Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 06 April 2023

Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 1
Elevasi : - Koordinat : -5.508230,104.48117

PENETRATION CONUS TEST


(ASTM D 3441 - 86)
Conus Total Friction
Friction
Depth Penetration Penetration HL x 20 JHL Ratio
(PK) (JP) HL=(JP-PK)/10 FR=(HL/PK)
(METER) (KG/CM2) (KG/CM2) (KG/CM2) (KG/CM) (KG/CM) (%)

0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.20 5.00 15.00 1.00 20.00 20.00 20.00
0.40 20.00 20.00 0.00 0.00 20.00 0.00
0.60 26.00 30.00 0.40 8.00 28.00 1.54
0.80 33.00 35.00 0.20 4.00 32.00 0.61
1.00 38.00 40.00 0.20 4.00 36.00 0.53
1.20 48.00 50.00 0.20 4.00 40.00 0.42
1.40 40.00 35.00 0.50 10.00 30.00 1.25
1.60 35.00 30.00 0.50 10.00 20.00 1.43
1.80 30.00 30.00 0.00 0.00 20.00 0.00
2.00 30.00 30.00 0.00 0.00 20.00 0.00
2.20 32.00 35.00 0.30 6.00 26.00 0.94
2.40 25.00 20.00 0.50 10.00 16.00 2.00
2.60 20.00 20.00 0.00 0.00 16.00 0.00
2.80 25.00 28.00 0.30 6.00 22.00 1.20
3.00 30.00 37.00 0.70 14.00 36.00 2.33
3.20 40.00 45.00 0.50 10.00 46.00 1.25
3.40 46.00 48.00 0.20 4.00 50.00 0.43
3.60 55.00 62.00 0.70 14.00 64.00 1.27
3.80 65.00 66.00 0.10 2.00 66.00 0.15
4.00 70.00 70.00 0.00 0.00 66.00 0.00
4.20 80.00 84.00 0.40 8.00 74.00 0.50
4.40 94.00 100.00 0.60 12.00 86.00 0.64
4.60 109.00 110.00 0.10 2.00 88.00 0.09
4.80 120.00 130.00 1.00 20.00 108.00 0.83
5.00 150.00 170.00 2.00 40.00 148.00 1.33
5.20 140.00 130.00 1.00 20.00 128.00 0.71
5.40 136.00 146.00 1.00 20.00 148.00 0.74
5.60 130.00 130.00 0.00 0.00 148.00 0.00
5.80 120.00 120.00 0.00 0.00 148.00 0.00
6.00 130.00 155.00 2.50 50.00 198.00 1.92
6.20 150.00 150.00 0.00 0.00 198.00 0.00
6.40 150.00 165.00 1.50 30.00 228.00 1.00
6.60 155.00 159.00 0.40 8.00 236.00 0.26
6.80 160.00 190.00 3.00 60.00 296.00 1.88
7.00 190.00 200.00 1.00 20.00 316.00 0.53
7.20 190.00 191.00 0.10 2.00 318.00 0.05
7.40 195.00 194.00 0.10 2.00 316.00 0.05
7.60 192.00 193.00 0.10 2.00 318.00 0.05
7.80 200.00 230.00 3.00 60.00 378.00 1.50
8.00 230.00 240.00 1.00 20.00 398.00 0.43
8.20 235.00 249.00 1.40 28.00 426.00 0.60
8.40 250.00 251.00 0.10 2.00 428.00 0.04
8.60
8.80 0.00 0.00 0.00 #DIV/0!
9.00 0.00 0.00 0.00 #DIV/0!
Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 06 April 2023
Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 1
Elevasi : - Koordinat : -5.508230,104.48117

PENETRATION CONUS TEST


(ASTM D 3441 - 86)

Total Friction (kg/cm2)


300 600 900 1200 1500
0.00

Conus Penetration Kg/Cm2

Total Friction Kg/Cm2

1.00

2.00

3.00

4.00
Depth (m)

5.00

6.00

7.00

8.00

9.00
0 50 100 150 200 250

Conus Penetration (kg/cm2)


FOTO DOKUMENTASI
PELAKSANAAN PEKERJAAN SONDIR

Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 06 April 2023


Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 1
Elevasi : -

Sketsa Lokasi :

SONDIR-1

ke Bukit Kemuning ke Kotabumi


Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 12 April 2023
Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 2
Elevasi : - Koordinat : -5.508230,104.48117

PENETRATION CONUS TEST


(ASTM D 3441 - 86)
Conus Total Friction
Friction
Depth Penetration Penetration HL x 20 JHL Ratio
(PK) (JP) HL=(JP-PK)/10 FR=(HL/PK)
(METER) (KG/CM2) (KG/CM2) (KG/CM2) (KG/CM) (KG/CM) (%)

