Professional Documents
Culture Documents
AP C104 19 - NCW4 Annexures V1.1
AP C104 19 - NCW4 Annexures V1.1
Contract Particulars
Item Relevant
Clause
1 1 Principal:
ABN:
Principal's address:
2 1 Contractor:
ABN:
Contractor's address:
3 2 and 23 Superintendent:
Superintendent's address:
6 5 Amount of security:
(“Nil” applies if not filled in)
Form of security:
Amount or percentage of
security returned at practical
completion. (“50%” applies if not filled in)
Period after the date of
practical completion for the
whole of the Works for return
of remaining security: (“12 months” applies if not filled in)
Contract Particulars
Item Relevant
Clause
Contract Particulars
Item Relevant
Clause
Contract Particulars
Item Relevant
Clause
Guidelines
The Commercial Framework must be completed and issued as part of the tender
documents and, subject to any amendments, it is incorporated into the Contract.
It does not have a prescribed format, but at a minimum, it should address the following:
Clause 35.3: Any events outside of the reasonable control of the Contractor (such
as inclement weather or industrial conditions) for which the Contractor
has no entitlement to an extension of time. Alternatively, this may be
specified in Item 23. (If nothing is specified, the Contractor is entitled to
an extension of time for these events.)
Clause 36: Method for calculation of delay costs. (If nothing is specified, delay
costs will be determined by the Superintendent.)
Clause 40: Any rise and fall adjustment or currency fluctuation adjustment. (If
nothing is specified, there will be no adjustment to payment for
external factors.)
Clause 40.5: Whether or not rates and amounts are inclusive or exclusive of
overheads and profit (if nothing is specified, under clause 40.5 i) rates
and amounts are inclusive of overheads and profit).
Clause 48: Whether or not rates and amounts are inclusive or exclusive of GST.
(If nothing is specified, then under the GST Act, rates and amounts will
be deemed to be inclusive of GST.)