You are on page 1of 1

Keterangan

Keterangan
Beda Tinggi

Titik-titik Penting
STATIONING

Grade Muka Tanah Asli (%)


Elevasi Muka Tanah Asli (m)

Grade Muka Tanah Rencana (%)


70

60
80
90
130
140

Elevasi Rencana Muka Jalan (m)


100
110
120

: Galian
Awal Proyek F 4.11 100 95.89 0+0

: Timbunan
1.5 0.13
2.74 98.5 95.76 0+100

1.5 0.55
1.79 97 95.20 0+200

1.5 3.11
3.41 95.5 92.09 0+300

1.40 1.24
3.25 94.1 90.85 0+400

1.5 0.52
2.27 92.6 90.33 0+500

3.00 0.20
1.07 91.2 90.13 0+600

1.40 1.02
0.49 89.6 89.11 0+700

1.5 4.11
3.20 88.2 85 0+800

1.50
1.70 86.7 85 0+900

1.40
0.20 85.2 85 1+0

0.00
-1.20 83.8 85 1+100
2.5
-0.20 82.3 82.5 1+200

1.50

: Elevasi Muka Tanah Asli


0
-1.70 80.8 82.5 1+300

: Elevasi Rencana Muka Jalan


1.40 0.91
-2.29 79.3 81.59 1+400

1.5 0.16
-3.53 77.9 81.43 1+500

1.5 2.68
-2.35 76.4 78.75 1+600

1.40 0.54
-4.40 74.9 79.30 1+700
1.79
Gorong-gorong PPV 1 77.5 1+800
STA 1+800
77.5 1+850
77.5 1+900
77.5 1+925

-4.00
77.5 1+950
0.00

PI 1 77.5 1+975
Tikungan
PPV 1

STA 2+00 -1.85 75.35 2+0


-1.66 8.61 75.16 2+25
-1.44 0.75 74.94 2+50
-1.34 0.89 74.84 2+75
-1.31 0.38 74.81 2+100
0.14
PI 1

-1.34 0.07 74.84 2+150


-0.92 0.84 74.42 2+200
0.88
-0.04 73.54 2+300
73.5

0.61
0.57 72.93 2+400
0.00

0.49
1.06 72.44 2+500
0.49
1.54 71.96 2+600
0.48
2.02 71.48 2+700
0.49
2.51 70.99 2+800
0.33
2.84 70.66 2+900
0.34
3.19 70.31 3+0
0.09
3.28 70.22 3+100
0.07
3.35 70.15 3+200
0.25
3.10 70.40 3+300
0.42
2.68 70.82 3+400

1.60 0.80
Gorong-gorong PPV 2 1.88 71.61 3+500
STA 3+500
1.7 0.77
2.71 75.1 72.39 3+600

1.7 1.08
3.33 76.8 73.47 3+700
PPV 2

0.80 1.30
3.73 78.5 74.77 3+800

Gorong-gorong PPV 3 4.00 1.06 75.30 3+850


STA 3+850
3.40 1.21 75.90 3+900
3.04 76.26 3+925
2.67 1.42 76.63 3+950
PI 2 2.26 1.50 77.03 3+975
Tikungan STA 4+00 -0.21 1.62 79.51 4+0
PPV 3

-0.70 9.91 81.93 4+25


79.30

0.00

-0.70 9.66 81.26 4+50


-0.70 2.66 80 4+75
SKALA VERTIKAL

-0.70 5.05 80 4+100


PI 2

0
-0.70 0 80 4+150
Gorong-gorong PPV 4 -4.71 6.40 8.02 84.01 4+200
STA 4+200
3.2 1.40
-0.11 82.5 82.61 4+300

3.2 3.33
-0.24 85.7 85.94 4+400
PPV 4

3.2 8.47
-5.00 88.9 93.90 4+500

3.2 1.88
-0.42 92.1 92.52 4+600

3.20 1.55
4.33 95.3 90.97 4+700
3.76

Gorong-gorong PPV 5 3.77 94.73 4+800


STA 4+800
1.66
4.93 93.57 4+900
3.45
1.98 96.52 5+0
PPV 5

0.00

2.70 1.43 95.80 5+50


= 1 : 1000

3.36 1.33 95.14 5+100


-1.31 99.81 5+125
-0.96 18.68 99.47 5+150
SKALA HORIZONTAL = 1 : 20.000

PI 3 -0.63 1.36 99.13 5+175


Tikungan STA 5+200 -0.11 1.35 98.61 5+200
2.09 2.08 96.41 5+225
98.50

1.65 8.78 96.85 5+250


1.22 1.74 97.28 5+275
-1.59 1.72 100.09 5+300
11.27
-1.94 0.70 100.44 5+350
PI 3

-2.78 1.67 101.29 5+400


1.55

Gorong-gorong PPV 6 -4.33 102.83 5+500


STA 5+200
0.50
-3.13 100.2 103.32 5+600
2.34
-3.77 101.9 105.66 5+700
PPV 6

0.61
-1.46 103.6 105.06 5+800
GAMBAR PENAMPANG MEMANJANG JALAN TRASE 1

3.91
1.7