You are on page 1of 49

PAINTING REQUIREMENTS FOR

PIPING - EQUIPMENT AND STRUCTURES

MOZAMBIQUE LNG – 6.44 MTPA

1 21-MAY-2020 Issued for Design M. Turetta P. Khoei C. Borghesan


0 16-JAN-2020 Issued for Design M. Turetta P. Khoei C. Borghesan

Issued for Review and


B 24-OCT-2019 M. Turetta P. Khoei C. Borghesan
Acceptance

Issued for Review and


A 04-SEP-2019 M. Turetta P. Khoei C. Borghesan
Acceptance

Revision Date Description Prepared by: Reviewed by: Approved by:

Security COMPANY USE Total number of Pages (including Cover sheet): 49

Contractor
Contract No. Contractor Document No.
For Rev.
Contractor
Documents LNG19-00079,
000-KA-E-093001 1
SSF19-00080

Company Project System Originator Discipline Doc. Type Sequence Language Revision
Document
No. MZ 000 CCX MC SPC 00001 - 1
This document is Work Product under the Agreement between ANADARKO
MOÇAMBIQUE AREA 1, LIMITADA (“COMPANY”) and CCS JV S.c.a.r.l. (“CONTRACTOR”).
All rights, title and interest in this Work Product, including any and all copyrights therein,
are owned by COMPANY, except as reserved under the Agreement.
Uncontrolled if Printed
Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

REVISION MODIFICATION LOG

Page No. Section Description of Changes

7 1.4.1 Clarification on scope for liquid paint use added


15 3.0 Wording Improvement on Bolt/Nuts requirements
Listing of Standard Production Items added as indication. Guarantee
16 3.2
terms scope clarified.
Change-mark to Clarify Miscellaneous Items Coatings and Extent
37 / 38 / 39 APP. 2
between Intertidal and Permanently Immersed Areas
43 APP. 4 Rotating and Automation / Instruments finish color detailed

HOLD LOG

HOLD No. Description of Holds

INPUTS / REFERENCE DOCUMENTS

Document Number Title Status

Uncontrolled if Printed Page 2 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

TABLE OF CONTENTS
1.0 INTRODUCTION .................................................................................................................5
1.1 Project Description ...........................................................................................................5
1.2 Document Purpose ...........................................................................................................5
1.3 Acronyms, Abbreviations and Definitions.......................................................................... 5
1.4 Scope ...............................................................................................................................7
1.4.1 General .....................................................................................................................7
1.4.2 Exclusions .................................................................................................................7
1.4.3 Responsibilities ......................................................................................................... 8
1.4.4 Air Data for Final Installation Site............................................................................... 9
2.0 REFERENCES .................................................................................................................. 10
2.1 Codes and Standards ..................................................................................................... 10
2.2 Regulations .................................................................................................................... 13
2.3 Other Specifications ....................................................................................................... 13
3.0 DESIGN ............................................................................................................................ 14
3.1 General Requirements ................................................................................................... 15
3.2 Standard Production Items ............................................................................................. 16
3.3 Piping Items.................................................................................................................... 16
3.4 Machined Surfaces, Bolts and Bolt Holes ....................................................................... 17
4.0 DOCUMENT SUBMITTALS .............................................................................................. 17
5.0 MATERIALS ...................................................................................................................... 18
6.0 COATING PREQUALIFICATION AND TESTING.............................................................. 19
7.0 SURFACE PREPARATION ............................................................................................... 19
7.1 Preliminary Operations ................................................................................................... 21
7.2 Environmental Conditions ............................................................................................... 21
7.3 Cleaning Precautions for Stainless Steel and special Alloy............................................. 21
7.4 Cleaning Precautions for Galvanized Steel ..................................................................... 22
7.5 Power Tool Cleaning ...................................................................................................... 22
8.0 APPLICATION................................................................................................................... 22
8.1 General .......................................................................................................................... 22
8.2 Environmental Conditions ............................................................................................... 23
8.3 Stripe Coat ..................................................................................................................... 24
8.4 Complementary Requirements ....................................................................................... 24
8.5 Galvanized Steel ............................................................................................................ 25
9.0 INSPECTION AND TESTING ............................................................................................ 25
9.1 General .......................................................................................................................... 25
9.2 Abrasive / Paint Material Storage ................................................................................... 26
9.3 Environment Conditions.................................................................................................. 26
9.4 Ventilation ...................................................................................................................... 27
9.5 Surface Preparation Inspection....................................................................................... 27
9.6 Coating Inspection .......................................................................................................... 27
10.0 REPAIR AND COMPLETION ............................................................................................ 28

