You are on page 1of 11

SDN BONJOK

Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (17org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng 9825 bh, lisplang MOS,PO 4
2 Keramik Lantai 320 dus MOS 2
3 Plafon 716 m2 MOS 4
Merah 3 pile, Ext
4 Cat Putih 3 PO 2
5 Sanitair Sink 1, Floor drain 5 PO 2
6 Pagar 78 m1 MOS 4
7 ME Fitting 54 PO 2
8 Saluran 68m1 MOS 2
9 Septictank 1 unit MOS 2
10 Paving 270 m2 PO 3
11 Folding Gate 1 set PO 3
12 Kusen 63 unit PO 3
SDN WAGIR PANDAN
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (20org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng 3000 PO 5
2 Keramik Lantai MOS 4
3 Plafon 100 m2 MOS 4
4 Cat Merah 3 pile PO 2
5 Sanitair Wastafel Meja 4 PO 2
30 Besi 13, 45 Besi
6 Pagar 12, 62 Besi 8 PO 5
7 Septictank 1 Unit MOS 2
8 ME MOS 2
9 Saluran MOS 2
10 Paving 700 m2 PO 3
11 Tower Air 1 Unit PO 3
12 Folding Gate 1 Unit MOS 3
13 Kusen 69 unit PO 3
SMPN PREMBUN
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (22org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng MOS 6
2 Keramik Lantai 300 dus 40x40 PO 4
3 Plafon 460 m2 MOS 4
4 Cat Biru Biru 4 pile Biru PO 6
5 ME MOS 1
6 Tower Air 1 Unit PO 3
7 Kusen 25 Unit PO 3
SDN KALIJERING
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (20org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng MOS 4
2 Keramik Lantai MOS 4
3 Plafon MOS 4
4 Cat Merah 3 pile PO 2
5 Opening MOS 4
6 Sanitair MOS 2
7 Pagar 36 m1 PO 4
8 Septictank 1 unit MOS 2
9 ME MOS 1
10 Saluran 52 m MOS 2
11 Paving 187 m2 PO 2
12 Folding Gate 1 unit MOS 3
13 Kusen 49 unit PO 3
SDN TANJUNGREJO
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (16org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25
Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des

8/15=10, 8/12=6,
6/12=20, 5/7=77,
2/3=7,
genteng=2310bh,
1 Atap Genteng kerpus=52bh PO 4
2 Keramik Lantai MOS 2
14 box, hollow 12
3 Plafon ikat, skrup 5dos PO 2
4 Cat Merah 2 pile MOS 2
5 Opening MOS 4
6 Pagar MOS 4
7 ME MOS 1
8 Saluran PO 1
9 Kusen 48 Unit PO 3
SDN TLOGOREJO
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (10org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng list plank 56bh PO 4
2 Keramik Lantai MOS 2
3 Plafon MOS 2
4 Cat merah 2 pile MOS 2
5 Opening MOS 4
6 ME MOS 1
7 Saluran PO 1
8 Paving 168 m2 PO 2
9 Kusen 63 unit PO 3
SDN JLEGIWINANGUN
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (20org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap Genteng Lisplang 66m PO 4
2 Keramik Lantai 110m2 MOS 2
3 Plafon PO 2
4 Cat Merah 3 pile PO 2
5 Sanitair MOS 2
6 Septictank 1 Unit MOS 2
7 ME MOS 1
8 Saluran MOS 1
9 Paving 100m2 PO 2
10 Tower Air 1 unit PO 3
11 Kusen 56 unit PO 3
SDN PEKUNCEN
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (10org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap MOS 4
2 Keramik Lantai 240m2 PO 2
3 Plafon 732 m2 MOS 2
4 Cat Merah 3 pile PO 2
5 Pagar Batu 80m3, Besi PO 4
6 Septictank 1 Unit MOS 2
7 ME MOS 1
8 Saluran 206 m1 MOS 2
9 Paving 304 m2 PO 2
10 Tower Air 1 Unit PO 2
12 Folding Gate 1 Unit MOS 3
13 Kusen 60 unit PO 3
SDN GUNUNG WETAN
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (11org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Keramik Lantai 85m2 PO 2
2 Plafon 112m2 MOS 2
3 Cat 3 pile Merah PO 2
4 Sanitair Wastafel Meja 4 PO 2
5 Pagar 113 m MOS 4
6 Septictank 1 unit MOS 2
7 ME MOS 1
8 Saluran 215 m1 MOS 2
9 Paving 346m2 PO 2
10 Tower Air 1 unit PO 2
11 Kusen 38 unit PO 3
SDN PARUNG KAMAL
Material Tenaga
No Pekerjaan M23 M24 M25 M26 M27 M28 M29 M30 (16org)
31 Okt - 7 - 13 14 - 20 21 - 27 28 Nov - 5 - 11 12 - 18 19 - 25 Volume Keterangan
6 Nov Nov Nov Nov 4 Des Des Des Des
1 Atap MOS 5
2 Keramik Lantai 131 m2 MOS 2
3 Plafon 180 m2 PO 2
4 Cat Merah 4 pile PO 3
5 Sanitair Wastafel 6, Sink PO 2
6 Pagar 70 m1 MOS 5
7 Septictank 2 unit MOS 2
8 ME MOS 1
9 Saluran 182m1 MOS 2
10 Paving 918m2 PO 2
11 Tower Air 2 unit PO 2
12 Kusen 95 unit PO 3