Professional Documents
Culture Documents
Case Study - D4
Case Study - D4
___________________________________________________________________
KAM2285D
PREPARED BY:
SUBMITTED TO:
SUBMISSION DATE:
1
TABLE OF CONTENTS
1. Introduction 3
2. Problems 7
3. Solutions 13
4. Recommendations 19
5. Conclusions 23
6. References 25
2
1.0 INTRODUCTION
The monorail system in Putrajaya, Malaysia, is still under construction. Although there
has been little progress on the project since 2004, it was announced in 2020 that it will be
finished by 2025. Light rail was initially intended for Putrajaya, but as tunnel work for the
aforementioned system got underway, plans were altered and a monorail design was chosen
in its place. Two sublines were proposed: Line 1, a 12-kilometer (7.5-mile) monorail route with
17 stops, and Line 2, a 6-kilometer (3.7-mile) monorail route with 6 stations. To restart the
abandoned monorail project, the government suggested a new Light Rapid Transit (LRT)
system in 2019. The Monorail Suspension Bridge, which is still under construction, and the
Putra Bridge will be part of the monorail. At the Putrajaya/Cyberjaya ERL station, the monorail
line would enable connections to the already-existing KLIA Transit, which connects to Kuala
Lumpur and Kuala Lumpur International Airport, and the still-under-construction MRT
Putrajaya line. The initial cost of the project was RM 400 million.
The Auditor General's 2021 Series 2, which was just issued, claims that the Putrajaya
Monorail project's postponement has had an impact on the federal territory's integrated
transport system and that it would be a waste if the infrastructure developed is not used.
According to the research, the monorail's development delay also had an effect on bus
services and the usage of connected facilities. The monorail is the foundation of Putrajaya's
public transportation system. The research said that in order to alleviate traffic congestion in
the downtown and residential neighbourhoods, the government had to supply TLK (parking
spots). According to the article, work has not yet been finished on the two-route monorail
project, which includes Line 1 (13.2 km) and Line 2 (6 km), as well as the monorail station at
The audit was unable to substantiate the reasons for the project's suspension in 2004
since no supporting papers were received, according to the report, which was made public.
"The audit's physical visit on August 16, 2022, confirmed that a part of the infrastructure, such
as the pillar structure for the tracks, and the bridge for the monorail, had been constructed,"
3
the report stated. Only three forms of transport were completely exploited out of the four major
infrastructure projects that were finished, it claimed. Express Rail Link (ERL), bus, water
transportation, pedestrian walkways, and cycling lanes are four projects that have been
finished, whereas ERL, bus, pedestrian walkways, and bicycle lanes are the three modes that
are now completely used. In order to guarantee that the proper infrastructural facilities can be
constructed and used, the study advised the Federal Territories Ministry (KWP) and the
Putrajaya Corporation (PPj) to examine the development plan in light of the conceptual
changes of Putrajaya's growth. Additionally, it is advised that the KWP, the Ministry of
Transportation, and the PPj determine how the infrastructure should be used to serve the
According to a statement from the transport minister, Datuk Seri Wee Ka Siong, the
ministry of transport (MOT) has been informed on the plans for a maglev (magnetic levitation)
train system for Putrajaya. The development of a maglev monorail for Putrajaya as well as its
integration with existing rail and transportation systems would be the subject of additional
negotiations between the transport ministry and the ministry of federal territories, according to
the transport minister. The briefing was part of a visit to the transport ministry by several heads
of industry from Korean companies, including Park Geunhwa, the representative of Hyundai
Corporation in Malaysia, Min Jun Sung, the senior managing director of EP Korea, Yoo Jai
Tark, and Chung Dong Wan, the chairman of Maglev MKC. Rani Hisham, the CEO of KTM
Berhad, and Shahriman Shafein, the MOT DG for rail, were also present. The use of Hyundai
Rotem's Class 83 and Class 91 trains by Malaysian rail operator KTM Berhad is "a testimony
to their durability and reliability" with the assistance and support of the Korean company, the
transport minister said. The rail operator's ETS (Electric Train Service) utilises Class 91 trains.
