ENTRY DATA
References RTKB 354 GL 345 Rig GYP 8
Well : K-442 (KDN-16) Date 9/6/2017 day spud 21-07-2017 Rpt No 48
Depth (mMD) 1089 Depth (mTVD RT 1089 Progress ROP m/h
Current Formation Khurmala E4a
R/D Cementing head & cementing lines and slip spider.
Current Operation at 24:00:
RIH w/ 7'' 26 ppf L-80 casings f/227 m t/1085,5 m. Filled annulus from kill line w/water, no return. Totaly RIH: FS + 2 ea 7'' 26 ppf L-80 casing + FC + 21 ea 7'' 26 ppf L-80
casing + ACP + DV + 74 ea 7'' 26 ppf L-80 casing. FS: 1085,5 m, FC: 1062 m, ACP: 841 m(Top End) length of ACP: 5,08 m, DV: 840 m.
M/U circulation head and start to circulation. Pumped water from inside the casing and annulus at the same time,total pump rate:8,7 bpm,observed 2,1 bpm return on
shaker. Meanwhile, prepared for cementing job.
7'' Casing 1st Stage Cementing: Held PJSM then P/T for cement lines to 3000 psi / 5 min , OK. Pumped 8,7ppg 40 bbl spacer w/losses material by rig pumps. Pumped 15,8
ppg 64 bbl GT slurry(w/losses material) w/3 bpm from c/u. When pumping on shaker. Dropped shut off plug, displaced w/water w/3,3 bpm from c/u. When displacing
cement, at the same time pumped water from kill line w/3,7 bpm and observed cement, at the same time pumped water from kill line w/3,7 bpm and observed 3 bpm return
1 bpm return on shaker.After displacing 132,7 bbl, shot the plug in. Pressure increase up to 840 psi. Bleed off pressure, no return. Inflated ACP w/1600 psi, started
Operations last 24 hours(00:00 to 24:00) circulation from trip tank to annulus, observed no loss. Bleed off pressure, no return. B/O cementing head, dropped opening bump. Waited 20 min. Increased pressure up to
600 psi, openned stage collar ports.
Started to circulation, after pumping 180 bbl observed spacer on shaker, however no cement. FR: 4,9 bpm, SPP: 130 psi, no loss, no gain.
B/O kill line, choke line and hyraulic lines of BOP. Untighted bolts between 13 5/8'' 5M-11'' 5M CHH and 11'' 5M - 13 5/8'' 5M DSA.Hanged BOP stack to rotary beams.
Placed 7'' casing hanger slips and sit the casing on slips w/50klbs.
Prepared for the 2nd stage cementing.
7'' Casing 2nd Stage Cementing: Held PJSM then P/T for cementing lines to 3000 psi / 5 min, OK. Pumped 40 bbl water as spacer from c/u w/3,4 bpm 100 psi. Pumped
15,8 ppg 86 bbl cement slurry w/3,5 bpm 300 psi. Dropped closing plug, displaced w/water from c/u. After displaced cement slurry w/94 bbl water, observed cement on
surface, cement weight on surface is 15,7 ppg. After displaced cement slurry w/105 bbl water, closing plug bumbed with 2200 psi, test 5 min. Bleed off pressure, no return.
R/D Cementing head & cementing lines and slip spider.
Take TOTCO survey Azi -
2 Inc 677 Azi -
Inc Azi -
Inc
Take Anderdrift survey Azi -
Last Survey m MD
Inc Azi -
Inc Azi -
Take TOTCO survey Azi -
Inc Azi -
Inc Azi -
MW(kg/l) Csg Size (inch) 13 3/8" Csg Depth (m) 410
MW(kg/l) Csg Size (inch) 9 5/8" Csg Depth (m) 884.5
MW(ppg) 8.4 Csg Size (inch) Csg Depth (m)
MW(kg/l) Csg Size (inch) Csg Depth (m)
MW(kg/l) Csg Size (inch) Csg Depth (m)
GEOLOGICAL SUMMARY
Interval m. MD Lithology Descriptions
NO DRILLING NO SAMPLE
Shows
Interval m. MD Description
GAS DATA
Gas Type Interval Total C1 C2 C3 iC4 nC4 iC5
(m) (%) ppm ppm ppm ppm ppm ppm
Background Gas 885-887 0.009 82 - - - - -
887-902 0.0069 287 39 10 Tr Tr -
902-906 0.186 1504 159 56 28 19 14
906-924 0.74 4172 376 115 41 31 14
887-891 0.0978 190 16 7 4 4 3
891-899.5 0.14 753 66 26 11 9 5
899.5-902 0.19 1102 105 43 19 15 9
902-906 0.089 313 32 13 7 5 4
906-907 0.064 177 33 16 11 9 2
907-940 0.86 6074 493 155 54 41 19
978-980 1.51 9618 781 261 83 69 29
980-1000 17.2 85115 8725 2191 581 334 125
1038-1047 0.067 23 - - - - -
1089-1065 0.24 1025 100 33 21 17 15
Peaks
Trip Gas
Connection Gas
6:00AM
Depth (mMD) 1089 Depth (mTVD RT) 1089 Current Activity Waiting on cement
Waiting on cement
Operations 00:00–06:00