JABATAN KERJA RAYA MALAYSIA

KERJA-KERJA PENGGANTIAN LIF DAN DUMBWAITER SERTA LAIN-


LAIN KERJA BERKAITAN DI HOSPITAL SULTANAH NUR ZAHIRAH,
KUALA TERENGGANU, TERENGGANU.

NO. KONTRAK: JKR / IP / CKM / 273 / 2021

LAPORAN KEMAJUAN KERJA NO. 13


20 / 12 / 2022

KONTRAKTOR

DUTA JERNIH SDN BHD


No.5A, Jalan Pelangi 2, Taman Pelangi Jaya,
51100 Gombak, Kuala Lumpur
Tel: 03-40227632
Fax: 03-40227632
LAPORAN KEMAJUAN KERJA NO.13

Disediakan oleh: Disemak oleh:


DUTA JERNIH SDN BHD DUTA JERNIH SDN BHD

……………………….. …………………………
Nama : Muhammad Faiz Nama : Mohammad Azam
Tarikh : 20hb Disember 2022 Tarikh : 20hb Disember 2022

Disemak oleh:
JKR CKM TERENGGANU

………………………..
Nama :

2|Page
KANDUNGAN
R

1. Ringkasan Eksekutif -3

2. Maklumat Projek -5

2.1. Carta Organisasi Projek

2.2. Carta Organisasi Kontraktor

3. Laporan Kemajuan Kerja -6

3.1. Ringkasan Kemajuan Fizikal

3.1.1. S-Curve Fizikal

3.1.2. Stastitik Pekerja

3.2. Kemajuan Kerja Terperinci

3.2.1. Maklumat Aktiviti Kritikal

3.2.2. Kerja Yang Disiapkan Bulan Ini

3.2.3. Kerja Yang Dijadualkan Bulan Hadapan

4. Prestasi Kewangan Kontrak -9

4.1. Ringkasan Prestasi Kewangan Kontrak

4.1.1. Maklumat Kewangan Kontrak

4.1.2. S-Curve Kewangan

5. Isu Berkenaan Kontrak - 13

6. Risiko dan Isu Kritikal - 13

7. Kesimpulan - 13

8. Lampiran - 14

A. Kemajuan Kerja Terperinci

B. Gambar Projek

C. Senarai Kelulusan Bahan


3|Page
1. RINGKASAN EKSEKUTIF

Projek adalah berkenaan KERJA-KERJA PENGGANTIAN SISTEM LIF DA


DUMBWAITER SERTA LAIN-LAIN KERJA YANG BERKAITAN DI HOSPITAL
SULTANAH NUR ZAHIRAH, TERENGGANU. Skop kerja yang terlibat termasuklah
menanggal semua peralatan lif dan meletakkan di satu kawasan yang diarahkan oleh pihak
pegawai penguasa. Seterusnya memesan peralatan lif baru dan memasang serta termasuk
mendapatkan kelulusan JKKP. Kerja lain berkaitan ialah pemasangan kabel elektrik dan
kerja bangunan berkaitan

Keutamaan pihak kami adalah projek yang akan dijalankan ini dapat disiapkan mengikut
jadual dengan kos yang telah ditetapkan serta mematuhi semua kehendak kontrak.

Tempoh asal bagi menyiapkan projek ini termasuk kerja-kerja lain berkaitan adalah selama
64 minggu dari tarikh pemilikan tapak namun projek ini telah medapat lanjutan masa no.1
yang berjumlah 72 hari yang disebabkan oleh total lockdown di china. Manakala tempoh
kecacatan atau jaminan adalah selama setahun dari tarikh serahan kepada pihak pelanggan.

Lif yang dibekalkan bagi projek ini adalah lif berjenama OTIS ELEVATOR yang
menggunakan model GeN2-MR & GeN2-LMR.

4|Page
2. MAKLUMAT PROJEK
TAJUK PROJEK KERJA-KERJA PENGGANTIAN LIF DAN
DUMBWAITER SERTA LAIN-LAIN KERJA
BERKAITAN DI HOSPITAL SULTANAH NUR
ZAHIRAH, KUALA TERENGGANU,
TERENGGANU

NO KONTRAK JKR / IP / CKM / 273 / 2021

PELANGGAN KEMENTERIAN KESIHATAN MALAYSIA

PEGAWAI PENGUASA PENGARAH JKR NEGERI TERENGGANU.

KETUA JURUTERA MEKANIKAL NEGERI


JKR CAWANGAN KEJURUTERAAN
WAKIL PENGAWAI PENGUASA MEKANIKAL NEGERI TERENGGANU
JALAN BUKIT KECIL,
21100 KUALA TERENGGANU

HARGA KONTRAK RM 4,810,842.00

TARIKH MILIK TAPAK 19 OCTOBER 2021

TEMPOH KONTRAK 64 MINGGU

LANJUTAN MASA NO.1 72 HARI

TARIKH SIAP KERJA ASAL 10 JANUARI 2023

TARIKH SIAP KERJA SEMASA 23 MAC 2023

TARIKH TAMAT TEMPOH


24 MAC 2024
KECACATAN

5|Page
2.2. CARTA ORGANISASI PROJEK

6|Page
2.2. CARTA ORGANISASI KONTRAKTOR & PEMBEKAL(OTIS)

DUTA JERNIH SDN BHD

7|Page
3. LAPORAN KEMAJUAN KERJA

3.1. RINGKASAN KEMAJUAN FIZIKAL

KEMAJUAN FIZIKAL BULAN SEBELUM KEMAJUAN FIZIKAL BULAN SEMASA


20/11/2022 20/12/2022
JADUAL SEBENAR VARIAN JADUAL SEBENAR VARIAN VARIAN SIAP
(%) (%) (%) (%) (%) (%) (HARI)

72 66 -6 79 70 -9 -40

Ini menunjukkan kemajuan fizikal pada bulan semasa mengikut jadual 79% dan kemajuan sebenar adalah
70% bersamaan 40 hari lewat.

Punca utama dan/atau sebab yang menyumbang kepada kelewatan / lebih awal dari jadual adalah:

SEBAB-SEBAB KELEWATAN / LEBIH TINDAKAN CATATAN


AWAL

1) Kerja-kerja pentaulihan
dumbwaiter belum selesai

2) Kerja-kerja pentaulihan lif lif 3


blok acc belum selesai.

3) Kerja-kerja fasa 2 belum


dimulakan

8|Page
3.1.1. S-CURVE FIZIKAL

9|Page
3.1.2. STATISTIK REKOD PEKERJA NOV

10 | P a g e
3.2. KEMAJUAN KERJA TERPERINCI

3.2.1 MAKLUMAT AKTIVITI KRITIKAL (CRITICAL TASK)

Terdapat aktiviti kritikal semasa didalam tempoh pelaporan. Maklumat terperinci adalah
seperti di Lampiran A.

3.2.2 MAKLUMAT AKTIVITI TERGELINCIR (SLIPPING TASK)

Terdapat aktiviti didapati tergelincir daripada jadual. Maklumat terperinci adalah seperti
di Lampiran A.

3.2.3 MAKLUMAT AKTIVITI TIDAK DIMULAKAN MENGIKUT


JADUAL (UNSTARTED TASK)

Tiada aktiviti yang sepatutnya telah bermula pada tarikh laporan tetapi masih belum
dimulakan. Maklumat terperinci adalah seperti di Lampiran A.

3.2.4 KERJA YANG DISIAPKAN BULAN SEBELUM

Terdapat aktiviti yang telah disiapkan dalam tempoh pelaporan. Maklumat terperinci
adalah seperti di Lampiran A.

3.2.5 KERJA YANG DIJADUALKAN BULAN INI

Kerja-kerja yang dijadualkan daripada tarikh laporan semasa sehingga tarikh laporan akan
datang adalah seperti di Lampiran A.

3.2.6 KERJA YANG TERGENDALA AKIBAT HUJAN/PUNCA LAIN

Terdapat kerja-kerja yang tergendala akibat Penularan wabak Covid-19. Maklumat terperinci
adalah seperti di Lampiran A.

