You are on page 1of 46

LANDFALL DEPARTMENT

CIVIL WORKS DOCUMENT

INST. 12613: Generic Duct Route, Manhole and


Headwall Construction Guidelines

Submarine Fibre Optic Cable Systems


Land Cable Installation Section

ASN. © 2022
Alcatel Submarine Networks
Telegraph House, 10 Telcon Way,
Greenwich, London, SE10 0AG, UK
Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Document Details
Document Name: Generic Duct Route, Manhole and Headwall Construction Guidelines

Document Owner: Alcatel Submarine Networks

Document No: INST. 12613

Issue No: 04

Department: Landfall Operations | Civil Works

Version History
Issue No. Authors Reviewed By Approved By Approved Date Revision Details

04 C. K. John J. Clark C. Higgs 06/11/2022 Includes new civil


drawings & updates
L. Addis G. Burrows
on ducting
requirements

03 G. Burrows J. Clark C. Higgs 17/06/2021 Manhole security


recommendations &
seaward duct details

02 G. Burrows J. Clark J. Clark 02/03/2018 Formatting updates

01 G. Burrows J. Clark J. Clark 26/04/2012 Initial Issue

Authorisation
Signatory Name Date

Authors: Charls Kavumpurathu John & Luke Addis 28/10/2022

Reviewed By: Gareth Burrows & Julian Clark 31/10/2022

Approved By: Colin Higgs 06/11/2022

©Alcatel Submarine Networks 2022 Page 2 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Table of Contents
Document Details ..........................................................................................................................................2
Version History ..............................................................................................................................................2
Authorisation .................................................................................................................................................2
Table of Contents...........................................................................................................................................3
1 Purpose ..................................................................................................................................................5
2 Scope......................................................................................................................................................5
3 Definitions/ Abbreviations .....................................................................................................................5
4 Introduction ...........................................................................................................................................9
5 Health, Safety and Environment............................................................................................................9
6 General Responsibilities ......................................................................................................................10
7 Reporting .............................................................................................................................................11
7.1 Operational Reports ......................................................................................................................12
7.2 Daily Reports .................................................................................................................................12
7.3 Handing Over Reports ...................................................................................................................12
8 Materials & Document(s) Approval .....................................................................................................13
9 Site Survey & Subsoil Investigation .....................................................................................................15
10 Site Preparation ...................................................................................................................................15
11 Design and Drawings ...........................................................................................................................16
12 Excavation And Earthworks .................................................................................................................17
12.1 NOC’s & Approvals ....................................................................................................................17
12.2 Safety .........................................................................................................................................17
12.3 Dewatering ................................................................................................................................17
12.4 Trench Line for Duct Installation ...............................................................................................18
12.5 Width & Depth ..........................................................................................................................18
12.6 Backfilling & Compaction ..........................................................................................................18
13 Concrete Works ...................................................................................................................................19
14 Manhole Accessories – Fittings & Furniture ........................................................................................20
14.1 Manhole Covers.........................................................................................................................20
14.2 Name Labels ..............................................................................................................................20

©Alcatel Submarine Networks 2022 Page 3 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

14.3 Ladder Mount ............................................................................................................................21


14.4 Anchor Irons (Hooks) .................................................................................................................21
14.5 Cable Racks ................................................................................................................................21
14.6 Steel Structures .........................................................................................................................21
14.7 Earth Rod ...................................................................................................................................21
14.8 Sump pit with sump cover .........................................................................................................21
15 Duct Installations .................................................................................................................................21
15.1 Duct Specification ......................................................................................................................21
15.2 Duct material .............................................................................................................................22
15.3 Line of duct lay ..........................................................................................................................22
15.4 Duct installation close to Power cables.....................................................................................22
15.4.1 Single core High voltage cables .............................................................................................22
15.4.2 Multi core High voltage cables ..............................................................................................22
15.4.3 Low voltage cables .................................................................................................................23
15.5 Duct section joints .....................................................................................................................23
15.6 Duct end sections ......................................................................................................................23
15.7 Configuration of multiple duct lays ...........................................................................................23
15.8 Duct plugs ..................................................................................................................................23
15.9 Duct testing ...............................................................................................................................24
15.10 Duct seals and building entries .................................................................................................24
15.11 Duct entries ...............................................................................................................................24
15.12 Duct encasement.......................................................................................................................24
15.13 Warning Tapes ...........................................................................................................................25
15.14 Duct Spacers ..............................................................................................................................25
15.15 Further guidance notes .............................................................................................................25
16 Site Remediation..................................................................................................................................25
17 Demobilisation .....................................................................................................................................26
18 Debriefing ............................................................................................................................................26
19 Appendix ..............................................................................................................................................26

©Alcatel Submarine Networks 2022 Page 4 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

1 Purpose
The purpose of these guidelines is to set down minimum requirements for undertaking Duct installations
& Civil works for Manholes & Headwall constructions. Where a discrepancy exists between ASN Drawings,
this guideline, and previous versions of ASN guidelines, the Contractor or Customer shall seek clarification
from ASN Landfall Department. This document must be read in conjunction with relevant supporting
documents and data available for the work, which include but are not limited to:
• Survey report(s) and relevant local utility plans, including positions of existing in-service
cables and other services
• As-built documents of existing infrastructure provided by the Customer, or other relevant
third party
• Marine installation program Plan of Work
• Scope of Work & BOQ if available
• General Drawings & Previous As-Built Drawings
• Local Authority Guidelines of respective Country
• A copy of relevant principal and environmental permits already in place.
• Municipal plans & Permits in Principle conditions.

2 Scope
The scope of this document is designed to deal specifically with manhole construction from Cable Landing
Stations (CLS) to the Beach Manhole (BMH), including seaward ducts and Concrete Headwalls. Other
issues such as land route surveys and HDD engineering are not covered in this document.
This document is prepared in the assumption that the construction of front haul works including Beach
Manholes is for the purposes of installing ASN optical fibre systems. If this document is referenced by the
system purchasers, landing party or provider or their subcontractors, the HSE standards, documentations
and submittals and its procedures (Section 4 to 10 & Section 16 to 18) shall be as per the standards of the
respective Landing Party or Provider, not of ASN. The technical guidelines (section 11 to 15) can be
referred for construction purposes and to understand the ASN requirements for the installation of its
terrestrial and submarine cables.

3 Definitions/ Abbreviations
Term Meaning

ASN Alcatel Submarine Networks

ASP/AP Articulated Split Pipe

BH Borehole

©Alcatel Submarine Networks 2022 Page 5 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Term Meaning

BMH Beach Manhole

BOQ Bill of Quantities

CAD Computer Aided Design

CLS Cable Landing Station

CS Confined Space(s)

DPR Daily Progress Report

DTS Desktop Study

EEZ Exclusive Economic Zone

ERT Electrical Resistivity Tomography

GNSS Global Navigation Satellite System

GDPR General Data Protection Regulation

GPR Ground Penetrating Radar

GPS Global Positioning System

GRP Glass Reinforced Plastic

HC Hardened Concrete

HDD Horizontal Directional Drilling

HDPE High Density Polyethylene (Pipe/duct)

HIRA Hazard Identification & Risk Analysis

HSE Health, Safety & Environment

ID Internal Diameter

IR Inspection Request

IS In-Service

KP Kilometre Point

©Alcatel Submarine Networks 2022 Page 6 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Term Meaning

L/HWM Low/High Water Mark

MDD Maximum Dry Density

MOP Method of Procedure

MSWP Method Statement Work Plan

MPa Megapascals

NOC No Objection Certificate

OD Outside Diameter

OSP Outside Plant (Infrastructure)

PF Prefabricated

PCC Plain Cement Concrete

POW Plan of Work

PTW Permit to Work

PVC Poly-vinyl Chloride (Pipe/duct)

QC Quality Control

QHSE Quality, Health, Safety & Environment

RA Risk Assessment

RAMS Risk Assessment Method Statement

RCC Reinforced Cement Concrete

RFP Request for Proposal

RPL Route Position List

SCT Standard Compaction Test

SOW Scope of Work

SPT Standard Penetrating Test

©Alcatel Submarine Networks 2022 Page 7 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Term Meaning

SRC Sulphate Resistant Cement

SRT Seismic Refraction Tomography

SWD Seaward Duct

TBT Toolbox Talk

uPVC Unplasticized Polyvinyl Chloride (Pipe/Duct)

Infrastructure Element Meaning

Beach Manhole The BMH is the transition between the marine cable and the terrestrial cable
and will house the beach joint. This manhole should be in an area of stable
ground, behind the beach or landing point, with good access for installation
and maintenance activities.

Concrete Concrete structure to support the transition between directly buried Marine
Headwall/Plinth cable from sea and ducted cable to BMH. This structure should normally be
located towards the back of the beach or landing point with good access for
installation and maintenance activities. Normally the structure is buried 2m
below existing ground level to enable smooth transition for beach burial
protection.

Pulling/Turning Manhole provided for cable pulling & installation. This manhole should be
Manhole placed at maximum 250 metre intervals for both powered and unpowered
systems.

Intermediate Manhole provided for cable splicing/ jointing. This manhole should be placed
Jointing/Splicing at 2000 metre intervals for powered system and 1000 metre intervals for
Manhole unpowered systems.

Site Refers to any area where construction, engineering, survey or testing related
activities are taking place, or are planned to take place as part of the project.

Outside Plant Refers to the Cable Landing Station infrastructure, including the Beach
Manhole, Fronthaul duct route to Cable-Vault or Zero MH located at the CLS.

Responsible Party Meaning (engineering & construction operations)

Contractor A Contractor is any company or individual who directly employs or engages


construction workers or manages construction work. Contractors include sub-
contractors, nominated agents or suppliers, and any individual self-employed
worker or business that carries out, manages, or controls construction work.

©Alcatel Submarine Networks 2022 Page 8 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Responsible Party Meaning (engineering & construction operations)

Principal Contractor The Contractor company directly hired by the Customer to perform contract
specific tasks. This Contractor is normally responsible for other
subcontractors, nominated agents, suppliers or self-employed workers
involved with the project.

Competent Person(s) Someone who has sufficient training and experience or knowledge and other
qualities that allow them to assist properly in executing a specific task.

Customer Organisation or person buying goods or services to perform construction or


engineering work. This could be the Landing Party or Provider, System
Owner(s), or ASN.

Customer Contractor point of contact during construction operations phase.


