You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/250091426

Operating Experience with the SplitMR Machinery Configuration of the C3MR


LNG Process

Article  in  SPE Projects Facilities & Construction · June 2006


DOI: 10.2118/105623-PA

CITATIONS READS
0 2,807

3 authors, including:

Samiran Ghosh
TOTAL
2 PUBLICATIONS   0 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Samiran Ghosh on 12 May 2015.

The user has requested enhancement of the downloaded file.


Operating Experience With the Split MR
Machinery Configuration of the C3MR
LNG Process
A. Brimm, ExxonMobil Development Co.; S. Ghosh, RasGas Co. Ltd.; and
D.J. Hawrysz, ExxonMobil Upstream Research Co.

Summary compressor was split into LP and HP cases so that the LP case
Efficiency and economics have motivated RasGas Trains 3 could be driven by the gas turbine and the HP section could be
through 5 to implement a novel compressor-driver arrangement driven by a separate motor.
comprising both propane and mixed-refrigerant (MR) compressors Subsequently, RasGas Trains 1 and 2 were designed with a
on a single shaft. One Frame 7E gas turbine drives the low-pres- substantially higher throughput than the QatarGas trains. The proj-
sure (LP) and medium-pressure (MP) MR compressors, while a ect determined that the use of Frame 7E drivers could reduce the
second Frame 7E drives the propane and high-pressure (HP) MR number of drivers and provide economy of scale advantages over
machines. With minor control system adjustments after startup, the the Frame 5 series. Trains 1 and 2 used Frame 7E drivers for both
refrigerant compressors in RasGas Train 3 are operating reliably. the propane and MR services. These trains provided some MR
intercooler duty with propane refrigerant as a method of shifting
Introduction duty from the MR compressors to the propane compressors—a
concept that increased the propane circulation rate and, therefore,
The propane precooled mixed refrigerant (C3MR) process devel- the duty. At the same time, the MR compressor duty was decreased
oped by Air Products has been the dominant process technology because the compressor suction temperature was lowered. A single
employed in the liquefied natural gas (LNG) industry for more variable-frequency drive (VFD) served two 8-MW motors re-
than 30 years. This process uses a propane refrigerant system to quired for starting the gas turbines. These motors were only rated
chill the feed gas from ambient temperature to approximately for short-duration use.
–33°C and an MR to chill the gas to LNG temperatures. Because The RasGas expansion project, consisting of three trains of
pure propane is used in the precooling refrigeration cycle, the higher capacity than RasGas 1 and 2, further took the concept of
minimum temperature of this cycle is limited to the boiling tem- shifting load to the propane driver. Instead of circulating more
perature of propane near atmospheric pressure. The total duty that propane, this concept arranged the machines so that one of the MR
can be transferred to the propane refrigerant is thereby naturally compressor bodies was coupled to the propane driver. Such an
limited to heat that can be transferred within this range. arrangement is convenient because the compressor supplier has a
Because of the propane’s limited temperature range, one of the great deal of flexibility in selecting an MR compressor section that
characteristics of the C3MR process arrangement is that the MR can absorb the remaining power from the propane driver.
refrigeration system requires nearly double the compression power By implementing this arrangement, these trains were able to
of the propane refrigeration system. The actual difference depends fully use two identical Frame 7E drivers while taking advantage of
on the number of propane stages, the ambient conditions, the the relative efficiency and economy of scale offered by these ma-
environmental cooling medium, and other process arrangements. chines. Each gas turbine is equipped with a 12-MW motor that
To drive these refrigeration compressors, early LNG plants assists in starting and also provides power when the gas turbine is
used steam turbines that could be sized to fit the required service derated because of high ambient temperature or fouling. RasGas
(e.g., Marsa el Brega). Later projects determined that gas-turbine Train 3, the first train to employ this concept, started up in 2004.
drivers were a more efficient and less costly option for driving Train 4 subsequently started up in the third quarter of 2005, and
the compressors. Train 5 will start up in 2006.
For procurement, maintainability, and sparing purposes, an op-
erating facility would prefer to have each of the compression ser- Process Overview
vices driven by the same type and model of gas-turbine driver. For
the C3MR process, such an arrangement is typically inconvenient RasGas Train 3 was designed to process 800×106 scf/D of feed gas
because of the inherent power consumption mismatch between the to LNG. After treatment to remove C5+ hydrocarbon liquids, free
propane and MR services. water, and acid gas, the feed gas is chilled by one stage of propane
refrigerant before dehydration. Following dehydration and mer-
cury removal, the gas is chilled by four more stages of propane
Use of Gas-Turbine Drivers
refrigerant. Designated as low-low pressure (LLP), LP, MP, and
ExxonMobil has been driving LNG plant-compression systems HP, the evaporation levels chill the feed gas and the MR to
with gas turbines since 1978, with the startup of the PT Arun LNG –33°C—a temperature at which the MR is partially condensed and
plant in Indonesia. Each train of this plant used three Frame 5C enough feed gas is condensed to reflux the scrub column. The
gas-turbine drivers, one for the propane system and two for the MR evaporated propane refrigerant is compressed in a single compres-
system. This arrangement was a good fit for the desired capacity as sor body with four inlets and one discharge nozzle. The com-
well as the 2:1 power/draw ratio for the MR and propane services. pressed propane is then cooled and condensed by a closed-loop
When designing the QatarGas facility, each train was supplied cooling water system.
with four Frame 5D drivers, one for the propane service and three The MR is responsible for cooling the feed gas to approxi-
for the MR service. To satisfy the characteristic 2:1 power ratio, mately –156°C. The compressed refrigerant is chilled by four
more power was required on the propane service. The propane stages of propane, where it is separated into vapor and liquid
refrigerants that enter the bottom of the main cryogenic heat ex-
changer (MCHE) in separate tube-side passes. The HP liquid por-
Copyright © 2006 Society of Petroleum Engineers
tion is subcooled as it travels up the MCHE and exits at a midpoint
This paper (SPE 105623) was revised for publication from paper IPTC 10861 and first in the exchanger, where it is expanded across a hydraulic turbine
presented at the 2005 International Petroleum Technology Conference, Doha, Qatar, 21–23
November. Original manuscript received for review 12 December 2005. Paper peer and introduced to the shell side as the refrigerant. The HP vapor
approved 20 March 2006. portion of the MR is condensed and subcooled as it travels to the

