Research Work Plan for Water Testing

This research work plan outlines a study to test the amount of grease in water over the course of one month. It involves gaining approval from an adviser, preparing research tools, conducting water testing over 14 days to determine grease levels, analyzing the results over 2 days, writing a summary and conclusions in 1 day, editing and providing a presentation and feedback that will last 3 days to discuss findings with school administrators. The timeline is designed to be completed within 1 month.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views1 page

Research Work Plan for Water Testing

This research work plan outlines a study to test the amount of grease in water over the course of one month. It involves gaining approval from an adviser, preparing research tools, conducting water testing over 14 days to determine grease levels, analyzing the results over 2 days, writing a summary and conclusions in 1 day, editing and providing a presentation and feedback that will last 3 days to discuss findings with school administrators. The timeline is designed to be completed within 1 month.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Research Work Plan

Title of Research:

Proponent:

Activities Timeline

1 Written approval and 1 day


recommendation from the research
adviser.
2 Preparation of the venue and 1 day
research tools we’ll be using for the
study.

3 The researchers will begin the 14 days


research process.
4 Water testing to determine the 7 days
amount of grease in water.
5 Tallying of results 1 day
6 Analysis and interpretation of Data 2 days
7 Writing of the summary, 1 day
conclusions, and recommendations.
8 Editing and proof reading 1 day
9 Presentation and Feedback 3 days
10 Table discussions with the School 1 day
Administrators
TOTAL DAYS 1 month