Representative

4 Introduction
This document details the work required to construct a terrestrial Outside Plant (OSP) infrastructure
network between a Cable Landing Station (CLS) and a Beach Manhole (BMH).
The civil engineering work may be performed on behalf of a Landing Party, System Purchaser or System
Supplier, referred to throughout this document as the ‘Customer’. The guidelines are intended to inform
a ‘Contractor’ of the standard technical engineering requirements for the safe and efficient installation of
submarine fibre optic cable systems by Alcatel Submarine Networks (ASN).
This document includes details on site investigations designed to aid in the design and build stages of the
manhole and duct route construction and should not be interpreted read as a Specification or Scope of
Work document. Engineering and construction requirement may differ from site to site, and the
nominated Contractor should provide its own engineering and construction designs for Customer review.
Due attention shall be paid to all aspects of the design and construction including internal and external
appearance, durability of materials, resistance to moisture, structural stability, fire resistance allied to
means of escape in case of fire, ventilation, and public health & security requirements. The infrastructure
should be built with a design life of minimum twenty-five (25) years.
The Standard Drawings show the preferred layout arrangement of each manhole type and the preferred
dimensions, and these shall not be changed without the written approval of the Author(s) of this
document.

5 Health, Safety and Environment


The Contractor shall conform to recognised international safety practices during all aspects of the
operation appropriate to the Site (location, region, country) and the planned work. The Contractor must

©Alcatel Submarine Networks 2022 Page 9 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

identify and record those practices that are applicable to the work, site and resources mobilised and
compliance demonstrated in the Contractor’s plans and procedures.
Each party shall ensure that its servants and agents shall, during the contracted operations, observe any
local regulations and permit requirements pertaining to HSE.
The Contractor shall operate International Safety Management (ISM) and Health, Safety and
Environmental (HS&E) systems based on legislation relevant to the proposed activities.
All equipment to be used for the works, both by the Contractor and nominated agents, suppliers, and
subcontractors, shall be approved, and certified by an independent authority or classification society or
where appropriate by the Contractor or nominated agent, supplier or subcontractor as fit for the intended
use, with associated documentation provided.
The Contractor shall ensure the certification remains valid for three (3) months beyond the scheduled
demobilisation date. Where appropriate, equipment may be self-certified by the Contractors or
Subcontractor’s nominated Competent Person in accordance with stated industry standards.
All personnel shall be made aware of their obligations under the local HSE regulations and shall possess
appropriate protective clothing and safety equipment. They shall be in possession of an in date and valid
medical certificate. The Contractor shall provide an alcohol and drugs policy statement for Customer
review.
A detailed QHS&E plan for the construction operations should be provided to the Customer no less than,
twenty-eight (28) days prior to mobilisation.
Prior to the start of operations, the Contractor will provide written confirmation to the Customer that all
assessments, as required by the QHS&E Plans (e.g., Risk Assessments, RAMS & HSE evaluations etc.) have
been carried out. This will apply to the overall project work area, as well as the specific equipment and
manning levels and expertise that will be utilised during the operations.
A paper copy of the QHS&E Plan and written compliance statement from the Contractor’s project
manager shall be displayed on each work site for access by all personnel with hard copies of all approved
plans, procedures, and risk assessments available on site.
ASN reserves the right to audit operations, equipment, and documentation where construction
operations fall under ASN scope.

6 General Responsibilities
The Contractor shall be responsible for:
• Health, Safety and Security, complying with local and international standards to cover all site
work operations.
• Planning, management, and direct supervision of the construction operations.
• Provide all required documentation as required during the RFP process.
• Provide regular preparation and operational updates.

©Alcatel Submarine Networks 2022 Page 10 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

• Obtaining all operational permitting, including but not limited to notification to local
authorities/ harbour master/ local councils/ landowners/ highway authorities and any other
authorities specific to a particular site (ASN will provide access to Permit in Principle (PIP)
where applicable.
• Comply with PIP requirements, local environmental regulations, recommendations, and
practices that are specific to the installation and construction operations.
• Obtain all work permits, and entry visas for on-site personnel.
• The Contractor shall obtain/arrange access to all sites for all equipment and plant required
during all phases of the manhole installation operations, including:
o Location, Identification and marking of existing services.
o Perform exploratory geophysical & geotechnical survey operations, where required.
o Have accountability for all equipment mobilised to site.
o Provide all support equipment, including heavy lift, formwork, welding & cutting
equipment, and welfare facilities.
• QC of positioning for land-based survey & construction work.
• Disposal of any waste material generated and clear debris and dispose at a designated site.
• Provide Preliminary, and Final reports for each survey or construction operation.
• Provide safe and comfortable place of work for the Customer Representative(s).
• Timely delivery of serviceable equipment to site to meet the construction Plan of Work.
• Manage and supervise the installation and construction of the manhole and duct route, and
seaward duct infrastructure, as required.
• Control, manage and supervise all stages of the installation, construction, and site remediation
operations in line with operational permitting requirements.
• Complete all operations in a safe and timely manner, in line with current POW in force.
• Assume overall responsibility for all subcontractors on site, acting as Principal Contractor
through the duration of the civil construction works.
• At no time must the operations of the Contractor endanger any pre-existing infrastructure
identified prior to commencing construction work on site.
• Remain responsible for the Health, Safety & Welfare of all personnel on site, acting as
Principal Contractor for the management of QHSE on site.
• Provide suitable manning levels for all operations to run efficiently and in line with local
regulations & ASN guidelines.
• Provide the Preliminary Report after completing the manhole installation operations and
Final As-Built Reports as per contract requirements.

7 Reporting
All documentation shall be prepared in the English language unless otherwise specified and made
available to ASN prior to cable installation operations.

©Alcatel Submarine Networks 2022 Page 11 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

7.1 Operational Reports


The Contractor shall provide periodic updates in terms of its progress in performing the Scope of Work.
In addition, the Contractor shall provide such updates as are requested by the Customer and do so in a
timely fashion. Updates should show dates for elements of the work partially and fully completed and
estimated dates for performance of those elements of the work not yet performed, up to the estimated
point of completion of the Scope of Work. Such updates shall be in substantially the same form as the
Contract Plan of Work.
7.2 Daily Reports
A Daily Progress Report (DPR) should be emailed to the Customer on completion of each working day. A
copy of the DPR shall be provided to the Customer Representative at the end of each day for signature.
The exact content and distribution of the DPR will be discussed and agreed with the Customer
Representative prior to the start of the operations.
The DPR will be issued from the start of the mobilisation process until the end of the demobilisation
process. The content of the report will include as a minimum the following:
• Project and segment name, DPR number, date, contact numbers and email addresses.
• Weather conditions during the preceding 24 hours and weather forecast.
• List of personnel / plant / equipment on site.
• Summary of the work performed during the preceding 24 hours.
• Summary of the work planned for the next 24 hours.
• Summary of progress against the plan of work and estimated completion.
• Time spent on effective work during each 24-hour period and the cumulative total.
• Weather downtime during each 24-hour period and the cumulative total.
• Equipment downtime during each 24-hour period and the cumulative total.
• Other non-operational time during each 24-hour period and the cumulative total.
• List of events logged in the last 24 hours.
• QHSE Metrics & any issues/concerns.
• Endorsement of the report by the Customer Representative(s).
• Space for comment by the Purchasers and or ASN Representatives.
7.3 Handing Over Reports
After the completion of civil construction operations, the Contractor should provide the following:
• A written statement that the manhole and seaward duct installation has been completed in
full, having obtained all the necessary file data required as outlined in this Scope of Work.
• Other relevant information.
The Contractor shall provide a Provisional Report for the manhole and concrete headwall Installation,
including geotechnical & other survey operation results and findings.
The Contractor shall provide the hard copies and electronic copies of the Provisional Report after
completion of the operations unless confirmed otherwise in writing.

©Alcatel Submarine Networks 2022 Page 12 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Prior to the start of the civil construction operations, the Contractor may provide a generic report
template so that the format of the report is in line with Customer requirements. If this is not provided,
then the contents of each report should include as a minimum the following:
• Introduction and Scope of Work.
• Summary of Operations and Diary of events.
• Materials specification, size, length, and condition.
• Project planning and preparation summary.
• List of all personnel.
• Project resources information and equipment specifications (including calibration certificates
• Completed Operational Permits Matrix.
• Detailed operations specifics including number of seaward ducts installed and length.
• All DPRs.
• Photographs of the manhole Installation location and surrounding area prior to start of works,
during works and on completion of all works.
• Any electronic drawings/ charts should be issued in a CAD file (e.g., DWG/DXF) and PDF format.
• All report text and or photographs should be issued in original (e.g., MS Word/JPEG etc) and
PDF format.
• All videos should be issued in native DVD format or common computer formats (e.g.,
MPEG/AVI).
• As Built Drawings.
• Guaranty & Warranty Letters.
• Defects Liability Period Maintenance Letter.
The Contractor shall provide the hard copies and electronic copies of the Final Report after receipt of
Customer review and comments on the Provisional Report.

8 Materials & Document(s) Approval


For all materials used on site, material approval request shall be submitted with relevant documents duly
attached. Material delivery Inspection Requests shall be submitted to the Customer upon delivery of any
material on site.
Prior to the start of any mobilisation operations, the Contractor must provide the following:
• Information on equipment to be used, including calibrations and service records and operator
details.
• Crew/ Personnel lists with detailed specifications and all certifications and calibrations in date,
whilst respecting GDPR guidance or other local personal data protection laws.
• Quality, Health Safety and Environmental Plan.
• Emergency Response Plan.
• Construction Plan Drawings.
• Submission of all Technical Materials.

©Alcatel Submarine Networks 2022 Page 13 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

• Plan/ Schedule of Work.


• Operational Permits Matrix.
• Method of Procedure, Work Area, and HIRA.
• Risk Assessment Method Statement.
• Alcohol & Drugs Policy Statement.
During the execution of work, the Contractor must provide the following:
• Daily, Weekly, or Monthly work plan & progress reports.
• Inspection Requests prior for all major works.
• Test Results/Reports for major activities.
• Summary overview of as-found ground conditions to be shared with the Customer prior to
completion of ground investigations.
• Overview information of all areas requiring enclosure for site access and segregation of the
public, including lay down yards, or equipment and materials staging areas.
• Overview of locations of all buried infrastructure and utilities, and location of surface marker
painted positions where possible.
• Notification in good time of any deviations from the Method Statement, Risk Assessment Plan
Drawings, Toolbox Talks and overall SOW requirements.
ASN recommends the following documents submission deadlines:

1 Operational Procedure & Plan/ Schedule of Work 28 days prior to mobilisation

2 Operational Permits Matrix 28 days prior to mobilisation

3 Method of Procedure, Work Area, and HIRA 28 days prior to mobilisation

4 Crew/Personnel lists with detailed specifications 28 days prior to mobilisation


and all certifications and calibrations in date.

