FREQUENCIES QUALITY CONTROL TEST

Name of Work :-

Description of No. of Tests Executed No. of Test No. of Test Done by


S.No. Unit Quantity Name of Test Frequency of Test
Item of work Required Qty. done J.En. A.En. E.E. S.E. Q.C.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 Granular Sub Cum Two Test per 500 Cum
Base Gradation GSB or Per day
Two Test per 500 Cum
Atterberg limits GSB or Per day
Moisture Content at the time of Two Test per 500 Cum
Compaction or Per day
Density of Compacted Layer One set of Tests per
2000 Sqm

Total
2 Base Coursee Cum One Test per 250 Cum or
WBM Gr.-II Agg. Impact Value Gr.-II Source
Two Test per 500 Cum
Gradation of Agg. & Screening or per day
One test per 250 Cum or
Flakiness Index per day
Two Test per 500 Cum
Atterberg Limits Binding material or per day
Total

3 Base Course Cum One Test per 250 Cum or


WBM Gr.-III Agg. Impact Value Gr.-III Source
Two Test per 500 Cum
Gradation of Agg. & Screening or Per day
One test per 250 Cum or
Flakiness Index per day
Total

Two Tests per 500 Cum


Atterberg Limits Binding Material or per day
One Test per source
Water Absorpation of Agg.
Description of No. of Tests Executed No. of Test No. of Test Done by
S.No. Unit Quantity Name of Test Frequency of Test
Item of work Required Qty. done J.En. A.En. E.E. S.E. Q.C.
1 2 3 4 5 6 7 8 9 10 11 12 13 14

2 Sqm Two Test per day or per


Priming Coat 1000 Sqm.
Rate of Spread of Binder/Emulsion
& Tack Coat
Total
3 Open Graded Sqm 1 Test per lot or 10
Premix Penetration Tonne
Carpet with 1 Test per lot or 10
Seal Coat Softening Point Tonne
1 Test per 250 Cm per
Agg. Impact Value Source
1 Test per 250 Cm per
Flakiness Index Source
1 Test per source
Stripping of Agg.

1 Test per source


Water Absorption

1 Test per 50 Cum or per


Grading of Agg. day
2 Test per day
Binder Content

Total

Assistant Engineer Executive Engineer


Km x 4 FORM No. SB-1

Test For Granular Sub-Base


Sieve Analysis (IS:2720 (Part 4) - 1985

Test 1

Date of Testing
Road/Section Details Weight of Soil Sample Taken [gm]
Sample No.
Dry Sieving

I.S. Seive Weight of Sample Percentage of Cumulative Percentage of Wt. Prescribed Limits
percentage of Wt. [Percentage of Wt.
designation retained [gm] Wt. retained Passing
retained [%] Passing/Retained]

Wet Sieving Weight of Soil Sample Taken

Cumulative
I.S. Seive Weight of Sample Percentage of Percentage of Wt. Prescribed Limits
percentage of Wt. [Percentage of Wt.
designation retained [gm] Wt. retained Passing
retained [%] Passing/Retained]

Whether Confirm to the Prescribed Limits [Yes/No]


If Results don't conform to the prescribed limits, non conformance Report will be issued by the PIU. The reference of the
Page No. Of this Register on Which Non Conformance Reports copy Preserved
Page ………………… Dage of Issue…………………………

Checked by Tested by
Instruction for Blending

(Date & Signature)


Officer in Charge
S/2
Form No. SB-3

Moisture Content Test of Soil at the Time of Compaction

If No, Date of
Location of Test Wt. of Tin Wt. of Wt. of Tin+dry Loss of Water Wt. of dry Soil Moisture Confirm to Limits Issue of
Test No. Date of Test Sample No. Tin+Wet soil Prescribed Tested by Checked by
Point [gm] W1 [gm] W2 Soil [gm] W3 [gm] W2-W3 [gm] [W3-W1] Content [%] [Yes/No] NCR/Page No. of
Q/C
1 2 3 4 5 6 7 8 9 10 11 12 13 14