Uncontrolled if Printed Page 3 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

10.1 Repair of Defects ............................................................................................................ 28


10.1.1 Small Dimension Damage ....................................................................................... 28
10.1.2 Medium Dimension Damage ................................................................................... 29
10.1.3 Extensive Damage .................................................................................................. 29
10.2 Completion of Zinc ethyl-silicate primed surfaces ........................................................... 29
10.3 Partially Coated Items .................................................................................................... 29
11.0 HANDLING OF COATED ITEMS ...................................................................................... 30
12.0 REPORTING AND SUBMITTAL........................................................................................ 30
12.1 Reporting Documents ..................................................................................................... 30
12.2 Submittals ...................................................................................................................... 30
12.3 Final Documentation....................................................................................................... 31
13.0 GUARANTEE .................................................................................................................... 31
14.0 DURABILITY ..................................................................................................................... 33
15.0 APPENDICES.................................................................................................................... 33
APPENDIX 1 PAINT PRODUCTS ............................................................................................. 34
APPENDIX 2 PAINT SCHEDULE ............................................................................................. 36
APPENDIX 3 PAINT SYSTEM DESCRIPTION ......................................................................... 40
APPENDIX 4 FINAL COAT COLORS ....................................................................................... 43
APPENDIX 5 TEST ITEMS........................................................................................................ 45

Uncontrolled if Printed Page 4 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

1.0 INTRODUCTION

1.1 Project Description


Mozambique LNG is a two-train, nominal 6.44 MTPA per train, LNG facility using APCI
liquefaction technology. Hydrocarbon condensate, separated from the feed is processed
and exported separately.

The facility will be constructed at a remote coastal location in the Cabo Delgado province of
Mozambique.

The feed stream is fed to the LNG plant which comprises gas/liquid separation, gas
treatment (removal of acid gas, dehydration and mercury), heavy component (C5+)
removal followed by gas liquefaction, storage and export. Condensate stabilization and
export facilities are also included.

Phase 1a of the project consists of the first two (2) LNG trains and relevant utilities.

1.2 Document Purpose


This standard specification establishes and defines surface preparation and protective
coating systems (liquid paints) to be applied to vessels, exchangers, heaters, machinery,
instruments, piping, structures, and other items.
This document outlines the inspection and testing criteria and guarantee requirements for
protective coating works.

1.3 Acronyms, Abbreviations and Definitions


The following acronyms, abbreviations and definitions apply to this document:
TERM DEFINITION
COMPANY Anadarko Moçambique Area 1 Limitada
Chiyoda, CB&I and Saipem Joint Venture,
CCS JV
Also termed as Purchaser or Contractor
LNG Liquefied Natural Gas
Protective Coating
Used synonymously throughout this specification
And Paint
Dry Film Thickness Specified in (mils) and SI microns.
(DFT) One mil equals 25 microns.
Carbon Steel Steel containing up to two (2) percent carbon.
Steel containing up to five and one-half (5-1/2) percent chromium
Low Alloy Steel
or three and one-half (3-1/2) percent nickel.
Any group (i.e. 300, 400 series) of corrosion-resistant iron-
chromium alloys, containing 10% or more chromium, sometimes
Stainless Steel
containing other elements, such as nickel, silicon, molybdenum,
tungsten, and niobium.

