Kazi Para Jame Mosque

Material Estimate and Costing


SI. Name of item Quantity Rate Amount
1 Foundation & Ground floor
a Cement 694.00 450.00 312300.00
b Sand 1921.80 65.00 124917.00
c Aggregate(stone chips) 2461.00 210.00 516810.00
d Rebar 5964.00 85.00 506940.00
e Brick 20665.00 15.00 309975.00

2 1st floor
a Cement 582.00 450.00 261900.00
b Sand 1371.00 65.00 89115.00
c Aggregate(stone chips) 1869.00 210.00 392490.00
d Rebar 10043.00 85.00 853655.00
e Brick 16402.00 15.00 246030.00

2 2nd floor
a Cement 618.00 450.00 278100.00
b Sand 1930.00 65.00 125450.00
c Aggregate(stone chips) 1869.00 210.00 392490.00
d Rebar 10043.00 85.00 853655.00
e Brick 22272.00 15.00 334080.00

3 Finishing & Electrical Work L.S L.S 2926940.00

4 Labour Cost including shuttering L.S L.S 3000000.00

Air Conditioner(Gree GS-30CZ 2.5


5 Ton Split) 36.00 85000.00 3060000.00

6 Miscellaneous cost L.S L.S 500000.00

Total 15084847.00