11 | P a g e
4. PRESTASI KEWANGAN KONTRAK

4.1. RINGKASAN PRESTASI KEWANGAN KONTRAK


PRESTASI BULAN SEBELUM PRESTASI BULAN SEMASA
20/11/2022 20/12/2022

JADUAL SEBENAR VARIANS JADUAL SEBENAR VARIANS


(RM) (RM) (RM) (RM) (RM) (RM)

3,779,736.50 3,283,423.60 496,312.80 3,952,750.50 3,283,423.70 669,326.80


(79.30%) (68.89%) (10.41%) (82.93%) (68.89%) (14.04%)

• Pelaporan prestasi kewangan semasa tidak mengambil kira skop kerja penyelenggaraan selepas
DLP

12 | P a g e
4.1.1. MAKLUMAT KEWANGAN PROJEK

a) Anggaran Perbelanjaan Tahun Semasa (2022) : RM3,952,750.50

b) Kos Kontrak Semasa : RM 4,766,242.00

c) Bayaran Tahun Semasa : RM 3,283,423.70(68.89%)

d) Nilai kerja yang dilaksanakan hingga kini : RM 3,382,832.80

e) Unjuran kerja yang dilaksanakan hingga kini : 70.97 %

TUNTUTAN DIPERAKUKAN
NILAI TUNTUTAN TARIKH
NO TARIKH BAYARAN TERMASUK WJP
INTERIM (RM) DIPERAKUKAN
(RM)

1. 20 Feb 2022 No.1 Rm 36,348.60 28 Feb 2022 Rm 36,348.60

2. 26 Mac 2022 No.2 Rm 38,450.00 28 Mac 2022 Rm 38,450.00

3. 18 April 2022 No.3 Rm 30,050.00 28 April 2022 Rm 30,050.00

4. 20 May 2022 No.4 Rm 150,935.00 26 Mei 2022 Rm 150,935.00

5. 20 Jun 2022 No.5 Rm 70,434.00 25 Jun 2022 Rm 70,434.00

6. 20 Julai 2022 No.6 Rm 1,608,700.00 28 Julai 2022 Rm 1,608,700.00

7. 20 Ogos 2022 N0.7 Rm 681,727.00 28 Ogos 2022 Rm 681,727.00

8. 20 Sep 2022 No.8 Rm 284,103.50 28 Sep 2022 Rm 284,103.20

9. 20 Oct 2022 No.9 Rm 369,578.60 28 Oct 2022 Rm 369,578.00

10. 20 Nov 2022 No.10 Rm 13,096.50 27 Nov 2022 Rm 13,096.50

11

12

JUMLAH TERKUMPUL Rm 3,283,423.70

13 | P a g e
4.1.2. S – CURVE KEWANGAN

14 | P a g e
Scheduled Financial Curve (Value ) Table

Cost (RM) Cum. Cost (RM) Cum. Actual Cost (RM)


RM0.00 RM8,415.00 RM 0.00
Oct-21
RM461,768.00 RM470,183.00 RM 0.00
Nov-21
RM26,451.50 RM496,634.50 RM 0.00
Dec-21
RM17,641.50 RM514,276.00 RM36,348.00
Jan-22
RM20,970.00 RM546,347.50 RM 74,798.00
Feb-22
RM136,614.00 RM682,961.50 RM 104,848.00
Mar-22
RM65,341.00 RM748,302.50 RM 255,783.00
Apr-22
RM2,857,025.50 RM3,605,328.00 RM 326,217.00
May-22
-RM3,232,042.00 RM373,286.00 RM 1,934, 917.00
Jun-22
RM72,923.50 RM446,209.50 RM 2,616.644.00
Jul-22
RM82,455.00 RM528,664.50
Aug-22 RM 2,900,747.50
RM2,630,000.00 RM3,158,664.50 RM3,270,325.50
Sep-22
RM346,283.00 RM3,504,947.50
Oct-22 RM 3,383,423.70
RM274,789.00 RM3,779,736.50
Nov-22
RM173,014.00 RM3,952,750.50
Dec-22
RM121,062.00 RM4,073,812.50
Jan-23
RM432,552.00 RM4,506,364.50
Feb-23
RM259,877.50 RM4,766,242.00
Mac-23

*Nota:

1) Nilai cumulative cost adalah bedasarkan cut off pada tarikh 20 haribulan setiap
bulan.Manakala Bagi cumulative actual cost adalah bedasarkan kerja sebenar di tapak

15 | P a g e
5. ISU BERKAITAN KONTRAK
1) Skop kerja penyenggaraan lif-lif dan dumbwaoter sebelum penggantian yang dinyatakan pada
Schedule of Price 8.1.7 telah dikeluarkan daripada skop kontrak.

6. RISIKO DAN ISU KRITIKAL

1) Kelewatan penyediaan & lukisan kerja dan kelulusan bahan untuk kelulusan menyumbang
kepada kelewatan kemajuan di tapak.
2) Isu penularan jangkitan covid-19 di kalangan pekerja dan di tapak kawasan kerja akan
menjejaskan kemajuan di tapak.
3) Isu berkenaan ketinggian pintu dumbwaiter dari aras lantai di tingkat 3 menyumbang kepada
kelewatan pengunjian dumbwaiter dan pemeriksaan JKKP
4) Isu banjir menyebabkan pengerakan pekerja terjejas seterusnya menyebabkan kerja-kerja
tergendala.

7. KESIMPULAN
.Semasa laporan ini kerja – kerja telah bermula secara berperingkat serta dilaksanakan dengan
mematuhi segala peraturan yang telah ditetapkan. Pihak kami komited bagi memastikan projek ini siap dalam
tempoh yang ditetapkan.

16 | P a g e
LAMPIRAN A
KEMAJUAN KERJA TERPERINCI

17 | P a g e
1.0 Critical Task

Task Name Duration Start Finish % Complete


KERJA-KERJA PENGGANTIAN LIF DAN
DUMBWAITER SERTA LAIN-LAIN KERJA
BERKAITAN DI HOSPITAL SULTANAH NUR 460 days Tue 19/10/21 Fri 7/4/23 70%
ZAHIRAH, KUALA TERENGGANU,
TERENGGANU.
LIFT INSTALLATION PHASE 2 (4 LIFTS) 103 days Fri 18/11/22 Fri 17/3/23 27%
LIFT L8 MAIN BLOCK 87 days Fri 18/11/22 Mon 27/2/23 26%
LIFT INSTALLATION WORKS 44 days Mon 28/11/22 Tue 17/1/23 18%
Installation Works (Hoistway) 16 days Tue 6/12/22 Fri 23/12/22 41%
Hacking works for landing door openings 6 days Thu 8/12/22 Wed 14/12/22 83%
Installation Works (Motor Room) 29 days Mon 28/11/22 Fri 30/12/22 5%
Hacking works for I-beam and motor beam
1 day Thu 15/12/22 Thu 15/12/22 0%
opening
Construct New Plinth/Foundation/Base
2 days Fri 16/12/22 Sat 17/12/22 0%
Plate
Install Traction Motor Equipment and Wiring 3 days Mon 19/12/22 Wed 21/12/22 0%
Governors and Ropes 2 days Thu 22/12/22 Fri 23/12/22 0%
Controller and shaft information 2 days Sat 24/12/22 Mon 26/12/22 0%
Lift Switchboard c/w Lightning and Surge
1 day Tue 27/12/22 Tue 27/12/22 0%
Protectors
Cables, Wiring, Hot Dipped Galvanised
2 days Wed 28/12/22 Thu 29/12/22 0%
Trunking
Intercom System 1 day Fri 30/12/22 Fri 30/12/22 0%
Installation Works (Lift Pit) 4 days Sat 31/12/22 Wed 4/1/23 0%
New Cat Ladder 1 day Sat 31/12/22 Sat 31/12/22 0%
Car Buffer and Counter Weight Buffer 1 day Sat 31/12/22 Sat 31/12/22 0%
Installation Works (Lift Car & Lift Lobby) 14 days Mon 2/1/23 Tue 17/1/23 0%
Lift Car Assembling 3 days Mon 2/1/23 Wed 4/1/23 0%
Car Safety Gear 1 day Thu 5/1/23 Thu 5/1/23 0%
Install Landing Door Frame and Door 5 days Fri 6/1/23 Wed 11/1/23 0%
Hall Lantern (s), Position Indicators, Call
2 days Thu 12/1/23 Fri 13/1/23 0%
Buttons
Lift interior Finishes 2 days Sat 14/1/23 Mon 16/1/23 0%
Crash Bumper 1 day Tue 17/1/23 Tue 17/1/23 0%
TESTING, ADJUSTING, BALANCING &
35 days Wed 18/1/23 Mon 27/2/23 0%
COMMISSIONING
Complete Testing and Commisioning 14 days Wed 18/1/23 Thu 2/2/23 0%
JKKP Inspection 14 days Fri 3/2/23 Sat 18/2/23 0%
ELECTRICAL WORK 221 days Sat 9/7/22 Thu 23/3/23 66%
SISTEM CCTV 62 days Wed 11/1/23 Thu 23/3/23 29%
BLOK UTAMA (LIFT NO.1, 6, 7 DAN 8) 45 days Wed 11/1/23 Fri 3/3/23 40%
Kerja-kerja pemasangan CCTV termasuk
45 days Wed 11/1/23 Fri 3/3/23 40%
pendawaian
PUSAT RAWATAN HARIAN (LIFT NO.1, 2
17 days Sat 4/3/23 Thu 23/3/23 0%
DAN 3)
Kerja-kerja pemasangan CCTV termasuk
14 days Sat 4/3/23 Mon 20/3/23 0%
pendawaian