Uncontrolled if Printed Page 5 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

TERM DEFINITION
The temperature for determining the coating system, the governing
operating temperature is the temperature which prevails inside
Operating equipment and piping during any intended normal operation.
Temperature Unless otherwise specified this is the minimum operating (cold
insulated services) or maximum operating temperature (all other
cases).
Unpainted spot, thin spot or void in the coating film which
Holiday eventually could allow moisture or other contaminants to contact
the substrate.
Severe/Seacoast Within five miles of coast/seawater and in presence of
Environment industrial plants subject to aggressive external corrosion.
Party responsible for the supply of a particular product, good or
service. In case of painting service the party responsible for surface
Supplier
preparation and application of the external coating, also referred
as Applicator.
A SUPPLIER, reputable and experienced to execute the Protective
Coating Works, organized and qualified, entitled by a purchase or
Applicator
work order, either directly as CONTRACTOR’s SUPPLIER or
Indirectly as VENDOR’s Sub-Supplier.
Owner or Owner’s authorized agent: Chiyoda, CB&I and Saipem
Purchaser
Joint Venture, collectively referred as CCS JV.
SSPC The Society for Protective Coatings

DFT Dry Film Thickness


ASTM American Society for Testing and Materials

ISO International Organization for Standardization

MSDS Material Safety Data Sheets


PPE Personal Protective Equipment

VOC Volatile Organic Compound


MEK Methyl Ethyl Ketone

NACE National Association for Corrosion Engineers

QCP Quality Control Plan


Globally Harmonized System of Classification and Labelling of
GHS
Chemicals
WFT Wet Film Thickness
HB High Build

Uncontrolled if Printed Page 6 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

TERM DEFINITION
Aluminium, when termed as Marine Type Aluminum is intended as
ALU
alloy 5xxx series and greater.
NSF National Sanitation Foundation
Joint venture between Saipem S.p.A., McDermott and Chiyoda
CCS JV
Corporation

1.4 Scope

1.4.1 General
This document outlines the coating systems to be used for plant location, including the
marine facilities, which are exposed in high humidity, marine, and corrosive environments.
The site shall be considered category as per ISO 12944-2 “C5” for the atmospheric part,
“Im2” for Immersed Structures and “Im3” for Buried Structures.
Specific chemical exposures, special applications, product availability, and other factors
likely will require a departure from this specification in some systems.
The coating systems here specified recalls for use of liquid paints.

1.4.2 Exclusions
This specification excludes underground piping required to be fusion bonded epoxy (FBE)
coated.
This specification excludes architectural paint requirements and tank lining works.
The following surfaces shall not be painted unless specified in other applicable purchase
documents:
a. Corten steel
b. Brickwork and tile, concrete fireproofing, Concrete
c. Plastic, glass, rubber, Mastic
d. Marine Grade Aluminum, brass, galvanized steel (except for safety color) or
cathodic protection anodes
e. Machined parts of operating equipment and gasket surfaces
f. Earthing bosses
g. Factory finished items (including nameplates) except to match the color scheme
h. Metal jacketing and weatherproofing of insulation
i. Anode attachment points that must provide a conductive path between anode and
cathodically protected steel
j. Valve stems, motor shafts and other such moving parts in order not to impair their
free movement
k. Glass surfaces of gauge and sight glasses
l. Weld bevels to be welded by others
m. Electrical/instruments wire and cable
n. Impulse and Instrument tubing
o. Equipment nameplates or special instructions permanently attached to equipment
p. Nonferrous metals other than Stainless Steel (e.g., nickel, titanium, aluminum, etc.)
q. Surfaces 50 mm min. (2 inches minimum coat-back) of field welds, unless
otherwise specified

Uncontrolled if Printed Page 7 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

r. Stainless Steels Shims 300-400 series


Paint and coating materials shall be free of heavy metals such as arsenic, barium, cadmium,
lead, mercury, silver, chromium, selenium, tin, and other hazardous substances. They shall
not be used on any piping, equipment, or packaged units. However, zinc coatings containing
barium sulfate and less than 0.02% lead are acceptable.
No coating is required, unless required for safety or identification purposes, for 22Cr Duplex
Stainless-Steel operating at a temperature lower than 100°C, 25Cr Super Duplex Stainless
Steel operating at a temperature lower than 110°C and Super-austenitic Stainless-Steel (e.g.
6% Mo) operating at a temperature lower than 120°C.
No coating is required for Copper, Copper Alloys, Monel, Hastelloy and Incoloy.