More material and knowledge partners are presently being added to the National Rail Centre
of Excellence by the transport ministry. In order to improve the ministry's training in technical
knowledge related to railway and highway speed, the ministry said it is working out the
4
specifics for the work and partnership with the Korea Railroad Research Institute (KRRI)
Government away from Kuala Lumpur City Centre, Putrajaya has been developed as the
country's administrative hub. The transfer procedure began in 1999 and is anticipated to be
finished in 2011 or 2012. Sadly, it appears that no preparation has taken place for the private
sector in this process. Without the presence of the private sector operating in Putrajaya, the
dominance of ministries, departments, and agencies in urban economics is still unable to have
a multiplier impact on the city's economy. Putrajaya's economic activities are mostly focused
on giving residents access to amenities including stores and dining options. However, if a well-
planned marketing is put in place, tourism has the greatest potential for growth among non-
government economic activity. The research done on the projected development, which
includes the building of Putrajaya Monorail Transit System Line 1 (PMT1), is presented in this
inexpensive, practical public transit, especially for trips between their homes and places of
employment. The purpose of the research is to assess the financial viability of developing
PMT1 in Putrajaya as well as the commercial value of operating monorail services and the
Tram infrastructure development was intended to begin within three years, according
to Federal Territories Minister Datuk Seri Tengku Adnan Tengku Mansor. The development of
the tram system, which is now under the control of the Economic Council, was recommended
for construction by the minister because it would be more affordable than the abandoned
monorail projects. After receiving approval from the EC, SPAD had anticipated to launch a
procurement process for the Putrajaya–Bangi tram line in 2018. During their annual review of
public transit for 2017, SPAD made this announcement. The tram system was chosen
because it was significantly less expensive to build and operate than traditional rail systems.
In addition to covering the distance between Cyberjaya and Kajang, the tram system is
5
anticipated to be connected with the current and upcoming rail lines between Putrajaya and
Bangi. The MRT Kajang Line only goes as far as Kajang, however the MRT Putrajaya Line
will stop at the operational KT3 PY41 Putrajay Sentral station. One of the anticipated stations
along the intended tram line will be the upcoming HSR station at Kampung Abu Bakar
Baginda. Due to the large roadways between Putrajaya and Bangi, which enable the tram
6
2.0 PROBLEMS
private-sector company that can be used to finance, build, and operate projects, such as public
transportation networks, parks, and convention centers. Financing a project through a public-
private partnership can allow a project to be completed sooner or make it a possibility in the
first place.
intensive building project, but a private enterprise might be interested in funding its
construction in exchange for receiving the operating profits once the project is complete.
Private projects can touch up all the flaws that government agencies have. Government
agencies for some part need to cooperate with the public sector that at the end of the day will
7
give benefits for the government itself. If the government agency itself notices that they cannot
stand on their own, then the government cannot be selfish to refuse to get help from the private
sector.
This is due to the fact that , as the former Prime Minister said, there is a private agency
that wants to cooperate and there are companies ready to take over the project. However, the
minister at that time refused to cooperate, thus the companies were ignored by the
government. This shows that , if the private sector was allowed to do it , it could have been
done through a process of tender and the project could have been completed as the fact that
this project was started in 2004. The Putrajaya Monorail could be done if the project is handed
Private sector can contribute to public revenues, which are critical to increasing
countries’ self-reliance and sustainable growth. If financial problems are one of the reasons
why this project failed, partnership with the private sector maybe can help by giving their
financial support. This joint statement fully recognizes the diverse forms of engagement that
the private sector brings to support development, together with governments, donors and civil
society. These include core business activities, public private partnerships, social
This joint statement recognizes the important role played by governments and other
public development actors in enabling and leveraging these private sector activities. It stresses
the common objective across all partners to build on the various forms of private sector
engagement. From this cooperation with the private sector can cooperate in investment,
capacity building, inclusive business models, knowledge sharing and innovation and
contributions to policy dialogue. This shows that Putrajaya Monorail can reach success as the
project also gets support from the private sector as the private sectors can provide support
8
2.2 Poor Financial Planning and Cost
There might not have been enough thought put into the budgeting and financial
planning for this project, which led to its failure. The cost of a project is essential for
determining, budgeting, and maintaining cost control in order to ensure that the project can be
finished without exceeding the amount of money that was set aside for it. The process of
is referred to as Estimate Costs. The process of aggregating the estimated costs of individual
Determine Budget.