June 2006 SPE Projects, Facilities & Construction 1


top of the MCHE, where it is expanded across a Joule-Thompson
(JT) valve and introduced to the shell side as the refrigerant.
The evaporated refrigerant from the MCHE is recompressed in
three separate compressor bodies, designated as the LP, MP, and
HP MR compressors.

Mechanical Design
The machinery arrangement for RasGas Trains 3 through 5 is
depicted in Fig. 1. The propane and HP MR compressors are
coupled to a gas-turbine driver, site rated at 77,554 kW, as the
Fig. 1—Compressor-driver arrangement.
prime mover. The LP and MP MR compressors are coupled to a
second GE Frame 7EA gas-turbine drive, site rated at 78,285 kW.
The HP MR takes up roughly 30% of the load of the gas-turbine Startup Procedure
drive. This arrangement was chosen to balance the power usage
This section will briefly describe the startup procedure of the two
between the two gas turbines. The compressor supplier first de-
compression strings following defrost with a methane-rich gas.
signed the propane machine to define the speed necessary to meet
the process conditions. It then selected the HP MR compressor to
Propane System Startup. The propane system, isolated from the
define the suction pressure needed to meet the required MR dis-
defrost gas system, is pressurized with propane vapor from storage
charge pressure, realizing that the HP MR machine would turn at
and vented several times to purge the majority of the methane from
the same speed as the propane compressor. Finally, the LP and MP
the system. Significant residual methane could lower the liquid evap-
MR compressors were designed to meet the inlet pressure require-
oration temperature to the extent that the evaporator metallurgy
ments for the HP MR machine.
could be in danger. To prevent this danger, any residual light com-
Speed/torque curves were developed for these arrangements to
ponents are purged from the propane accumulator during operation.
determine that 12-MW motors were needed for starting. These motors
The propane compressor recycle system is charged with pro-
are rated for continuous use so that they can be used to supplement
pane vapor from storage to 1.4 bara, and liquid propane, also from
the gas-turbine power, particularly during the hot summer months.
storage, is loaded into the accumulator and the evaporators. At this
An individual VFD is coupled to each of these motors.
time, the 1st- and 2nd-stage propane recycle valves are open, and
Vendors are required to submit to a meticulous qualification
the 3rd- and 4th-stage recycle valves are closed. The gas-turbine
process when bidding for a project of such a magnitude. When
driver for the propane and HP MR compressors can be started once
providing their quotation for this project, Elliott demonstrated that
cooling water flow is initiated to the propane desuperheater, con-
these compressors were within their experience limits. They were
denser, and subcooler. As the compressor starts and the suction
able to demonstrate that there were no technology limitations con-
pressure drops, propane is made up to the 1st-stage suction to keep
sidering wheel dimensions case size, shaft diameter, bearing span,
this pressure above atmospheric. The 1st-stage antisurge controller
bearing size, thrust balancing, or dry gas seals.
has a suction-pressure override control to prevent deep vacuum
The effectiveness of this machinery arrangement is partially
conditions at the main suction of the compressor; see Fig. 2 for
responsible for the capacity increase of Train 3 relative to Trains
value arrangement.
1 and 2. The annualized throughput of RasGas Trains 1 and 2
The control system automatically runs up the speed to the mini-
is now approximately 3.3 million tons per annum (MTA) per train.
mum governor speed of 95%, at which time the 1st-stage suction