18 | P a g e
Kerja-kerja pengujian sistem CCTV lengkap
3 days Tue 21/3/23 Thu 23/3/23 0%
dengan laporan pengujian.
KERJA ELEKTRIK DISIAPKAN 0 days Thu 23/3/23 Thu 23/3/23 0%
OTHER GENERAL WORKS 106 days Tue 6/12/22 Fri 7/4/23 9%
SIGNAGES (To Supply & Install) 7 days Fri 24/3/23 Fri 31/3/23 0%
PMA plate number inside lift car using
Perspex/steel plate with a minimum thickness of 5 1 day Fri 24/3/23 Fri 24/3/23 0%
mm (Perspex)/ 2mm (steel plate).
BAHAYA, BILIK JENTERA, DILARANG
MASUK DENGAN TIADA KEBENARAN, secured on 1 day Sat 25/3/23 Sat 25/3/23 0%
the external side of the Lift Machine Room door,
JANGAN GUNAKAN LIF SEMASA
KECEMASAN, GUNAKAN TANGGA at every 1 day Mon 27/3/23 Mon 27/3/23 0%
landing,
DILARANG MEROKOK inside every lift car. 1 day Tue 28/3/23 Tue 28/3/23 0%
LIF BOMBA at every fireman's lift at ground
1 day Wed 29/3/23 Wed 29/3/23 0%
floor.
Electric shock first aid chart in the Lift Machine
1 day Thu 30/3/23 Thu 30/3/23 0%
Room.
Warning/hazard signage at any necessary
1 day Fri 31/3/23 Fri 31/3/23 0%
location
Remedial and Touch up works wherever
3 days Wed 5/4/23 Fri 7/4/23 0%
applicable

19 | P a g e
2.Slipping Task/Late Task
Task Name Duration Start Finish % Complete Schedule.
KERJA-KERJA PENGGANTIAN LIF DAN
DUMBWAITER SERTA LAIN-LAIN KERJA
447 Tue
BERKAITAN DI HOSPITAL SULTANAH NUR
days 19/10/21
Thu 23/3/23 70% 79%
ZAHIRAH, KUALA TERENGGANU,
TERENGGANU.
444 Tue
PRELIMINARIES Mon 20/3/23 96% 97%
days 19/10/21
444 Tue
RECURRING Mon 20/3/23 81% 82%
days 19/10/21
Comprehensive Service & Maintenance of 104 Sat Mon
0% 40%
Phase 1 ( Lift PL3 ACC, PL1 & PL6 Main Block) days 19/11/22 20/3/23
Comprehensive Service & Maintenance of
1 day Sat 19/11/22 Sat 19/11/22 0% 100%
Phase 1 ( Lift PL3 ACC, PL1 & PL6 Main Block) 1
PROCUREMENT (Material Approval/Shop 321 Tue Thu
98% 100%
Drawings) days 19/10/21 27/10/22
Rubber Mat 2 days Wed 24/8/22 Thu 25/8/22 99% 100%
Procurement Start 0 days Thu 25/8/22 Thu 25/8/22 0% 100%
ACSU Switchboard 6 days Wed 28/9/22 Tue 4/10/22 92% 100%
Approval of Shop Drawings 1 day Tue 4/10/22 Tue 4/10/22 50% 100%
Thu
Jamb Crash 6 days Fri 21/10/22 17% 100%
27/10/22
Approval of Supplier/Material 1 day Sat 22/10/22 Sat 22/10/22 0% 100%
Mon Tue
Preparation Shop Drawings 2 days 0% 100%
24/10/22 25/10/22
Wed Wed
Shop Drawing Submission for Approval 1 day 0% 100%
26/10/22 26/10/22
Approval of Shop Drawings 1 day Thu 27/10/22 Thu 27/10/22 0% 100%
Thu
Procurement Start 0 days Thu 27/10/22 0% 100%
27/10/22
LIFT INSTALLATION PHASE 1 (3 LIFTS & 1 251
Tue 8/2/22 Sat 26/11/22 88% 100%
DUMBWAITER) days
162
DUMBWAITER (MAIN BLOCK) Tue 8/2/22 Mon 15/8/22 75% 100%
days
41
DUMBWAITER INSTALLATION WORKS Tue 1/3/22 Sat 16/4/22 91% 100%
days
10
Machine Space Compartment Sat 12/3/22 Wed 23/3/22 83% 100%
days
To provide and install technical data
1 day Wed 23/3/22 Wed 23/3/22 0% 100%
nameplate
The provide machine space signage/
1 day Wed 23/3/22 Wed 23/3/22 0% 100%
notice
12
Lobby Thu 24/3/22 Wed 6/4/22 87% 100%
days
To provide floor signage at each landing
1 day Sat 2/4/22 Sat 2/4/22 0% 100%
lobby
To provide and install PMA plate number
1 day Sat 2/4/22 Sat 2/4/22 0% 100%
using Perspex
TESTING, ADJUSTING, BALANCING & 72
COMMISSIONING days
Mon 23/5/22 Sat 13/8/22 43% 100%
14
JKKP Inspection Thu 21/7/22 Fri 5/8/22 0% 100%
days
PMA Approval 7 days Sat 6/8/22 Sat 13/8/22 0% 100%
Open For Use 1 day Mon 15/8/22 Mon 15/8/22 0% 100%
20 | P a g e
150 Wed
LIFT L3 ACC BLOCK Thu 2/6/22 93% 100%
days 23/11/22
47 Thu
LIFT INSTALLATION WORKS Sat 20/8/22 98% 100%
days 13/10/22
41 Thu
Installation Works (Lift Car & Lift Lobby) Sat 27/8/22 94% 100%
days 13/10/22
Wed Wed
Crash Bumper 1 day 0% 100%
12/10/22 12/10/22
TESTING, ADJUSTING, BALANCING & 35 Wed
Fri 14/10/22 81% 100%
COMMISSIONING days 23/11/22
Wed Wed
PMA Approval 7 days
16/11/22 23/11/22
0% 100%
152
LIFT L1 MAIN BLOCK Thu 2/6/22 Fri 25/11/22 97% 100%
days
111 Mon
LIFT INSTALLATION WORKS Fri 10/6/22 99% 100%
days 17/10/22
15 Mon
Installation Works (Lift Car & Lift Lobby) Fri 30/9/22 96% 100%
days 17/10/22
Crash Bumper 1 day Sat 15/10/22 Sat 15/10/22 0% 100%
102
LIFT L6 MAIN BLOCK Thu 7/7/22 Wed 2/11/22 97% 100%
days
62
LIFT INSTALLATION WORKS Fri 29/7/22 Sat 8/10/22 99% 100%
days
15
Installation Works (Lift Car & Lift Lobby)
days
Wed 7/9/22 Fri 23/9/22 96% 100%
Crash Bumper 1 day Thu 22/9/22 Thu 22/9/22 0% 100%
TESTING, ADJUSTING, BALANCING & 35
Fri 23/9/22 Wed 2/11/22 91% 100%
COMMISSIONING days
Wed
PMA Approval 7 days Wed 2/11/22 50% 100%
26/10/22
LIFT L6 MAIN BLOCK COMPLETED 0 days Wed 2/11/22 Wed 2/11/22 0% 100%
51
OTHER WORKS FOR PHASE 1 Thu 15/9/22 Sat 12/11/22 51% 100%
days
Miscellanesous Works in Motor Room L1 & 31 Thu
Thu 15/9/22 91% 100%
L6 days 20/10/22
To construct kerb and to be painted with
1 day Fri 23/9/22 Fri 23/9/22 0% 100%
black and yellow stripes
To provide rubber mat of suitable size and
Tue
thickness to be placed on the floor in front of every 1 day Tue 18/10/22 0% 100%
18/10/22
switchboad
Wed
Air Conditioning Installation 5 days Fri 14/10/22 52% 100%
19/10/22
To supply and install two (2) nos. of ceiling
Mon
mounted/suspended ACSU (inverter type and min. 2 days Sat 15/10/22 80% 100%
17/10/22
18,000 Btu/hr each)
To supply and install new ACSU Tue
1 day Tue 18/10/22 0% 100%
Switchboard 18/10/22
Testing and commissioning of the complete Wed Wed
1 day 0% 100%
ACSU system 19/10/22 19/10/22
Wed
SIGNAGES 4 days Sat 29/10/22 0% 100%
26/10/22
To label all lift equipment in the machine Wed Wed
1 day 0% 100%
room using Perspex 26/10/22 26/10/22
To provide and install technical data Thu
1 day Thu 27/10/22 0% 100%
nameplate for L3 ACC, Lift 1 and Lift 6 Main Block 27/10/22
To provide floor signage at each landing
1 day Fri 28/10/22 Fri 28/10/22 0% 100%
lobby FOR Lift L3 ACC, L1 & L6 Main Blokc