The process of controlling costs includes keeping an eye on how far along the project
currently is. It is essential to have an accurate cost estimate for the project in order to be able
to determine very important things, such as the amount that will be spent or the amount of
money that will be needed. It is the best way to be able to understand and manage the
investment that the project requires, and it is also the most straightforward way to do so. When
looking at cash flow, one should look at the schedule for how much money will be made and
how much money will be spent on the programme. It is stated to be the analysis of the funding
needs, taking into consideration, for instance, that in the construction industry, funds are
According to the most recent report from the Auditor General, the government of
Malaysia has lost an estimated RM812.91 million from the development of its administration
capital Putrajaya. A large portion of this loss, RM799.34 million, was caused by a monorail
project that was put on hold in 2004. Of the monies spent on the monorail project, some
RM797.18 million was used for the development of the project, while another RM2.16 million
was for the maintenance of a transportation. The amount of money that the government of
9
However, it’s possible that the government itself was unaware of their negative cash
flow and the poor financial planning they were doing. In the case of the monorail project, there
is a possibility that this project will face difficulties in financial planning as well as a low financial
plan. Losses could result from the management team neglecting to give adequate attention to
the project’s financial planning. During the process of financial planning, it is possible to
guarantee that financial control and cost control will be carried out in the most efficient manner
possible. This will guarantee that all of the items will remain within the allotted spending limit
Inputs include contract requirements, a project financial plan, cost and revenue
benefits, and change requests. The impact of change requests, either in cost or revenue
streams, must be analysed and incorporated into the financial plan, and their effect in
borrowing and other features must be considered. The conclusion that can be drawn from this
is that, in the absence of adequate funding, projects will struggle to obtain the appropriate
resources and will have a very difficult time locating the money that is required. Mainly due to
the fact that the choice that is made regarding the project’s finances will have a significant
10
2.3 A Complete and Total Waste of Money
One of the most significant challenges facing the building and construction industry is
waste management. During the design and construction process, there are many activities
practitioners. Waste is generated throughout the various stages of construction, including the
planning, estimating, and construction stages, according to Wahab and Nawal. In addition,
waste can be produced during the design phase, during operational phases, during
procurement, and during the material handling process. The vast majority of these consume
time and effort without adding value for the customer, which results in material losses, delay
According to the Auditor General’s Report for Year 2021 Series 2, which was published
today, the audit review discovered that there was waste for Putrajaya’s development
management amounting to RM812.91 million. This information was disclosed in the report.
Auditor General, Datuk Seri Nik Azman According to Nik Abdul Majid, the waste involved the
11
delay of the monorail project as the backbone of the transport system in the Federal
Building a better bus infrastructure requires a total of RM200 million, which is the only
amount that will allow for the renovation of Putrajaya Central, the maintenance of existing bus
stops, the addition of bus lanes, and the installation of a traffic signal priority system for buses.
When taking into consideration that the monorail track infrastructure has not yet been installed,
the tunnels that are used by the monorail could even be used by the buses. With that amount
of money, the dreadful bus system in Putrajaya could most definitely be upgraded. Buses will
be able to travel at higher speeds as a result of the implementation of bus lanes and a traffic
signal priority system, which will also result in an increase in the frequency of buses and a
reduction in the amount of time needed for commutes. Because buses are so adaptable, this
initiative will have a more significant impact on the city and will reach more people.
The productivity of an organization, the amount of material that is lost, and the amount
of time it takes to finish a project are all directly impacted by waste, which ultimately results in
a significant revenue loss. The landfill receives a sizeable portion of its volume from the waste
that is physically present. The amount of waste generated by the construction industry is
comparable to that generated by households four times over, and more than fifty percent of
As a result, in order to reduce the amount of waste that is produced, the government
of Malaysia needs to investigate the primary reason for the generation of waste in order to
resolve the issues that have been occurring with the Putrajaya Monorail. There are a variety
of factors that contribute to waste in the construction industry, and the money that is spent on
waste removal could be put towards something that is of higher priority. Such as, fix any
problems that related to the public problems. Government will need to allocate budget for a
12
3.0 SOLUTIONS
The project’s revival was first mooted in 2016 when MMC Corporation Berhad (MMC)
submitted a proposal to the Economic Council (EC), following the government’s investment
into the Klang Valley MRT project. Therefore, the government has taken several measures to
One of the primary reasons for the project's halt was a lack of funding. Therefore, it
may be possible to secure the necessary funding by exploring new financing options, such as