1.4.3 Responsibilities
When Required the Applicator shall submit to the Contractor its own painting procedure
based on this specification.
All coatings work shall be performed in accordance with the requirements of this
specification, data sheets, drawings, purchase requisition, and Purchaser approved
procedures. Any conflict between these documents shall be referred to the Purchaser for
clarification/resolution before proceeding with the coating application.
Supplier shall not make assumptions to replace information not furnished by Purchaser.
Supplier is required to obtain necessary information from Purchaser.
Any and all claims arising from lack of knowledge of required information will be rejected by
Purchaser.
Supplier shall list and fully describe all deviations from this specification and the related
codes.
Supplier is responsible for furnishing all material, equipment, labor, application, inspecting,
and testing of coatings.
Supplier shall take into account all weather conditions and logistics consequent to the
project location for coating of field erected items.
Supplier is responsible for furnishing all material, equipment, labor, application, inspecting,
and testing of coatings.
Supplier shall provide contractor with the required complete Guarantee documentation.
If dismantling of assembly item is impossible after functional test, inaccessible area shall
be painted with the first coat minimum (plus the tie-coat in case of zinc ethyl silicate primer-
based paint system) before assembly.
Any inaccessible surfaces for proper coating application and/or inspection shall be coated
prior to final assembly. Specifically, flange and bolt holes shall be coated prior to final
installation.
Shop fabricated equipment and packaged units with associated piping are to have surface
preparation, primer, intermediate (where specified), and finish coat applied in the shop by
the Supplier prior to dispatch to site.
Onsite shop or vendor’s fabricated pipe spools and bulk piping are to have surface
preparation, primer, intermediate (where specified) and finish coat applied in the shop.
Site paint activities should be reduced at the minimum necessary: on prefabricated item
any primer, intermediate coat (where specified) and finish coat shall be applied at shop,
while site activities be limited to paint film damage repairs and to weld joints complete
painting.

Uncontrolled if Printed Page 8 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

1.4.4 Air Data for Final Installation Site


In this paragraph the Air Data of final site of installation, are given as a reference for use in
site work planning and performance assessment:

Air Temperature (Dry Bulb) Relative Humidity


Design Maximum 32°C 66%
Annual Average 28°C 88%
Design Minimum 21°C 93%

Uncontrolled if Printed Page 9 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

2.0 REFERENCES
The following codes and standards, including applicable addenda, form part of this specification to
the extent specified herein.

2.1 Codes and Standards


ASTM - American Society for Testing and Materials
ASTM B117 Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM D 520 Standard Specification for Zinc Dust Pigment
ASTM D610 Standard Test Method for Evaluating Degree of Rusting on Painted
Steel Surfaces
ASTM D1654 Standard Test Method for Evaluation of Painted or Coated Specimens
Subjected to Corrosive Environments
ASTM D3359 Measuring Adhesion by Tape Test
ASTM D4228 Qualification of Coating Applicators for Application of Coating to Steel
Surfaces
ASTM D4285 Standard Test Method for Indicating Oil or Water in Compressed Air
ASTM D4417 Standard Test Methods for Field Measurement of Surface Profile
of Blast Cleaned Steel
ASTM D4541 Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM D4752 Standard Test Method for Measuring MEK Resistance of Ethyl Silicate
(Inorganic) Zinc-Rich Primers by Solvent Rub
ASTM D5162 Standard Practice for Discontinuity (Holiday) Testing of
Nonconductive Protective Coating on Metallic Substrates
ASTM D5402 Standard Practice for Assessing the Solvent Resistance of Organic
Coatings Using Solvent Rubs
ASTM E337 Standard Test Method for Measuring Humidity with a Psychrometer
(the Measurement of Wet- and Dry-Bulb Temperatures)

SSPC - The Society for Protective Coatings


SSPC AB 1 Mineral and Slag Abrasives
SSPC AB 3 Ferrous Metallic Abrasive
SSPC SP 1 Solvent Cleaning
SSPC SP 2 Hand Tool Cleaning
SSPC SP 3 Power Tool Cleaning
SSPC SP 5 / NACE No.1 White Metal Blast Cleaning
SSPC SP 6 / NACE No.3 Commercial Blast Cleaning
SSPC SP 7 / NACE No. 4 Brush-off Blast Cleaning - NACE No. 4
SSPC SP 10 / NACE No. 2 Near-White Metal Blast Cleaning
SSPC SP 11 Power Tool Cleaning to Bare Metal