10

11

12

13

14

15

16
Km x 2 FORM No. SB-4

Test For Granular Sub-Base


Data Sheet for Compaction Test of Soil [IS: 2720 [Part 7] 1983
Test 1
Date of Testing
Road/Section Details Weight of Dry Soil
Sample No.
Discription of Sample

Type of test

Weight of mould W1 [gm]

Volume of mould Vm [cc]

Per cent retained on 20 mm IS Sieve


Weight of wet soil [gms]

Moisture content determination


Wet density [gm/cc]
Weight of mould +
compacted [gms]

Weight container +

Weight of Dry Soil

Moisture Content
Weight of water
Container + wet
container [gms]

dry Soil [gms]


Container No.
W2-W1

Dry density
[Ww] [gms]

[Ws] [gms]
Soil [gms]
Weight of

Weight of

S.No.

[%] [W]

[gm/cc]
1
2
3
4
5
6

Whether confirm to the


Layer Value Permissible Limit Prescribed Limits
[Yes/No]

If Results don't conform to the prescribed limits, non conformance Report will be issued by the PIU. The
reference of the Page No. Of this Register on Which Non Conformance Reports copy Preserved
Page ………………… Dage of Issue…………………………

Checked by Tested by

W2 - W1
Wet density of compacted soil Ym =
Vm gm/cc
Where : W2 - Weight of mould + Soil [gm], W1- Weight of Mould [gm], Vm - Volume of mould [cc]
100
Dry density of compacted soil Yd = x Ym
100 + W
Where W = moisture content
Km x 2 FORM No. SB-5
Thickness of Layer Test
Deviation to be If No, Date of
Location Measurement of Specified corrected more than Variation in issue of
Test No. Date of Testing Reference Thickness using Depth [mm] or less than specified prescribed Limit NCR/Page No. Tested by Checked by
Wooden Blocks [mm] [mm] [Yes/No] of Q.C.

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

7
Average Depth [Cm]
Km x 2 FORM No. GB-6
Thickness of Layer Test Water Bond Macadam Grade 2
Deviation to be If No, Date of
Location Measurement of Specified corrected more than Variation in issue of
Test No. Date of Testing Reference Thickness using Depth [mm] or less than specified prescribed Limit NCR/Page No. Tested by Checked by
Wooden Blocks [mm] [mm] [Yes/No] of Q.C.

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

7
Average Depth [Cm]
Km x 2 FORM No. GB-6
Thickness of Layer Test Water Bond Macadam Grade 3
Deviation to be If No, Date of
Location Measurement of Specified corrected more than Variation in issue of
Test No. Date of Testing Reference Thickness using Depth [mm] or less than specified prescribed Limit NCR/Page No. Tested by Checked by
Wooden Blocks [mm] [mm] [Yes/No] of Q.C.

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

Average Depth [Cm]

7
Average Depth [Cm]
2 FORM BL-3
Test for Rate of Spread of Binder
Weight of Whether with in If No, Date of
Test No. Reference of the Date Time Binder on Rate of Spread prescribed issue of Tested by Checked by
sample Trey Limits [Yes/No] NCR/Page No.
Of Q/C
Strengthening and widening of road bikaner jhajhu dasuri MDR-35 km. 146/0 to 172/0 [CRIF]
FORM No. SL-8

Aggregate for Bituminous Macadam [BM]


Sieve Analysis (IS:2720 (Part 4) - 1985

Test

Road/Section Details Date of Testing


Sample No. Weight of Soil Sample Taken [gm]

Cumulative
I.S. Seive Weight of Sample Percentage of Percentage of Wt.
percentage of Wt.
designation retained [gm] Wt. retained % Passing%
retained [%] Permissible Value

Whether Confirm to the Prescribed Limits [Yes/No]


If Results don't conform to the prescribed limits, non conformance Report will be issued by the PIU. The reference of the
Page No. Of this Register on Which Non Conformance Reports copy Preserved
Page ………………… Dage of Issue…………………………

Checked by Tested by
Instruction for Blending

(Date & Signature)


Officer in Charge