public-private partnerships or through government grants in order to complete the project. For
example, in 2019, Putrajaya Corporation chose to sell 80% of its Nadi Putra shares to GETS
Global, allowing Putrajaya to relaunch the monorail project. Despite the fact that the
suspension bridge and tunnels for the monorail project are already completed, the cost of
continuing and finishing the projects is expected to be over RM2 billion. This is the reason as
to why the government chose to release a Request for Proposal (RFP) to any firms interested
in pursuing or resurrecting the project. Since there were numerous methods to execute the
project successfully, depending on the sort of technology used and employed, an RFP would
enable private businesses to provide cost quotations. As part of the RFP, a comprehensive
timeline and budget were included, as well as a detailed plan for construction, operation,
13
Figure 3.1.1: Federal Territories Minister Khalid Abdul Samad in Press Conference
In January 2020, Federal Territories Minister Khalid Abdul Samad mentioned the
RM400 million Putrajaya Monorail Project which was left abandoned for nearly 16-years-old,
was expected to be completed in 2025 following the discussions between the Ministry of
In April 2020 along with the meeting and RFP, Putrajaya Corporation (PPj) has
confirmed that the Malaysian government will proceed with the completion of the Putrajaya
monorail project. According to the KWP, the goal of the RFP is to request cost inquiries and
recommendations from the private sector. The KWP will then investigate the feasibility of
continuing the Project under a public-private partnership framework and decided on the sort
of equipment and technological resources to be employed for the project's development and
implementation. The KWP also confirmed that the RFP would be flexible, and that it is willing
procurement for the Project will be substantially influenced by the system technologies
chosen.
14
The cabinet made a request to the Federal Territories Ministry (KWP) to have
a meeting with the MoT. The meeting was held two weeks before, and a contract was made
for the KWP to proceed with further action. This is to solicit private-sector proposals. The
remaining work will be done by examining the viability of continuing this project through
collaboration with the private sector, since several firms have expressed interest in partnering
on the project to the point of submitting proposals for the project. Following that, according to
Tan Sri Annuar Musa, the federal territories minister, the RFP will allow the government and
private sector to work together hand-in-hand to ensure the success and completion of the
project.
In a press conference held in October 2020, The ministry announced that it welcomes
any proposal following the launch of the RFP within three months. The project's design and
planning phases began, which included the production of reliable technical plans along with
price estimations. The government also looked at possible sources of funding for the project.
However, one year after the press conference in October 2021, no additional information
regarding the RFP and offers has been presented. Nevertheless, Datuk Henry Sum Agong,
the Deputy Minister of Transportation, pointed out that the project was expected to be
To conclude here, according to Annuar, the federal government opted to issue the RFP
since a few companies expressed their interest in partnering on the project and even
presented their proposals to them. This was one of the reasons to which the government
decided to continue on this project. Annuar also stated that the monorail construction was
already halfway completed, and that the essential infrastructure, such as vaults and overhead
roadways, had been created with significant amounts. "Putrajaya, as the country's
remarked. He also stated that the routes and tracks had been finalised, with nine stations
guaranteed. Annuar, on the other hand, emphasised that this may change with regard to the
15
proposal adopted since there are other planned stations connecting the administrative capital
with Cyberjaya, Bangi, Putrajaya, and Kajang are under the Transport Ministry's jurisdiction.
One of the main goals in the project's planning is to establish an efficient transit
infrastructure adequate for a 21st-century city design. The development of a transport strategy
must be performed with the goal of pleasing as many people as possible while minimising air
and noise pollution. In this regard, due of the numerous obstacles involved in evaluating such
investments, most concessionaires are equivocal about judging the worth of investment return
with reference to infrastructure projects (Alias et al., 2014). Thus, a financial evaluation on the
abandoned Putrajaya Monorail Project would include a review of the project’s costs and
benefits, as well as the prospective return on investment by the government and others parties
involved.
The costs associated with the project would include the design and engineering,
construction, land acquisition, equipment, and ongoing maintenance and operations. These
costs must be carefully assessed to determine the total investment required for the total
completion project. This is to avoid and minimise wastage in the future. Meanwhile, the
benefits of the project included the increased mobility and accessibility, reduced traffic
congestion, and economic development in the surrounding areas. These benefits have to be
quantified and compared to the costs to determine if the project is financially viable. In addition
to that, the sources of funding for the project had to be evaluated to determine if they are
sufficient to cover the costs, unless, alternative funding sources must be explored aftermath.
Last but not least, the potential return on investment must be analysed to determine if the
project will generate a positive financial return. This may involve forecasting future revenue
16
3.3 Continuous Review of the Project
Continuous review is also essential to the success of the Putrajaya Monorail Project.