Uncontrolled if Printed Page 10 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

SSPC SP 12 Surface Preparation and Cleaning of Steel and Other Hard Materials
by High-and Ultrahigh-Pressure water Jetting Prior to Recoating
SSPC SP 16 Brush Off Blast Cleaning of Coated and uncoated Galvanized Steel,
Stainless Steels and Non-Ferrous Metals
SSPC PA 1 Shop, Field, and Maintenance Painting of Steel
SSPC PA 2 Procedure for Determining Conformance to Dry Coating Thickness
Requirements
SSPC PA 3 Guide 3 Paint Application Guide No. 3 – A Guide to Safety in Paint
Application
SSPC Paint 20 Zinc-Rich Coating Type I Inorganic and Type II Organic
SSPC VIS 1 Guide and Reference Photographs for Steel Surfaces Prepared by
Dry Abrasive Blast Cleaning

ISO – International Organization for Standardization


ISO 2178 Non-magnetic coatings on magnetic substrates — Measurement of
coating thickness — Magnetic method
ISO 2360 Non-conductive coatings on non-magnetic electrically conductive
basis materials – Measurement of coating thickness – Amplitude
sensitive eddy current method
ISO 4628-1 Paints and varnishes — Evaluation of degradation of coatings —
Designation of quantity and size of defects, and of intensity of uniform
changes in appearance — Part 1: General introduction and
designation system
ISO 4628-2 Paints and varnishes — Evaluation of degradation of coatings —
Designation of quantity and size of defects, and of intensity of uniform
changes in appearance — Part 2: Assessment of degree of blistering
ISO 4628-4 Paints and varnishes — Evaluation of degradation of coatings —
Designation of quantity and size of defects, and of intensity of uniform
changes in appearance — Part 4: Assessment of degree of cracking
ISO 4628-5 Paints and varnishes — Evaluation of degradation of coatings —
Designation of quantity and size of defects, and of intensity of uniform
changes in appearance — Part 5: Assessment of degree of flaking
ISO 8501-1 Preparation of steel substrates before application of paints and related
products - Visual assessment of surface cleanliness - Part 1: Rust
grades and preparation grades of uncoated steel substrates and of
steel substrates after overall removal of previous coatings
ISO 8502-6 Preparation of Steel substrates before application of paints and
related products – Tests for the assessment of surface cleanliness –
Part 6: Extraction of soluble slats contaminants for analysis –
The Bresle Method.
ISO 8502-9 Preparation of Steel substrates before application of paints and
related products – Tests for the assessment of surface cleanliness –
Part 9: Field method for the conductimetric determination of
water-soluble salts.

Uncontrolled if Printed Page 11 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

ISO 8503-5 Preparation of steel substrates before application of paints and related
products Surface roughness characteristics of blast-cleaned steel
substrates Part 5: Replica tape method for the determination of the
surface profile
ISO 8504-3 Preparation of Steel Substrates Before Application of Paints and
Related Products - Surface Preparation Methods - Part 3: Hand- and
Power-Tool Cleaning
ISO 8573 - 9 Compressed air,
ISO 11126 Preparation of Steel Substrates before Application of Paints and
Related Products – Specifications for Non-metallic Blast-cleaning
Abrasives (10 Parts)
ISO 16276-1 Corrosion protection of steel structures by protective paint systems –
Assessment of, and acceptance criteria for, the adhesion/cohesion
(fracture strength) of a coating – Part 1: Pull-off testing
ISO 16276-2 Corrosion protection of steel structures by protective paint systems
Assessment of, and acceptance criteria for, the adhesion/cohesion
(fracture strength) of a coating – Part 2: Cross-cut testing and X-cut
testing.
ISO 12944-2 Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 2: Classification of Environments
ISO 12944-4 Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 4: Types of Surface and Surface
Preparation
ISO 12944-5 Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 5: Protective Paint Systems
ISO 12944-7 Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 7: Execution and Supervision of
Paint Work

NACE – National Association of Corrosion Engineers


NACE SP0178 Fabrication Details, Surface Finish Requirements, and Proper Design
Considerations for Tanks and Vessels to be Lined for Immersion
Service
NACE SP0188 Discontinuity (Holiday) Testing of New Protective Coatings on
Conductive Substrates
NACE SP0198 Control of Corrosion Under Thermal Insulation and Fireproofing
Materials—A Systems Approach

ASME – The American Society of Mechanical Engineers

ASME A13.1 Scheme for the Identification of Piping Systems

Uncontrolled if Printed Page 12 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

2.2 Regulations
This specification requires compliance with all applicable Federal, State and Local laws,
regulations, ordinances, etc. of the nation pertaining to the work and coating materials
manufacture.

