Professional Documents
Culture Documents
Ly001-Let-Bon-Fial-0007
Ly001-Let-Bon-Fial-0007
Libyan Branch
Sidi Abdul Jalil
Zanzour – Tripoli
Libya
Tel. +218 (91) 2200051
______________________________
References to quote in any reply
FERROSTAL INDUSTRIENLAGEN
Réf. n. LY0001-LET-BNT-FIAL-0008 LIBYEN LTD
______________________________
LIBYA BRANCH
Al Nasreen Street nearby Ben Nabee
Tripoli, ………………. Mosque
Al Mansoura
(Tripoli – Libya)
Dear Sir,
As a general remark, and in addition to the comments individually made on the referenced
documents, CONTRACTOR reminds that the SUBCONTRACTOR’s document shall be
aligned to the documents submitted to COMPANY by CONTRACTOR.
Best Regards
____________________
Project Manager
Attachments:
Grégory
00 29-09-2022 Yousab Bassili Joaquim Lima Zajaczkowski Issue of document.
Owner/Company:
BONATTI Job No.: FIAL Job No.: Formatted: Italian (Italy)
NAFUSAH OIL OPERATIONS B.V.
Contractor: C-001-PRO-2019 FPO-22001
BONATTI S.P.A.
Document Number: Revision: Department/Doc: IDM Ref. No.: Contractor Doc. No.: Supplier Doc. No.:
Formatted: Portuguese (Portugal)
Project QA/QC FIA2101215 N/A N/A
22001-QAPR-705 0 Procedure
Table of Contents
1. PURPOSE .................................................................................................... 3
2. SCOPE......................................................................................................... 3
3. DEFINITIONS AND ABBREVIATIONS ......................................................... 3
3.1 Definitions .................................................................................... 3
3.2 Abbreviations................................................................................ 4
4. REFERENCES DOCUMENTS ........................................................................ 4
5. RESPONSIBILITIES ........................................................................................... 5
6. REQUIREMENTS ................................................................................................. 5
6.1 General Requirements .................................................................... 5
6.2 Weld ........................................................................................... 6
6.2.1 General .................................................................................................... 6
6.3 Welding Procedures ....................................................................... 6
6.3.1 General .................................................................................................... 6
6.3.2 Application Method .................................................................................... 6
6.3.3 Joint Design .............................................................................................. 6
6.3.4 Materials .................................................................................................. 7
6.4 Welding Procedure Qualifications ...................................................... 7
6.5 Welder Qualification ....................................................................... 7
6.5.1 General .................................................................................................... 7
6.5.2 API 1104 .......................................................................................................... 8
6.5.3 ASME Section IX ....................................................................................... 8
6.5.1 Records of Qualified Welders and Welding Operators ............................................. 8
6.6 Weld Execution. ............................................................................ 9
6.6.1 General .................................................................................................... 9
6.6.2 Compliance with Specifications .................................................................... 9
6.6.1 Weld Preparations..................................................................................... 9
6.7 Inspection and Nondestructive Examination of Welds .............................. 14
6.7.1 General ...................................................................................................14
6.7.1 Disposition of Defective Welds ........................................................................... 14
6.7.2 NDE Records ............................................................................................14
6.7.3 Standards of Acceptability .......................................................................... 15
6.7.4 Repair of Welds Containing Defects .................................................................... 15
1. PURPOSE
The Purpose of this Procedure is to present all the welding work methodology and requirements
as laid down in the project specifications and referenced codes, standards, and management
procedures.
2. SCOPE
This Procedure applies to all welding works to be performed on the fabrication and erection of
equipment, structures, and piping, to be executed on the Ferrostaal Industrieanlagen Libya
Limited (FIAL) projects.
Welding Inspection
This is the function for monitoring all welding activities for acceptance, verifying the weld
preparation, including documentation as WPS, PQR and welders/operators’ qualification, the
welding material according to the WPS, an inspection of fit-ups before welding, checking correct
parameters during the welding process, and inspect the completed welds for acceptance.
Following and verifying all the welding register, Welding log, NDE reports and others as required.
Inspection Authority / 3rt Party
The independent organisation represents the Owner that verifies that the equipment and facilities
have been designed, constructed, inspected and tested in accordance with the requirements
and specifications of the Purchase Order/Contract.
QA/QC Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection
Authority verifies that the equipment and facilities have been designed, constructed, inspected
and tested in accordance with the specifications, applicable code, standards and the
requirements of the Purchase Order/Contract.
Records
Its written elements to provide evidence that the realisation processes and resulting products
meet requirements.
Welding Consumables
Any material used for making or protecting a weld, such as a Coated electrode, rods,
solid/tubular wires, fluxes or shielding gases.
3.2 Abbreviations
FIAL Ferrostaal Industrieanlagen Libyen, Ltd.
API American Petroleum Institute
ASME American Society of Mechanical Engineers
GES General Engineering Specification
NDE Non-Destructive Examination
PQR Procedure Qualification Record
QA/QC Quality Assurance / Quality Control SQM Site Quality Manager
SM Site Manager
WI Welding Inspector
WPS Weld Procedure Specification
WS Welding Supervisor
4. REFERENCES DOCUMENTS
Project Manager
The Project Manager is responsible for providing all human and material resources for properly
executing the welding works according to the Project's requirements.
Site Quality Manager /Welding Engineer
The SQM Is responsible for ensuring that all required documentation is available and that field
personnel possess the latest revision. Ensure all required information is reviewed, approved,
recorded, and completed documentation.
Ensure that any requests to deviate from the standards and/or specifications are thoroughly
reviewed and approved by the client or their representative.
Welding Inspector
The Welding Inspector is responsible for ensuring that all the welds are carried by the Welder with
valid certification, according to the correct welding parameters of applied WPS, covered by a
qualified procedure (PQR). Ensure that all required NDE are performed according to the
Inspection and Test Plan and that the reports are confirmed and approved.
Ensure all weld elements are correctly recorded in the Weld Map and Weld Log, including the
NDE log.
Welding Supervisor
The WS is responsible for ensuring that all welding activities are carried out according to the
project requirements and the applicable code, standards, and procedures.
Welder
The Welder is responsible for ensuring that he has all the materials and welding equipment in good
condition and has in hispossession all the referenced documentation up to date, such as the
Performance Certificate and corresponding WPS, and that he understands and follows.and he
should have the ability to perform a sound weld as per certified WPQ
All directives from the WS are understood and followed.
6. REQUIREMENTS
6.2 Weld
6.2.1 General
Perform all welding, including tack welds, temporary welds, and utility piping welds, using qualified
welding procedures approved for use by Quality Department.
Use welders who are qualified for the welding procedure specification to be used.
Ensure a qualified Welding Inspector witnesses all welding of process piping, gas transmission,
hazardous liquid, or other types of pressurised piping, including temporary welds.
The Welding Inspector checks the validity of certification records for each Welder.
Engineering to assure that proper and current qualification data is on file and is appropriate for
the welding to be performed.
6.3.1 General
Use the following processes, or combinations thereof, for welding procedures:
Shielded metal arc welding (SMAW)
Gas tungsten arc welding (GTAW)
Other welding processes may be used if approved by the Company.
6.3.4 Materials
Pipe and Components Base Metal
Weld materials according to their P-Number and Group Number, as given in ASME Section IX, or
the base material groupings as given in API 1104. Materials that do not conform to the P-Number
and Group Numbers specified above are considered to be unassigned. Do not use unassigned
base metals, as described in ASME BPVC Section IX, Clause QW-424.
