Professional Documents
Culture Documents
net/publication/250091426
CITATIONS READS
0 2,807
3 authors, including:
Samiran Ghosh
TOTAL
2 PUBLICATIONS 0 CITATIONS
SEE PROFILE
All content following this page was uploaded by Samiran Ghosh on 12 May 2015.
Summary compressor was split into LP and HP cases so that the LP case
Efficiency and economics have motivated RasGas Trains 3 could be driven by the gas turbine and the HP section could be
through 5 to implement a novel compressor-driver arrangement driven by a separate motor.
comprising both propane and mixed-refrigerant (MR) compressors Subsequently, RasGas Trains 1 and 2 were designed with a
on a single shaft. One Frame 7E gas turbine drives the low-pres- substantially higher throughput than the QatarGas trains. The proj-
sure (LP) and medium-pressure (MP) MR compressors, while a ect determined that the use of Frame 7E drivers could reduce the
second Frame 7E drives the propane and high-pressure (HP) MR number of drivers and provide economy of scale advantages over
machines. With minor control system adjustments after startup, the the Frame 5 series. Trains 1 and 2 used Frame 7E drivers for both
refrigerant compressors in RasGas Train 3 are operating reliably. the propane and MR services. These trains provided some MR
intercooler duty with propane refrigerant as a method of shifting
Introduction duty from the MR compressors to the propane compressors—a
concept that increased the propane circulation rate and, therefore,
The propane precooled mixed refrigerant (C3MR) process devel- the duty. At the same time, the MR compressor duty was decreased
oped by Air Products has been the dominant process technology because the compressor suction temperature was lowered. A single
employed in the liquefied natural gas (LNG) industry for more variable-frequency drive (VFD) served two 8-MW motors re-
than 30 years. This process uses a propane refrigerant system to quired for starting the gas turbines. These motors were only rated
chill the feed gas from ambient temperature to approximately for short-duration use.
–33°C and an MR to chill the gas to LNG temperatures. Because The RasGas expansion project, consisting of three trains of
pure propane is used in the precooling refrigeration cycle, the higher capacity than RasGas 1 and 2, further took the concept of
minimum temperature of this cycle is limited to the boiling tem- shifting load to the propane driver. Instead of circulating more
perature of propane near atmospheric pressure. The total duty that propane, this concept arranged the machines so that one of the MR
can be transferred to the propane refrigerant is thereby naturally compressor bodies was coupled to the propane driver. Such an
limited to heat that can be transferred within this range. arrangement is convenient because the compressor supplier has a
Because of the propane’s limited temperature range, one of the great deal of flexibility in selecting an MR compressor section that
characteristics of the C3MR process arrangement is that the MR can absorb the remaining power from the propane driver.
refrigeration system requires nearly double the compression power By implementing this arrangement, these trains were able to
of the propane refrigeration system. The actual difference depends fully use two identical Frame 7E drivers while taking advantage of
on the number of propane stages, the ambient conditions, the the relative efficiency and economy of scale offered by these ma-
environmental cooling medium, and other process arrangements. chines. Each gas turbine is equipped with a 12-MW motor that
To drive these refrigeration compressors, early LNG plants assists in starting and also provides power when the gas turbine is
used steam turbines that could be sized to fit the required service derated because of high ambient temperature or fouling. RasGas
(e.g., Marsa el Brega). Later projects determined that gas-turbine Train 3, the first train to employ this concept, started up in 2004.
drivers were a more efficient and less costly option for driving Train 4 subsequently started up in the third quarter of 2005, and
the compressors. Train 5 will start up in 2006.