21 | P a g e
To supply and install lift label for L3 ACC, Lift
1 day Sat 29/10/22 Sat 29/10/22 0% 100%
L1 & L6 Main Block at all floors
14
JAMB CRASH INSTALLATION Fri 28/10/22 Sat 12/11/22 0% 100%
days
Install jamb crash/high impact protection for
6 days Fri 28/10/22 Thu 3/11/22 0% 100%
Lift 1
Install jamb crash/high impact protection for Thu
6 days Fri 4/11/22 0% 100%
Lift 6 10/11/22
Install jamb crash/high impact protection for
2 days Fri 11/11/22 Sat 12/11/22 0% 100%
Lift 3 ACC Block
103
LIFT INSTALLATION PHASE 2 (4 LIFTS)
days
Fri 18/11/22 Fri 17/3/23 4% 32%
87
LIFT L7 MAIN BLOCK Fri 18/11/22 Mon 27/2/23 0% 42%
days
18
DISMANTLING WORKS Fri 18/11/22 Thu 8/12/22 0% 100%
days
Notify User to start work 7 days Fri 18/11/22 Fri 25/11/22 0% 100%
87
LIFT L8 MAIN BLOCK Fri 18/11/22 Mon 27/2/23 0% 42%
days
18
DISMANTLING WORKS Fri 18/11/22 Thu 8/12/22 0% 100%
days
Notify User to start work 7 days Fri 18/11/22 Fri 25/11/22 0% 100%
190
ELECTRICAL WORK Sat 9/7/22 Wed 15/2/23 55% 54%
days
47
KERJA-KERJA PERMULAAN
days
Sat 9/7/22 Thu 1/9/22 91% 100%
Kerja-Kerja mengetuk/ menebuk slab, siling ,
3 days Tue 26/7/22 Thu 28/7/22 50% 100%
tiang, dinding untuk pendawaian dan memperelok
Menyediakan laporan kemajuan bergambar
7 days Fri 29/7/22 Fri 5/8/22 50% 100%
sebelum, semasa dan selepas kerja dilaksanakan
56 Tue
KERJA-KERJA PENDAWAIAN Mon 19/9/22 50% 100%
days 22/11/22
BLOK UTAMA (BILIK MOTOR LIF 7 DAN 28 Tue
Fri 21/10/22 0% 100%
LIF 8) days 22/11/22
Mata lampu I/d suis kutub tunggal terlitup 14
Fri 21/10/22 Sat 5/11/22 0% 100%
logam 10A days
Mon
Mata lampu kecemasan (tanpa suis) 7 days Mon 7/11/22 0% 100%
14/11/22
Mata soket alur keluar berkembar I/d soket Tue
7 days Tue 15/11/22 0% 100%
13A 3 pin terlitup logam 22/11/22

22 | P a g e
3. Kerja yang Disiapkan Bulan Sebelum
Task Name Duration Start Finish % Complete Schedule.
KERJA-KERJA PENGGANTIAN LIF DAN
DUMBWAITER SERTA LAIN-LAIN KERJA Tue
447 days Thu 23/3/23 70% 79%
BERKAITAN DI HOSPITAL SULTANAH NUR 19/10/21
ZAHIRAH, KUALA TERENGGANU, TERENGGANU.
Tue
PRELIMINARIES 444 days Mon 20/3/23 96% 97%
19/10/21
Tue
RECURRING 444 days
19/10/21
Mon 20/3/23 81% 82%
Tue Mon
Work Program 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Updating Work Program 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Contractor Management Cost 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Contractor Management Cost 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Site Meetings 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Site Meetings 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Montly Progress Report 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Montly Progress Report 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Site Diary 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Site Diary 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Full Time Site Supervisor 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Full Time Site Supervisor 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Site Safety Supervisor 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Site Safety Supervisor 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Safety Report 444 days 83% 83%
19/10/21 20/3/23
Mon Mon
Safety Report 15 1 day 100% 100%
19/12/22 19/12/22
Tue Mon
Safety in The Workplace - To Comply with SOP 444 days 83% 83%
19/10/21 20/3/23
Safety in The Workplace - To Comply with SOP Mon Mon
1 day 100% 100%
15 19/12/22 19/12/22
Comprehensive Service & Maintenance of Phase Sat Mon
104 days 0% 40%
1 ( Lift PL3 ACC, PL1 & PL6 Main Block) 19/11/22 20/3/23

23 | P a g e
Comprehensive Service & Maintenance of Phase Mon Mon
1 day 0% 100%
1 ( Lift PL3 ACC, PL1 & PL6 Main Block) 2 19/12/22 19/12/22
LIFT INSTALLATION PHASE 1 (3 LIFTS & 1
251 days Tue 8/2/22 Sat 26/11/22 88% 100%
DUMBWAITER)
Wed
LIFT L3 ACC BLOCK 150 days Thu 2/6/22 93% 100%
23/11/22
TESTING, ADJUSTING, BALANCING & Wed
35 days Fri 14/10/22 81% 100%
COMMISSIONING 23/11/22
Wed Wed
PMA Approval 7 days 0% 100%
16/11/22 23/11/22
Wed Wed
LIFT L3 ACC BLOCK COMPLETED 0 days 0% 100%
23/11/22 23/11/22
LIFT L1 MAIN BLOCK 152 days Thu 2/6/22 Fri 25/11/22 97% 100%
TESTING, ADJUSTING, BALANCING & Mon
COMMISSIONING
35 days
17/10/22
Fri 25/11/22 91% 100%
PMA Approval 7 days Fri 18/11/22 Fri 25/11/22 50% 100%
LIFT L1 MAIN BLOCK COMPLETED 0 days Fri 25/11/22 Fri 25/11/22 0% 100%
OPEN FOR USE FOR PHASE 1 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
PHASE 1 INSTALLATION COMPLETED 0 days Sat 26/11/22 Sat 26/11/22 0% 100%
LIFT INSTALLATION PHASE 2 (4 LIFTS) 103 days Fri 18/11/22 Fri 17/3/23 4% 32%
LIFT L7 MAIN BLOCK 87 days Fri 18/11/22 Mon 27/2/23 0% 42%
DISMANTLING WORKS 18 days Fri 18/11/22 Thu 8/12/22 0% 100%
Notify User to start work 7 days Fri 18/11/22 Fri 25/11/22 0% 100%
Mon
Provide safety barricade at the landing doors 2 days Sat 26/11/22 0% 100%
28/11/22
To provide laminated A3 sized warning signs
1 day Sat 26/11/22 Sat 26/11/22 0% 100%
and notices
To provide a waste container 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Tue Tue
Termination Power Supply 1 day
29/11/22 29/11/22
0% 100%
Tue Wed
Dismantle Equipment in Machine Room 2 days 0% 100%
29/11/22 30/11/22
Dismantle Lift Car and Accessories 1 day Thu 1/12/22 Thu 1/12/22 0% 100%
Dismantle Landing Doors and Frame &
2 days Fri 2/12/22 Sat 3/12/22 0% 100%
Accessories
Dismantle Guide Rails, Ropes, Buffers &
1 day Mon 5/12/22 Mon 5/12/22 0% 100%
Counterweights
Demolish Existing Plinth (LMR) 1 day Thu 8/12/22 Thu 8/12/22 0% 100%
Dismantle and cart away electrical fittings inc.
1 day Mon 5/12/22 Mon 5/12/22 0% 100%
wiring
Store all the Lift Equipment 2 days Tue 6/12/22 Wed 7/12/22 0% 100%
Mon
LIFT INSTALLATION WORKS 44 days Tue 17/1/23 0% 45%
28/11/22
Installation Works (Hoistway) 16 days Tue 6/12/22 Fri 23/12/22 0% 91%
Check Shaft Before Installation Works 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Scaffolding Erection 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Erection of Templates 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Plumb set out works 1 day Wed 7/12/22 Wed 7/12/22 0% 100%
Supply & Install additional structural support
14 days Thu 8/12/22 Fri 23/12/22 0% 79%
(c-channel & bend channel)
Wed
Hacking works for landing door openings 6 days Thu 8/12/22 0% 100%
14/12/22