In contrast, the annualized throughput of Train 3 is approximately
pressure is adjusted to its operating point. The 3rd- and 4th- stage
4.7 MTA.
recycle valves are now fully opened. The startup bypass valve can
now be closed—at which time the recycle valves can be placed in
Control Philosophy automatic operating mode. At this time, the propane-compression
The control philosophy is designed to maximize the production of system can be connected to the propane heat-exchanger system
on-spec LNG when faced with the challenges of process upsets, and the level controllers are placed on automatic.
feed-gas changes, and ambient condition changes. The HP MR compressor is on the same shaft as the propane
The speed of the propane compressor is set to maintain refrig- compressor and must be started at the same time. The HP MR
eration performance at the current conditions. On the same shaft as recycle loop is initially pressurized with defrost gas to no more
the propane machine, the HP MR compressor is constrained to the than 1.6 bara. As the propane system starts, this compressor runs
same speed. The speed of the LP and MP MR compressors are on total recycle with defrost gas being made up to keep the suction
controlled to meet both the HP MR discharge pressure and the pressure higher than atmospheric pressure.
required refrigeration capacity. If the refrigeration capacity is too
low, the speed of the driver is increased to increase the flow rate. MR System Startup. To start the MR system, gas from the scrub-
If the driver reaches maximum speed and cannot provide the re- column reflux drum is used to pressurize the LP and MP recycle
quired refrigeration capacity, the LNG flow rate is reduced. If the systems to 1.61 bara. Cooling water is introduced to the intercool-
driver is at the minimum speed and the refrigeration capacity is ers and aftercooler, and the gas-turbine driver is started and auto-
still too high, then the recycle valves are opened. matically controlled to its minimum governor speed of 95%, dur-
The propane system operates with the load determined by the ing which time the suction pressures are controlled so that they do
MR system. The propane-compressor discharge pressure is not not exceed 1.6 bara. After minimum governor speed is attained, the
directly controlled, but is determined by the vapor pressure at the discharge pressures are controlled so that they do not exceed the
condensing temperature. The compressor speed can be manually maximum operating pressures. The recycle valves are now placed
adjusted, if necessary. in automatic mode. As the suction pressure drops, gas is made up
The composition of the MR is primarily controlled through from the scrub column reflux drum such that the suction pressure
monitoring the temperatures at the top, middle, and bottom of is maintained at approximately 1.4 to 1.5 bara.
the MCHE. Adjusting the vapor/liquid ratio in the MR separator At this time, methane-rich gas from the scrub column reflux
is the primary means for dealing with day-to-day fluctuations. drum is introduced to the MP MR suction drum to equalize the MP
To deal with more extreme fluctuations, the MR composition is suction pressure to the LP compressor discharge pressure. After
adjusted by purge and component makeup. There are various equalization, the LP MR discharge valve may be opened. The HP
ways to reduce production, depending on the extent and duration MR compressor, on the same shaft as the propane machine, is
of the reduction (e.g., light components in the MR system may be already running with defrost gas on full recycle. The suction pres-
vented to reduce refrigerant mass flow rate and provide less re- sure of HP MR is equalized with the discharge of MP MR, by
frigeration capacity). adjusting flow from the scrub-column reflux drum. Once the dis-