2.3 Other Specifications


MZ-000-CCX-MC-SPC-00003 SPECIFICATION FOR INTERNAL LINING OF
EQUIPMENT
MZ-000-CCX-MC-SPC-00004 EXTERNAL COATING FOR BURIED
PIPELINE AND PIPING COMPONENTS – FBE
AND FJC
MZ-000-CCX-MC-SPC-00008 EPOXY INTUMESCENT FIREPROOFING
FOR EQUIPMENT SUPPORT AND
STRUCTURAL STEEL
MZ-000-CCX-MC-SPC-00017 SPECIFICATION FOR GALVANIZING
MZ-000-AM1-OP-SPC-00001 PLANT LABELLING SPECIFICATION

Uncontrolled if Printed Page 13 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

3.0 DESIGN
Selection of Paint system shall be the final step of the decisional analysis carried out on the basis
of the design data to be considered for involved external surface; such as the material of
construction, operating temperature regime, exposure to the environment, the presence of thermal
insulation, the presence of fireproofing material, etc.
During the design and the construction of metallic components, the basic criteria listed in standard
ISO 12944-3 shall be taken into due consideration.
The construction should be designed in such a way that it will not interfere with the abrasive blasting
or paint application according to this Specification.
Welding shots drops, and spatters, pores in the weld seams, lamination defects, edges, flame cuts,
fragments, and dents or any other foreign object not removed during construction shall be
considered imperfections and therefore shall be removed before surface preparation.
The steel imperfections detected before, during or after surface preparation shall be removed with
suitable power tools according to the requirements of standard ISO 8501-3 as follows:
Grade P3: For all surfaces intended to be permanently or intermittently immersed or
buried. Edges from flame or mechanical knife cutting shall be rounded to a
minimum radius of 2 mm. Spot and discontinue welds shall be not permitted on
these surfaces.
Grade P2: For all surfaces exposed to marine and industrial environment. Edges from flame
or mechanical knife cutting shall be adequately rounded by three pass grinding.
Spot and discontinue welds shall be not permitted on these surfaces.
Grade P1: For all other surfaces not exposed to aggressive environment and atmosphere.
As far as possible, contact of different metals shall be avoided. In case, due to the unavoidable
design requirements, the contact cannot be avoided, a suitable insulating material (i.e., Teflon or
similar) shall be installed between the different metals. This includes pipes and related supports,
bolts, clips, etc. installed in permanent or intermittent immersed areas and on external areas.
In case of welded assembly or direct coupling made of dissimilar metals with different nobility the
following methods are recommended to reduce and prevent Galvanic Corrosion:

1) Electrically Insulate two materials from each other. If they are not in electrical contact, no
galvanic couple will develop. This can be achieved by using non-conductive materials
between metals of different electro-potential and/or
2) The prevention of contact with an electrolyte can be done by coating the different metals
joined with an impermeable protective layer (on the whole surface) or
3) If it is not possible to coat both materials, the coating should be applied to the material
with the higher electrode potential. In such case, a Minimum of 50 mm coating overlap
from the noble material onto the less noble adjoining substrate is required to provide a
desirable separation (i.e., a coating system for SS substrate shall be extended a
minimum of 50mm over connected CS substrate). If the coating would be applied only
on the more active material, there will be a large cathodic area if the coating is damaged
and for the exposed, very small anodic area, the corrosion rate will be correspondingly
high.
Stainless steel structures and components shall be carefully inspected before their installation
and before any surface preparation.
Any damages noticed on the structures and components shall be immediately notified by the
Supplier to the Contractor, which shall provide instructions for repairs or disposal of the damaged
structures and components.