24 | P a g e
Thu
Install Guide Rail Bracket and Guide Rail 3 days Sat 17/12/22 0% 100%
15/12/22
Thu Thu
Traveling Cable c/w accessories 1 day 0% 100%
15/12/22 15/12/22
Thu
Counterweight Frame and Counterweight 2 days Fri 16/12/22 0% 100%
15/12/22
Thu
Traction Ropes 2 days Fri 16/12/22 0% 100%
15/12/22
Mon
Install new wiring and lighting 2 days Sat 17/12/22 0% 100%
19/12/22
Mon
Installation Works (Motor Room) 29 days
28/11/22
Fri 30/12/22 0% 30%
Mon Mon
Provide two (2) nos of fire extinguishers 1 day 0% 100%
28/11/22 28/11/22
Hacking works for I-beam and motor beam Thu Thu
1 day 0% 100%
opening 15/12/22 15/12/22
Construct New Plinth/Foundation/Base Plate 2 days Fri 16/12/22 Sat 17/12/22 0% 100%
Mon Wed
Install Traction Motor Equipment and Wiring 3 days 0% 67%
19/12/22 21/12/22
LIFT L8 MAIN BLOCK 87 days Fri 18/11/22 Mon 27/2/23 0% 42%
DISMANTLING WORKS 18 days Fri 18/11/22 Thu 8/12/22 0% 100%
Notify User to start work 7 days Fri 18/11/22 Fri 25/11/22 0% 100%
Mon
Provide safety barricade at the landing doors 2 days Sat 26/11/22 0% 100%
28/11/22
To provide laminated A3 sized warning signs
1 day Sat 26/11/22 Sat 26/11/22 0% 100%
and notices
To provide a waste container 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Tue Tue
Termination Power Supply 1 day 0% 100%
29/11/22 29/11/22
Tue Wed
Dismantle Equipment in Machine Room 2 days
29/11/22 30/11/22
0% 100%
Dismantle Lift Car and Accessories 1 day Thu 1/12/22 Thu 1/12/22 0% 100%
Dismantle Landing Doors and Frame &
2 days Fri 2/12/22 Sat 3/12/22 0% 100%
Accessories
Dismantle Guide Rails, Ropes, Buffers &
1 day Mon 5/12/22 Mon 5/12/22 0% 100%
Counterweights
Demolish Existing Plinth (LMR) 1 day Thu 8/12/22 Thu 8/12/22 0% 100%
Dismantle and cart away electrical fittings inc.
1 day Mon 5/12/22 Mon 5/12/22 0% 100%
wiring
Store all the Lift Equipment 2 days Tue 6/12/22 Wed 7/12/22 0% 100%
Mon
LIFT INSTALLATION WORKS 44 days Tue 17/1/23 0% 45%
28/11/22
Installation Works (Hoistway) 16 days Tue 6/12/22 Fri 23/12/22 0% 91%
Check Shaft Before Installation Works 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Scaffolding Erection 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Erection of Templates 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Plumb set out works 1 day Wed 7/12/22 Wed 7/12/22 0% 100%
Supply & Install additional structural support
14 days Thu 8/12/22 Fri 23/12/22 0% 79%
(c-channel & bend channel)
Wed
Hacking works for landing door openings 6 days Thu 8/12/22 0% 100%
14/12/22
Thu
Install Guide Rail Bracket and Guide Rail 3 days Sat 17/12/22 0% 100%
15/12/22
Thu Thu
Traveling Cable c/w accessories 1 day 0% 100%
15/12/22 15/12/22
25 | P a g e
Thu
Counterweight Frame and Counterweight 2 days Fri 16/12/22 0% 100%
15/12/22
Thu
Traction Ropes 2 days Fri 16/12/22 0% 100%
15/12/22
Mon
Install new wiring and lighting 2 days Sat 17/12/22 0% 100%
19/12/22
Mon
Installation Works (Motor Room) 29 days Fri 30/12/22 0% 30%
28/11/22
Mon Mon
Provide two (2) nos of fire extinguishers 1 day 0% 100%
28/11/22 28/11/22
Hacking works for I-beam and motor beam Thu Thu
opening
1 day
15/12/22 15/12/22
0% 100%
Construct New Plinth/Foundation/Base Plate 2 days Fri 16/12/22 Sat 17/12/22 0% 100%
Mon Wed
Install Traction Motor Equipment and Wiring 3 days 0% 67%
19/12/22 21/12/22
LIFT L1 ACC BLOCK 95 days Sat 26/11/22 Thu 16/3/23 18% 20%
LIFT INSTALLATION WORKS 86 days Sat 26/11/22 Mon 6/3/23 0% 31%
Installation Works (Hoistway) 12 days Sat 26/11/22 Fri 9/12/22 0% 100%
Check Shaft Before Installation Works 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Scaffolding Erection 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Erection of Templates 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Mon Mon
Plumb set out works 1 day 0% 100%
28/11/22 28/11/22
Tue
Hacking works for landing door openings 6 days Mon 5/12/22 0% 100%
29/11/22
Install Guide Rail Bracket and Guide Rail 3 days Tue 6/12/22 Thu 8/12/22 0% 100%
Traveling Cable c/w accessories 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
Counterweight Frame and Counterweight 2 days Tue 6/12/22 Wed 7/12/22 0% 100%
Traction Ropes 2 days Tue 6/12/22 Wed 7/12/22 0% 100%
Install new wiring and lighting 2 days Thu 8/12/22 Fri 9/12/22 0% 100%
LIFT L2 ACC BLOCK 95 days Sat 26/11/22 Thu 16/3/23 0% 18%
LIFT INSTALLATION WORKS 91 days Sat 26/11/22 Sat 11/3/23 0% 27%
Installation Works (Hoistway) 8 days Sat 26/11/22 Mon 5/12/22 0% 100%
Check Shaft Before Installation Works 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Scaffolding Erection 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Erection of Templates 1 day Sat 26/11/22 Sat 26/11/22 0% 100%
Mon Mon
Plumb set out works 1 day 0% 100%
28/11/22 28/11/22
Tue Wed
Hacking works for landing door openings 2 days 0% 100%
29/11/22 30/11/22
Install Guide Rail Bracket and Guide Rail 3 days Thu 1/12/22 Sat 3/12/22 0% 100%
Traveling Cable c/w accessories 1 day Thu 1/12/22 Thu 1/12/22 0% 100%
Counterweight Frame and Counterweight 2 days Thu 1/12/22 Fri 2/12/22 0% 100%
Traction Ropes 2 days Thu 1/12/22 Fri 2/12/22 0% 100%
Install new wiring and lighting 2 days Sat 3/12/22 Mon 5/12/22 0% 100%
Installation Works (Motor Room) 72 days Thu 1/12/22 Wed 22/2/23 0% 5%
Hacking works for I-beam and motor beam
1 day Thu 1/12/22 Thu 1/12/22 0% 100%
opening
Tue
OTHER WORKS FOR L1 ACC & L2 ACC BLOCK 94 days Fri 17/3/23 0% 81%
29/11/22
Tue Wed
Miscellanesous Works in Motor Room 14 days 0% 100%
29/11/22 14/12/22