2 June 2006 SPE Projects, Facilities & Construction


Fig. 2—Propane-compressor startup.

charge pressure of the MP MR compressor equalizes with the Operational Experiences


suction pressure of the HP MR compressor, the MP MR com- As with any first-time installation, several minor operational issues
pressor discharge valve may be opened. At this time, the main have been corrected since the initial startup of Train 3.
cryogenic heat-exchanger pressure may be equalized with the LP
MR suction pressure, and the MR separator pressure may be equal- Maintenance Considerations. A characteristic of the RasGas
ized with the HP MR compressor discharge pressure. The MR Trains 1 to 2 machinery configuration is that the gas-turbine driv-
composition is then adjusted to the design conditions; see Fig. 3 ing the propane compressor is typically approximately 70%
for value arrangement. loaded, while the MR gas turbine is approximately 100% loaded.

Fig. 3—MR-compressor startup.

June 2006 SPE Projects, Facilities & Construction 3


Consequently, degradation of the propane-gas turbine is less of a Upon the hydraulic turbine trip, the flow rate dropped at a
concern than degradation of the MR gas turbine. Capacity of the sufficiently high rate that the usual PID action of the antisurge
train is, therefore, intimately linked to the performance of the MR valves could not react quickly enough, resulting in the compressor
gas turbine. surging. The control philosophy was subsequently modified to
In RasGas Train 3, both gas turbines are equally loaded, mean- prevent these surge events by implementing a kickback action.
ing that the performance of the train is intimately linked to the Rather than allowing the local indicators to initiate the antisurge
performance of both turbines. If one of the gas turbines degrades action, a feed-forward signal was initiated from the process-trip
or fouls faster than the other, it could result in operational diffi- interlock. This trip signal immediately set the antisurge controllers
culties and more trips. To prevent this situation, all seals in both to ramp open. Additionally, a safety system was implemented to
gas turbines will be replaced at each overhaul, whether or not they trip the machine upon the occurrence of three surge counts within
appear worn. 30 seconds. These modifications to the control system have pre-
vented spurious trips and have improved reliability.
Initial Startup. The first attempts to start the train resulted in Another series of surge event was caused by the HP MR re-
some trips of the first gas turbine to be started. The trips were the cycle valve becoming stuck closed. Multiple surge events were
result of an enhanced safety factor imposed by the gas-turbine recorded in a short period of time, resulting in the trip of the HP
control center. During startup, the gas-turbine controls monitor the MR gas turbine. The kickback action prevented the LP MR and
speed of the turbine and ensure that the speed increases during MP MR compressors from tripping, resulting in a minimal loss of
every 30-second interval. The design of Trains 1 and 2 ensure only inventory and reduced startup time.
that the speed did not decrease during a 30-second interval, which
is a less stringent condition. During the Train 3 startup, the gas Future Projects
turbine encountered 30-second intervals during which the speed The compressor arrangements described in this paper have already
remained constant, resulting in a trip of the turbine. been proved in RasGas Train 3 and will be used in Trains 4 and 5.
The root cause of this delay in speed increase is still being The next phase of expansion of the RasGas facilities is already
assessed. A possible cause is that the gas-turbine speed/torque under way. Each train of this two-train project will produce 7.8
curve does not match the load speed/torque curve because of the MTA of LNG, using the proprietary AP-X* LNG Process. This
pressure in the compressors. There is also uncertainty whether the process includes the C3MR process to liquefy the feed gas and a
extra protection afforded by this trip mechanism is necessary be- separate nitrogen refrigeration cycle to subcool the LNG, resulting
cause it was not needed in the Train 1 and 2 operation. in three refrigeration services.
The plant operators have developed several techniques to pre- To power the compressors required for this process, the project
vent this trip condition and to successfully start the train. Options will install three Frame 9E gas turbines in mechanical-drive ser-
