CONTENTS
PARAGRAPH PAGE
1 PURPOSE 2
2 SCOPE 2
3 DEFINITIONS 2
4 PERSONNEL 2
5 RESPONSIBILITY 2
6 PROCEDURE 2
7 APPENDICES 5
8 REFERENCES 5
This Document is Uncontrolled When Printed, Copied or Removed from the QEHS Drive
1.0 Purpose
1.1 The purpose of this Procedure is to ensure that control is exercised over the receipt
and distribution of all drawings received from external sources, and also drawings
issued by the company
1.2 This Procedure also ensures that appropriate records are maintained and that
drawing flow and control activities, for all contract documentation, are carried out
in line with Company policy.
2.0 Scope
2.1 This Procedure covers the control of all drawings received or issued by the
company, whether in hard copy or electronic media and describes the steps that
the Company shall implement in respect of drawing flow and control, in the office
and on site.
4.0 Responsibilities
4.1 The Managing Director is responsible for appointing a competent Site Manager for
this project.
4.2 The Contracts Manager/Project Manager is responsible for the effective
management of this procedure and is responsible for the receipt and distribution of
Client drawings, and for issuing for construction.
4.3 It is the responsibility of the Contracts Managers, Project Engineers and BIM
Engineer to ensure that any CAD drawings produced, received or issued by the
company are controlled in accordance with the procedure below.
4.4 The Quality Manager is responsible for providing any Quality information required
4.5 The Project Engineer / Document Controller is responsible for the effective
operation of this procedure
4.6 The Site Manager is responsible for the control of drawings on the site
4.7 All other responsibilities are defined within this procedure.
5.6.7 Where relevant, the Company takes the lead role in the co-ordination of
Builders Works drawings and the Contracts Manager ensures that the
drawings are overlaid and reviewed for access, clashes, etc.
5.6.8 On agreement with the Contractors, the drawings are ready for formal
approval following a final check.
5.6.9 Combined Builders Works drawings are issued in accordance with the
schedule provided all Contractors have supplied the necessary information.
5.8.4 Upon mechanical completion of the installation, the red line drawings are re-
issued as “Record Drawings” and supersede all previous drawings associated
with the system(s).
5.8.5 All future queries in relation to the system route / layout are referred to the
“Record” Drawings.
5.8.6 One set of “Record” Drawings is inserted in each O&M Manual issued, in
accordance with the Project Handover Document procedure SP10
5.8.7 A “soft copy” of the “Record” Drawings is also provided with the O&M Manual
in the event that the paper copies are misplaced.
6.0 Appendices
MF1.1, Transmittal Form
SF2.1, Drawings Received Register
SF2.2, Drawings Issued Register
SF2.2A, T&D Drawing Issue Register
SF2.3, As-built Drawing Status Register
7.0 References
MP1, Document Control procedure
SP10, Project Handover Documentation procedure