Filler Metals
Select filler metals to match the deposited tensile strength appropriate for the welded materials.
Evaluate consumables listed in vendor/contractor welding procedures to ensure they are
appropriate for the welded materials. All consumables must be according to the WPS that
requires Company approval prior to use.
Store and handle properly filler metals and fluxes to avoid damaging them and their shipping
containers. Protect consumables in opened containers from deterioration and protect coated
filler metals from excessive moisture changes. Discard filler metals and fluxes that show signs of
damage or deterioration. Commented [DG3]: Low Hydrogen consumable
Store low-hydrogen type covered electrodes in hermetically sealed, moisture proof containers. shall be purchased with vacuum pack
After opening, store low-hydrogen electrodes in appropriate holding ovens at a temperature of
350°F + 50°F (175°C + 27°C) degrees or the Manufacturer's recommended holding temperature.
Do not store other electrode types (e.g., cellulosic) in holding ovens with low-hydrogen Commented [DG4]: Please to replace all the
electrodes. wording “do not” with the wording “shall not”,
as well as, “do” with “shall”.
Welding Consumables materials are managed according to the specified Welding Consumable
Procedure
6.5.1 General
Assign welders a unique symbol for the purpose of identification on all welds. Once a symbol is
assigned to a welder, do not reassign it to another welder during the Project.
Conduct qualification of welders in the presence of a Company representative.
Repair welder qualifications are determined according to the applicable code of Construction.
No welder repair separate qualification is required. Commented [DG5]: Repair Welder require
Welder qualifications performed for non-Company affiliated companies are notshall not be separate qualification according to welding
procedure specification.
considered.
A welder who has successfully completed an approval test, qualified in accordance with this
procedure, shall be qualified within the limits of the essential variables described in API 1104 or
ASME Section IX ,where applicable. If any specified variables are changed, the Welder using
the new Procedure shall be qualified.
Where the contracting parties agree that the failure of a welder to pass the test was because of
conditions beyond his control, the Welder may be given a second opportunity to gain approval.
No further retests shall be permitted until the Vendor/Contractor has submitted proof of
subsequent Welder training acceptable to the Company.
If a welder is responsible for a high level of repairs in production, he shall be removed from the
work and shall undergo a retraining programme approved by the Company before being
retested.
Welder Qualification shall be performed following the specific Welder and Welding Procedure
Qualification Procedure.
Following satisfactory welder qualification, a welder qualification test report (WQTR) shall be
prepared to show the actual test results and the range of material diameters, if pipe, and
thicknesses for which the Welder is qualified. This report shall also show the WPS number to which
the Welder is qualified.
A welder qualification index shall be prepared showing, as a minimum, the welders name,
identification number, which welding procedure specifications the Welder is qualified to, the date
of qualification for each WPS and the date when revalidation of qualification is due for each
Procedure.
6.6.1 General
During construction, ensure copies of the welding specifications are available for reference at the
local work site where the welding is performed.
check, with preference given to an ultrasonic flaw detector with an "A" scan display. Determine
the weld location before cutting the pipe.
Examine the prepared weld bevel using magnetic particle inspection. Lamination or other
conditions that could affect the completed weld found on the bevel with a circumferential length
greater than 0.25 in. (6 mm) are classified as defects. Cut back the pipe until no lamination or
other deleterious condition is present at the pipe end.
6.6.1.4 Grinding of Seam Welds
For welds subject to NDE using radiography, grind the pipe seam welds flush (-0, +1/64in.) for a
minimum distance of 1 in. (25 mm) from the bevel edge (internally and externally), with a gradual
transition to the weld reinforcement.
For welds subject to NDE using ultrasonic examination, grind the pipe seam welds flush (-0, +1/64
in.) for a minimum distance of 4 in. (100 mm) from the bevel edge (internally and externally), with
a gradual transition to the weld reinforcement.
6.6.1.5 Alignment and Fit-Up
Do not use mitre joints. (Deflections up to 3° caused by misalignment are not considered mitre
joints.)
Minimise external forces required to align pipes. If pipes to be joined are in place:
Below grade, expose a sufficient length of each end of the pipes so they can be moved
without imposing detrimental external stresses on the joint.
Below or above grade, and there is insufficient length to allow free movement, cut and
reinstall the pipes to bring the misalignment within the allowable tolerance.
For buried piping, except in the case of bends, stagger longitudinal seam welds on the
adjacent pipe at approximately the 10 o'clock and 2 o'clock positions.
On longitudinal seam welded pipe, place the seam at right angles ±10° to the bending
plane.
For above-grade piping, locate the seams welds to not interfere with possible branch
connections at the 12, 3, 6, or 9 o'clock positions.
Where two-seam welds on adjacent pipes meet at a common girth weld, offset the two
seams by a minimum distance of 2 in. (50 mm) from each weld toe.
Do not locate pipe seam welds on top of any pipe support (i.e., beam or concrete
support).
Do not hammer pipe. (Use of small hard plastic or steel hammer to signal the release of
internal clamps is acceptable as long as there is no damage to the pipe surface or
adjacent coating). Where external line-up clamps are used, correct minor out-of-
roundness and misalignment using wedges.
On new mainline construction, use internal line-up clamps for all welds. External clamps
may be used for tie-ins, facility construction, NPS 4 (114 mm OD) or smaller pipe, and
specific situations approved by the Company.
For pipe-to-pipe welds of the same nominal wall thickness, do not exceed 1/8 in. (3.2 mm)
maximum offset or misalignment of the abutting pipe ends.
For pipe to component joints of equal nominal wall thickness, do not exceed 1/8 in.
(3.2mm) external offset. Ensure internal offsets exceeding 3/32 in. (2.4 mm) conform to
the conditions specified in Section 2.42 of this Specification.
Do not fully insert the pipe into socket fittings using the Manufacturer's recommended
gap.
Gapolets are an acceptable means of maintaining the gap requirements.
6.6.1.6 Pipe Support
Do not weld supports, bracing bars or counterbalance weights to pressure piping and
components.
Ensure the pipe is supported in accordance with standard industry practice. Report any
occurrence of a section of line falling from its support to the Company, together with any tests,
inspections, and remedial work performed as a result of the fall. The Company determines
whether or not the piping is acceptable for use.
6.6.1.7 Weather Conditions
Protect welds during welding from weather conditions considered detrimental to weld quality.
Portable enclosures may be used to make conditions satisfactory for welding.
Wrap the completed weld in a clean, dry welding blanket when the ambient temperature at
the time of welding is below 50°F (10°C). Remove the blanket once the weld area reaches
ambient temperature.
6.6.1.8 Grounding and Cables
Securely attach grounding devices in a manner to prevent arc burns. Do not weld grounding
devices to the pipe or place them on the pipe body. Preferably make contact within the weld
groove, and ensure it is large enough to prevent local overheating or arcing (i.e., minimum 0.5 in.
(12.7 mm) wide and 1/8 in. (3.2 mm) thick). Ensure devices grounding in the bevel area are made
of steel. Do not use copper or bronze tips for such a purpose.
Ensure welding cables, ground clamps, and connections are insulated to prevent arcing to the
pipe surface. Avoid ground paths through valves.
6.6.1.9 Protection of Coatings
Protect existing coatings on piping to minimise the damage that may result from the welding
operations.
6.6.1.10 Preheating, Inter-pass
The WPS shall specify the minimum preheat and maximum inter-pass temperatures in accordance
with the following:
Preheat
Where the material surface is wet or the metal temperature is below 50°F (10°C), preheat shall
be employed to dry the surfaceas per applicable WPS.
