DJTECH ELECTRICAL AND CIVIL ENGINEERING SERVICES

Chapter 6 San Juan Aplaya, Digos City


Contact No: 09203357540 / Email Add: joelzcalub@gmail.com

Date: April 19, 2023


Project Title: Installation of Distribution Transfomer 37.5 kVa
Address: Purok Dike, Rizal, Bansalan, Davao del Sur
Owner: Ridragon Resort
Subject: Quotation to supply labor, equipments and materials

No. Description Qty Unit


Distribution Transformer
1 Distribution Transformer – 37.5kVA, Brandnew, Pole Type, oil immersed, 2HV and 1 Unit
3LV bushing, 13200/7620 grd Y, 120/240V Secondary, 60 Hz, Single Phase with 2 ½ %
tap above and below normal high voltage, 95 KV Primary BIL and 30 KV secondary BIL,
self cooled with 2.0% IMP.

Distribution Transformer Accesories


1 Fuse Cut-Out Assembly – Fuse Cutout and arrester combination, 15KV BIL, 100 1 Set
2 Fuse Link – 8 Amperes AB Chance Brand 3 Pcs
3 Hot Line Clamp – 100 Amperes 1 Pcs
4 Transformer Hanger – Hot Deep Galvanized with complete set of 2 pcs Mounting 1 Set
5 Fabricated Secondary Rack - 3 Spools with Spool Insulators 1 Set
6 Service Drop Wire – 50mm2 THHN Wire 10 Mtr
7 Solderless Copper Connector – 50mm2 2 Pcs
8 Hot Line Clamp Stirrup 2/0 1 Pcs
9 Sleeve Connector (Log Type) CAT #PT 22-6 for Copper Conductor 2 Pcs
Metering Accesories & Service Drop Wire
1 Entrance Cap 1.5" dia 1 Pcs
2 RSC Pipe 1.5" dia 1 Pcs
3 Elbow, LB, Nipples, Metal Clip & Adopter 1 lot
4 Electrical Tape 1 roll
5 Silicon Sealant 1 tube
6 Expansion Bolt 4 Pcs
7 THHN Copper Wire 14mm2 (grounding) 6 Mtr
8 THHN Copper Wire 50mm2 12 Mtr
9 150AT, 2P, 240V, MCB in NEMA 1 lot
Installation & Permitting
1 Labor, Installation & Processing
2 Signed & Sealed CFEI & EP, LGU Permitting fee's
1 lot
3 Dasureco Appication fee's & charge
4 DASURECO Statement of Account (With DASURECO Official Receipt)

TOTAL PROJECT COST 280,000.00


Terms & Conditions:
Terms of payment : Full payment before processing of documents.
Delivery terms : Five (5) days upon recieve of payment (start of processing).
Processing Duration (15-25 days from done installation of Service Entrance Pedestal)
Warranty : Two (2) years against inheret defects from the date of energized
: All materials to be installed are all brandnew and in accordance with DASURECO standard.

Scoop of Work:
1. To coordinate with DASURECO for the installation of distribution transformer
2. Processing of permits and other document required by DASURECO for energization of transformer (37.5kva)
(Signed Electrical Plan with CFEI and Electrical Permit, Brgy. Clearance, Transformer Test Result and Certificate,
Certificate of Energization) *we may need some documents from client as addtional requirement.
3. Supply labor, equipment and materials
4. Delivery of transformer to DASURECO for testing
5. Installation of service entrance, service drop wire and MCB if available
6. Include payment of Permitting fees, Survey / Inspection Fees, Bill Deposit

Notes: Price by quotation may change as content may change depending on the final inspection of Dasureco.

Prepared by:
CHERISH BELLE C. CUBILO
Office-In-Charge
0920 335 7540