow to the precipitator, if possible,
little or no stack draft is desired.
3. Remove all personnel from ductwork associated with the pre-
cipitator.
39
8. Compare air load data between each transformer-rectifier set
and with any prior air load. Account for any serious discrepan-
cies before concluding air-load.
3.0 STARTUP
3.1 OVERVIEW
During the initial air load of the precipitator, the transformer-rectifier
control parameters are preset to allow the transformer-rectifier sets to
operate at optimum power levels for maximum collection efficiency.
Startup consists of simply turning on the precipitator controls in the
correct sequence when process conditions are suitable.
40
The following standard checklist may be modified if necessary to suit
the particular requirements of your plant: Any questions related to
proper startup procedure, sequence, etc., should be referred to ACC-
EEG.
) Check that all required outage maintenance has been completed, all
grounding devices removed, and all doors closed securely. (A
brief air-load test at this time is useful to ensure that all sections
are free of grounds.)
) Turn on seal air system at least three hours prior to introducing flue
gas into the precipitator. Check thermostat setting of seal air heater.
41
) Turn on transformer-rectifier controls, and check control displays
for indications of normal operation.
42
5.0 EVALUATING OPERATION
43
5.2 TYPICAL PROBLEMS
Following is a summary of the most frequently occurring problems,
which might show up in transformer-rectifier electrical readings.
1. PROBLEMS - Grounded high voltage bus section.
SYMPTOMS - Abnormally low primary and secondary Voltage.
- Control trips off on "Under-voltage."
CAUSES - Hopper overfilled to level of bottom frame.
- Grounding device left on high voltage frame.
- Foreign material left in precipitator.
- Broken high voltage insulator.
2. PROBLEM - High resistance ground or close clearance between
high voltage and ground.
SYMPTONS - Abnormally low primary and secondary voltage.
- Abnormally low primary and secondary current.
- Abnormally high spark rate.
CAUSE - Hopper overfilled to level of bottom frame.
- Dirty wet, or cracked H.V. insulators.
- Rappers not working, allowing dust bridging between
electrodes.
3. PROBLEM - Automatic control failing to increase power to highest
level for efficiency.
SYMPTOMS - Abnormally low primary and secondary voltage.
- Abnormally low primary and secondary current.
- No sparking or very little sparking.
CAUSES - Control turned down manually.
- External signal turning control down (Remote
manual control. Energy Management System, etc.)
- Automatic control misadjusted or Control
malfunction.
44
4. PROBLEM - Automatic control failing to limit current below
Name plate rating.
SYMPTOMS - Abnormally high primary and secondary current
- Control trips off on "Over-current."
CAUSES - Automatic control misadjusted.
- Control malfunctioning.
5. PROBLEM - Excessive emissions while precipitator is operating at
high power.
SYMPTOMS – Normally, primary and secondary voltage.
- Normally low primary and secondary current.
- Abnormally high stack opacity.
CAUSES - Rappers misadjusted to excessively high intensity or
Short cycles.
- Volume of flue gas above design.
- Change in stack gas chemistry, due to ammonia
injection, or other cause of non-particulate emissions.
6.0 DATA SHEETS
Proper record keeping is essential to the maintenance of efficient and
reliable precipitator operation. The following standardized data sheets
should be used to document baseline operation for comparison over
the lifetime of the equipment.
6.1 PRECIPITATOR AIR LOAD READINGS
This data sheet is appropriate for recording voltage/current
relationships under air load conditions. Data recorded on these forms
should be compared with air load readings provided by ACC-EEG in
the startup report from the original commissioning of the equipment.
This data should be taken after any major outage where work has been
done in the precipitator that might affect electrode.
45
ESP Field #1 A
Date Time Weather Conditions
Set No. Set Size ___
E.PRI
ISEC 50 100 150 200 250 300 350 400 450 500
IPRI
E SEC.KV1
SPK RATE
ESP Field # 1B
Set No. Set Size ___
E.PRI
ISEC 50 100 150 200 250 300 350 400 450 500
IPRI
E SEC.KV1
SPK RATE
ESP Field #2
Set No. Set Size ___
E.PRI
ISEC 50 100 150 200 250 300 350 400 450 500
IPRI
E SEC.KV1
SPK RATE
46
ESP Field #3
Set No. Set Size ___
E.PRI
ISEC 50 100 150 200 250 300 350 400 450 500
IPRI
E SEC.KV1
SPK RATE
ESP Field #4
Set No. Set Size ___
E.PRI
ISEC 50 100 150 200 250 300 350 400 450 500
IPRI
E SEC.KV1
SPK RATE
For generating such data, the purchaser should devise a suitable form
which encompasses all parameters likely to affect gas stream volume,
temperature and chemistry of dust. A typical sheet is enclosed.
Variations of this format can be generated based on the type of
application
Daily log sheet:
Date:
Time Field Pri. Pri. Sec. Sec. Spark % ESP ESP Plant
Volts Amps Kv MA /min O2 I/L I/L Load
Temp press Data
Note: 1. For spares list of TR set and panel, Rapper panel refer individual
Manuals enclosed.
2. For spare list of MCC refer details of BOM furnished by
Manufacturer
49
SECTION -9
50