5 Quality, Health Safety and Environmental Plan 28 days prior to mobilisation

6 Alcohol & Drugs Policy Statement 28 days prior to mobilisation

7 Emergency Response Plan 28 days prior to mobilisation

8 Daily Progress Report On completion of each working day

9 Material Submission Form for materials approval 28 days prior to mobilisation

10 Inspection Requests 48 hours before the activity

©Alcatel Submarine Networks 2022 Page 14 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

9 Site Survey & Subsoil Investigation


Prior to constructing any landfall infrastructure, including the Beach Manhole & Concrete Headwall, it is
essential that adequate data has been acquired through preliminary site investigations and subsoil
analyses. This preliminary stage involves assessing a site for its suitability and the overall feasibility of
installing underground infrastructure in each site location, including performing the necessary subsoil
investigations.
The specific installation and construction requirements will depend on the nature of the site, accessibility,
resources and whether significant road or other infrastructure crossings are necessary.
It is important to establish whether the preliminary Desktop Studies (DTS) is sufficient to proceed with
the design or whether physical ground investigations are required, as each site has its own distinctive
engineering and survey requirements.
The Contractor shall carry out the sub-soil investigations and in-situ or laboratory tests required to
completely satisfy the design parameters he chooses for foundation or other geo-technical design.
Samples shall be taken as necessary and tested to determine the physical and chemical characteristics of
the various strata and of ground water, if encountered.
Records of boring and trial pit excavations and results of tests on samples shall be incorporated into a
sub-soil investigation report. This shall include recommendations on the type of foundation and on the
safe design bearing capacity of the sub-soil. The Contractor shall survey the site of the works to precisely
establish the site boundaries and ground levels over the whole area. The site survey plan shall be prepared
showing the survey results and the proposed layout of new works. Copies of this plan shall be sent to the
Customer for review.

10 Site Preparation
The contractor is responsible for:
• Preparatory works at the installation site for the manhole construction, subsoil investigations,
utility surveys and reinstatement operations.
• Mobilise all plant, equipment & personnel to the installation work site. Set up site hoardings,
protective barriers and secure the working area in preparation for the construction operations.
• Physical location of any buried services identified during the Desktop Study.
• Install any warning markers and communicate existence of buried services to all personnel as
part of a Toolbox Talk or pre-Job Safety Analysis workshop.
• Provide a detailed overview of all buried services locations for Customer Representative to
review prior to breaking ground.
• Perform ground investigations using appropriate methodology and serviceable equipment to
ensure subsurface geology conditions are known and the existence of other infrastructure is
recorded.

©Alcatel Submarine Networks 2022 Page 15 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

• An ASN approved & accepted survey spread, and drilling rig for test bores or water table
monitoring will be provided by the Contractor.
• Final site safety walkaround to ensure the site is safe to commence construction operations.
• Identify works area and enclose with safety fencing and barriers as required.
• Take photos of the installation site and immediate area to record “as-found” condition prior
to commencement of operations.
• Hold toolbox talk (TBT) with all employees and subcontractors on site, conduct safety audit
and review the HIRA and all applicable project procedures.
• Establish safe access into and exit out of the work site.
• Clear any vegetation, trees or shrubs as required to gain safe access to the work location.
• Establish a survey datum, as required, to enable beach profile to be made and to provide
correlation for depth of boring and IS cable burial measurement.
• Identify any existing services and in-service Transmission and/or Power Cables, and mark
clearly.
• Prepare equipment for survey or construction operations, before mobilising equipment to the
site ensure equipment checks are completed to minimise any risk of spillage or delays.
• Review Method of Procedure (MOP) and work plan documentation with key personnel and
record any deviations following approval of the Customer Representative.
• Provide mobilisation report for Customer review & acceptance.
• It is anticipated that though the Sites will be relatively level and free from obstructions it may
be necessary to provide fill to raise the ground level or to cut and remove to bring down the
ground level to heights like those for adjacent buildings, sites or the main roads and gate levels
as obtained from the Local Authority.

11 Design and Drawings


The Contractor shall design the engineering works and prepare complete working drawings as necessary
for the construction of the works. List of all drawings shall be submitted in the initial stage of the project.
The design of all construction works shall be the responsibility of the Contractor.
Civil engineering works and services for manholes, headwall and duct installations shall all be designed
and constructed in accordance with the relevant Codes of Practice for the purpose of satisfying the
Building Regulations of the Local Authority and obtaining the necessary Permit approval from the Local
Authority as required. Supervision of civil construction and or survey works must fulfil local authority’s
requirements.
Design calculations and detailed drawings must be submitted to the Customer for review at least four (4)
weeks before the relevant construction work is carried out.
Duct layouts and drawings shall be designed giving due consideration to the findings of the site visit and
site constraints.

©Alcatel Submarine Networks 2022 Page 16 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Steel reinforcement and concrete mix design shall be designed by the contractor considering the loads
applied on the concrete structures and the local authorities’ rules and regulations. The reinforcement
details and concrete details provided in our drawings are the minimum requirement recommended by
ASN.

12 Excavation And Earthworks


12.1 NOC’s & Approvals
All excavations for manholes, headwalls and duct installations shall be carried out to the widths, lengths,
and depths in accordance with the approved drawings. No unlicensed or indiscriminate digging shall be
permitted. All NOC’s & Permits to excavate shall be obtained from local authorities prior to any works
being undertaken. Any underlaying services shall be identified & moved or diverted in accordance with
owners/operators requirements, prior to the civils excavation process commencing.
The Contractor shall allow for risk of meeting and having to excavate through all types of subsoil of
material, including rock. The use of explosives shall not be used unless deemed necessary and approved.
If the manhole or headwall installation site is in a developed area where utilities and buried services may
be present, particular attention should be taken to reference positions of all existing infrastructure prior
to breaking ground with any type of equipment, to avoid damage to any in-service operational cables or
other underground infrastructure or utilities that may already be installed; this applies to all land-based
operations, including within the coastal zone.
12.2 Safety
The Contractor may excavate by any method he considers suitable, subject to the local authority and
permitting approval. This includes No-Dig trenchless methods and open trench techniques.
At all times, the required road guarding items, warning signs, cones, protection barriers shall be placed
both before and during the time that work is taking place. The Contractor shall include all the timbering,
sheet piling and shoring necessary to maintain the stability of the excavations. All trenches more than
1.2m depth will have the trench sides supported by close boarding and/or shoring. The contactor is to
include all strutting and shoring necessary for the safe execution of the construction works.
The Contractor shall protect the exposed faces of excavation with approved material and lay any slope
protection in proper and timely sequence to suit the proposed method of construction. The bottom of all
excavated areas shall be trimmed, levelled, and well rammed.
12.3 Dewatering
The excavated surfaces shall be kept dry and clean by pumping, or other method deemed necessary if
water table is higher than the foundation level. Water from such dewatering shall be properly drained
away from the site and disposed of offsite in accordance with operational permitting requirements. The
water table should be brought down to minimum 300 mm below the foundation level.

©Alcatel Submarine Networks 2022 Page 17 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Where a de-watering system is used, all necessary measures must be taken to avoid any land subsidence
due to soil migration. It is essential that the trench remains stable and firm during these temporary works
operations and that the lowered water level shall be maintained until the backfill has been placed and
compacted to the level of the surrounding ground water.
12.4 Trench Line for Duct Installation
Trench lines will be set to take into consideration the subsequent and all future cabling and jointing
operations. The trench will be kept as straight as possible considering other utilities, plants & trees,
structures, or other obstructions. The proposed trench lines will be set in advance over distances of 300
– 400 metres and then proved feasible by performing trial excavations and pilot holes, at 90 metre
intervals thus establishing the optimum line of the trench. Once excavation starts, the line will be
confirmed with trial holes at 30 metre spacing. This should be done in advance of the actual trenching
works commencing.
12.5 Width & Depth
The excavation will be no wider than is reasonably necessary for the execution of the work. In grass verges
the excavation can be wider if the Contractor wishes to use an excavator provided that the extra width
will not be detrimental to property or carriageway.
All excavations will be executed to a depth that is necessary to achieve the specified depth of cover from
the top of the ducts or concrete encasing. The measurement definition is detailed below.
The excavated floor will be flat and free from stones and rock. Where necessary suitable excavated
material or an imported fine fill may be used as a soft bed under the ducts. Extra excavation depth will be
necessary to allow for such a soft bed.
Depth of cover is defined as the measurement from the paving surface to the top of the uppermost duct
or for ducts encased in concrete to the top of the concrete surround. In the case of carriageway and grass
verge the measurement is from the surface to uppermost duct and where there is a banked verge the
measurement reference shall be from the road surface. A general guide for depth of cover for duct
installation is 1m in footway, unmade surfaces, and carriageway.
12.6 Backfilling & Compaction
Backfilling of trenches, excavations and levelling of the site shall be deposited in layers not exceeding 250
mm in thickness of uncompacted soil. Each layer watered when necessary and well rammed or otherwise
consolidated to minimum 95% of the Maximum Dry Density (MDD) obtained using an approved Standard
Compaction Test (SCT).
If soil improvement is not mentioned for any sub structure works, 200 mm thick road base material below
foundation shall be provided and compacted to not less than 98% MDD.
Should any slips occur in the excavations, banks, or filling during the execution of the works or during the
Defects Liability Period from any cause whatsoever, the Contractor shall execute the necessary remedial
works by means and use of materials approved by the Customer Representative. The Contractor shall
make good all settlement of filling that may occur up to the issue of the Final Take Over Certificate.

©Alcatel Submarine Networks 2022 Page 18 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

13 Concrete Works
The Contractor shall employ at the works a Competent Person whose first duty shall be to supervise all
stages in the preparation, placing, compacting, curing and protection of concrete for the construction of
manholes, headwalls & duct encasements. The Contractor is responsible for the day-to-day control of the
quality of the concrete, preparing reports and keeping record of these QC Reports. All test cubes shall be
made, and site tests carried out under his/her virtual supervision.
All concrete except where specifically permitted by the Customer shall be supplied by an approved
supplier of ready-mix concrete having a microprocessor controlled batching plant.
• The minimum cement content of any structural concrete for sub-structure shall be 370 kg/m3.
• The maximum cement content of any structural concrete shall be 480 kg/m3
• The maximum free water/cement ratio shall be 0.42.
• The maximum temperature of the fresh concrete shall not be more than 300C.
• The minimum temperature of the fresh concrete shall not be less than 90C.
• The concrete for RCC shall be ready mix concrete with SRC 35 grade
• The concrete for PCC shall be ready mix concrete with SRC 15 grade
• Mild steel and high yield steel bars and steel fabric shall comply with relevant approved standards.
• All reinforcement steel shall be deformed bars
Strength of Hardened Concrete (HC) in general shall be as per the specification below unless differing
values are specified in other clauses or for special properties and applications.

