PROJECT PROPOSAL

Rationale

1. Title of the Project : Construction of Anopog Diversion Dam


2. Project Type : Infrastructure
3. Proponent : LAMAC MULTI-PURPOSE COOPERATIVE
4. Project Site/Location : Anopog, Pinamungajan, Cebu
5. Duration : January – June 20____
6. Contact Person : Name : CHARLITA B. PANGAN
Position: Assistant General Manager
Lamac Multi-Purpose Cooperative
Contact No.: 09183468782

Name : LEONIDA U. YONGCO


Position: Municipal Agriculturist
Pinamungajan, Cebu
Contact No.: 09562256874

7. Project Cost : Total Estimated Cost : Php ______________


Fund Source : DA Fund/Allocation
Proponent: Operation and Maintenance of the System

8. PROJECT DESCRIPTION

Pinamungajan is considered a second class town in terms of income category for local
government. It belongs to the third legislative district of Cebu and is composed of 26 barangays.
It is located a mere 70 kilometers away from Cebu City and is situated on the southwestern
seaboard of Cebu Island, along the scenic Tañon Strait and with a view of the majestic Mt.
Kanlaon, the most active volcano in the Visayas Group of Islands.

Although it can be accessed from various points in Cebu, the quickest way to Pinamungajan
from the South Bus Terminal in Cebu City is by passing through the scenic Naga-Uling road
connecting Naga and Toledo cities.

A large part of Pinamungajan is covered with agricultural lands. The town also focuses on
agriculture which showcases agricultural products from different barangays within the
municipality and other entrepreneurs from the other parts of the province. With the construction
of Anopog Diversion Dam (DD), there will be an increase of rice production. The farmers will be
able to contribute to the food sufficiency program of the province and increase their income.

8.2. Project Objectives

8.2.1. General:
To construct the agricultural productivity, accelerate development, and improved
the economic resources of the small farmers.

8.2.2. Specific:
1. To construct our irrigation system for our rice farmers in Anopog,
Pinamungajan, Cebu.
2. To increase rice production area and yield of the farmers.
3. To increase production income.

8.3. Project Beneficiaries and Influence Areas:

Barangay No. of Farmers Service Rice Area (ha) Average Yield (MT/ha)
Anopog

8.4. Project Benefits / Impacts:

The construction of this irrigation system in Anopog, Pinamungajan, Cebu will:

1. Increase rice production attributed to proper water management in the service area.
2. Adequate water supply needed in the whole cropping season.
8.5. Components and Strategies:

Component Title Activities


1.1. Conduct inspection and validation of
the proposed site.
1.2. Preparation and Approval of Plans,
1 Pre-implementation Phase
Designs and Program of Works
1.3. Signing of the Memorandum of
Agreement (Cooperative & DA)
2.1. Site Clearing and Lay Outing
2.2. Procurement and Delivery of
2 Implementation Phase Materials
2.3. Construction of Irrigation System
2.3.1 Concreting of irrigation canal
3.1. Conduct regular project M & E
Project Monitoring and Evaluation 3.2. Preparation and Submission of
3
(M & E) Progress Report
3.3. Photo Documentation
Establishment of Management 4.1. Managing the Project
4
Committee 4.2. Monitoring
5.1. Final Inspection
5 Post-implementation Phase
5.2. Project Turn-Over and Acceptance

8.6. Implementation Schedule:

Duration (mos) 2022 Duration (mos) 2023


ACTIVITIES
7 8 9 10 11 12 1 2 3 4 5 6
1. Pre-Implementation Phase
1.1. Conduct inspection and validation of
the proposed site.
1.2. Preparation and Approval of Plans,
Designs and Program of Works
1.3. Signing of the Memorandum of
Agreement (Cooperative & DA)
2. Implementation Phase
2.1. Site Clearing and Lay Outing
2.2. Procurement and Delivery of
Materials
2.3. Construction of Irrigation System
3. Project Monitoring and Evaluation
(M & E)
3.1. Conduct regular project M & E
3.2. Preparation and Submission of
Progress Report
3.3. Photo Documentation
4. Establishment of Management
Committee
4.1. Managing the Project
4.2. Monitoring
5. Post-implementation Phase
5.1. Final Inspection
5.2. Project Turn-Over and Acceptance
8.7. Work and Financial Plan

Cost Sharing
Components Duration Cost
DA-RFO 7 Proponent
Component 1
3 months - - -
Pre-implementation Phase
Component 2
Implementation Phase
(Construction of Anopog DD) 2 months -
(please see the attached Bill of
Materials and Cost Estimates)
Component 3
Project Monitoring and Evaluation 2 months - - -
(M & E)
Component 4
Establishment of Management 2 months - - -
Committee
Component 5
1 month - - -
Post-implementation Phase
Operation
TOTAL and
Maintenance

Prepared by: Checked and noted by:

CHARLITA B. PANGAN LEONIDA U. YONGCO


Assistant General Manager MA – Pinamungajan, Cebu

Recommending Approval: Approved:

GERRY S. AVILA, Ph.D. Dir. JOEL A. ELUMBA


Chief, Field Operations Division OIC – Regional Executive Director