26 | P a g e
To dismantle and cart away existing wall Tue Tue
1 day 0% 100%
mounted exhaust fan 29/11/22 29/11/22
To seal off unnecessary openings in the Tue Wed
2 days 0% 100%
machine room 29/11/22 30/11/22
To dismantle and cart away existing lift machine
1 day Thu 1/12/22 Thu 1/12/22 0% 100%
room door
To supply and install new fire rated doors 1 day Thu 1/12/22 Thu 1/12/22 0% 100%
To construct kerb and to be painted with black
1 day Thu 1/12/22 Thu 1/12/22 0% 100%
and yellow stripes
To supply and install two (2) nos. 13 amp
1 day Thu 1/12/22 Thu 1/12/22 0% 100%
socket complete
To paint existing trap door with black and yellow
stripes
1 day Thu 1/12/22 Thu 1/12/22 0% 100%
Make good to any damages done during
3 days Thu 1/12/22 Sat 3/12/22 0% 100%
installation works
Painting of the machine room inclusive of walls,
6 days Mon 5/12/22 Sat 10/12/22 0% 100%
door, roof slab, etc.
Non slip epoxy paint glossy finish for the entire Mon Wed
3 days 0% 100%
machine room floor slab 12/12/22 14/12/22
Mon Mon
To provide rubber mat for Lift L1 and Lift L2 1 day 0% 100%
12/12/22 12/12/22
Tue Tue
SIGNAGES 1 day 0% 100%
13/12/22 13/12/22
To label all lift equipment in the machine room Tue Tue
using Perspex
1 day
13/12/22 13/12/22
0% 100%
To provide and install technical data nameplate Tue Tue
1 day 0% 100%
for L1 and L2 13/12/22 13/12/22
To provide floor signage at each landing lobby Tue Tue
1 day 0% 100%
for L1 & L2 13/12/22 13/12/22
To supply and install lift label for Lift L1 & L2 at Tue Tue
1 day 0% 100%
all floors 13/12/22 13/12/22
ELECTRICAL WORK 190 days Sat 9/7/22 Wed 15/2/23 55% 54%
Tue
KERJA-KERJA PENDAWAIAN 56 days Mon 19/9/22 50% 100%
22/11/22
Tue
BLOK UTAMA (BILIK MOTOR LIF 7 DAN LIF 8) 28 days Fri 21/10/22 0% 100%
22/11/22
Mata soket alur keluar berkembar I/d soket 13A Tue Tue
7 days 0% 100%
3 pin terlitup logam 15/11/22 22/11/22
Wed
KERJA-KERJA MEMBEKAL DAN MEMASANG 42 days Tue 10/1/23 87% 57%
23/11/22
Wed
BLOK UTAMA (BILIK MOTOR LIF 1 DAN LIF 6) 22 days Sat 17/12/22 100% 100%
23/11/22
Papan Suis Kecil lekapan dinding bukaan Wed
9 days Fri 2/12/22 100% 100%
depan I/d eksesori 23/11/22
Papan Agihan (DB) 'L&P' 6 hala 40Amp TPN
Tue
terlitup logam I/d MCB, SPN PLAB, busbar dan sistem 9 days Sat 3/12/22 100% 100%
13/12/22
pembumian secukupnya
Lampu Flourecent LED (1x20W) di bilik Motor Wed Wed
1 day 100% 100%
Lift 14/12/22 14/12/22
Thu Thu
Lampu Decorative LED Di pintu Lobi Lif 1 day 100% 100%
15/12/22 15/12/22
Downlight Rises 18W LED Di Lobi Lif 1 day Fri 16/12/22 Fri 16/12/22 100% 100%
Lengkapan lampu kecemasan jenis LED dan
1 day Sat 17/12/22 Sat 17/12/22 100% 100%
permukaan berkapasiti 3 jam
Mon
BLOK UTAMA (BILIK MOTOR LIF 7 DAN LIF 8) 20 days Tue 10/1/23 72% 10%
19/12/22

27 | P a g e
Papan Suis Kecil lekapan dinding bukaan Mon Wed
9 days 80% 22%
depan I/d eksesori 19/12/22 28/12/22
OTHER GENERAL WORKS 75 days Tue 6/12/22 Thu 2/3/23 0% 9%
Renewal of Fire Extingushiers 1 day Tue 6/12/22 Tue 6/12/22 0% 100%
PRE HANDING OVER 90 days Mon 5/12/22 Sat 18/3/23 0% 25%
Remove all Safety Barricades, Warning Signages,
1 day Mon 5/12/22 Mon 5/12/22 0% 100%
etc.

