You are on page 1of 2

CONCRETE PRE-POUR INSPECTION REPORT

Contract
Client
Concessionaire
IC
EPC Contractor
Report No. Date & Time of Inspection

Concrete Grade Design Mix No. Ref.Post-pour Report No.

Ref.Drg.No.:

Location of the
Structure/Pour

S.No. Description of Activity YES NO N/A Remarks


01 Approval of Materials and Design Mix Concrete

02 Survey Checkd as per Approved and latest revised Drawings Survey Report No:

03 Excavation/Trenching/Filling and Surface preparation as per Drawing

04 Sprinkling water/PCC bedding as per Drawing

05 Approval of Bar Bending Schedules BBS No:

06 Reinforcement placing,tieing with specified binding wire and welding, if required, as per BBS/Drawings

07 Providing adequate no.of Cover Blocks of required thickness

08 Position of Spacers,Chairs,Splices,Laps etc as per BBS/Drawings

09 Position of Construction Joints,Embedment plates,Pipe inserts,if any,etc.as per Drawing

10 Location of Pre-Stressed Tendons,Ducts,Anchors etc. as per Drawing

11 Check for Line,level,alignment,plumb,supports and mould release Oil etc. of Shuttering

Check for availability of Batching Plant,Transit Mixers,Placer Pump,Vibrator,Slump Cone and Cube
12
Moulds etc. before start of Concreting

Contractor's Representative Consultant's Representative

Name : :
Name
Designation : Designation :
Sign : Sign :
Date : Date :
Page No.: 1 of 1