For procurement, maintainability, and sparing purposes, an op-
erating facility would prefer to have each of the compression ser- Process Overview
vices driven by the same type and model of gas-turbine driver. For
the C3MR process, such an arrangement is typically inconvenient RasGas Train 3 was designed to process 800×106 scf/D of feed gas
because of the inherent power consumption mismatch between the to LNG. After treatment to remove C5+ hydrocarbon liquids, free
propane and MR services. water, and acid gas, the feed gas is chilled by one stage of propane
refrigerant before dehydration. Following dehydration and mer-
cury removal, the gas is chilled by four more stages of propane
Use of Gas-Turbine Drivers
refrigerant. Designated as low-low pressure (LLP), LP, MP, and
ExxonMobil has been driving LNG plant-compression systems HP, the evaporation levels chill the feed gas and the MR to
with gas turbines since 1978, with the startup of the PT Arun LNG –33°C—a temperature at which the MR is partially condensed and
plant in Indonesia. Each train of this plant used three Frame 5C enough feed gas is condensed to reflux the scrub column. The
gas-turbine drivers, one for the propane system and two for the MR evaporated propane refrigerant is compressed in a single compres-
system. This arrangement was a good fit for the desired capacity as sor body with four inlets and one discharge nozzle. The com-
well as the 2:1 power/draw ratio for the MR and propane services. pressed propane is then cooled and condensed by a closed-loop
When designing the QatarGas facility, each train was supplied cooling water system.
with four Frame 5D drivers, one for the propane service and three The MR is responsible for cooling the feed gas to approxi-
for the MR service. To satisfy the characteristic 2:1 power ratio, mately –156°C. The compressed refrigerant is chilled by four
more power was required on the propane service. The propane stages of propane, where it is separated into vapor and liquid
refrigerants that enter the bottom of the main cryogenic heat ex-
changer (MCHE) in separate tube-side passes. The HP liquid por-
Copyright © 2006 Society of Petroleum Engineers
tion is subcooled as it travels up the MCHE and exits at a midpoint
This paper (SPE 105623) was revised for publication from paper IPTC 10861 and first in the exchanger, where it is expanded across a hydraulic turbine
presented at the 2005 International Petroleum Technology Conference, Doha, Qatar, 21–23
November. Original manuscript received for review 12 December 2005. Paper peer and introduced to the shell side as the refrigerant. The HP vapor
approved 20 March 2006. portion of the MR is condensed and subcooled as it travels to the
Mechanical Design
The machinery arrangement for RasGas Trains 3 through 5 is
depicted in Fig. 1. The propane and HP MR compressors are
coupled to a gas-turbine driver, site rated at 77,554 kW, as the
Fig. 1—Compressor-driver arrangement.
prime mover. The LP and MP MR compressors are coupled to a
second GE Frame 7EA gas-turbine drive, site rated at 78,285 kW.
The HP MR takes up roughly 30% of the load of the gas-turbine Startup Procedure
drive. This arrangement was chosen to balance the power usage
This section will briefly describe the startup procedure of the two
between the two gas turbines. The compressor supplier first de-
compression strings following defrost with a methane-rich gas.
signed the propane machine to define the speed necessary to meet
the process conditions. It then selected the HP MR compressor to
Propane System Startup. The propane system, isolated from the
define the suction pressure needed to meet the required MR dis-
defrost gas system, is pressurized with propane vapor from storage
charge pressure, realizing that the HP MR machine would turn at
and vented several times to purge the majority of the methane from
the same speed as the propane compressor. Finally, the LP and MP
the system. Significant residual methane could lower the liquid evap-
MR compressors were designed to meet the inlet pressure require-
oration temperature to the extent that the evaporator metallurgy
ments for the HP MR machine.
could be in danger. To prevent this danger, any residual light com-
Speed/torque curves were developed for these arrangements to
ponents are purged from the propane accumulator during operation.
determine that 12-MW motors were needed for starting. These motors
The propane compressor recycle system is charged with pro-
are rated for continuous use so that they can be used to supplement
pane vapor from storage to 1.4 bara, and liquid propane, also from
the gas-turbine power, particularly during the hot summer months.
storage, is loaded into the accumulator and the evaporators. At this
An individual VFD is coupled to each of these motors.