Areas of use Concrete Grade Type of Minimum Max. Free Max. Nominal
Cement Cement Content Water/ aggregate size
(BS EN 206)
ASTM- (kg/m3) Cement (mm)
(minimum) fck
Ratio
cube (MPA)

PCC – Below C 15 Type II/V 250 - 20


Ground

Duct Encase C20 Type II/V 250 - 20


Concrete

RCC - Below C 35 Type II/V 370 0.42 20


Ground

Unless otherwise directed by the Customer, approved power-driven vibrators of the immersion type shall
be used. They shall be inserted at standard distances apart or applied in such a manner to ensure that the
concrete is satisfactorily and uniformly compacted.
The concrete shall be covered by a layer of, Hessian, or similar absorbent material or a layer of washed
sand, constantly maintained wet for a period of no less than ten (10) days.

©Alcatel Submarine Networks 2022 Page 19 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

ASN recommends a set of six (6) test cube samples shall be made from three (3) consecutive batches.
Three (s) from each set of six (6) samples shall be tested after seven (7) days and three (3) at an age of
twenty-eight (28) days. The cubes shall be made, cured, stored, transported, and tested in compression
in accordance with approved standards and at an approved independent laboratory.
Concrete from each pour shall be tested for slump & temperature. No water shall be added to the
concrete after batching. The acceptable slump shall generally be 150 ± 25mm.
Where required by the drawings, high quality bitumen-based water-resistant emulsion paint in black
colour sourced from reputed manufacturers shall be applied to all concrete surfaces.
Care shall always be taken to ensure that concrete, mortar, or cement are not allowed to enter drains or
gullies, and that all spillages are satisfactorily cleaned up.

14 Manhole Accessories – Fittings & Furniture


14.1 Manhole Covers
K2C type heavy duty ductile iron frames and covers are recommended and shall be embedded in the cover
slab and matched to adjacent grade level. All manhole frames and covers shall be of the heavy-duty type
regardless of manhole cover type proposed by the Contractor. The covers shall withstand a static load
test of 400 KN or 40 tonnes. The cover shall be minimum of D400 class inline with BS EN 124:2015. The
Contractor will provide technical data of the frames and covers along with a construction phase plan
document. All manholes are to be secure with suitable locking mechanism to mitigate against the risk of
damage to the Outside Plant (OSP) infrastructure and any system cables installed within. The secured
locking device should be an integral part of all OSP infrastructure making up the land cable duct section,
including the Beach Manhole and Cable Vault (MH0), and all manholes in between.
The inclusion of Integrated locking devices ensure that best endeavours have been made to protect
against personal injury at all stages of the communications system life cycle, including but not limited to
terrestrial cable installation activities, system commissioning to decommissioning, and service &
maintenance operations. Any security locking keys should be kept with a responsible person, normally
with the Cable Landing Station Manager or other person(s) appointed by the system operator or owner
and contact details should be provided to the Customer.
14.2 Name Labels
For all individual manholes, suitable nameplate, signs, and labels shall be provided to ensure
identification, safe operation, and warning of danger. The text, which shall be both in English and in
regional language, shall be approved by the Customer.
The sign board(s) shall be fabricated by 1.5 mm thick aluminium with digital printing vinyl on engraved
plate.
All nameplates, signs and labels shall be UV resistant, non-deteriorating and non-warping under
aggressive weather conditions and shall be guaranteed for a minimum period of five (5) years.

©Alcatel Submarine Networks 2022 Page 20 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Nameplate’s signs and labels shall be securely attached using bolts, nuts, or screws; adhesives will not be
permitted.
14.3 Ladder Mount
Ladder mounts shall be made from steel and hot dipped galvanised for corrosion protection. The ladders
are to be hooked at the top to engage the steel ladder support positioned in the manhole shaft.
14.4 Anchor Irons (Hooks)
Anchor irons provide a strong and convenient attachment for pulling-in blocks when installing cables and
subducts. The irons are set into the concrete opposite the duct entrances and below the MH shaft
entrance. The anchor irons should be constructed of hot forged steel and hot dipped galvanised for
corrosion resistance. Generally, the anchor irons are 16 mm diameter, but vary in design and size from
country to country.
14.5 Cable Racks
High quality Galvanised C channel cable trays to be provided for tying the cables inside the manholes. The
arrangements of C channel inside the manhole shall be as per standard ASN drawings.
14.6 Steel Structures
I beam or other steel structure shall be provided for supporting the manhole covers depending on the
anticipated traffic load passing over the manhole cover. Manholes shall be properly supported with steel
structures and those steel structures exposed to atmosphere shall be galvanised to avoid rust and
corrosion. Additional reinforcement shall be provided around the manhole cover to support the cover in
cases where steel structures are not used. All nuts and bolts connecting galvanized members shall be hot
dip galvanized.
14.7 Earth Rod
One (1) copper earth rod of 14 mm diameter and two (2) metres long is to be provided in all jointing
manholes at 100 mm distance from the corner of wall.
14.8 Sump pit with sump cover
Sump pit should be a minimum 300 x 300 x 200 mm in size and shall be provided inside all manholes. The
manhole base slab should be designed to have a slight fall towards the sump pit to ensure drainage of
water towards the sump pit. Heavy-duty Glass Reinforced Plastic (GRP) shall be used for the sump cover.

15 Duct Installations
15.1 Duct Specification
Wherever possible, 110 mm OD / 100 mm ID PVC ducts should be installed along the terrestrial route.
This size requirement increases to 150 mm minimum ID for seaward ducts, where possible. In all instances,
the duct specification should be provided to the Customer prior to purchase. For both powered &

©Alcatel Submarine Networks 2022 Page 21 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

unpowered systems, the terrestrial route will also consist of a conventional duct and manhole
configuration, with a minimum of four (4) 100 mm ID main ducts. One (1) of the four (4) 100 mm main
ducts will be sub-ducted with two (2) inner ducts, each with a minimum 38 mm ID. Typical subduct
specifications used by ASN are 42/38MM (OD/ID). These subducts are installed to house the transmission
cable and the earth return cables whilst collocating one 110/100 mm main duct. In all instances, the duct
specification should be provided to the Customer prior to purchase.
All cable ducts shall be laid in straight lines and regular gradients as described or directed in the drawing.
Minimum internal diameters are to be maintained while installing the ducts.
All sub-ducts shall be installed using a swivel end assembly to minimize the risk of the ducts twisting or
crossing within the main duct during installation.
15.2 Duct material
Cable ducts may be PVC, UPVC, HDPE or other material approved by the Customer and obtained from an
approved manufacturer. It may be necessary to use steel ducts in areas where sufficient burial depth
cannot be achieved. In these exceptional cases the internal sections of the steel duct must be sleeved
with the 110 mm PVC duct. It is recommended that flexi duct is not used along terrestrial routes unless
these are kept straight and not used to achieve directional changes to the duct routing and have smooth
internal walls with lubricated surfaces to facilitate cable and/or subduct installation.
15.3 Line of duct lay
The line of the ducts must be as straight as possible.
Wherever possible the natural curve of a straight duct section should be used to negotiate bends and
natural hazards without stressing the duct. A maximum of two (2) slow 22.5-degree or four 11.25-degree
bends shall be permitted in a nominal MH to MH section (250 metres). Where special circumstances
dictate the duct section length may be increased following consultation with the Customer and ASN.
The preferred position of the duct is in the footway, verge, or rough unmade ground. Carriageway duct
should only be considered when all other options have been exhausted. The ducts shall be kept well clear
of other utilities and a minimum clearance of 150 mm should be observed in all cases.
15.4 Duct installation close to Power cables
15.4.1 Single core High voltage cables
Single core high voltage cables for electricity supplies exceeding 1000 volts shall have a minimum
clearance of 450 mm with no exceptions.
15.4.2 Multi core High voltage cables
Multi core high voltage cables exceeding 1000 volts used for any purpose shall have a minimum clearance
of 300 mm. Where this is not possible concrete shall be used to separate the cable from the ducts. The
concrete shall have a minimum thickness of 50 mm and shall have an overlap on each side for the entire
length where the clearance is less than 150 mm.

©Alcatel Submarine Networks 2022 Page 22 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

15.4.3 Low voltage cables


Low voltage cables for electricity supply systems not exceeding 1000 volts shall have a minimum clearance
of 50 mm between the cable and the duct. In situations where the minimum distance cannot be achieved
then concrete shall be used. The minimum thickness of the concrete shall be 25 mm.
15.5 Duct section joints
Where two (2) or more ducts are placed together in the same trench the sockets shall be offset by a
minimum of 500 mm. Cutting ducts shall be done with a suitable tool. The inside of the duct will be
bevelled to form a slight bell mouth. All burrs must be removed before joining sections. All cut duct ends
should be square to the axis of the duct. The marks on the spigot end of a duct indicate the maximum
distance the duct can be inserted into the socket.
15.6 Duct end sections
The ducts entering the concrete manhole will be cut 10 mm short of the inside face of the chamber and
rendered with concrete to form a smooth bell mouth. The duct nest will be split approximately 6 metres
from the manhole position so that the ducts incur the slightest of angles as they enter each side of the
manhole end wall. The ducts entering the manhole will be arranged in pairs, one above the other (one on
one).
15.7 Configuration of multiple duct lays
The following should apply for multiple duct lays.
2 way – Two ducts flat
3 way – One on two
4 way – Two on two
6 way – Three on three or three on two
In situations such as bridge crossings, structural restrictions, or other difficulties where the depth of cover
is restricted the configuration can be changed so that the ducts lay all flat. When laying the ducts flat it is
important to maintain the same sequence so that ducts that have been laid flat are readily identified.
Refer to General Duct Installation Drawings Sheet No GN04.
The bottom two ducts are pushed outwards to allow the top two ducts to fall in between. Should the flat
formation be required in a manhole the formation remains the same, but it is strongly recommended that
the manhole positions be carefully planned so that this eventuality does not occur.
15.8 Duct plugs
Duct ends shall be blanked off with the correct size duct plastic caps or expanding plugs if the work is
stopped for any reason or when manhole sections are completed. The plugs or caps must stay in the
manholes until the section is ready for testing and subducting.