One of the most important aspect in reviewing the project is the project progress itself. Regular
reviews should be done to examine the project's present condition. This should contain an
assessment of the completed goals, deadlines, budget, and risk management method.
Furthermore, technical specifications are crucial components that the government must
consider in order to resurrect this project. The project's technical requirements should be
evaluated on a regular basis in order to assure that they are relevant as well as effective. Any
updates required should be made in a timely manner. Besides, stakeholders' needs and
concerns should be addressed and incorporated into the project through regular engagement
For instance, the Land Public Transport Commission (SPAD) has agreed to begin a
study of feasibility for a railway and tram service in Putrajaya and Cyberjaya as the
government received a bid to resurrect the abandoned 2004 project in 2016 (Aziz, 2020).
MMC Corporation Berhad (MMC) has proposed an initiative to the Economic Council (EC) to
resume the Putrajaya Monorail project, which was halted in 2004 owing to budget restrictions.
If authorised, the project is projected to be finished by 2021, coinciding with the completion of
MRT 2 (Sg Buloh-Putrajaya) the same year. It is uncertain if MMC is working alone on the
Putrajaya monorail project or in collaboration with other construction parties because the MMC
is currently in a JV with Gamuda Berhad in the construction of the MRT. Syed Hamid Albar,
Chairman of the SPAD, is also claimed to have acknowledged to the newspaper that MMC
had made a request to the EC to resurrect the project and that SPAD will now perform a
feasibility assessment for monorail and tram services in both Putrajaya and Cyberjaya.
Another effort done by the government on the project was in April 2019. Putrajaya
Corporation (PPj) has stated that the government plans to resume construction on the project,
17
that had been earlier postponed in mid-2004. Former PPj president Aminuddin Hassim stated
that construction was going to begin as soon as possible, and that a study would be carried
out beforehand. In accordance with PPj, there are now around 90,000 people residing in
there's at that moment no indication of the RFP's information and further content, yet
considering that this is a private-partnership project (PPP), they had presumed terms typical
Along with the government's ongoing review, the KWP and PPj have examined the
concept by the middle of 2019, so that appropriate facilities and amenities may be provided in
effective and efficient way. Among those to be examined were the route to be taken and the
method of funding, including whether it will be partially funded by the private sector or vice
versa. Despite that, the various ministries and agencies have collaborated to establish the
best path ahead for the utilisation of existing facilities that will assist people and minimise cost.
The efforts made by the Malaysian government towards the abandoned Putrajaya
Monorail Project can be seen as mixed. On one hand, the government showed its commitment
to improving transportation infrastructure in the country by proposing the monorail project and
investing some initial funds towards its development. However, on the other hand, the project
faced numerous hurdles that ultimately led to its abandonment, suggesting a lack of adequate
planning and foresight. Overall, while the government's efforts towards the project were
commendable, the outcome highlights the need for better planning and risk mitigation
strategies in future infrastructure projects. It is important for the government to learn from the
challenges faced by this project and apply those lessons to future initiatives, to ensure that
public investment is utilized in the most effective and efficient manner possible.
18
4.0 RECOMMENDATIONS
The government might make an effort to resolve any technological issues that would
have slowed the project advancements. This can entail completing further feasibility analyses.
Choosing the different routes or building techniques or consulting an expert on how to get over
any legal or regulatory obstacles. Make sure all permits and approvals for the project
construction are obtained. In assessing the feasibility of transportation options in urban areas,
one important factor is the cost-effectiveness of different systems. As such, comparing the
would be most financially viable for a given context. According to Datuk Seri Tengku Adnan
Mansor (2016) the government viewed trams as being a suitable alternative to the abandoned
A tram utilizes a hybrid trackless train and electric bus system called an automated
rapid transit (ART) that is eco-friendly and cheaper compared to conventional rail public
19
transportation systems. A tram system can be built using existing infrastructure, while monorail
construction requires much more extensive preparation, vertically designed tracks, and
guideway for a monorail system is higher than that of constructing a guideway for a tram
system. Project management and maintenance for monorail systems are also more
expensive, particularly due to the specialized engineering knowledge required and the cost of
replacement parts. A good and effective project management requires more planning and
resources for monorail projects, which adds considerably to their overall cost.