Uncontrolled if Printed Page 14 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

In particular, handling shall be carried out with particular care and precautions shall be
implemented to avoid ferrous contamination of the stainless-steel structures and components.
Furthermore, the handling shall be accomplished using suitable equipment to avoid damages
and contaminations of the surfaces.

The surface preparation of stainless steel and special alloys shall be performed when these
surfaces must be coated. In this case, abrasive blasting will be executed with the only purpose
to rough the metallic surface according to the requirements of the provided paint system.
In no case, steel-grit and/or shot material shall be used for abrasive blast cleaning of stainless
steel and special alloys. The only use of non-metallic abrasive is mandatory to perform abrasive
blast cleaning on stainless steel.

Use of mild-steel brushes, or brushes previously used on carbon-steel or other ferrous/less


noble, such as zinc or copper alloy material for brushing of stainless-steel surfaces is not
allowed.
There is a possibility that austenitic stainless steels (300 series) and nickel alloys, such as
Incoloy 800 and Inconel 625, may suffer zinc embrittlement when exposed to molten zinc at
temperatures in excess of 700°C. For these alloys, direct contact with zinc should be avoided.
The following should be taken into consideration at the design stage to protect the above
materials and their welds from zinc contamination:

• Bolts and nuts, in contact with austenitic stainless steel or high Ni alloys, shall not be
galvanized, nor primed with zinc rich primers.
• Austenitic stainless steel and nickel alloy equipment and piping shall be suitably protected
or located such that molten zinc from adjacent galvanized structures will not drip onto them
during field welding operations or in the unlikely event of a fire.
• Insulation weatherproofing on or in the vicinity of austenitic stainless steel or nickel alloy
equipment and piping shall not be fabricated from galvanized sheet.
• Galvanized or zinc coated components shall not be welded to austenitic stainless steel or
nickel alloy equipment or piping paints and primers containing metallic zinc shall not be used
on stainless steel or nickel alloy substrates.

3.1 General Requirements


Applicator shall provide all methods, means, materials, and quality assurance necessary to perform
the surface preparation, application of primer, intermediate, and finish coating in accordance with
The Society for Protective Coatings, SSPC PA1, PA2, PA3 and per Paint Manufacturer’s instructions
and requirements. This includes all storage, handling, mixing, applying, curing, testing, repairs, and
disposal of all associated waste.
Paint systems for different items, either insulated or not insulated, different operating temperatures,
and carbon steel or stainless steel are listed in APPENDIX 2 and APPENDIX 3. These tables define
the requirements for surface preparation and the numbers of coats required with DFT range.
APPENDIX 1 identifies different manufacturers’ products for generic types of paints. APPENDIX 4
specifies finish color requirements. APPENDIX 5 specifies the Test Items normally required during
the protective coating works.
All carbon steel surfaces exposed to view in the assembled condition including uninsulated surfaces
of insulated items (such as piping, equipment, etc.) shall be finish coated to paint system 1, 2, 3 or
4 as required by maximum operating temperature.
Cementitious fireproofed surfaces shall be treated the same as insulated surfaces in regard to
painting per this specification and shall be painted per paint system 5. Intumescent, ablative, or

Uncontrolled if Printed Page 15 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

subliming fireproofed surfaces require PFP material manufacturer approved primers and shall be
painted in accordance per paint system 13, Reference to MZ-000-CCX-MC-SPC-00008 shall be
made.
Carbon Steel Lines and equipment receiving partial insulation or metal cages for personnel
protection purpose shall be treated as uninsulated items for selection of paint and shall be painted
per paint system 1, 2, 3, or 4 as required by maximum operating temperature.
For heat exchangers, the higher operating temperature of inlet and outlet temperature shall be used
to select the paint system.

