BILL OF QUANTITY

( CIVIL & ARCHITECTURE WORK )

OWNER : PT.SEMEN JAWA


PROJECT : AF SOLID WASTE STORAGE
DEPT.REQUEST : PRODUCTION

MATERIAL
No. DESCRIPTION SPESIFICATION UNIT QTY
U /PRICE AMOUNT
I. SITE PREPARATION
1.1 Mob. & Demob LS 1.00 5,000,000 5,000,000
1.2 Scafolding installation Hight 12 meter LS 1.00 1,500,000 1,500,000
1.3. Safety and other preparation LS 1.00 2,000,000 2,000,000
TOTAL SITE PREPARATION ( 1 ) 8,500,000

II. CLADING INSTALLATION For EXISTING PORTAL


2.1 Metalsheet colorcoat 130*7 meter thik. 0.45mm m2 946.00 150,000 141,900,000
2.2 Metal Ridge colorcoat thik. 0.45mm meter 45.00 150,000 6,750,000
2.3 CNP 100 x 50 x20 thk.3,2 mm 5.5kg/m kg 3,669.30 15,000 55,039,500
2.4 Wind Bracing RB 12 mm 0.888kg/m kg 179.38 15,000 2,690,700
2.5 Sagrod RB 12 mm 0.888kg/m kg 279.72 15,000 4,195,800
2.6 Plate thk 3 mm for support joint 23.55kg/m kg 280.41 15,000 4,206,150
2.7 Equal angle 60x60 thk. 3 mm ( CNP support ) 2.71kg/m kg 97.56 15,000 1,463,400
TOTAL CLADDING INSTALATION ( II ) 216,245,550

III. EXPANSION ROOF


3.1 Metalsheet colorcoat 10.25 x 45 meter dan 5,5 x 45 m thik.0.45mm m2 708.75 150,000 106,312,500
3.2 Metalsheet flushing 45 meter @ 4line thik.0.45mm meter 180.00 150,000 27,000,000
3.3 CNP 150x50c20 thk.2.8 mm 5,97kg/mm kg 3,761.10 15,000 56,416,500
3.4 Wind bracing RB 12 mm 0.888kg/m kg 149.18 15,000 2,237,700
3.5 Sagrod RB 12 mm 0.888kg/m kg 239.76 15,000 3,596,400
3.6 Structure HC 300x150x6,5x9 36.7kg/m kg 2,312.10 15,000 34,681,500
HC 250x125x6x9 29.6kg/m kg 905.76 15,000 13,586,400
WF 350x175x7x11 49.6kg/m kg 1,785.60 15,000 26,784,000
WF 300x150x5,5x8 36.7kg/m kg 1,321.20 15,000 19,818,000
Plate 6 mm for joint 47.1kg/m kg 701.40 15,000 10,521,000
Base plate tebal 15 mm 117.75kg/m kg 350.20 15,000 5,253,000
WF 250x125x6x9 mm 29.6kg/m kg 2,664.00 15,000 39,960,000
UNP 200x80x7,5x11 mm 24.6kg/m kg 1,062.72 15,000 15,940,800
3.7 Foundation for roof structure concrete K-300 m3 24.00 1,000,000 24,000,000
Formwork m2 131.52 95,000 12,494,400
rebar steel DB 13@1.042 kg/m kg 2,334.50 16,800 39,219,600
rebar steel RB 10@0.617 kg/m kg 592.32 16,800 9,950,976
Lean concrete m3 3.10 850,000 2,635,000
Soil excavantion for foundation m3 104.20 -
Sand Bed m3 3.10 350,000 1,085,000
3.8 Roof gutter Base gutter zinc thk.0.4mm m2 56.25 88,000 4,950,000
MATERIAL
No. DESCRIPTION SPESIFICATION UNIT QTY
U /PRICE AMOUNT
Frame gutter L 40x40x3 1.83kg/m kg 65.88 15,000 988,200
Support frame strip plate 50x3 1.1775kg/m kg 70.65 15,000 1,059,750
Piping PVC 4 inch Rucika meter 8.00 85,000 680,000
Support frame CNP 100x50x20x2,3 4.06kg/m kg 158.34 15,000 2,375,100
3.9 Plate thk.3 mm for support joint 23.55kg/m2 kg 210.31 15,000 3,154,650
TOTAL EXPANSION ROOF ( III ) 464,700,476

IV. PRECAST FENCE 122 meter


4.1 Install coloumn fence quality K -225 20x20x320 cm Coulumn 54.00 -
4.2 Install panel fence quality K -225 5x40x240 cm panel 245.00 -
4.3 Masonry Foundation m3 8.10 -
4.4 Compacted soil existing meter 120.80 -
4.5 Soil excavation and filling back m3 15.55 -
TOTAL PRECAST FENCE ( IV ) -

V. RIGID PAVEMENT For STORAGE AREA


5.1 Concrete K- 300 13 x 45 m thk. 150mm m3 87.75 1,000,000 87,750,000
5.2 Base stone Grading stone thk. 150mm m3 87.75 350,000 30,712,500
5.3 Formwork wood m2 27.00 95,000 2,565,000
5.4 Plastic sheet bracing m2 585.00 80,000 46,800,000
5.5 Curing water with geotextile m2 585.00 100,000 58,500,000
TOTAL RIGID PAVEMENT ( V ) 226,327,500

JUMLAH TOTAL I + II + III + IV + V 915,773,526