Preheat shall be applied, where necessary, to avoid cracking or undesirable hardening of
weldments as per WPS requirements.
For carbon steels, this shall take into account joint design, heat input, presence of diffusible
hydrogen and the base metal composition, including the effects of higher carbon and alloy
content. Unless specifically agreed otherwise, minimum preheats shall be in accordance with
ASME Code, Section VIII, Table UCS-56 and UCS-56.1.
Apply preheat for a minimum distance of:
4 in. (102 mm) to each side of the weld for the full circumference; in the case of girth
welds
6 in. (152 mm) from any point of the area to be repaired, in the case of repairs.
Maintain mMinimum preheat temperatures shall be maintained for completing all welding.
Check to preheat and inter-pass temperatures at the top, bottom, and both sides of the
pipe using temperature-indicating crayons or contact thermocouple probes in areas 0.5 to
1 in. (12.7 to 25 mm) from the edge of the bevel. Ensure temperatures are within the
specified limits after each pass. Do not use Infrared pyrometers. Crayons which indicate
temperature by colourcolor change shall not be used.
Temperatures shall be measured immediately prior to the commencement of welding and
around the whole of the joint during the welding operation.
Whenever possible, the temperature shall be measured on the side opposite to that on which
the heat has been applied. Otherwise, the temperature shall be measured on the heated
side following removal of the heat source and allowing a time-lapse for temperature
equalisation. Up to 1" (25 mm) thickness, this time-lapse shall be 2 minutes. For each additional
½" (12 mm) above that thickness, 1 minute shall be added.
Do not cool passes of a weld at a rate greater than that provided by natural air cooling.
Preheat may be applied by either gas or electrical means. The method used shall be that
used during welding procedure qualification and shall be approved by the Company stated
in the applicable WPS.
Preheat shall be applied in such a manner as to avoid damage to any coating.
The minimum preheat temperature shall be as specified in the WPS, and the maximum shall Formatted: Strikethrough
not exceed it by more than 50°C.
area would typically be on the bottom of the pipe but could be on the top of the pipe in an
overbend situation or on the sides of the pipe in a side bend situation.
Record the welder identification number/letter on the weld log, NDE inspection record, and
relevant drawing/spool sheets.
Should any welder leave the Project, do not reassign their unique identification to another welder.
6.6.1.21 Closure Welds
Submit welds that are not hydrostatically tested to in-process examination as outlined in Weld-
Tie-In.
6.6.1.22 Weld Clean-up
Completely remove weld spatter, coating, or loose debris s from the joint's surface for a
minimum distance of 4 in. (100 mm) on each side of the weld, as required for NDE inspection.
6.7.1 General
Inspect completed welds for 100% of their lengths and assess any imperfection using the
applicable standard of acceptability ASME IX ASME B31.3 for piping as well asand API 1104 for Formatted: Strikethrough
pipeline. Fully document all inspections.
Perform a visual inspection. At a minimum, ensure the completed weld is uniform appearance,
free from excessive profile defects, cracks, inadequate penetration, and burn-through, and
presents a neat workman-like appearance. Ensure the undercut meets the requirements of API
1104.
Document the visual inspection of each weld on the appropriate form along with the disposition
(Acceptable or Non-Acceptable to API Welding of Pipelines and Facilities and ASME B31.3 for
pipingand ASMEIX). Formatted: Strikethrough
Do not submit welds that do not pass visual inspection in accordance with this Procedure and API
1104 to NDE until the discrepancy has been rectified or repaired according to WPS to the
satisfaction of the Company.
Use radiographic inspection according to API 1104 of Welds or ultrasonic inspection methods, or
a combination of such methods, for butt weld NDE. For welds having a wall thickness difference
shall be taken into consideration to choose the appropriate NDE technique.
Do not use the manual ultrasonic inspection as girth welds' primary method.
For buried service, unequal wall thickness pipe to pipe field welds (NPS 12 and greater) with one
side having a back-bevel transition, an ultrasonic inspection shall be performed when cellulosic
consumables are used. This shall be a secondary inspection to screen for lack of fusion in the root
or cracking. This ultrasonic inspection should be performed at least 24 hours after the weld has
been completed where other delayed hydrogen cracking mitigations have not been
implemented.
Use magnetic particle inspection on ferromagnetic materials and use liquid penetrant inspection
on non-ferromagnetic materials for fillet weld NDE in accordance with API 1104 and ASME V.
Inspect repair welds with the same NDE method originally used to identify the defect.
destructively tested, the number rejected, and the disposition of the welds.
Provide the inspection records to the Company. Keep these records for the life of the pipeline.
Submit a Contractor Turnover Package to the Company at the completion of the Project that
includes, but is not limited to, the following:
Purchase order number, Project number
Filler Material Certificates
Weld Map and Weld Log, including NDE log
List of welding procedures, consumable welding documentation, welding parameter
reports, and welder identification used for field installation
NDE reports (i.e., visual inspection records, radiographic film, and ultrasonic testing
records) identify the procedure method and technique used for the inspection.
8.1 Procedures
Welding Consumable Procedure
Non-Destructive Examination Procedures
Welder and Welding Procedure Qualification Procedure
Mechanical Completion & Pre-commissioning
Any other documentation required in project specification
requirement
8.2 Forms
Welding Daily Visual Inspection Report
Inspection Report
Non-Destructive Examination Reports
Piping Logbook (In-Plant Piping)
Piping Logbook (Flowline/Pipeline Piping)
Any other documentation required in project specification
requirement
Doc. No.: 22001-QAPR-705 Rev. 0 IDM No.: FIA2101215 Ver. 0 Page 18 of 15
© Property of Ferrostaal, Ltd. ● All rights reserved This document when printed is a non-controlled copy
General Procedure for Welding Activities
Gathering Network and Oil Export Pipeline
Grégory
00 29-09-2022 Yousab Bassili Joaquim Lima
Zajaczkowski
Issue of document.
Owner/Company:
BONATTI Job No.: FIAL Job No.: Formatted: Italian (Italy)
NAFUSAH OIL OPERATIONS B.V.
Contractor: C-001-PRO-2019 FPO-22001
BONATTI S.P.A.
Document Number: Revision: Department/Doc: IDM Ref. No.: Contractor Doc. No.: Supplier Doc. No.:
Formatted: Portuguese (Portugal)
Project QA/QC FIA1900616 N/A N/A
22001-QAPR-706 0 Procedure
Table of Contents
1. PURPOSE ...................................................................................................... 3
2. SCOPE........................................................................................................... 3
3. TERMS, DEFINITIONS ....................................................................................... 3
4. STANDARD AND DOCUMENT REFERENCES ....................................................... 4
5. RESPONSIBILITIES ......................................................................................... 4
6. EVALUATION OF REQUIREMENTS ..................................................................... 4
7. REQUIRED RESOURCES .................................................................................... 5
7.2 Test Piece ....................................................................................... 6
7.3 Consumables .................................................................................. 6
7.4 Human Resources ............................................................................. 6
7.5 Physical Resources ............................................................................ 6
8. WELDING PROCEDURE QUALIFICATION ......................................................... 87
8.1 Welding Procedure QUALIFICATION .................................................... 87
8.2 Non-destructive Testing (NDT) ............................................................ 87
8.3 Post Welding Heat Treatment (PWHT) .................................................... 87
8.4 Destructive Testing .......................................................................... 87
8.5 Procedure Qualification Record (PQR) .................................................. 87
8.6 PQR Re-Testing .............................................................................. 98
8.7 PQR Approval ................................................................................ 98
9. WELDER PERFORMANCE QUALIFICATION (WPQ) ............................................ 98
9.1 Welder Performance Qualification Test (WPQT). ...................................... 98
9.2 WPQT Validity ................................................................................. 98
10. ANNEXES .................................................................................................... 98
1. PURPOSE
The purpose of this procedure is to define the methods for performing the required Welding
Procedures Qualification Record (WPQR) and Welder Performance Qualifications (WPQ) to be Commented [DG1]:
applied on the welding activities.
