SHOVEL

80% shovel availability


85% shovel utilisation
TRUCKS
330 Tonnes

CYCLE
15 Minutes CASE STUDY
Mining3 Shovel Optimisation:
SHOVEL LOADING Reduced cycle times
4 PASS: 3min 16sec (18min 16sec)
309 trucks/d * 330 tonnes/truck = 101,970 t

3 PASS: 2min 50sec (17min 50sec)


391 trucks/d * 330 tonnes/truck =
129,030 t
VALUE PROPOSITION
26,994t
DIFFERENCE (t)
3 VS. 4 PASS
*
3.5g
GRAMS PER
TONNE
*
0.03215
CONVERT TO
OUNCES
*
$1300
AUD PER
OUNCE
= $3.9m
GAIN PER DAY

Difference between 3 and 4 pass loading tonnes


GOLD 16:32
COMMODITY OPERATING HRS
PER DAY