©Alcatel Submarine Networks 2022 Page 23 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

15.9 Duct testing


A rope will be blown through the ducts in all sections before the duct test takes place. The testing of the
duct will be done using a brush and mandrel.
The brush should be 105% of the duct internal diameter and a minimum of 200 mm in length.
The mandrel should be 90% of the duct internal diameter and a minimum of 250 mm in length. The brush
and mandrel can be joined and drawn through the ducts in one operation with the brush preceding the
mandrel.
A suitable rope will be used to pull through the brush and mandrel and draw rope or mule tape will be
attached to the end of the test configuration. The draw rope will be polypropylene and have a minimum
breaking strength of 5KN. On completion of the tests the draw rope will be securely tied off.
Joining draw ropes within a manhole section is not permitted.
On completion of testing, duct plugs will be inserted to prevent any ingress of water, silt, or debris. The
draw ropes will be secured to the inside of the plugs.
15.10 Duct seals and building entries
All duct seals on systems entering client’s buildings and premises should be gas and watertight to the
standards approved by local utility operators.
It is important that an effective seal is made between the outside of the duct and the fabric of the building
as well as sealing the inside of the duct. Sub-ducts must be cut short of the seal so that there is no space
between the subduct and cable and that the cables are sealed to the wall of the main duct.
It is important that the Contractor selects a Competent Person for sealing building duct entries.
15.11 Duct entries
• Towards Turning Manhole
The duct entries are to be such that they offer the maximum turning distances to the subducts and cables.
Refer Turning Manhole drawings
• Towards Straight Manholes
Minimum 6 metres distance shall be maintained while diverging or converging the ducts.
Refer to General Duct Installation Drawings Sheet GN01
The centre of the two ducts will be 150 mm from the side wall and a separation between the ducts of 150
mm centre to centre is preferred.
15.12 Duct encasement
The concrete used for the duct encasement shall have a minimum compressive strength (fck) of 20 MPa
(C20) after twenty-eight (28) days. There shall be a minimum cover of 75 mm around the duct nest.

©Alcatel Submarine Networks 2022 Page 24 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

Formers should be used when pouring concrete around the ducts and the concrete should be vibrated in,
if necessary, around the ducts to provide proper fill with no voids.
15.13 Warning Tapes
Telecommunications warning tape will be laid directly over the duct nest during the trench backfill. The
tape will be placed 300 mm above the concrete surround along the entire length of the duct.
15.14 Duct Spacers
Duct spacers of approved brand providing minimum spacing of 50 mm shall be used at regular intervals
while laying the duct for providing the spacing between ducts.
15.15 Further guidance notes
When planning a route such as a four (4-way) duct system the duct bank should be split so that the ducts
enter and leave the manhole close to the side walls of the chamber. To achieve this the ducts should be
branched at a minimum distance of 6 metres from the manhole where a top and bottom duct are placed
so that they enter and leave each side of the manhole. This slight deviation of the ducts does not impinge
on the pulling tensions but will offer a far better cable management system in the manholes and will
eliminate the need to pull back the subduct to set back on the bearers.
Much time is taken up with setting cables and subduct in manholes where the duct bank enters and leaves
in the centre. The ducts in the centre system also on occasions prevent good access to the chamber
whereas by using the side walls, personnel access to the MH is unhindered. The subduct and cables can
then pass through the manhole and be comfortably supported each side allowing easy access into the
manhole. There is little difference to the route construction works, as the excavated area by a manhole is
always substantially larger. Therefore, there is no increase of labour time, and the finished item provides
a safer and more desirable cable management system.

16 Site Remediation
• Re-establish ground level where required and make good any disturbed ground or shoreline
excavations, grout, and compact borehole points (where required).
• Demobilise all construction equipment, remove from site along with any waste materials.
• Reinstate displaced vegetation, re-turf grass areas and remove security fencing and hoardings.
• Road resurfacing to be done in line with local municipality/council requirements in agreed
timeframes under all circumstances.
• Clean and clear site as appropriate.
• Photograph the construction area, including staging areas and lay-down areas in the
immediate vicinity of the installation site to prove the ‘as left’ condition.
• Inspect the site with the Customer Representative and any other local representatives prior to
demobilizing from site.

©Alcatel Submarine Networks 2022 Page 25 of 26


Document No: INST. 12613
Issue No: 04

Generic Duct Route, Manhole and Headwall Construction Guidelines

LANDFALL DEPARTMENT - CIVIL WORKS

17 Demobilisation
The Contractor shall provide all the necessary evidence and documentation required to demonstrate that
work has been performed according to all the SOW requirements before any demobilisation may take
place.
Only on the agreement of the Customer Representative may demobilisation take place. If the Customer
Representative does not agree to demobilisation from site, and the Contractor believes this is
unreasonable, this grievance should be formalised in the form of a CV claim from the Contractor to the
Customer at the end of all operations. However, demobilisation must only occur following agreement
with the Customer Representative.

18 Debriefing
The Contractor shall de-brief all Customer & Environmental Representatives on site on what has been
achieved daily and explain and document where it has not been possible to meet the required SOW
requirements or where Non or Partial-Compliance has been documented.
The end-of-job debriefing shall include discussion and evidence on:
• Existing infrastructure condition and status.
• Performance of all equipment
• Preliminary findings from any onsite analysis, including soil classifications.
• Comprehensive data record, subsoil sample, survey positioning, photographic & videographic
data.
• Issues encountered, including failures or omissions of SOW items, both mechanical & technical.
• Provide demobilisation report for Customer review & acceptance.

19 Appendix
1. General Guideline Drawings for duct installation and manhole constructions.

END OF DOCUMENT

©Alcatel Submarine Networks 2022 Page 26 of 26


3
GN04

Concrete Head Wall Pulling Manhole ( Road Pulling Manhole ( Road


at Right Side) at Right Side) 90 Degree Right
1 Intermediate Splicing Turning Manhole
2 BMH Manhole
3
4

Road

General Duct Laying Layout


1 1 : 100

Pulling Manhole ( Road


at Left Side)

90 Degree Left
Turning Manhole

• Drawings provided are for general reference only. Construction


Drawings shall be submitted and approved by Client in
accordance with the local Authorities regulations and
requirements prior to commence of all works.
• All NOC's, Approvals & Permits for construction shall be
obtained by the contractor prior to commencement of
construction.
• Drawings shall be read in conjunction with ASN Guidelines.
• Drawings are not to scale.
• Recommended maximum spacing between Intermediate
Jointing Manholes or BMH is 2000 meters
• Recommended maximum spacing between Pulling or Turning
manholes is 250 meters

No. Date Drawn By Approved By Description


General Site Plan

02/11/2022 12:07:22 PM
V1 29/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 14000: Typical Trench & Duct Layout


Date 31 October 2022
Drawn By Charls John
GN01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 100

- Front

-
BMH
ConcreteHeadwall

2 1
2
3
1 4
3
4

BMH to Concrete Head wall Connection


1

No. Date Drawn By Approved By Description


BMH to Headwall Layout

02/11/2022 12:07:26 PM
V1 29/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 14000: Typical Trench & Duct Layout


Date 31 October 2022
Drawn By Charls John
GN02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale
Pulling Manhole
4x 100mm ID Ducts

4x 100mm ID Ducts
Intermediate Splicing Manhole

Pulling Manhole

Front Haul Different Manhole Connections


1

No. Date Drawn By Approved By Description


Front Haul Layout

02/11/2022 12:07:30 PM
V1 29/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 14000: Typical Trench & Duct Layout


Date 31 October 2022
Drawn By Charls John
GN03
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale
Compacted Roadbase
Road/ Surface Level
0

300
Clear Depth of Ducts
Telecom Warning Tape

Compacted Backfill

Concrete Encasement
for Ducts
175 150 175
Duct Spacer 2 3
8mm Steel stirups at
200mm c/c spacing

150
4 x 100mm min ID ducts 1 with 1 4
2 subduct 38mm min ID
8 Nos 12mm main

200
reinforcement

150
Compacted Soil
Clear Cover

1 2 3 4

General Duct Laying Section Duct Arrangement Two on Two to Flat


1 1 : 10 2 1 : 10

Minimum 6m Minimum 6m

Converging & Diverging Ducts Layout


3 1 : 25

No. Date Drawn By Approved By Description


General Duct Installation

02/11/2022 12:07:32 PM
V1 29/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 14000: Typical Trench & Duct Layout


Date 31 October 2022
Drawn By Charls John
GN04
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale As indicated
-

1 - Rear
HW02

100 500 100

250 100
Flange Adaptor 1
(Supply and
Installation by ASN)

400
2
3
Sea Side

Land Side
HW02
4x150mm

700
(Min Inner
HW01 5 Dia) Sleeves
(End Cap 4 HW01
with draw
3 line To be
installed)

400
4

100 250
3 Front

HW01

Site Plan {3D}


2 1 : 20 1

Road/ Natural Ground


Surface Level Road/ Natural Ground Road/ Natural Ground
0 Surface Level Surface Level
0 0

Compacted Soil Compacted Soil Compacted Soil


2000

1 3 3
HW02 HW02 HW02

4x150mm (Min
Inner Dia) Sleeves
(End Cap to be
Installed)
Raft Footing Raft Footing Raft Footing
-2000 -2000 1 2 3 4 1 -2000 1
250

4 3 2 1
HW02 HW02
Flange Adaptor Sleeves To the BMH
(Supply and
100 250

Installation by ASN) 250 400 700 400 250 250 400 700 400 250

PCC PCC PCC


-2500 -2500 -2500
Compacted Soil Level Compacted Soil Level Compacted Soil Level

-2600 -2600 -2600

Front Sea Side Land Side


3 1 : 20 5 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Architectural Drawings

02/11/2022 12:29:15 PM
V1 11/06/2021 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Edition

Inst. 14019: Concrete Foot Headwall Details


Date 31 October 2022
Drawn By Charls John
HW01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
• All reinforcement shall be minimum Fe415 grade • Drawings provided is for general reference only.
• The concrete for RCC shall be readymix concrete with SRC 35 grade Construction Drawings shall be submitted and
• The concrete for PCC shall be readymix concrete with SRC 15 grade approved by Client in accordance with the local
• 50mm concrete cover shall be maintained for all reinforcement steel Authorities regulations and requirements prior to
• Mix Design of concrete and Reinforcement Technical sheet shall be submitted pior to commence of all works.
commence of works • All NOC's, Approvals & Permits for the construction
3
shall be obtained by the contractor prior to
HW02
commencement of all works.
• The load/ traffic over the concrete to be considered
while designing the Construction drawings
• All Materials used shall be approved by Client.
8mm Stirups 9 8mm Stirups 9 • Inspection Requests shall be raised by the contractor
Nos spacing as 100 300 100 300 200 200 300 100 300 100 Nos spacing
shown as shown with photos and approved from Client before all
Concrete works.
• Compaction Test results for Compacted Soil shall be
submitted to Client.
• Cube Test Results for 7 days & 28 Days of all RCC
Raft Footing concrete shall be submitted to Client.
• Drawings shall be read in conjunction with ASN Civil
-2000
Guidelines.
• All Dimensions are in mm unless specified.
• Drawings are not to scale.