2. SCOPE
This procedure applies to all construction sites under the authority of Ferrostaal Industrieanlagen
Libyen Ltd. for all welding activities.
WPS A formal written document provides the required welding variables for a
specific application, as per the code requirements, which provides direction
to the welder or welding operators for making sound and quality production
welds.
WPQ A Welder Performance Qualification is a test certificate that shows that the
welder is qualified to weld in the range specified, according to the
reference code.
Doc. No.: 22001-QAPR-706 Rev. 0 IDM No.: FIA1900616 Ver. 0 Page 3 of 8
© Property of Ferrostaal, Ltd. ● All rights reserved This document when printed is a non-controlled copy
Welder and Welding Procedure
Qualification Procedure
Gathering Network and Oil Export Pipeline
The governing codes and standards for the above work procedure are listed here, which will be
strictly implemented, and work will be carried out in compliance with such codes or standards:
ASME IX ASME Boiler and Pressure Vessel Code - Welding, Brazing, and Fusing
Qualifications
ASME SEC II C Standard for Material and Consumable of Welding
API 1104 Standard for welding Pipelines and Related Facilities
ASME B31.4 Pipeline Transportation Method for Liquid and Formatted: English (United States)
Slurries
Welding Consumable Handling Procedure (later) Commented [DG3]: Also insert Bonatti
specification references:
- LY0001-000-ZH-11023 - PIPELINE WELDING
SPECIFICATION
-LY0001-000-ZH-11002 – WELDING
SPECIFICATION FOR PIPING
5. RESPONSIBILITIES
Quality Manager (QM) Is responsible for ensuring that this procedure is followed and giving support
to the WE in the evaluation of the needs for the execution of the welding works, specifically the
processes to be applied, considering the applicable codes, the base materials, diameters and
thickness to be welded, including the necessity of qualifying new welding procedures and/or
welders.
Welding Engineer (WE) is responsible with the QM for drawing up the proposed WPS, pre-qualify
WPS for producing PQR, and approved WPS. Further, he is responsible for maintaining records of
all submitted WPSs and their relevant PQRs.
Maintaining all records related to PQR, WQT, WPS. Including, but not limited to:
Updating Welders Qualification Test Record Summary, with the WPSs for which are qualified.
Certified Welding Inspector (CWI) is responsible for supervising the WQTs and WPQTs and shall
witness the qualification tests, perform random inspections and Testing, and sign the test results.
Other responsibilities of CWI include but are not limited to:
Inform Client and Third-Party Welding Inspector about place and time and facilitation of
WQT & WPQT exams.
Cross-checking Non-destructive test and destructive test results of WQTs and WPQTs.
6. EVALUATION OF REQUIREMENTS
When the technical information for the project is placed available, i.e., Tender Documents,
Doc. No.: 22001-QAPR-706 Rev. 0 IDM No.: FIA1900616 Ver. 0 Page 4 of 8
© Property of Ferrostaal, Ltd. ● All rights reserved This document when printed is a non-controlled copy
Welder and Welding Procedure
Qualification Procedure
Gathering Network and Oil Export Pipeline
Project Specifications, Drawings, Isometrics, etc., the Quality Department perform a detailed
analysis of the welding needs for the project.
The Welding Engineer (WE) with Quality Manager (QM) evaluate the needs for the execution of
the welding works, specifically the processes to be applied, considering the design codes, the
base materials, diameters, and thickness to be welded, including the necessity of qualifying new
welding procedures and/or welders according to project code.
With all previous elements, all Welding Procedure Specifications (WPS) covering all welding
activities planned for the project will be prepared. All WPS need to be covered by the approved
ProcedureWelding Procedure Qualification Record (WPQR). In the fault of a WPQR to validate
any of the WPS identified, a revised or new Preliminary Welding Procedure Specification
(PWPS) will be prepared to perform the needed WPQR.
WE and/or QM give the elements to the Project Manager to provide resources to perform the WPQR
and the need for Welders Performance Qualification.
In accordance with ASME BPV Code Section IX and API 1104, WPS and welding procedure
qualifications are the sole ownership of the company or entity that develops the procedures
and employs the welders. This welding documentation is non-transferable between companies
without Company approval and when considered by fabrication code (e.g. ASME B31.3 PAR. 328.2.2)
7. REQUIRED RESOURCES
To perform Welder and Welding Procedure Qualifications, it is necessary to organize the following
resources:
7.3 Consumables
All welding consumables shall be in accordance with the WPS, namely the standard designation,
dimensions of the filler metals, and, if required manufacturer and trade name, etc.
During qualification, the welding consumables shall be stored and used in accordance with
specific Welding Consumables Procedure and manufacturer recommendations in a way that
avoids proprieties deterioration or physical damage to them and their packages. Consumables
that show any kind of deterioration or visible damage shall be destroyed to avoid being used.
Humidity resistant package (Vacuum pack or equivalent) shall be purchased for electrodes
packaging.
Welders that will be deployed for welding work on pipelines or piping shall have a WPQ for the
applicable WPS by successfully completing the Welder Qualification Test (WPQT) according with
code requirements and applicable project specification.
10. ANNEXES
Not applicable.
Rev. 0
September 2022
SUMMARY
1 INTRODUCTION ................................................................................................................... 5
1.1 DEFINITIONS ......................................................................................................................................... 6
1.2 ABBREVIATIONS ................................................................................................................................... 7
2 REFERENCE STANDARD AND SPECIFICATIONS............................................................. 9
1.3 GENERAL ............................................................................................................................................. 9
1.4 PROJECT’S SPECIFICATIONS ................................................................................................................. 9
1.5 INTERNATIONAL CODES AND STANDARDS .............................................................................................. 9
1.6 LANGUAGE......................................................................................................................................... 11
1.7 UNITS OF MEASUREMENT ................................................................................................................... 11
1.8 WELDING TERMS ........................................................................................................................... 11
3 SCOPE ................................................................................................................................ 13
4 GENERAL REQUIREMENTS.............................................................................................. 14
4.1 WELDING PROCESS ............................................................................................................................ 14
4.2 JOINT DESIGN .................................................................................................................................... 14
4.3 EQUIPMENT ........................................................................................................................................ 15
4.4 MATERIALS ........................................................................................................................................ 15
5 WELDING PROCEDURE SPECIFICATION ........................................................................ 16
5.1 GENERAL ........................................................................................................................................... 16
5.2 QUALIFICATION OF WELDING PROCEDURE ............................................................................. 17
5.3 ADDITIONAL ESSENTIAL CHANGES ...................................................................................................... 17
5.4 TEST WELD ACCEPTABILITY FOR DESTRUCTIVE TESTING..................................................................... 18
5.5 DESTRUCTIVE TESTING ....................................................................................................................... 18
5.6 TRANSVERSE TENSILE TEST ............................................................................................................... 18
5.7 IMPACT TOUGHNESS TESTING ............................................................................................................. 18
5.8 HARDNESS TESTING ........................................................................................................................... 19
5.9 BEND TESTING ................................................................................................................................... 19
5.10 MACROSCOPIC EXAMINATION .............................................................................................................. 19
5.11 REPAIR WELDING ............................................................................................................................... 19
6 QUALIFICATION OF WELDERS ........................................................................................ 20
6.1 GENERAL ........................................................................................................................................... 20
6.2 QUALIFICATION TEST PERFORMANCE................................................................................................... 20
6.3 REPAIR WELDER QUALIFICATION ........................................................................................................ 20
6.4 TEST WELD ACCEPTABILITY FOR WELDER QUALIFICATION .................................................................. 20
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 3 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
1 INTRODUCTION
The operator, Nafusah Oil Operations B.V. was established in 2013 to develop A/47 commercially declared
discoveries. North Hamada field is an onshore oil field consists of several hydrocarbon bearing structures.