include increasing the analysis interval from 30 to 60 seconds, vice (e.g., 126-MW Intl. Standards Organization). The first turbine
introducing richer fuel gas to the turbine, and depressuring the will power the propane compressors; the second, the MR com-
compressor cases as much as possible, which has been the most pressors; and the third, the nitrogen machines. Each shaft will also
effective option. have a motor and VFD rated for 45 MW of continuous duty and 60
MW of intermittent duty. The 60-MW intermittent duty is for
Sympathy Trips. A unique problem of “sympathy” trips occurred startup under full-pressure conditions.
as a result of the configuration of the compressors. Upon a trip of The power mismatch between the propane and MR compres-
the propane compressor, the HP MR compressor was forced to trip sors still exists for this process, although it is not as severe because
because the two machines share a common driver. After the trip of some of the MR duty is taken up by the nitrogen cycle. Depending
the HP MR compressor, the discharge pressure of the MP MR on conditions, the MR compressors may require 20 to 50% more
machine rose enough to cause it to trip also, resulting in a loss of power than the propane machines in this process. The power draw
MR inventory and an increase in downtime and restart time. of the nitrogen machines is slightly higher than that of the propane
The system was initially designed such that a propane com- compressors.
pressor trip caused all of the propane antisurge valves and the HP To adjust to the power-draw mismatch, the motors and VFDs
MR antisurge valve to open fully. However, the LP and MP MR- are used to transfer power among machines. Under all conditions
compressor recycle valves were allowed to react to the normal but the hottest days, the gas turbines driving the propane and
process variables, which was too slow to prevent those machines nitrogen compressors can generate more power than the compres-
from tripping. sors can absorb. In this case, the motors can act as generator
The problem of sympathy trips has been resolved by modifying to export power to the MR compressor-helper motor or to the grid.
the control logic to allow a kickback action. A feed-forward signal In case the propane and nitrogen drivers cannot supply all of the
from the tripped compressor triggers the remaining recycle valves extra power required by the MR driver, extra power is drawn from
to ramp open. This signal allows the MP MR system to react the grid.
much faster than the normal process instrument diagram (PID)
action of the antisurge controllers, resulting in better control during Conclusions
trip events. To prevent the gas turbine from bogging down because
The C3MR process has been widely used in the baseload LNG
of the sudden load increase, the LP and MP MR recycle valves
industry, despite the inherent power-consumption mismatch be-
are opened over a 12-second interval, rather than their fastest
tween the propane and MR refrigerant services. Considering the
opening time of 6 seconds. The gas turbine driving the LP and MP
procurement and operational advantages to using identical drivers
MR machines can now remain running in the event of a propane
for all services, techniques have been developed to effectively
system trip.
install the required driver capacity. Steam-turbine drivers that can
be sized to any load were initially used, but later gas-turbine driv-
Surge Events. A high number of MR-compressor surge events
ers were found to be a less costly and more efficient option. When
occurred because of the installation of a hydraulic turbine on the
driving the refrigerant compressors with gas turbines, early trains
MR stream, which was a feature not included in RasGas Trains 1
simply installed multiple drivers on the MR refrigerant service and
and 2. The control logic was initially set up to trip the MR hy-
a single driver on the propane circuit. Attempting to minimize
draulic turbine in the event of any process trip. Because the ma-
rotating equipment, later trains used a single driver for each service
jority of the MR flow normally passed through the hydraulic tur-
and attempted to shift load to the propane drive by using propane
bine, the trip of the turbine acted as a blocked discharge on HP MR
to intercool the MR compressor.
machines. This phenomenon was not observed on Trains 1 and 2
because the 60-second closure time of the JT valve caused the flow
rate to decrease much more slowly than the flow decrease associ-
ated with a hydraulic turbine trip. * Trademark of Air Products and Chemicals Inc., Allentown, Pennsylvania (11 July 2005).