PCC
-2500

Compacted Soil Level


-2600

Section 2
1 1 : 10 1
HW02

HW01 Concrete Headwall

Sea Side
5

Raft Footing 150mm Sleeves


-2000

8mm Stirups 8mm Stirups 100 mm thick PCC Blinding


3x 12mm Dia Main
Reinforcement 200mm PCC
HW02

Spacing Top & Bottom


2

-2500 Compacted Soil

Compacted Soil Level


1 : 10
Plan View

-2600

50
200

HW02
1
Section 1
200
3
HW01

1 : 10
3 Front

- Rear

-
50

No. Date Drawn By Approved By Description


Structural Details

02/11/2022 12:29:16 PM
V1 11/06/2021 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Edition

Inst. 14019: Concrete Foot Headwall Details


Date 31 October 2022
Drawn By Charls John
HW02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 10
200100 250 3000 250 100200

- Rear

250 100 200


Minimum 2 Layers of
Bituminous Paint

350

350

Land Side
4 2 BM02
4 x 150mm BM02 4 x 100mm (min Inner
(min Inner Dia) Dia) PVC telco grade
Sea Side

Ducts 300 x 300 x 200mm Sump ducts, 1 with 2

2000
with 350 x 350 x 25mm subducts 38mm (min)
GRP Gratings Inner Dia
BM02 1
300 150
1
BM03

150 300
3 100 Copper Earth Rod
350

350
BM02
100

200 100 250


2 4
3 Front
BM03 BM03

BM01
Inside Plan View {3D}
2 1 : 25 1
2
4 -
BM03
BM03

- Rear

Road/ Surface Level


0
250

Heavy Duty K2C Manhole


Cover 1800 x 900x 148mm with

800
Key opening System. Key to

Land Side
Handed over to the Terminal
Station

4 2 BM02
BM02
2000

2000

Sea Side

2500

900
BM02 1

1
BM03
850 1800 850
3
Raft Footing

800
BM02
-2250
3500
PCC
-2500
Road Base Level
-2600
2 4
3 Front
BM03 BM03

BM01

Front Site Plan


3 1 : 25 4 1 : 25
No. Date Drawn By Approved By Description
Architectural Drawings-1

02/11/2022 12:14:59 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Beach Manhole Layout


Date 31 October 2022
Drawn By Charls John
BM01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
• Drawings provided is for general reference only.
Construction Drawings shall be submitted and
1 1
approved by Client in accordance with the local
3 4
4
BM03 BM02
3
BM03 Authorities regulations and requirements prior to
BM02
BM02 BM02 commence of all works.
• All NOC's, Approvals & Permits for the construction
Road/ Surface Level Road/ Surface Level shall be obtained by the contractor prior to
0 0 commencement of all works.
• The load/ traffic over the manhole & nature of ground
soil to be considered while designing the Construction
drawings
Minimum 2 Layers of Minimum 2 Layers of • All Materials used shall be approved by Client.
Bituminous Paint Bituminous Paint • Inspection Requests shall be raised by the contractor
with photos and approved from Client before all
2 Concrete works.
3 4 x 100mm (min
Inner Dia) PVC
• Compaction Test results for Compacted Soil and
2 3 4 telco grade ducts, 1 1 Roadbase laid shall be submitted to Client.
4 x 150mm with 2 subducts • Cube Test Results for 7 days & 28 Days of all RCC
(min Inner Dia) 38mm (min) Inner
1 4 Dia concrete shall be submitted to Client.
Ducts
• Drawings shall be read in conjunction with ASN Civil
Guidelines.
• All Dimensions are in mm unless specified.
• Drawings are not to scale.
Raft Footing Raft Footing
-2250 -2250

PCC PCC
-2500 -2500
Road Base Level Road Base Level

-2600 -2600

Copper Earth Rod 14mm dia


2m long

Sea Side Land Side


1 1 : 25 2 1 : 25
Heavy Duty K2C Manhole
2 Cover 1800 x 900 x 148mm with 2
4 4
BM03
BM03 BM03 Key opening System. Key to BM03
Handed over to the Terminal
Station

Road/ Surface Level Road/ Surface Level


0 0
Manhole Cover

Ladder Mount
1050

2 Nos I Beam 100 x 50 x 5mm Ladder Mount 25mm Dia


1375

to support Manhole Cover Tube 750mm long welded


through out the span to I Beam

I Beam 100mmx50mmx 5mm


200

1
BM03
250

300 x 300 x 200mm Sump


1000

with 350 x 350 x 25mm


GRP Gratings
625

200
Raft Footing Raft Footing
-2250 -2250
PCC PCC
-2500 -2500

Road Base Level Road Base Level


-2600 -2600
Copper Earth Rod 14mm dia
2m long

Section 4
3 1 : 25 Section 5 Ladder Mount & I Beam
4 1 : 25 5
No. Date Drawn By Approved By Description
Architectural Drawings-2

02/11/2022 12:15:02 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Beach Manhole Layout


Date 31 October 2022
Drawn By Charls John
BM02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
• All reinforcement shall be minimum Fe415 grade • Drawings provided is for general reference only.
- • All reinforcement shall be 16mm with maximum spacing of 200mm c/c Construction Drawings shall be submitted and
• The concrete for RCC shall be readymix concrete with SRC 35 grade approved by Client in accordance with the local
- Rear • The concrete for PCC shall be readymix concrete with SRC 15 grade Authorities regulations and requirements prior to
• 25mm concrete cover shall be maintained for all reinforcement steel commence of all works.
• Mix Design of concrete and Reinforcement Technical sheet shall be submitted pior to • All NOC's, Approvals & Permits for the construction
commence of works shall be obtained by the contractor prior to
commencement of all works.
1
4
BM03 3 • The load/ traffic over the manhole & nature of ground
BM02
BM02 soil to be considered while designing the Construction

Land Side
drawings
Road/ Surface Level • All Materials used shall be approved by Client.
• Inspection Requests shall be raised by the contractor
0

250
4 2 BM02
with photos and approved from Client before all
BM02
Seaward Direction Concrete works.
Sea Side

Land Direction
• Compaction Test results for Compacted Soil and
2000

16mm Dia Galvanised


Roadbase laid shall be submitted to Client.
BM02 1 Steel Hook for • Cube Test Results for 7 days & 28 Days of all RCC
Pulling Cable concrete shall be submitted to Client.
1
BM03
• Drawings shall be read in conjunction with ASN Civil
4 x 100mm (min
Inner Dia) PVC telco
Guidelines.

2000
3 grade ducts, 1 with 2 • All Dimensions are in mm unless specified.
BM02 subducts 38mm • Drawings are not to scale.
(min) Inner Dia

16mm Dia Galvanised


Steel Hook for
Pulling Cable
Raft Footing
2 4
3 Front -2250

200 100 250


BM03 BM03

BM01 PCC
-2500
Road Base Level
Inside Plan
3 1 : 25
-2600
Section 2
2 1 : 25
2 3 1 4
4
BM03 BM02 BM03 BM02
BM03

I Beam 100mm x 50mm x5mm


for Supporting Manhole Cover
Road/ Surface Level Road/ Surface Level
0 0
Slab with Manhole Cover
150

120150

16mm Dia Galvanised


Steel Hook for Pulling
500

Cable
150
16mm Dia Galvanised
500 Cable Racks Steel Hook for
500 RCC Wall Pulling Cable

952 952
1200

4 x 150mm
(min Inner Dia)
Ducts

Copper Earth 16mm Dia


16mm Dia Galvanised Steel RCC Footing Rod 14mm dia galvanised Hook
300

Hook for Pulling Cable Raft Footing for Pulling Cable


130

Raft Footing
Minimum 200mm Thick Compacted 100mm thick
100 -2250
Roadbase over compacted Soil PCC Blinding -2250
200
PCC PCC
-2500 -2500
Road Base Level
Road Base Level
-2600
-2600

Section 1 Section 3
1 1 : 25 4 1 : 25

No. Date Drawn By Approved By Description


Structural Details

02/11/2022 12:15:03 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Beach Manhole Layout


Date 31 October 2022
Drawn By Charls John
BM03
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
200100 250 3000 250 100200

- Rear

250 100 200


Minimum 2 Layers of
Bituminous Paint

350

Land Side
4 2 IM02
4 x 100mm (min Inner IM02 4 x 100mm (min Inner
Dia) PVC telco grade Dia) PVC telco grade
Sea Side

ducts, 1 with 2 300 x 300 x 200mm Sump ducts, 1 with 2

2000
subducts 38mm (min) with 350 x 350 x 25mm subducts 38mm (min)
Inner Dia GRP Gratings Inner Dia
IM02 1
300 150
1
IM03

150 300
3 100 Copper Earth Rod

350
IM02
100

200 100 250


2 4
3 Front
IM03 IM03

IM01
Inside Plan View {3D}
2 1 : 25 1
2
4 -
IM03
IM03

- Rear

Road/ Surface Level


0
250

Heavy Duty K2C Manhole


Cover 1800 x 900x 148mm with

800
Key opening System. Key to

Land Side
Handed over to the Terminal
Station

4 2 IM02
IM02
2000

Sea Side

2500

900
IM02 1

1
IM03
850 1800 850
3
Raft Footing

800
IM02
-2250
3500
PCC
-2500
Road Base Level
-2600
2 4
3 Front
IM03 IM03

IM01

Front Site Plan


3 1 : 25 4 1 : 25
No. Date Drawn By Approved By Description
Architectural Drawings-1

02/11/2022 12:26:26 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Intermediate Splicing Manhole Details


Date 31 October 2022
Drawn By Charls John
IM01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
• Drawings provided is for general reference only.
Construction Drawings shall be submitted and
1 1
approved by Client in accordance with the local
3 4
4
IM03 IM02
3
IM03 Authorities regulations and requirements prior to
IM02
IM02 IM02 commence of all works.
• All NOC's, Approvals & Permits for the construction
Road/ Surface Level Road/ Surface Level shall be obtained by the contractor prior to commence
0 0 of all works.
• The load/ traffic over the manhole & nature of ground
soil to be considered while designing the Construction
drawings
Minimum 2 Layers of Minimum 2 Layers of • All Materials used shall be approved by Client.
Bituminous Paint Bituminous Paint • Inspection Requests shall be raised by the contractor
with photos and approved from Client before all
3
2
4 x 100mm (min
3 2 Concrete works.
4 x 100mm (min
1 Inner Dia) PVC 4 Inner Dia) PVC • Compaction Test results for Compacted Soil and
telco grade ducts, 1 4 telco grade ducts, 1 1 Roadbase laid shall be submitted to Client.
with 2 subducts with 2 subducts
38mm (min) Inner 38mm (min) Inner
• Cube Test Results for 7 days & 28 Days of all RCC
Dia Dia concrete shall be submitted to Client.
• Drawings shall be read in conjunction with ASN Civil
Guidelines.
• All Dimensions are in mm unless specified.
• Drawings are not to scale.
Raft Footing Raft Footing
-2250 -2250