It is located in the northern part of the prolific Ghadames Basin, NW Libya, 250km SW Tripoli within the
contract Block-47 awarded in ESPA IV round of 2005 to MEDCO-VERNEX consortium.
In 2014 MEDCO conducted comprehensive 3D-Reservoir simulation study led to a full development plan
(FDP) OF North-Hamada Field consisted of drilling 23 infill producers, 50.000 BOPD production capacity.
A FEED study executed the full scale development project through 3 main packages:
Package “A” Gathering system and exports pipelines.
Package “B” central processing facilities (CPF)
Package “C” Field Infrastructures.
Following the drop in Oil prices and instability in Libya, due to internal civil conflict, have raised the risks
associated to the FDP. The Management committee (MC) decided to pursue a phased-out development
strategy, an approach that considers an implementation of fast-track-development plan to reduce CAPEX,
expedite first oil and generate early cash flow to offset cost and enhance second party economics.
In 2018 phased out fast-track concept is envisioned, starting by an initial development phase, called fast-
track-early production period (FTEPF); for 3 years, 10000BOPD plateau, using 25000BOPD production train,
initially flaring the remaining associated raw gas and differing gas processing to the follow up phase.
The adopted Fast-track phased out development plan, is to be less costly, maintains integrity of
standards/quality and mitigate associated risks; thus achieves the objectives of expediting first oil to
generate early cash flow to offset cost, minimize high capital investment exposure, hence relaxes financial
obligations and evaluate reservoir performance to cater for future production optimization.
The Package “A” Gathering system and Oil Exportline” object of this Contract has been awarded to Bonatti
SpA in May 2022 and is relevant to the EPCC of the Pipeline Gathering Network and the Oil Exportline as
described in the following scheme.
The package “B” Central Processing Facility (CPF) will be substitute by a new Early Production Facility
(EPF) out of this Contract scope of work.
Gathering Facilities
9 Oil Production Wells
2 Water Wells
1 Remote Manifold Station (RMS)
2 Temporary RMS
1 EPF Manifold
Oil Exportline Facilities
1 Oil Exp. Tie-in Station
1 Block Valve Station
Pipelines
9 Oil Prod. Flowlines (4’’ & 6’’) 30 km
1 Trunkline 16’’ – 23 Km
1 Oil Exportline 12’’ – 50 Km
1 Water Flowline 4’’ - 1.5 km
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 6 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
1.1 DEFINITIONS
PROJECT: North Hamada (Area 47) Field Development – Gathering Network and Oil
Export Pipeline (EPCC)
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 7 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
WORK: All the activities, accessories and equipment, necessary to cover the scope
of work
SHALL: Use of the word “shall” implies a mandatory requirement, which can be
relaxed only with the written confirmation by the CONTRACTOR and/or
COMPANY
1.2 ABBREVIATIONS
All works described in this specification shall be carried out in accordance with the laws of Libya.
Unless otherwise stipulated, the latest edition of the international standards (at the Contract signature date)
and specifications referenced hereinafter shall apply.
1.4 PROJECT’S SPECIFICATIONS
1.6 LANGUAGE
All documents and any other written information shall be submitted by the SUPPLIER in the English
language.
1.7 UNITS OF MEASUREMENT
International System (SI) shall be used, unless otherwise specified in the applicable specifications.
Arc Strikes Localized areas where an electrical arc has heated an area away from
the weld joint bevel and weld heated affected zone.
Cap Pass The final weld layer or pass in a multi-pass weld.
Internal Bead that is properly fused to and completely penetrates the pipe wall
Concavity thickness along both sides of the bevel but whose centre is somewhat
below the inside surface of the pipe wall.
Latent Defects Welding defects, which take time to initiate and propagate e.g.
hydrogen cold cracks
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 12 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
Qualified Welder who has demonstrated the ability to produce welds that meet
Welder the requirements of Section 6 of this standard.
Root Bead First or stringer bead that initially joins two sections of pipe, a section of
pipe to a fitting, or two fittings.
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 13 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
Semiautomatic Arc welding with equipment that controls only the filler metal feed. The
Welding advance of the welding is manually controlled.
Stacked Individual imperfections aligned in the radial (through thickness)
Defects direction, at the same circumferential location, and exceed the
acceptance standards.
Tack Welds A temporary weld segment designed to hold a weldment in alignment
prior to and during welding
Tie-In Welds Welds for the purpose of connecting piping sections or connections to
prefabricated assemblies, normally carried out in a ditch.
Travel Speed The rate of a weld passes along the axis of the weld; i.e. distance
travelled over a period of time.
Weld Repair The percentage of welds, which do not meet specified weld acceptance
Rate criteria. The Weld Repair Rate is calculated by dividing the total
number of welds produced during a given period by the number of
welds that require repair over the same period
Welding (WPS) The WPS identifies the essential changes recorded during the
Procedure development of the PQR and extends these into a range of essential
Specification changes to be followed for a specific task. Welding requirements such
as preheat temperatures, consumables and heat inputs are identified in
the WPS.
3 SCOPE
This document describes the technical requirements that SUPPLIER shall follow for the execution of pipeline
girth welds and mainly related to:
• Bevel Preparation.
• Equipment and Materials.
• Welding Procedures Qualification.
• Welder Qualification Testing.
• Production Welding.
• Visual and Non-Destructive Examination.
• Repair Welding Procedure.
This specification shall govern the welding processes permitted for use in the construction of all equipment
covered by these specifications.
This specification shall apply to all suppliers, sub-suppliers, and fabricators of welded equipment who shall
not sub-contract the welding fabrication of any equipment without COMPANY and/or CONTRACTOR prior
written approval. Such written approval shall not be forthcoming until approval for the type of welding to be
carried out by the proposed welding fabricator has been granted.
This standard also covers the procedures for radiographic, magnetic particle, liquid penetrant, and ultrasonic
testing, as well as the acceptance standards to be applied to production welds tested to destruction or
inspected by radiographic, magnetic particle, liquid penetrant, ultrasonic, and visual testing methods.
The SUPPLIER shall furnish all labour, materials, and equipment necessary for the cleaning, surface
preparation, and inspection of the weld in accordance with this specification.
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 14 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
In addition to the SUPPLIER’s inspections, CONTRACTOR may perform any inspection to verify compliance
with this specification. Inspection may include all work equipment, inspection equipment, materials or
procedures and may be conducted at any time CONTRACTOR chooses.
The SUPPLIER shall correct any work which CONTRACTOR has determined not to comply with the
requirements of this specification. Corrections shall be made without additional cost to CONTRACTOR.
Failure to discover or reject defective work or materials does not constitute acceptance of such work or
materials.