28 | P a g e
4. Kerja yang Dijadual Bulan Ini
Task Name Duration Start Finish % Complete
KERJA-KERJA PENGGANTIAN LIF DAN DUMBWAITER
SERTA LAIN-LAIN KERJA BERKAITAN DI HOSPITAL
447 days Tue 19/10/21 Thu 23/3/23 70%
SULTANAH NUR ZAHIRAH, KUALA TERENGGANU,
TERENGGANU.
PRELIMINARIES 444 days Tue 19/10/21 Mon 20/3/23 96%
RECURRING 444 days Tue 19/10/21 Mon 20/3/23 81%
Work Program 444 days Tue 19/10/21 Mon 20/3/23 83%
Updating Work Program 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Contractor Management Cost 444 days Tue 19/10/21 Mon 20/3/23 83%
Contractor Management Cost 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Site Meetings 444 days Tue 19/10/21 Mon 20/3/23 83%
Site Meetings 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Montly Progress Report 444 days Tue 19/10/21 Mon 20/3/23 83%
Montly Progress Report 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Site Diary 444 days Tue 19/10/21 Mon 20/3/23 83%
Site Diary 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Full Time Site Supervisor 444 days Tue 19/10/21 Mon 20/3/23 83%
Full Time Site Supervisor 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Site Safety Supervisor 444 days Tue 19/10/21 Mon 20/3/23 83%
Site Safety Supervisor 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Safety Report 444 days Tue 19/10/21 Mon 20/3/23 83%
Safety Report 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Safety in The Workplace - To Comply with SOP 444 days Tue 19/10/21 Mon 20/3/23 83%
Safety in The Workplace - To Comply with SOP 16 1 day Thu 19/1/23 Thu 19/1/23 0%
Comprehensive Service & Maintenance of Phase 1 (
104 days Sat 19/11/22 Mon 20/3/23 0%
Lift PL3 ACC, PL1 & PL6 Main Block)
Comprehensive Service & Maintenance of Phase 1 (
1 day Thu 19/1/23 Thu 19/1/23 0%
Lift PL3 ACC, PL1 & PL6 Main Block) 3
LIFT INSTALLATION PHASE 2 (4 LIFTS) 103 days Fri 18/11/22 4%
Fri 17/3/23
LIFT L7 MAIN BLOCK 87 days Fri 18/11/22 Mon 27/2/23 0%
LIFT INSTALLATION WORKS 44 days Mon 28/11/22 Tue 17/1/23 0%
Installation Works (Hoistway) 16 days Tue 6/12/22 Fri 23/12/22 0%
Supply & Install additional structural support (c-
14 days Thu 8/12/22 Fri 23/12/22 0%
channel & bend channel)
Installation Works (Motor Room) 29 days Mon 28/11/22 Fri 30/12/22 0%
Install Traction Motor Equipment and Wiring 3 days Mon 19/12/22 Wed 21/12/22 0%
Governors and Ropes 2 days Thu 22/12/22 Fri 23/12/22 0%
Controller and shaft information 2 days Sat 24/12/22 Mon 26/12/22 0%
Lift Switchboard c/w Lightning and Surge
1 day Tue 27/12/22 Tue 27/12/22 0%
Protectors
Cables, Wiring, Hot Dipped Galvanised Trunking 2 days Wed 28/12/22 Thu 29/12/22 0%
Intercom System 1 day Fri 30/12/22 Fri 30/12/22 0%
Batteries with Trickle Charges 1 day Sat 24/12/22 Sat 24/12/22 0%
Automatic Rescue Device 1 day Sat 24/12/22 Sat 24/12/22 0%
Emegency Battery Operated Power Supply
1 day Sat 24/12/22 Sat 24/12/22 0%
(EBOPS)
Unintended Car Movement Protection (UCMP) 1 day Sat 24/12/22 Sat 24/12/22 0%
29 | P a g e
Ascending Car Overspeed Protection (ACOP) 1 day Sat 24/12/22 0%
Sat 24/12/22
Installation Works (Lift Pit) 4 days Sat 31/12/22 Wed 4/1/23 0%
New Cat Ladder 1 day Sat 31/12/22 Sat 31/12/22 0%
Car Buffer and Counter Weight Buffer 1 day Sat 31/12/22 Sat 31/12/22 0%
New wiring, socket outlet and lighing inside the lift
1 day Mon 2/1/23 Mon 2/1/23 0%
pit
Clean up the lift walls and floor 1 day Tue 3/1/23 Tue 3/1/23 0%
Epoxy paint glossy finish for the lift pit floor slab
and wall
1 day Wed 4/1/23 Wed 4/1/23 0%
Installation Works (Lift Car & Lift Lobby) 14 days Mon 2/1/23 Tue 17/1/23 0%
Lift Car Assembling 3 days Mon 2/1/23 Wed 4/1/23 0%
Car Safety Gear 1 day Thu 5/1/23 Thu 5/1/23 0%
Car Door Locking Device 1 day Thu 5/1/23 Thu 5/1/23 0%
COP for the diabled 1 day Thu 5/1/23 Thu 5/1/23 0%
Install Landing Door Frame and Door 5 days Fri 6/1/23 Wed 11/1/23 0%
Hall Lantern (s), Position Indicators, Call Buttons 2 days Thu 12/1/23 Fri 13/1/23 0%
Lift interior Finishes 2 days Sat 14/1/23 Mon 16/1/23 0%
Handrail at side and rear lift enclosure 1 day Sat 14/1/23 Sat 14/1/23 0%
Crash Bumper 1 day Tue 17/1/23 Tue 17/1/23 0%
Voice Synthesizer 1 day Mon 16/1/23 Mon 16/1/23 0%
To provide slope at each landing door 3 days Thu 12/1/23 Sat 14/1/23 0%
Make good to any damages done during
3 days Thu 12/1/23 Sat 14/1/23 0%
installation works
TESTING, ADJUSTING, BALANCING &
35 days Wed 18/1/23 Mon 27/2/23 0%
COMMISSIONING
Complete Testing and Commisioning 14 days Wed 18/1/23 0%
Thu 2/2/23
Reprogramming and interfacing for system 1 day Wed 18/1/23 Wed 18/1/23 0%
Intergration with existing system, firefighting etc 1 day Wed 18/1/23 Wed 18/1/23 0%
LIFT L8 MAIN BLOCK 87 days Fri 18/11/22 Mon 27/2/23 0%
LIFT INSTALLATION WORKS 44 days Mon 28/11/22 Tue 17/1/23 0%
Installation Works (Hoistway) 16 days Tue 6/12/22 Fri 23/12/22 0%
Supply & Install additional structural support (c-
14 days Thu 8/12/22 Fri 23/12/22 0%
channel & bend channel)
Installation Works (Motor Room) 29 days Mon 28/11/22 Fri 30/12/22 0%
Install Traction Motor Equipment and Wiring 3 days Mon 19/12/22 Wed 21/12/22 0%
Governors and Ropes 2 days Thu 22/12/22 Fri 23/12/22 0%
Controller and shaft information 2 days Sat 24/12/22 Mon 26/12/22 0%
Lift Switchboard c/w Lightning and Surge
1 day Tue 27/12/22 Tue 27/12/22 0%
Protectors
Cables, Wiring, Hot Dipped Galvanised Trunking 2 days Wed 28/12/22 Thu 29/12/22 0%
Intercom System 1 day Fri 30/12/22 Fri 30/12/22 0%
Batteries with Trickle Charges 1 day Sat 24/12/22 Sat 24/12/22 0%
Automatic Rescue Device 1 day Sat 24/12/22 Sat 24/12/22 0%
Emegency Battery Operated Power Supply
(EBOPS)
1 day Sat 24/12/22 Sat 24/12/22 0%
Unintended Car Movement Protection (UCMP) 1 day Sat 24/12/22 0%
Sat 24/12/22
Ascending Car Overspeed Protection (ACOP) 1 day Sat 24/12/22 0%
Sat 24/12/22
Installation Works (Lift Pit) 4 days Sat 31/12/22 Wed 4/1/23 0%
New Cat Ladder 1 day Sat 31/12/22 Sat 31/12/22 0%
Car Buffer and Counter Weight Buffer 1 day Sat 31/12/22 Sat 31/12/22 0%
30 | P a g e
New wiring, socket outlet and lighing inside the lift
1 day Mon 2/1/23 Mon 2/1/23 0%
pit
Clean up the lift walls and floor 1 day Tue 3/1/23 Tue 3/1/23 0%
Epoxy paint glossy finish for the lift pit floor slab
1 day Wed 4/1/23 Wed 4/1/23 0%
and wall
Installation Works (Lift Car & Lift Lobby) 14 days Mon 2/1/23 Tue 17/1/23 0%
Lift Car Assembling 3 days Mon 2/1/23 Wed 4/1/23 0%
Car Safety Gear 1 day Thu 5/1/23 Thu 5/1/23 0%
Car Door Locking Device 1 day Thu 5/1/23 Thu 5/1/23 0%
COP for the diabled 1 day Thu 5/1/23 Thu 5/1/23 0%
Install Landing Door Frame and Door 5 days Fri 6/1/23 Wed 11/1/23 0%
Hall Lantern (s), Position Indicators, Call Buttons 2 days Thu 12/1/23 Fri 13/1/23 0%
Lift interior Finishes 2 days Sat 14/1/23 Mon 16/1/23 0%
Handrail at side and rear lift enclosure 1 day Sat 14/1/23 Sat 14/1/23 0%
Crash Bumper 1 day Tue 17/1/23 Tue 17/1/23 0%
Voice Synthesizer 1 day Mon 16/1/23 Mon 16/1/23 0%
To provide slope at each landing door 3 days Thu 12/1/23 Sat 14/1/23 0%
Make good to any damages done during
3 days Thu 12/1/23 Sat 14/1/23 0%
installation works
TESTING, ADJUSTING, BALANCING &
35 days Wed 18/1/23 Mon 27/2/23 0%
COMMISSIONING
Complete Testing and Commisioning 14 days Wed 18/1/23 0%
Thu 2/2/23
Reprogramming and interfacing for system 1 day Wed 18/1/23 Wed 18/1/23 0%
Intergration with existing system, firefighting etc 1 day Wed 18/1/23 Wed 18/1/23 0%
OTHER WORKS FOR LIFT 7 AND LIFT 8 33 days Wed 18/1/23 Fri 24/2/23 7%
Miscellanesous Works in Motor Room 15 days Wed 18/1/23 Fri 3/2/23 8%
To dismantle and cart away existing wall mounted
1 day Wed 18/1/23 Wed 18/1/23 100%
exhaust fan
To seal off unnecessary openings in the machine
4 days Wed 18/1/23 Sat 21/1/23 0%
room
LIFT L1 ACC BLOCK 95 days Sat 26/11/22 Thu 16/3/23 18%
DISMANTLING WORKS 18 days Wed 18/1/23 Tue 7/2/23 82%
Notify User to start work 7 days Wed 18/1/23 Wed 25/1/23 100%
LIFT INSTALLATION WORKS 86 days Sat 26/11/22 Mon 6/3/23 0%
LIFT L2 ACC BLOCK 95 days Sat 26/11/22 Thu 16/3/23 0%
DISMANTLING WORKS 18 days Wed 18/1/23 Tue 7/2/23 0%
Notify User to start work 7 days Wed 18/1/23 Wed 25/1/23 0%
LIFT INSTALLATION WORKS 91 days Sat 26/11/22 Sat 11/3/23 0%
Installation Works (Motor Room) 72 days Thu 1/12/22 Wed 22/2/23 0%
OTHER WORKS FOR L1 ACC & L2 ACC BLOCK 94 days Tue 29/11/22 Fri 17/3/23 0%
ELECTRICAL WORK 190 days Sat 9/7/22 Wed 15/2/23 55%
KERJA-KERJA MEMBEKAL DAN MEMASANG 42 days Wed 23/11/22 Tue 10/1/23 87%
BLOK UTAMA (BILIK MOTOR LIF 7 DAN LIF 8) 20 days Mon 19/12/22 Tue 10/1/23 72%
Papan Suis Kecil lekapan dinding bukaan depan I/d
9 days Mon 19/12/22 Wed 28/12/22 80%
eksesori
Papan Agihan (DB) 'L&P' 6 hala 40Amp TPN terlitup
logam I/d MCB, SPN PLAB, busbar dan sistem pembumian 9 days Thu 29/12/22 Sat 7/1/23 80%
secukupnya
Lampu Flourecent LED (1x20W) di bilik Motro Lift 1 day Mon 9/1/23 Mon 9/1/23 0%
Lengkapan lampu kecemasan jenis LED dan
1 day Tue 10/1/23 Tue 10/1/23 0%
permukaan berkapasiti 3 jam