time, the 1st- and 2nd-stage propane recycle valves are open, and
Vendors are required to submit to a meticulous qualification
the 3rd- and 4th-stage recycle valves are closed. The gas-turbine
process when bidding for a project of such a magnitude. When
driver for the propane and HP MR compressors can be started once
providing their quotation for this project, Elliott demonstrated that
cooling water flow is initiated to the propane desuperheater, con-
these compressors were within their experience limits. They were
denser, and subcooler. As the compressor starts and the suction
able to demonstrate that there were no technology limitations con-
pressure drops, propane is made up to the 1st-stage suction to keep
sidering wheel dimensions case size, shaft diameter, bearing span,
this pressure above atmospheric. The 1st-stage antisurge controller
bearing size, thrust balancing, or dry gas seals.
has a suction-pressure override control to prevent deep vacuum
The effectiveness of this machinery arrangement is partially
conditions at the main suction of the compressor; see Fig. 2 for
responsible for the capacity increase of Train 3 relative to Trains
value arrangement.
1 and 2. The annualized throughput of RasGas Trains 1 and 2
The control system automatically runs up the speed to the mini-
is now approximately 3.3 million tons per annum (MTA) per train.
mum governor speed of 95%, at which time the 1st-stage suction
In contrast, the annualized throughput of Train 3 is approximately
pressure is adjusted to its operating point. The 3rd- and 4th- stage
4.7 MTA.
recycle valves are now fully opened. The startup bypass valve can
now be closed—at which time the recycle valves can be placed in
Control Philosophy automatic operating mode. At this time, the propane-compression
The control philosophy is designed to maximize the production of system can be connected to the propane heat-exchanger system
on-spec LNG when faced with the challenges of process upsets, and the level controllers are placed on automatic.
feed-gas changes, and ambient condition changes. The HP MR compressor is on the same shaft as the propane
The speed of the propane compressor is set to maintain refrig- compressor and must be started at the same time. The HP MR
eration performance at the current conditions. On the same shaft as recycle loop is initially pressurized with defrost gas to no more
the propane machine, the HP MR compressor is constrained to the than 1.6 bara. As the propane system starts, this compressor runs
same speed. The speed of the LP and MP MR compressors are on total recycle with defrost gas being made up to keep the suction
controlled to meet both the HP MR discharge pressure and the pressure higher than atmospheric pressure.
required refrigeration capacity. If the refrigeration capacity is too
low, the speed of the driver is increased to increase the flow rate. MR System Startup. To start the MR system, gas from the scrub-
If the driver reaches maximum speed and cannot provide the re- column reflux drum is used to pressurize the LP and MP recycle
quired refrigeration capacity, the LNG flow rate is reduced. If the systems to 1.61 bara. Cooling water is introduced to the intercool-
driver is at the minimum speed and the refrigeration capacity is ers and aftercooler, and the gas-turbine driver is started and auto-
still too high, then the recycle valves are opened. matically controlled to its minimum governor speed of 95%, dur-
The propane system operates with the load determined by the ing which time the suction pressures are controlled so that they do
MR system. The propane-compressor discharge pressure is not not exceed 1.6 bara. After minimum governor speed is attained, the
directly controlled, but is determined by the vapor pressure at the discharge pressures are controlled so that they do not exceed the
condensing temperature. The compressor speed can be manually maximum operating pressures. The recycle valves are now placed
adjusted, if necessary. in automatic mode. As the suction pressure drops, gas is made up
The composition of the MR is primarily controlled through from the scrub column reflux drum such that the suction pressure
monitoring the temperatures at the top, middle, and bottom of is maintained at approximately 1.4 to 1.5 bara.
the MCHE. Adjusting the vapor/liquid ratio in the MR separator At this time, methane-rich gas from the scrub column reflux
is the primary means for dealing with day-to-day fluctuations. drum is introduced to the MP MR suction drum to equalize the MP
To deal with more extreme fluctuations, the MR composition is suction pressure to the LP compressor discharge pressure. After
adjusted by purge and component makeup. There are various equalization, the LP MR discharge valve may be opened. The HP
ways to reduce production, depending on the extent and duration MR compressor, on the same shaft as the propane machine, is
of the reduction (e.g., light components in the MR system may be already running with defrost gas on full recycle. The suction pres-
vented to reduce refrigerant mass flow rate and provide less re- sure of HP MR is equalized with the discharge of MP MR, by
frigeration capacity). adjusting flow from the scrub-column reflux drum. Once the dis-