It is the responsibility of the SUPPLIER to meet the requirements of this specification, to use equipment
capable of meeting the requirements, and to perform all inspections necessary to ensure compliance.
SUPPLIER shall provide, and maintain in good working order, all facilities required to meet this specification
including the following:
The SUPPLIER must liaise with qualified testing laboratory and experienced personnel and the
necessary equipment to perform all quality assurance tests required by this specification.
All equipment must be in good working order and properly calibrated. Testing must be completed in
a timely manner to avoid disrupting the production schedule.
The SUPPLIER shall notify CONTRACTOR at least three (3) weeks prior to beginning the PQR
It is the responsibility of the SUPPLIER to perform all work in a manner consistent with all applicable health
and safety regulations.
4 GENERAL REQUIREMENTS
Welding shall be performed in accordance with API 1104 22nd Edition and the additional
requirement of this document.
Butt welds between pipes of unequal nominal wall thickness shall be according to the permissible
weld configuration given in ASME B31.4 Figure 434.8.6-2. or as otherwise specified for NDE
purpose
Tack Welds
When necessary tack welds shall be performed with the same weld procedure specification as the
root run and by a welder qualified for that run. They have to be evenly distributed around the pipe
circumferences. Tack welds shall be at least 30 mm long and for > DN 400 at least 50 mm. Where
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 15 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
preheating is required for the root run, this shall be applied prior to tack welding and maintained until
the joint is completed.
4.3 EQUIPMENT
SUPPLIER shall supply all necessary welding equipment for the satisfactory completion of the work.
The equipment shall be maintained in such condition as to provide continuity of operation and safety
of personnel.
Welding equipment, both gas and arc, shall be of a size and type suitable for the work and shall be
maintained in a condition that ensures acceptable welds, continuity of operation, and safety of
personnel. Arc welding equipment shall be operated within the amperage and voltage ranges given
in the qualified welding procedure specification (WPS). Gas welding equipment shall be operated
with the flame characteristics and tip sizes given in the qualified welding procedure specification.
Equipment that does not meet these requirements shall be repaired or replaced.
SUPPLIES shall submit to CONTRACTOR all relevant calibration certificates for welding generators,
gas mixers or any other equipment to be used during production.
SUPPLIER shall use internal line-up clamps designed to avoid mechanical damage to the pipe and
maintain the alignment within the specified tolerances in WPS.
4.4 MATERIALS
Pipe and Components
Materials shall be welded according to the ranges of qualified welding procedure specification.
Material grouping system according to API 1104
All filler metals and fluxes shall conform to one of the following, except as provided below:
a) AWS A5.1,
b) AWS A5.2,
c) AWS A5.5,
d) AWS A5.17,
e) AWS A5.18,
f) AWS A5.20,
g) AWS A5.23,
h) AWS A5.28,
i) AWS A5.29.
All welding consumables shall be selected to produce welds with yield strength at least equal to the
minimum specified for the parent material.
All welding consumables shall be supplied in sealed, dirt and moisture proof containers. Filler metals
and fluxes shall be stored and handled in accordance with manufacturer’s datasheet
recommendations and to avoid any damage to the containers in which they are shipped. Filler metals
and fluxes in opened containers shall be protected from deterioration, and filler metals that are
coated shall be protected from excessive changes in moisture. Filler metals and fluxes that show
signs of damage or deterioration shall not be used.
Filler materials shall be supplied with certificate in accordance EN ISO 10204 at least 3.1 chemical
analysis, 2.2 for Tensile and Impact.
Shielding Gases
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 16 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
Components of shielding gases are recommended to have a purity of at least 99.5% and a dew point
of -34°C. Gas mixtures can be supplied in pre-mixed cylinders or by field mixing.
Shielding gases shall be kept in the containers in which they are supplied, and the containers shall
be stored away from extremes of temperature. Gases in containers that show signs of damage shall
not be used.
5.1 GENERAL
Before production welding is started, a detailed welding procedure specification shall be established
and qualified to demonstrate that welds produced are suitable in mechanical properties (such as
strength, ductility, and hardness) and soundness.
Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) for main line
welding, tie-in welding and repair welding procedures shall be submitted to CONTRACTOR prior the
commencement of production welding. SUPPLIER shall prepare and test all qualification test
coupons required to meet all design and materials within the scope of work.
The WPS shall represent a summary table showing type of process, filler materials/ consumables,
direction of welding, type of weld, WPS no., wall thickness range qualified, outer diameter, and
scope of specification.
The WPS shall be in accordance with Error! Reference source not found. and include the
additional details noted hereafter, in accordance with COMPANY and/or CONTRACTOR
requirements:
Welding procedure shall be qualified in accordance with essential variables in compliance with
Error! Reference source not found. and the additional requirements of this document. SUPPLIER
shall simulate field production welding as closely as practical during the qualification of Welding
Procedure.
Two pipe pup pieces shall be joined by following all the details of the preliminary welding procedure
specification.
The quality of the weld shall be determined by both destructive and non-destructive testing and shall
meet the requirements of Error! Reference source not found..
All welding procedure qualification tests shall be conducted in the presence of the Inspector and a
third party.
SUPPLIER shall be responsible for all aspects of welding procedure qualification, and shall:
Notify CONTRACTOR and/or COMPANY at least three (3) weeks in advance of welding
procedure qualification test;
Develop and document welding procedures for the entire range of materials and welding
variables within the scope of work;
Prepare and test all qualification test coupons required to meet all operation and materials
within the scope of work;
Instruct and supervise welding personnel during the preparation of test welds;
Measure and record welding parameters used during the preparation of test welds;
Check preheat/interpass temperatures to verify compliance with calibrated instrumentations;
Test the welds using both non-destructive (e.g. visual and radiographic) and destructive
tests;
SUPPLIER may submit previously qualified welding procedure qualifications for approval by
CONTRACTOR and/or COMPANY.
Change to a minimum design temperature lower (colder) than that used for impact toughness
testing or fracture toughness testing during procedure qualification shall necessitate retesting for
impact toughness.
5.4 TEST WELD ACCEPTABILITY FOR DESTRUCTIVE TESTING
Test welds shall meet standards of acceptability for non-destructive visual inspection given in API
1104 22nd Edition, Table 4, par. 9.
Test welds failing to meet the standards of acceptability for non-destructive inspection shall not be
submitted to destructive testing.
The specimens shall be air cooled to ambient temperature prior to being tested.
SUPPLIER shall destructively test weld procedure test coupons following successful completion of
non-destructive examination according with Error! Reference source not found., Table 2 and the
inspection methods of this specification.
SUPPLIER, unless otherwise agreed, shall prepare a cutting sheet detailing all the destructive test to
be performed each welding procedure qualification test coupon.
The facility chosen by SUPPLIER for Mechanical Testing shall be approved by COMPANY and/or
CONTRACTOR.
The tensile strength test specimens shall be broken under tensile load using equipment capable of
measuring the load at which failure occurs. The tensile strength shall be computed by dividing the
maximum load at failure by the smallest cross-sectional area of the specimen, as measured before
the load is applied.
The tensile strength of the weld, including the fusion zone of each specimen, shall be greater than or
equal to the specified minimum tensile strength (SMTS) of the pipe material but need not be greater
than or equal to the actual tensile strength of the material. If the specimen breaks outside the weld
and fusion zone (i.e., in the parent metal) at a tensile strength not less than 95 % of that of the SMTS
of the pipe material, the weld shall be accepted as meeting the requirements.
If the specimen breaks in the weld metal, it shall be considered acceptable provided that the
specified minimum tensile strength of the base metal has been achieved.