It is vital to recognize Putrajaya monorail project cost tools and techniques by utilizing
critical path method, program evaluation and review technique, and net present value in order
to ensure that the monorail project is completed timely and within budget. Hence, while both
tram systems and monorail projects have their advantages and disadvantages in terms of
transportation efficiency, it is generally more cost-effective for urban areas to opt for a tram
system due to their lower construction, maintenance, and project management costs
compared to monorail projects. It is important to note, however, that the decision of which
sustainable practices are becoming increasingly important priorities for cities around the world.
The tram also has been identified as one of the greenest urban transport modes due to its low
environmental impact when in operation. With technological improvements and changes, most
trams do not produce any pollution at the point of use. The delayed project construction may
feasibility studies and risk assessments before embarking on any transportation project to
20
A professional and effective project planning can contribute success in the project as
it allows for a clear understanding of the scope, timeline, budget, and potential risks. This
transportation system for urban areas. Overall, the decision to implement a tram system or
monorail project in urban areas must be made with careful consideration of all factors involved.
Therefore, the delayed project monorail due to lack of funds, it is better to use tram systems
as trams are much cheaper to install than metro trains, subways, or other forms of heavy rail.
important factors include the environmental impact of each transportation option and their
Figure 4.1.2: The 53km tram system will connect major cities such as Cyberjaya, Putrajaya,
According to Shen (1997), both the owner and contractor will suffer as a result of
delays in the completion of construction projects resulting extra cost and loss in financial
21
return. Thus, delay is costly for both owner and contractor. The Malaysia government financing
options explore various financing options to secure funding for the project such as public-
private partnerships international loans. By securing adequate funding, any problems during
construction could be avoided, hence, lead to the success. It is vital to have cost control on
the project to minimize the construction delays and blockers. The most significant cause of
project delays is poor cash flow management, followed by late payments, lack of resources,
economic growth.
completed within their timeframe. Construction projects are delayed by financial pressure
when estimating is not taken into account. It is extremely important that construction
companies avoid errors as they can significantly impact their bottom line and limit their capital.
The project will move forward if everything stays on track. By securing adequate funding, any
problems during construction could be avoided, hence, lead to the success. The Malaysia
government financing options explore various financing options to secure funding for the
analysis, risk assessment and feasibility study to ensure the successful implementation of any
transportation project. Therefore, it is imperative that cities thoroughly evaluate the benefits
and drawbacks of different transportation options before making a decision. Financials must
be carefully managed to ensure that the chosen transportation system can be sustained in the
long term.
To address the issue of the abandoned Putrajaya monorail project, it is imperative that
there be a collaborative effort between the government and private sector. Some of Public-
Private Partnerships have proven successful in the past, with Malaysia utilizing them through
companies such as Putrajaya Holdings Sdn Bhd and Kuala Lumpur City Center Bhd as the
project managers. Partnering with the private sector can ensure more efficient and successful
22
completion of such infrastructure projects, mitigating risks and sharing resources while also
reducing costs. Furthermore, adopting this approach would enable the government to prioritize
operation, and maintenance tasks to expert private sector entities. This approach provides a
practical solution that can address the problem of abandoned infrastructure projects in
It is essential to increase the political will and support for Public-Private Partnership
(PPP), as this would enable Malaysia to move ahead in the direction of achieving its
development goals effectively and efficiently. Therefore, it is essential for the government to
increase the political will and support by cooperating with the private sector and required
political backing in order to be successful. This might involve stakeholders, forming support
networks, and raising public knowledge of the advantages of the initiative. Furthermore,
involving the local community in decision-making processes and regularly communicating with
them throughout the project can improve transparency and increase public support for urban
transportation initiatives.
Planning a project appropriately and fulfil its requirement based on objective, scope
and timeframe. Guidelines supporting the plan's vision are essential to an effective
transportation plan. If decision-makers do not have this guidance, they will have to guess at
what actions are needed, inevitably leading to arbitrary decisions. Hence, action must be taken
so that other future Malaysia's development projects effective and efficiently be executed in
construction.