4 June 2006 SPE Projects, Facilities & Construction


RasGas Train 3 introduced a novel method of approaching this
problem. Instead of shifting loads between services, this project SI Metric Conversion Factors
placed the HP MR compressor body on the same shaft as the kW × 1.055 056 E+00 ⳱ Btu/s
propane compressor. Because it was coupled to the propane ma- m3/D × 1.589 873 E–01 ⳱ bbl/D
chine, the HP MR compressor was sized to fully load a Frame 7E
driver, while the LP and MP MR compressor fully loaded another Allen Brimm is currently coordinating evaluation of new tech-
Frame 7E gas turbine. RasGas Train 3 has proved our ability to nologies ready for commercialization or emerging technolo-
overcome the technical challenge of driving two refrigerant ser- gies for Exxonmobil in the following areas: liquefaction, utili-
vices with the same prime mover through sound design and oper- ties, storage, and loading for LNG plants (e-mail: allen.e
ating practices. .brimm@exxonmobil.com). His prior experience includes work-
This machinery arrangement initially started up with minor ing on design, construction, startup, and operation of oil and
operational problems, as can be expected in a new design. Updates gas facilities. He began his work at the Pegasus Gas Plant lo-
to the operating procedure and slight modifications to the control cated near Midland, Texas, and has worked on international
system resolved these issues and have resulted in the reliable op- projects for the last 15 years, including RasGas in Qatar. Brimm
holds a BS degree in chemical engineering from the U. of Illi-
eration of these machines. nois. Samiran Ghosh is the Lead Process Engineer in the Process
The benefit of implementing this machinery configuration is Engineering Section of RasGas LNG Co. in Doha, Qatar (e-mail:
clear. The balanced loading of the gas turbines allowed RasGas emailsghosh@yahoo.com). His last 8 years of experience has
Train 3 to be designed to produce 4.7 MTA of LNG. In contrast, been in LNG trains commissioning, trouble-shooting, debottle-
RasGas Trains 1 and 2 that used the same drivers in a more necking, and conceptualizing design of facility enhance-
traditional arrangement is currently producing approximately 3.3 ments. Previous to his joining RasGas, he had 10 years of ex-
MTA per train. perience in downstream refining facilities in fluid catalytic
cracking units in India. Ghosh holds a BS degree in chemical
engineering from the Jadvapur U., India. Daniel Hawrysz has
Acknowledgments worked for ExxonMobil in Houston since 2001, first as Senior
Research Engineer developing LNG process technology and
The authors gratefully acknowledge discussions with Kuruvilla supporting LNG capital projects, and currently as Lead Process
Philip and Venkat Venkatachalam of RasGas Co. Ltd., Jim Bla- Engineer supporting ExxonMobil’s Rocky Mountain natural gas
hovec of Elliott Turbomachinery, and William A. Kennington Jr. production. He holds a BS degree from the U. of Illinois and a
of Air Products and Chemicals Inc. PhD degree from Purdue U., both in chemical engineering.

June 2006 SPE Projects, Facilities & Construction 5

View publication stats

You might also like