0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.20 10.00 12.00 0.20 4.00 4.00 2.00
0.40 15.00 20.00 0.50 10.00 14.00 3.33
0.60 20.00 20.00 0.00 0.00 14.00 0.00
0.80 25.00 30.00 0.50 10.00 24.00 2.00
1.00 35.00 38.00 0.30 6.00 30.00 0.86
1.20 25.00 30.00 0.50 10.00 40.00 2.00
1.40 35.00 40.00 0.50 10.00 50.00 1.43
1.60 45.00 45.00 0.00 0.00 50.00 0.00
1.80 45.00 45.00 0.00 0.00 50.00 0.00
2.00 45.00 48.00 0.30 6.00 56.00 0.67
2.20 55.00 60.00 0.50 10.00 66.00 0.91
2.40 50.00 50.00 0.00 0.00 66.00 0.00
2.60 58.00 60.00 0.20 4.00 70.00 0.34
2.80 65.00 70.00 0.50 10.00 80.00 0.77
3.00 75.00 75.00 0.00 0.00 80.00 0.00
3.20 85.00 85.00 0.00 0.00 80.00 0.00
3.40 85.00 85.00 0.00 0.00 80.00 0.00
3.60 90.00 95.00 0.50 10.00 90.00 0.56
3.80 100.00 105.00 0.50 10.00 100.00 0.50
4.00 105.00 125.00 2.00 40.00 140.00 1.90
4.20 110.00 110.00 0.00 0.00 140.00 0.00
4.40 100.00 109.00 0.90 18.00 158.00 0.90
4.60 85.00 85.00 0.00 0.00 158.00 0.00
4.80 86.00 95.00 0.90 18.00 176.00 1.05
5.00 109.00 120.00 1.10 22.00 198.00 1.01
5.20 125.00 138.00 1.30 26.00 224.00 1.04
5.40 140.00 145.00 0.50 10.00 234.00 0.36
5.60 165.00 160.00 0.50 10.00 224.00 0.30
5.80 150.00 150.00 0.00 0.00 224.00 0.00
6.00 145.00 145.00 0.00 0.00 224.00 0.00
6.20 145.00 145.00 0.00 0.00 224.00 0.00
6.40 150.00 153.00 0.30 6.00 230.00 0.20
6.60 157.00 160.00 0.30 6.00 236.00 0.19
6.80 160.00 155.00 0.50 10.00 226.00 0.31
7.00 155.00 150.00 0.50 10.00 216.00 0.32
7.20 140.00 142.00 0.20 4.00 220.00 0.14
7.40 145.00 145.00 0.00 0.00 220.00 0.00
7.60 150.00 150.00 0.00 0.00 220.00 0.00
7.80 149.00 155.00 0.60 12.00 232.00 0.40
8.00 155.00 155.00 0.00 0.00 232.00 0.00
8.20 150.00 158.00 0.80 16.00 248.00 0.53
8.40 160.00 162.00 0.20 4.00 252.00 0.13
8.60 160.00 169.00 0.90 18.00 270.00 0.56
8.80 171.00 175.00 0.40 8.00 278.00 0.23
9.00 180.00 190.00 1.00 20.00 298.00 0.56
9.20 190.00 200.00 1.00 20.00 318.00 0.53
9.40 200.00 200.00 0.00 0.00 318.00 0.00
9.60 219.00 238.00 1.90 38.00 356.00 0.87
9.80 250.00 251.00 0.10 2.00 358.00 0.04
10.00 0.00 0.00 358.00 #DIV/0!
Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 12 April 2023
Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 2
Elevasi : - Koordinat : -5.508230,104.48117

PENETRATION CONUS TEST


(ASTM D 3441 - 86)

Total Friction (kg/cm2)


300 600 900 1200 1500
0.00

Conus Penetration Kg/Cm2

Total Friction Kg/Cm2


1.00

2.00

3.00

4.00
Depth (m)

5.00

6.00

7.00

8.00

9.00

10.00
0 50 100 150 200 250

Conus Penetration (kg/cm2)


FOTO DOKUMENTASI
PELAKSANAAN PEKERJAAN SONDIR

Pekerjaan : Perencanaan Teknik Jembatan Provinsi Lampung Tanggal : 12 April 2023


Lokasi : Jembatan Way Sabuk, Kabupaten Lampung Utara Operator : Ahmad Fauzi
No. Titik : Sondir - 2
Elevasi : -

Sketsa Lokasi :

SONDIR-2

ke Bukit Kemuning ke Kotabumi