Charpy impact tests shall be prepared and tested in accordance with ASTM E23, each test
corresponds to one set of three specimens.
The specimens shall be machined with their longitudinal axis transverse to the weld. The specimens
and notch locations with respect to weld cross-section shall be as described in ASTM E23.
The average value of the Charpy V-notch energy for the three (3) specimens shall be a minimum of
30 J, minimum impact for each specimen 27 J.
If the stated impact requirements are not satisfied for one set, three further specimens to be tested.
The mean value of all six tests shall be at least equal to the specified minimum average value.
Impact Test shall be conducted at or below -7°C.
Figure 2
The test specimen shall be prepared and etched in accordance with ISO 17639 on one side to
clearly reveal the fusion line, the HAZ and the build-up of the runs.
The test specimen shall include unaffected parent metal and shall be recorded by at least one
photograph of macro cross-section per procedure test.
All repair welding shall use a minimum preheat and interpass temperature of 120 °C. Each repair
weld shall be non-destructively tested by radiographic methods and magnetic particle methods after
the weld has cooled to ambient temperature and destructively tested.
Two transversal tensile tests, two root bends, two face bends (or 4 side bend as per par.5.9), weld
metal impact tests, HAZ impact tests, and a hardness survey shall be carried out on samples
removed.
As an option, separate qualification is required for internal root pass repair. The internal repair length
shall be minimum 100 mm, performed in one pass using low hydrogen electrodes of 2.5- or 3.2-mm
diameter. Repair area to be subjected to macro section, hardness test and bend test in accordance
with API 1104 22nd Edition.
6 QUALIFICATION OF WELDERS
6.1 GENERAL
The aim of WQT (welder qualification test) is to establish the ability of a welder to follow verbal or
written instruction and verification of a person’s skills are important factors in ensuring the quality of
the welded product.
Prior to starting the qualification tests, the welder shall be allowed reasonable time to adjust the
welding equipment to be used. The welder shall follow the requirements of the applicable qualified
welding procedure specification. The qualification of welders shall be conducted in the presence of a
representative acceptable to the company.
Each welder shall be qualified and shall submit a corresponding certificate according to API 1104 for
each welding work he will perform.
Each welder shall make a complete test weld (root, hot pass, filler and cap pass) regardless of the
type of weld he is assigned for.
For pipe diameter greater than 323,9 mm OD, for the purpose of welder qualification testing,
terminology “weld” shall mean one half of the total pipe circumference.
SUPPLIER shall provide training for welders before starting qualification test to allow them to obtain
adequate skills to produce acceptable welds on consistent basis.
SUPPLIER shall qualify welders performing repairs in accordance with the approved full through
thickness repair welding procedure, as this test shall qualify welders performing repairs to complete
for partial through thickness repairs and back weld repairs.
Test welds failing to meet the visual inspection requirements shall not be submitted to non-
destructive inspection;
6.5 RECORDS OF QUALIFIED WELDERS
Records shall be made of the tests given to welders and of the detailed results of each test.
A list of qualified welders and the procedure specifications in accordance with which they are
qualified to weld shall be maintained and shall be submitted to the Company upon request.
Welders shall be assigned a unique number for the purpose of identification on all welds. Once the
number is assigned to a welder it may not be re-assigned to another welder during the project.
SUPPLIER shall prepare and maintain a list of qualified welders and their qualification
7 PRODUCTION WELDING
SUPPLIER shall perform welding of pipe using qualified welders in accordance with Company
approved qualified welding procedure specifications. SUPPLIER shall continuously monitor welding
to ensure compliance with the welding requirements.
Piping shall be welded by qualified welders using qualified procedures. The surfaces to be welded
shall be smooth, uniform, and free from laminations, tears, scale, slag, grease, paint, and other
deleterious material that might adversely affect the welding. The joint design and spacing between
abutting ends shall be in accordance with the welding procedure specification used.
SUPPLIER shall clean the pipe removing bevel shavings, dirt, snow, ice, water prior to alignment for
welding
SUPPLIER shall clean to sound metal all piping ends which are to form a part of the welded joint
prior to welding to ensure complete removal of all paint, grease, oxide, rust and any other
extraneous matter. Cleaning shall extend for at least twenty-five (25) millimetres from the piping
edges on both internal and external surfaces. SUPPLIER shall grind out and blend small score
marks, indentations or other small defects within the joint preparation area shall. SUPPLIER shall
remove clusters of surface porosity, bead starts, heavy glass deposits and high points prior to
depositing weld metal over them.
7.4 LAMINATIONS
a) Should any lamination or split end be discovered at the bevelled end of a pipe joint, either
before or during welding, the joint shall be cut back until the lamination has been completely
removed and the end re-bevelled.
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 22 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
b) Consideration shall be given to using ultrasonic, liquid penetrant or magnetic particle inspection
methods to confirm the new cut end is free of laminations or splits prior to welding.
7.6 BEVELLING
If bevelling is mandatory as per Welding Procedure Specification, SUPPLIER shall supply suitable
labour to train in the use of the facing/bevel machine prior to starting production welding. SUPPLIER
shall use bevel dimensions as specified on CONTRACTOR approved welding procedure and shall
be checked and documented by SUPPLIER on a regular basis.
If the difference in nominal wall thickness of adjoining pipes exceeds 1.6 millimetres, transitioning of
the thicker pipe down to the thinner pipe shall be required, in accordance with ASME B31.4 Figure
434.8.6-2.
Original mill bevels shall be cleaned to a bright metal finish, internally and externally to at least 5-20
mm wide. Any dent not suitable for the welding process or any crack close to ends shall be cut and
bevelled again.
Field bevelling shall be made by machine tool or machine oxygen cutting. Bevelling by hand cutting
torch shall not be allowed. The bevelled ends shall be reasonably smooth and uniform, and
dimensions shall be in accordance with the qualified welding procedure.
When oxy-cut bevels is used, bevel surface shall be grind back to bright metal.
Consideration shall be given to protect existing coatings on piping to minimize damage that may
result from the welding operations.
SUPPLIER shall preheat using approved methods as specified on the approved welding procedure
specifications. The minimum preheat temperature shall extend around the entire circumference of
the pipe and at least fifty (50) millimetres on each side of the weld joint. During completion of the
weld, the joint shall be maintained at a temperature between the minimum and maximum interpass
temperatures and shall be checked using temperature indicating crayons or other suitable method
immediately prior to, and during the full welding operation.
SUPPLIER shall prevent overheating and no part of the area shall be heated more than two hundred
degrees (200°) Celsius
Preheating temperature shall be established during procedure qualification and specified in the
welding procedure. Interpass temperature shall not be allowed to exceed 200°C.
The minimum preheat temperature shall be checked for a band of 50 mm from the bevel edge. The
welds must be at the minimum preheat temperature (or higher) prior to welding each pass. When
preheating with a flame, a minimum of 15 seconds shall elapse after the flame is removed from the
surface before preheating and interpass temperatures are measured.
No passes of a weld shall be cooled at a rate greater than that provided by natural air-cooling.
Welding shall not commence until all parts to be joined are secured against movement.
When using internal line-up clamps the root pass shall be completed for 100% of the circumference
prior to release.
For external line-up clamps the root pass shall be at least 50% complete before removal of the
clamp.
Cautionary Note: To minimize the risk of cracking of manual welds it may be necessary to weld the
hot pass for an approximate length of 300 mm in highest anticipated stresses, prior to moving the
pipe. This area would typically be on the bottom of the pipe but could be on the top of the pipe in an
over-bend situation, or on the sides of the pipe in a side bend situation.