31 | P a g e
SISTEM CCTV 31 days Wed 11/1/23 Wed 15/2/23 18%
BLOK UTAMA (LIFT NO.1, 6, 7 DAN 8) 14 days Wed 11/1/23 Thu 26/1/23 40%
Kerja-kerja pemasangan CCTV termasuk
14 days Wed 11/1/23 Thu 26/1/23 40%
pendawaian
KERJA-KERJA BERKAITAN 20 days Wed 11/1/23 Thu 2/2/23 0%
Lukisan terpasang pemasangan elektrik dan lain-lain 14 days Wed 11/1/23 Thu 26/1/23 0%
Kerja-kerja mengalih Papan Agihan Sediada dan
memasang semula
14 days Wed 11/1/23 Thu 26/1/23 0%
OTHER GENERAL WORKS 75 days Tue 6/12/22 Thu 2/3/23 0%
PRE HANDING OVER 90 days Mon 5/12/22 Sat 18/3/23 0%

32 | P a g e
LAMPIRAN B

GAMBAR-GAMBAR PROJEK BULAN SEMASA

33 | P a g e
KERJA-KERJA MODIFIKASI DUMBWAITER

34 | P a g e
KERJA-KERJA PEMASANGAN CCTV DOME CAMERA

35 | P a g e
KERJA-KERJA MENGECAT BILIK MOTOR LIF & PINTU KALIS API DI BILIK
MOTOR BLOK UTAMA

36 | P a g e
KERJA-KERJA MENGECAT CAT EPOXY DI LANTAI BILIK MOTOR LIF

37 | P a g e
KERJA-KERJA PEMASANGAN KEMASAN DALAMAN LIF

38 | P a g e
WIDE JAMB YANG TELAH SIAP DIPASANG

39 | P a g e
PEMASANGAN ATTIC LADDER

40 | P a g e
PEMERIKSAAN OLEH PEGAWAI JKKP

41 | P a g e
LAMPIRAN C

Senarai Kelulusan Bahan

42 | P a g e
SENARAI KELULUSAN BAHAN
NAMA PROJEK: KERJA-KERJA PENGGANTIAN LIF DAN DUMBWAITER SERTA LAIN-LAIN KERJA YANG BERKAITAN DI HOSPITAL SULTANAH NUR ZAHIRAH, KUALA TERENGGANU, TERENGGANU.

Tarikh kemaskini: 07/12/2022

Rev A Rev B Rev C Rev D


Bil. Bahan Jenama / Model / Jenis Bahan Pengedar Tarikh Lulus Ulasan Terkini SO
Hantar Ulasan Hantar Ulasan Hantar Ulasan Hantar Ulasan
ELECTRICAL
1 DOWNLIGHT RISES 18W LED (DJSB/HSNZ/EL-01) GOODLITE/DL 90226 HC BRIGHTLITE (M) 13/9/22 25/9/2022
2 FLOURECENT LAMP (DJSB/HSNZ/EL-02) GOODLITE/(GLC 140/91/6W) UNITED U-LI(M) 13/9/22 25/9/2022
3 GALVANISED STEEL CONDUIT.GI (DJSB/HSNZ/EL-03) SOUTHERN PIPE/(25MM,ORANGE) SOUHTERN PIPE (M) 13/9/22 25/9/2022
4 SWITCHES (DJSB/HSNZ/EL-04) SELAMAT/2K101(1,2 WAYS) MAY QUALITY (M) 13/9/22 25/9/2022
5 SWITCH SOCKET OUTLET 13A (DJSB/HSNZ/EL-05) SELAMAT/2K132(WEATHERPROOF) MEM INDUSTRIES (M) 13/9/22 25/9/2022
6 RUBBER MAT (DJSB/HSNZ/EL-06) GSE RUBBER/GS-SLG 6MM GSE RUBBER 13/9/22 25/9/2022
7 CCTV MONITOR (DJSB/HSNZ/EL-07) DELL/24' (1080) P2422H DELL (M) 13/9/22 25/9/2022
8 CCTV-RECORDER DVR (DJSB/HSNZ/EL-08) HIK VISION/DS-8100HQHI-K8 HIK VISION 13/9/22 25/9/2022
9 CCTV-DOME CAMERA (DJSB/HSNZ/EL-09) HIK VISION/DS-2CCD1123GOE-I(L) HIK VISION 13/9/22 25/9/2022
10 CCTV-POE SWITCH (DJSB/HSNZ/EL-10) HIK VISION/DS-3E031OP-EM HIK VISION 13/9/22 25/9/2022
11 ASCU SWITCHBOARD (DJSB/HSNZ/EL-11) JENGKAL SEMAJU SDN BHD JENGKAL SEMAJU 13/9/22 25/9/2022
LIFT SWITCHBOARD/SUB SWITCHBOARD/ ELECTRICAL
12 ELECOL SWITCHGEAR/LV SWITCHBOARD UOA SDN BHD 13/9/22 25/9/2022
SWITCHBOARD (DJSB/HSNZ/EL-12)
ALPHA AUTOMATION
13 MINIATURE CIRCUIT BREAKER (MCB) (DJSB/HSNZ/EL-13) CHINT/NB1-63 32A & 40A 13/9/22 25/9/2022
(M)
ALPHA AUTOMATION
14 MOULED CASE CIRCUIT BREAKER (MCCB) (DJSB/HSNZ/EL-014) CHINT/NM8N-400C 4POLES 13/9/22 25/9/2022
(M)
PEKAT PROTECTIVE
15 SURGER PROTECTIVE DEVICE (DJSB/HSNZ/EL-15) NOVARIS/SDI-40DIN/3X 13/9/22 25/9/2022
DEVICE (M)
16 SIGNAL CABLE CCTV (DJSB/HSNZ/EL-16) PROLINK/CAT6 PROLINK (M) 13/9/22 25/9/2022
MECHANICAL
1 ACSU CEILING MOUNTED (DJSB/HSNZ/MK-01) DAIKIN/CEILING MOUNTED/4HP DAIKIN (M) 13/9/22 20/9/2022

2 ACSU WALL MOUNTED (DJSB/HSNZ/MK-02) DAIKIN/WALL MOUNTED/2HP DAIKIN (M) 13/9/22 20/9/2022
ARCHITECTURE

1 Paint 20/9/2022

2 Epoxy Paint (DJSB/HSNZ/AK-02) JOTUN/JOTUN FLOOR 88(GREEN) JOTUN(M) SDN BHD 13/9/22 20/9/2022

4 Fire Rated Door (DJSB/HSNZ/AK-01) GAYADOOR/2HRS FIRE RATED ROOFSEAL 13/9/22 20/9/2022