5.0CONCLUSION
The Putrajaya Monorail project, which was put on hold in 2004 owing to financial
restrictions, could be restarted. The Economic Council (EC) has received a request from MMC
Corporation Berhad (MMC) to resuscitate the project, according to today's The Sun. The
project, if allowed, is anticipated to be finished by 2021, which would coincide with the
23
completion of MRT 2 (Sg Buloh-Putrajaya), according to the article. The Economic Planning
Unit and other authorities will be in charge of the project. The insider was described by the
local daily as stating, "To begin with, the monorail station at Putrajaya Sentral will integrate
with the first station of MRT 2, with seamless connection via an 84m skybridge." It's unknown
if MMC is working on the Putrajaya monorail project alone or in collaboration with other project
delivery partners. The MRT is presently being built by MMC in a joint venture with Gamuda
Berhad. The insider also disclosed to The Sun that private finance or the use of a public-
private partnership model might be used to support the project. Phase One of the project was
expected to cost RM400 million for two lines under the initial concept put up in 2004. It's
unknown if MMC is working on the Putrajaya monorail project alone or in collaboration with
other project delivery partners. The MRT is presently being built by MMC in a joint venture
with Gamuda Berhad. The insider also disclosed to The Sun that private finance or the use of
a public-private partnership model might be used to support the project. Phase One of the
project was expected to cost RM400 million for two lines under the initial concept put up in
2004. The rehabilitation, which will include improved roads to Cyberjaya, Bangi, and Kajang,
is being described as one of the "unfinished businesses" preventing Putrajaya's progress. The
original plan for Putrajaya will be maintained, and an improved route is anticipated to
encourage linkage to other rail services such the East Coast Rail Link, Mass Rapid Transit,
and the high-speed train between Kuala Lumpur and Singapore. Both ministries were
reportedly looking at methods to launch the project as soon as possible last year, and the
24
REFERENCES
Abdul-Rahman, H., Takim, R. and Min, W.S. (2009). Financial-related causes contributing to
Alias, A., Zahari, W., Yusoff, W., & Samad, Z. (n.d.). The Financial Evaluation of
System. https://core.ac.uk/download/pdf/162013376.pdf
Azhar, K. (2018, December 15). Putrajaya Monorail RFP to be called next January. Biz
putrajaya-monorail-rfp-be-called-next-january
Aziz, A. (2020, October 2). Govt to revive Putrajaya monorail project. The Malaysian
https://themalaysianreserve.com/2020/10/02/govt-to-revive-putrajaya-monorail-
project/
Chan, M. (2022, June 15). Putrajaya area to get maglev monorail; to be integrated with other
https://paultan.org/2022/06/15/putrajaya-area-to-get-maglev-monorail-to-be-
integrated-with-other-rail-transportation-systems-wee-ka-siong/
Editor Selangor Journal. (2023, February 16). Delayed monorail project affected Putrajaya
https://selangorjournal.my/2023/02/delayed-monorail-project-affected-putrajaya-
integrated-transportation-system-ags-report/
Fairuz M.S. (2016). Tram service for Putrajaya within three years. New Straits Times.
service-putrajaya-within-three-years
FMT Reporters. (2016, September 23). MMC proposes Putrajaya monorail. Free Malaysia
25
https://www.freemalaysiatoday.com/category/nation/2016/09/23/mmc-proposes-
putrajaya-monorail/
Lim, M., & Razak, F. A. (2020, October 5). Malaysia: Revival of the Putrajaya Monorail
https://insightplus.bakermckenzie.com/bm/projects/malaysia-revival-of-the-putrajaya-
monorail-project
Nagapan, S., Rahman, I. A., Asmi, A., Memon, A. H., & Latif, I. (2012). Issues on
https://doi.org/10.1109/chuser.2012.6504333
Nagapan, S., Rahman, I. A., & Asmi, A. (2011b). A Review of Construction Waste Cause
https://www.researchgate.net/publication/258224434_A_Review_of_Construction_Wa
ste_Cause_Factors
New Straits Time. (2023, February 18). Dr Mahathir says Putrajaya monorail project could
have been continued via private sector. Nation. Retrieved May 14, 2023, from
https://www.nst.com.my/news/nation/2023/02/881247/dr-mahathir-says-putrajaya-
monorail-project-could-have-been-continued
Pinto, J. Â. C. (2009). Financing the project. Paper presented at PMI® Global Congress
Salim, S., & Aziz, A. (2023, February 16). Govt lost RM799m on axed Putrajaya monorail
https://theedgemalaysia.com/node/655575
Sangwon Han a et al. (2011). A system dynamics model for assessing the impacts of design
https://www.sciencedirect.com/science/article/pii/S0895717711003803
26
Zukri. (2020, January 10). Long-abandoned Putrajaya monorail set for completion by... The
https://themalaysianreserve.com/2020/01/10/long-abandoned-putrajaya-monorail-set-
for-completion-by-2025/
27