4. For how cross sections are used ? JUM : for cut and fill quantities.
5. What is the perception and reaction time for calculating the sight distance?
1 second
2.5 s
3.5 s
None of the above .
JUM : 1 second.
6. If a work, if the property decides to make a change in scope, what is the procedure to
do ?
Change order
Modification
....
JUM : Change order .
10. On relation to the use of air-entraining agents in concrete, which of the following
statements are true:
Improve the workability
Improving long-term durability
Makes a less dense mixture
...
JUM : all the above are true.
11.Rellenar the gap : The immediate ______________ are Necessary to Develop the
Following tasks in a breaking down of a project .
Critical activities
predecessor activities
successor activities
Burst activities
None of the above is correct.
JUM : Predecessor activities.
12. What of the following statements are false for a Work package:
Allocating resources must
It should designate a Work manager.
It should set deadlines "definitive "
None of the above is false .
JUM : You should set a timetable definitive .
13.On Work breakdown structure relative to project which of the following statements are
false ? .
Breaks up the project in a " top-down " .
It breaks down the draft as "down -top "
Used to handle large projects.
JUM : used to handle large projects.
18. Problem: "If in a plane I measure 7 ¼ " "(inches ) and is 1/62.500 scale , what is the
distance between the two points in miles ? " JUM : 7, 25 miles.
20. In a beam which points of stress due to the time and bearing is equal to 0 ?
In the neutral light center .
In the top center fiber light.
At lower fiber support.
In the neutral support .
JUM : the neutral center and the neutral light support .