PCC PCC
-2500 -2500
Road Base Level Road Base Level

-2600 -2600

Copper Earth Rod 14mm dia


2m long

Sea Side Land Side


1 1 : 25 2 1 : 25
Heavy Duty K2C Manhole
2 Cover 1800 x 900 x 148mm with 2
4 4
IM03
IM03 IM03 Key opening System. Key to IM03
Handed over to the Terminal
Station

Road/ Surface Level Road/ Surface Level


0 0
Manhole Cover

Ladder Mount
1050

1050

2 Nos I Beam 100 x 50 x 5mm Ladder Mount 25mm Dia


to support Manhole Cover Tube 750mm long welded
through out the span on I Beam

I Beam 100mmx50mmx 5mm


2250

200

200

1
IM03
300 x 300 x 200mm Sump
1000

1000

with 350 x 350 x 25mm


GRP Gratings

200
Raft Footing Raft Footing
-2250 -2250
PCC PCC
-2500 -2500

Road Base Level Road Base Level


-2600 -2600
Copper Earth Rod 14mm dia
2m long

Section 4
3 1 : 25 Section 5 Ladder Mount & I Beam
4 1 : 25 5
No. Date Drawn By Approved By Description
Architectural Drawings-2

02/11/2022 12:26:30 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Intermediate Splicing Manhole Details


Date 31 October 2022
Drawn By Charls John
IM02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
• All reinforcement shall be minimum Fe415 grade • Drawings provided is for general reference only.
- • All reinforcement shall be 16mm with maximum spacing of 200mm c/c Construction Drawings shall be submitted and
• The concrete for RCC shall be readymix concrete with SRC 35 grade approved by Client in accordance with the local
- Rear • The concrete for PCC shall be readymix concrete with SRC 15 grade Authorities regulations and requirements prior to
• 25mm concrete cover shall be maintained for all reinforcement steel commence of all works.
• Mix Design of concrete and Reinforcement Technical sheet shall be submitted pior to • All NOC's, Approvals & Permits for the construction
commence of works shall be obtained by the contractor prior to commence
of all works.
1
4
IM03 3 • The load/ traffic over the manhole & nature of ground
IM02
IM02 soil to be considered while designing the Construction

Land Side
drawings
Road/ Surface Level • All Materials used shall be approved by Client.
• Inspection Requests shall be raised by the contractor
0

250
4 2 IM02
with photos and approved from Client before all
IM02
Seaward Direction Concrete works.
Sea Side

Land Direction
• Compaction Test results for Compacted Soil and
2000

16mm Dia Galvanised


Roadbase laid shall be submitted to Client.
IM02 1 Steel Hook for • Cube Test Results for 7 days & 28 Days of all RCC
Pulling Cable concrete shall be submitted to Client.
1
4 x 100mm (min • Drawings shall be read in conjunction with ASN Civil
IM03 Inner Dia) PVC telco
grade ducts, 1 with 2 Guidelines.

2000
3 subducts 38mm • All Dimensions are in mm unless specified.
(min) Inner Dia
IM02 • Drawings are not to scale.

16mm Dia Galvanised


Steel Hook for
Pulling Cable
Raft Footing
2 4
3 Front -2250

200 100 250


IM03 IM03

IM01 PCC
-2500
Road Base Level
Inside Plan
3 1 : 25
-2600
Section 2
2 1 : 25
2 3 1 4
4
IM03 IM02 IM03 IM02
IM03

I Beam 100mm x 50mm x5mm


for Supporting Manhole Cover
Road/ Surface Level Road/ Surface Level
0 0
Slab with Manhole Cover
120150

16mm Dia Galvanised


Steel Hook for Pulling
500

Cable
150
16mm Dia Galvanised
500 Cable Racks Steel Hook for
500 RCC Wall Pulling Cable

4 x 100mm (min
952 952 Inner Dia) PVC
telco grade ducts,
1200

1 with 2 subducts
38mm (min) Inner
Dia

Copper Earth 16mm Dia


16mm Dia Galvanised Steel RCC Footing Rod 14mm dia galvanised Hook
300

Hook for Pulling Cable Raft Footing for Pulling Cable


130

Raft Footing
Minimum 200mm Thick Compacted 100mm thick
100 -2250
Roadbase over compacted Soil PCC Blinding -2250
200
PCC PCC
-2500 -2500
Road Base Level
Road Base Level
-2600
-2600
Section 3
4 1 : 25
Section 1
1 1 : 25

No. Date Drawn By Approved By Description


Structural Details

02/11/2022 12:26:31 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue

Inst. 13996: Typical Intermediate Splicing Manhole Details


Date 31 October 2022
Drawn By Charls John
IM03
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 25
Road

-
200 100 200 1800 200 100 200
- Road Side
Minimum 2 Layers of
Bituminous Paint
4 x 100mm (min Inner

200 100 200


Dia) PVC telco grade
ducts, 1 with 2

Land Side
subducts 38mm (min)
Inner Dia

Sea Side
2 PM02

150

150 150
4
PM02

150
PM02 1
300 125

900
300 x 300 x 200mm Sump
1

600
with 350 x 350 x 25mm

300
GRP Gratings PM03
3 100
PM02

125
100

200 100 200


3 Front
2 4
PM03 PM03
PM01

Inside Plan View


2 1 : 20
2
4
PM03
PM03
{3D}
1
Road/ Surface Level
0 Heavy Duty K2C Manhole
- Cover 1800 x 900x 148mm with
Key opening System. Key to
Handed over to the Terminal
- Road Side Station
1050

1050
1450

Land Side
PM033
PM02

Sea Side
2 PM02
200

200

4
PM02
PM02 1
200

200

Raft Footing
-1450
1
PM03
PCC 3
PM02
-1700
Road Base Level
-1800

3 Front
2 4
PM03 PM03
PM01

Front Site Plan


3 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Architectural Drawings-1

02/11/2022 12:55:54 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical Pulling Manhole Details (Road on Left Side of
Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
PM01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
1 1
4
4 3 PM03
PM02
PM03
PM02
PM02 • Drawings provided is for general reference only.
3
Construction Drawings shall be submitted and
PM02
approved by Client in accordance with the local
Road/ Surface Level Road/ Surface Level Authorities regulations and requirements prior to
0 0
commence of all works.
• All NOC's, Approvals & Permits for the construction
shall be obtained by the contractor prior to
commencement of all works.
• The load/ traffic over the manhole & nature of ground

1050

1050
soil to be considered while designing the Construction
Minimum 2 Layers of 4 x 100mm (min
Bituminous Paint Inner Dia) PVC
drawings
4 x 100mm (min
telco grade ducts, 1 Inner Dia) PVC • All Materials used shall be approved by Client.
with 2 subducts telco grade ducts, 1 • Inspection Requests shall be raised by the contractor
2 38mm (min) Inner with 2 subducts
3
Dia Minimum 2 Layers of 3 2
38mm (min) Inner
with photos and approved from Client before all
Bituminous Paint
Concrete works.

200

200
Dia
1
4 4 • Compaction Test results for Compacted Soil and
1 350
150 Roadbase laid shall be submitted to Client.

200

200
350 150
Raft Footing Raft Footing
• Cube Test Results for 7 days & 28 Days of all RCC
-1450 -1450 concrete shall be submitted to Client.
• Drawings shall be read in conjunction with ASN Civil
PCC PCC Guidelines.
-1700 -1700 • All Dimensions are in mm unless specified.
Road Base Level Road Base Level • Drawings are not to scale.
-1800 -1800

Copper Earth Rod 14mm dia


2m long

Sea Side Land Side


1 1 : 20 2 1 : 20

2
4
2 4 PM03
PM03 Heavy Duty K2C Manhole
PM03 PM03
Cover 1800 x 900 x 148mm with
Key opening System. Key to
Handed over to the Terminal
Station
Road/ Surface Level Road/ Surface Level
Manhole Cover
0 0 clamped or fixed
firmly with wall or slab

Ladder Mount 25mm Dia


1050

1050

Ladder Mount Tube 750mm long

Copper Earth
Rod 25mm
dia 2m long
200

200

300 x 300 x 200mm Sump


with 350 x 350 x 25mm
200

200

200
GRP Gratings
Raft Footing Raft Footing
-1450 -1450

PCC PCC
-1700 -1700

Road Base Level Road Base Level


-1800 -1800

Section 4 Section 5 Ladder Mount


3 1 : 20 4 1 : 20 5

No. Date Drawn By Approved By Description


Architectural Drawings-2

02/11/2022 12:56:00 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical Pulling Manhole Details (Road on Left Side of
Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
PM02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
• All reinforcement shall be minimum Fe415 grade • Drawings provided is for general reference only.
• All reinforcement shall be 12mm with maximum spacing of 200mm c/c Construction Drawings shall be submitted and
• The concrete for RCC shall be readymix concrete with SRC 35 grade approved by Client in accordance with the local
- • The concrete for PCC shall be readymix concrete with SRC 15 grade Authorities regulations and requirements prior to
• 25mm concrete cover shall be maintained for all reinforcement steel commence of all works.
- Road Side • Mix Design of concrete and Reinforcement Technical sheet shall be submitted pior to • All NOC's, Approvals & Permits for the construction
commence of works shall be obtained by the contractor prior to
commencement of all works.
Land Direction 1 • The load/ traffic over the manhole & nature of ground
4

Land Side
Seaward Direction PM02 PM03 3 soil to be considered while designing the Construction
PM02 drawings
• All Materials used shall be approved by Client.
Sea Side

2 PM02
4
Road/ Surface Level
• Inspection Requests shall be raised by the contractor
PM02 1
PM02
with photos and approved from Client before all
0 Concrete works.
• Compaction Test results for Compacted Soil and
900

1 Roadbase laid shall be submitted to Client.


PM03 • Cube Test Results for 7 days & 28 Days of all RCC
3
PM02
concrete shall be submitted to Client.
16mm Dia • Drawings shall be read in conjunction with ASN Civil
Galvanised Guidelines.
Steel Hook for
Pulling Cable
• All Dimensions are in mm unless specified.
• Drawings are not to scale.