Welding of a production weld shall normally continue without interruption and the weld temperature
shall be maintained above the minimum interpass temperature until at least two (2) passes are
completed, or half weld thickness is filled. If welding is interrupted at this point, the weld shall be
preheated to the minimum preheat temperature before welding commences.
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 24 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
Unless specified otherwise in the welding procedure, no beads shall commence until the preceding
bead has been completed.
The circumferential start locations of consecutive beads shall overlap by at least 25 mm.
The face of the completed weld should be 3 mm greater than the width of the original groove, but no
more than 5 mm greater.
Weld spatter, coating or loose debris shall be completely removed from the surface of the joint for a
minimum distance of 150 mm on each side of the weld.
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 25 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
8.1 GENERAL
Non-destructive inspection procedures used shall be documented and all such procedures shall be approved
by personnel qualified as specified in ISO 9712 Level III for the inspection method being employed and shall
be accepted by the company.
All butt welds shall be non-destructively inspected for 100% of their length by visual inspection and by
radiographic testing methods or automatic ultrasonic testing AUT, according with ASME and API
standards.
8.2 PERSONNEL
Inspectors shall be qualified in accordance with ISO 9712 and their qualifications shall be approved by the
CONTRACTOR and/or COMPANY.
CONTRACTOR and/or COMPANY can require personnel responsible for non-destructive inspection to
demonstrate the capability of the procedure to detect imperfections and to demonstrate their ability to
correctly interpret indications.
Only wire type Image Quality Indicators (IQI), according to ISO 19232-1 shall be used. The radiographic
technique shall comply with EN 1435 class B.
IQI's shall be placed so that each film has at least two: one within 25 mm from interpretable film extremity
and one at center of film. Four IQIs shall be placed 90° apart when a complete girth weld is radiographed in
a single exposure (panoramic exposure).
For qualification purpose (WPQ, welder qualification), radiographic technique shall comply with EN 1435
class B using film system class C2 according to ISO 11699-1.
Exposure shall be such that density through the weld is between 2.1 and 3.6.
Viewing conditions and facilities shall be such that film densities up to 4.0 can be viewed and interpreted. A
densitometer (with valid calibration) shall be available on Site at all times.
Inspection set-up SHALL be determined so that geometric unsharpness is maximum 0.25.
Final film interpretation shall be carried out on dry film.
Processing: All radiographic films shall be dried thoroughly prior to viewing and shall be processed and fixed
to allow storage of the films without image deterioration for at least 10 years. All films shall be re-fixed to
achieve the specified minimum archival life.
As a minimum, the film identification shall include:
Project Identification (as previously agreed with CONTRACTOR and/or COMPANY)
Line Size and Identification
Joint Number
Date (Day, Month, Year)
Radiographic Location.
The zero datum shall be located at the 12 o'clock position. The direction of numbering on tape shall be
clockwise when looking in the direction of flow. Defect location shall be in the metric system. Each
radiograph shall have reference markers at 100 mm (minimum) intervals.
All films shall be protected in individual plastic bags and stored in aluminium boxes closed with tight fit lids
before delivery to the Company. All film boxes shall be individually numbered and indexed (arrangement of
films to be stated) on their top.
Radiographers shall be certified level 2 in accordance with the requirements of ISO 9712, CSWIP scheme or
equivalent Company approved standard. At least one certified level 2 (minimum) radiographer shall be
present on each shift for film interpretation
The qualifications of each member of the NDT team shall be subject to approval of the Inspector.
Radiographic performance shall comply with the relevant Country and Project safety codes and radiation
acts. Attention is drawn to the necessity for audible and visual warning arrangements and for regular
monitoring or radiation levels.
If Computed radiography or radioscopy is considered it shall be qualified and used in production as per real
time radioscopy inspection optimum requirements.
Where quality and/or interpretation of radiograph is affected by the presence of a cable inside the pipe
(buckle detector …), an alternative NDE technique such as manual UT shall be qualified and used to inspect
the area.
8.5 MAGNETIC PARTICLE (MPI)
100% Magnetic Particle Inspection (MPI) is required for all fillet welds. Magnetic particle inspection according
to ASME V Art.7.
Magnetic particle inspection shall be used for:
Fillet Welds;
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 27 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
The finished weld bevel shall be Magnetic Particle Inspected following field cut back of pipe, at least when
this cut back is located within a range of 25 mm from original bevel.
Electromagnetic (a.c.) yoke and/or adjacent cable techniques shall be used.
SUPPLIER shall provide a MPI procedure based on ASTM E709 or equivalent for review and approval by
CONTRACTOR and/or COMPANY. Calibration blocks and approved magnetic flux indicators shall be
available on Site at all times.
Inspector reserves the right to test the proposed MPI procedure prior to acceptance.
MPI operators will be qualified level 2 in accordance with ISO 9712 or Company approved equivalent
standard.
Ultrasonic operators shall be certified level 2 in accordance with ISO 9712, CSWIP scheme or Company
approved equivalent standard. The Inspector reserves the right to test proposed UT operators on a test weld
prior to accept them on the job.
Manual ultrasonic (pulse echo technique) shall not be the primary inspection method for girth welds. MUT
might be applied only in the following cases:
o Lamination check and thickness measurement (0° probe angle);
o Examination of weld repair;
o Butt welds with a V or compound bevel preparation;
The inspection technique shall be contact method with register using TOFD - Time of Flight Diffraction in
combination with Phased Array technique that covers the entire volume of the weld plus HAZ.
Semiautomatic PAUT technique is applied for the inspection of:
o Examination of weld repair;
o Butt welds with a V or Compound bevel preparation;
The inspection technique, in lieu of RT, shall consist of a fully automatic Phased Array and TOFD inspection.
AUT system shall include an automatic multichannel ultrasonic flaw detector, which provides an adequate
number of channels for inspection to ensure 100 % volumetric examination of the weld including heat
affected zone through the thickness at one circumferential scan.
In addition, scanning for transverse defects shall be performed.
AUT technique could be applied for:
Butt-welds performed by mechanized welding on a narrow gap “J” bevel;
PROJECT AND LOCATION DOCUMENT NR.
LY0001-000-QA-11023
North Hamada (Area 47) Field
Development – Gathering Network and JOB NUMBER REV. SHEETS / OF
Oil Export Pipeline (EPCC) C-001-PRO-2019 0 28 / 29
CONTRACTOR DOCUMENT NUMBER
LY0001-000-ZH-11023
Butt-welds with V or Compound bevel preparation (Tie-In by Manual or Hybrid Welding Procedures);
Being AUT result highly sensitive on bevel changes, AUT inspection on repairs should not be allowed.
Defects other than cracks in the root, filler, and finish beads may be repaired with prior company
authorization. Repair welding procedures shall be prepared for both full thickness repairs and mid
thickness repairs.
A qualified repair procedure shall be required whenever a repair is made by welding when:
9.1 CRACKS
Metallurgical crack of any size shall not be repaired, and the joint cut out. Crater cracks of any
dimension shall be subject to repair.
A double repair requires prior COMPANY and/or CONTRACTOR authorization. For repair procedure
qualification purposes, this is a partial thickness or full thickness repair that tests a HAZ that has
received three full thermal cycles from welding. A grinding repair is not considered to be one of the
thermal cycles.
Subsequent repair of a double repair weld is not permitted unless specifically authorized by the by
the company and repaired with a qualified repair procedure appropriate for the number of thermal
cycles used.