3 Front
4
Raft Footing
PM03
2
PM01 -1450

200 100 250


PM03

PCC
-1700
Inside Plan
3 1 : 20
Road Base Level
-1800

Section 2
2
PM03
4 2 1 : 20 1
PM03
PM03 4
3
PM02 PM02

Road/ Surface Level Road/ Surface Level


0 0

16mm Dia Galvanised


Steel Hook for Pulling
Cable

160
160
Cable Racks 4x125mm Dia
RCC Wall DWCP (110mm
850

16mm Dia Galvanised (min) ID) PVC


Steel Hook for telco grade ducts,
Pulling Cable 1 with 2 subducts
38mm (min) Inner
352 500 500 352 RCC Footing Dia
150

150

Raft Footing Raft Footing


100mm thick-1450 -1450
Minimum 200mm Thick Compacted PCC Blinding
Roadbase over compacted Soil PCC PCC
-1700 -1700
Road Base Level Road Base Level
200 100
-1800 -1800 Copper Earth
Rod 14mm dia

Section 1 Section 3
1 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Structural Details

02/11/2022 12:56:01 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical Pulling Manhole Details (Road on Left Side of
Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
PM03
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
-

Minimum 2 Layers of - Front


Bituminous Paint

4 x 100mm (min Inner


Dia) PVC telco grade
ducts, 1 with 2
subducts 38mm (min)
Inner Dia
300 x 300 x 200mm Sump
with 350 x 350 x 25mm
GRP Gratings
- -
Sea Side

- -

Land Side
- Road Side

- Road

Inside Plan View


2 1 : 20

{3D}
1

- -

- Front - Front

Land Direction
Seaward Direction

- - - -
Sea Side

Sea Side
- - - -
Land Side

Land Side
- Road Side - Road Side Heavy Duty K2C Manhole
Cover 1800 x 900x 148mm with
Key opening System. Key to
- -
Handed over to the Terminal
Station
Site Plan
Inside Plan 4 1 : 20
3 1 : 20

No. Date Drawn By Approved By Description


Architectural Drawings-3

02/11/2022 12:42:59 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical Pulling Manhole Details (Road on Right Side
of Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
PM04
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
-

- Rear
200 100 200 1800 200 100 200

Minimum 2 Layers of
Bituminous Paint
4 x 100mm (min Inner

200 100 200


Dia) PVC telco grade
ducts, 1 with 2

Land Side
subducts 38mm (min)
Inner Dia

100
2 TM02

150 150
3
100
TM02 300 x 300 x 200mm Sump
125 300 with 350 x 350 x 25mm
Sea Side

GRP Gratings 1

900
TM03

300
TM02 1
4
150 150
TM02

125

200 100 200


3 Front
4
2 4 x 100mm (min Inner
TM03 Dia) PVC telco grade
TM01 TM03
ducts, 1 with 2
subducts 38mm (min)
Inner Dia

Inside Plan View


2 1 : 20
2
4
TM03
TM03
{3D}
1
Road/ Surface Level
-
0 Heavy Duty K2C Manhole
Cover 1800 x 900x 148mm with
- Rear Key opening System. Key to
Handed over to the Terminal
4 x 100mm (min Station
Inner Dia) PVC
1050

telco grade ducts, 1


with 2 subducts
38mm (min) Inner
1450

Dia

Land Side
4
3 2 TM02
2 TM02
200

200

1 3
4
150 150 200
200

200

TM02
Raft Footing

Sea Side
1
-1450
TM03

TM02 1
PCC 4
TM02
-1700
Road Base Level
-1800

3 Front
4
2
TM03
TM01 TM03

Front Site Plan


3 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Architectural Drawings-1

02/11/2022 12:41:49 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical 90 Degree Turning Manhole Details (Turning
Right Side of Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
TM01
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
1 1
4
4 3
TM03
TM02
TM02
TM03
TM02
• Drawings provided is for general reference only.
3
Construction Drawings shall be submitted and
TM02
approved by Client in accordance with the local
Road/ Surface Level Road/ Surface Level Authorities regulations and requirements prior to
0 0
commence of all works.
• All NOC's, Approvals & Permits for the construction
shall be obtained by the contractor prior to
commencement of all works.
• The load/ traffic over the manhole & nature of ground

1050
Minimum 2 Layers of
Bituminous Paint
soil to be considered while designing the Construction
Minimum 2 Layers of 4 x 100mm (min
Bituminous Paint Inner Dia) PVC
drawings
telco grade ducts, 1 • All Materials used shall be approved by Client.
with 2 subducts • Inspection Requests shall be raised by the contractor
2 3 38mm (min) Inner
Dia with photos and approved from ASN engineers before
all Concrete works.

200
1 • Compaction Test results for Compacted Soil and
4
Roadbase laid shall be submitted to Client.

200
350 150
Raft Footing Raft Footing
• Cube Test Results for 7 days & 28 Days of all RCC
-1450 -1450 concrete shall be submitted to Client.
• Drawings shall be read in conjunction with ASN Civil
PCC PCC Guidelines.
-1700 -1700 • All Dimensions are in mm unless specified.
Road Base Level Road Base Level • Drawings are not to scale.
-1800 -1800

Copper Earth Rod 14mm dia


2m long

Sea Side Land Side


1 1 : 20 2 1 : 20

2
4
2 4 TM03
TM03 Heavy Duty K2C Manhole
TM03 TM03
Cover 1800 x 900 x 148mm with
Key opening System. Key to
Handed over to the Terminal
Station
Road/ Surface Level Road/ Surface Level Manhole Cover
clamped or fixed
0 0 firmly with wall or
slab

Ladder Mount 25
mm
Tube 750mm long Dia
Ladder Mount
1450

Copper Earth
Rod 25mm 300 x 300 x 200mm Sump
dia 2m long with 350 x 350 x 25mm
GRP Gratings

Raft Footing Raft Footing


-1450 -1450

PCC PCC
-1700 -1700

Road Base Level Road Base Level


-1800 -1800

Section 4 Section 5 Ladder Mount


3 1 : 20 4 1 : 20 5

No. Date Drawn By Approved By Description


Architectural Drawings-2

02/11/2022 12:41:52 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical 90 Degree Turning Manhole Details (Turning
Right Side of Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
TM02
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
• All reinforcement shall be minimum Fe415 grade • Drawings provided is for general reference only.
-
• All reinforcement shall be 12mm with maximum spacing of 200mm c/c Construction Drawings shall be submitted and
• The concrete for RCC shall be readymix concrete with SRC 35 grade approved by Client in accordance with the local
- Rear • The concrete for PCC shall be readymix concrete with SRC 15 grade Authorities regulations and requirements prior to
• 25mm concrete cover shall be maintained for all reinforcement steel commence of all works.
• Mix Design of concrete and Reinforcement Technical sheet shall be submitted pior to • All NOC's, Approvals & Permits for the construction
commence of works shall be obtained by the contractor prior to
commencement of all works.
1 4 • The load/ traffic over the manhole & nature of ground

Land Side
Seaward Direction 3 TM03 TM02 soil to be considered while designing the Construction
TM02 drawings
• All Materials used shall be approved by Client.
2 TM02
Road/ Surface Level
• Inspection Requests shall be raised by the contractor
3
TM02
with photos and approved from Client before all
0 Concrete works.
Sea Side

1 • Compaction Test results for Compacted Soil and


900

TM03 Cable 250 250 Roadbase laid shall be submitted to Client.


Racks
TM02 1 • Cube Test Results for 7 days & 28 Days of all RCC
4
TM02
concrete shall be submitted to Client.
• Drawings shall be read in conjunction with ASN Civil
16mm Dia Guidelines.
Galvanised • All Dimensions are in mm unless specified.
Steel Hook for
Pulling Cable • Drawings are not to scale.

3 Front

Cable Exit
4
Raft Footing
TM03
TM01 -1450

200 100 250


2
TM03

PCC
-1700
Inside Plan
3 1 : 20
Road Base Level
-1800

Section 2
2
TM03
4 2 1 : 20 1
TM03
4 TM03
3
TM02 TM02

Road/ Surface Level Road/ Surface Level


0 0

16mm Dia Galvanised


Steel Hook for Pulling
Cable Ladder Mount

160
160
Cable Racks 4x125mm Dia
RCC Wall DWCP (110mm
850

16mm Dia Galvanised (min) ID) PVC


Steel Hook for telco grade ducts,
Pulling Cable 1 with 2 subducts
38mm (min) Inner
352 500 500 352 RCC Footing Dia
150

150

Raft Footing Raft Footing


100mm thick-1450 -1450
Minimum 200mm Thick Compacted PCC Blinding
Roadbase over compacted Soil PCC PCC
-1700 -1700
Road Base Level Road Base Level
200 100
-1800 -1800 Copper Earth
Rod 14mm dia

Section 1 Section 3
1 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Structural Details

02/11/2022 12:41:53 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999: Typical 90 Degree Turning Manhole Details (Turning
Right Side of Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
TM03
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20
4 x 100mm (min Inner
Dia) PVC telco grade
- ducts, 1 with 2
subducts 38mm (min)
Inner Dia
- Rear

200 100 200


125
150 150

300
- -
- -
Sea Side

Land Side
900
125 300
300 x 300 x 200mm Sump
with 350 x 350 x 25mm 100
GRP Gratings

150 150

100

200 100 200


4 x 100mm (min Inner
Dia) PVC telco grade
ducts, 1 with 2
subducts 38mm (min)
Inner Dia
Minimum 2 Layers of
Bituminous Paint
200 100 200 1800 200 100 200

- Front

Inside Plan View


2 1 : 20

{3D}
1

Heavy Duty K2C Manhole


Cable Exit Cover 1800 x 900x 148mm with
- - Key opening System. Key to
Handed over to the Terminal
Station
- Rear - Rear

- - - -
- - - -
Sea Side

Sea Side
Land Side

Land Side
Seaward Direction

- Front - Front

Inside Plan -
Site Plan -
3 1 : 20 4 1 : 20

No. Date Drawn By Approved By Description


Architectural Drawings-3

02/11/2022 12:45:05 PM
V1 22/10/2019 J. Finlay J. Clark Initial Issue
Alcatel Submarine Networks V2 31/10/2022 Charls John Colin Higgs Revised Issue
Inst. 13999. Typical 90 Degree Turning Manhole Details (Turning
Left Side of Cable Laying Direction towards Terminal Station)
Date 31 October 2022
Drawn By Charls John
TM04
Review by Luke Addis
Landfall Civil Works Department
Approved by Colin Higgs Scale 1 : 20

You might also like