3.2 Standard Production Items


Items such as pumps, motors, compressors, switchgear, control panels, control valves, and relief
valves including actuators shall be coated with manufacturer’s 3-coat system as a minimum, as long
as the following criteria are satisfied:

a) The site shall be considered C5 category as per ISO 12944-2. Paint system should be
designed to meet this environment condition.
b) The total paint system shall have a minimum corrosion resistance of 2000 hours when tested
in accordance with ASTM B 117. Any rust creep from the scribed line shall not exceed Table
1 procedure A, rating 8 of ASTM D 1654. Independent laboratory certification is required. In
alternative to ASTM B117 testing, the paint system shall have a test report (by independent
laboratory) to ISO 12944-6 accelerated corrosion (ageing) testing regime to meet, at least,
for “C5” environment and durability in service .
c) The system shall be capable of withstanding the environmental conditions for a period of 5
years, after which deterioration shall not exceed rust grade 8-G in accordance with ASTM D
610.
d) The Supplier shall submit proposed paint procedure to the purchaser for review and approval
before proceeding with the work.

The guarantees terms for coating systems of standard production items shall comply with Section
13.

3.3 Piping Items


Carbon steel and low alloy steel spec valves (bulk valves) shall be purchased with a 50-75 micron
coating of inorganic zinc silicate (Paint System 6), applied on the body.
Flanged Stainless-steel valves shall be coated with Paint System 4, primed and top-coated with 2-
coat of Inorganic High Build Copolymer Paint, 200-300 micron total DFT range, Aluminium color
Shade. Ends-to-weld Stainless steels valves shall receive SSPC SP1 then SP 16 surface
preparation and shop application (by valve Vendor) of wax based removable temporary protective
coating 50 microns DFT on valve body. At site Temporary coating shall be removed (by solvent or
steam cleaning method) from “ends-to-weld” Stainless Steel Valves and valve body shall than be
painted same as parent piping, including valve-to-pipe weld-joints.
Welding ends and flange facings shall not be coated but a temporary preservative shall be applied.
Bolt holes shall be coated with the temporary coating as stated above.
The purchaser will coat spec valves using the associated line (pipe) paint system in the field.

Uncontrolled if Printed Page 16 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Inorganic Zinc Silicate (IO Zinc) is NOT compatible with Paint System 5 (Epoxy Novolac Paint) hence
an IO Zinc compatible High Temperature (HT) resistant epoxy paint shall be used (at site) for paint
system completion purpose on carbon/low alloy steel (bulk) valves to be insulated and operated at
temperatures up to +150°C, so making unnecessary the complete IO Zinc primer removal by
abrasive blasting as preliminary reworking to the application of paint system 5. Examples of High
Temperature resistant epoxy paint (IO Zinc primer compatible) are noted in APPENDIX 1.
Stainless steel piping and valves shall be protected against atmospheric corrosion and service
exposure. They shall be shop coated with paint system required per operating temperature and
service conditions.
Gear boxes, actuators, levers, handwheels, etc. valve accessory components shall be painted with
systems specified for uninsulated surfaces and for the effective metal temperature achieved by the
component. Use of high temperature paint system on such components shall not be allowed.

3.4 Machined Surfaces, Bolts and Bolt Holes


Machined surfaces such as threads, valve stems, gasket contact surfaces, etc. shall be protected
with a solvent cutback asphalt temporary preservative (Tectyl 891, Rust Veto 344, or Rust-Ban 392)
or Buyer accepted equivalent.
Bolt holes shall be finish coated using the same paint system as equipment or valves. As a minimum,
a coat of primer is required in the bolt holes.
Stainless steel equipment shall be completely shop coated with the specified paint system, if
insulated or not and depending on the operating temperature conditions, unless it is protected by
some other means specified in the purchase order. Stainless steel exposed to the atmosphere shall
be finish coated as minimum to provide sufficient protection to the coastal environment.
Ancillary Requirements During production, in shop but also on field working areas and materials
shall be segregated in order to exclude cross-contamination of noble materials with less-noble
materials, i.e. Stainless Steel surfaces shall be segregated from carbon or Galvanized Carbon Steel;
mechanical tools used for a material shall not be used on another.
Any paint or crayon used for marking or color-coding austenitic materials shall be free of lead, zinc,
sulfur, and halides.
Sole plates should be primer coated prior to dispatch at site.
Where required for risk of external stress corrosion cracking (Austenitic Stainless-Steel operating
above 60°C), a suitable coating (e.g. Takecoat®, Xylan® or Equivalent) on bolts and nuts shall be
provided; such coating shall withstand the final operating condition. Bolt and Nut Coating system
shall comply with requirements of section 3.2 with no requirements to the minimum number of coats.
All bolts located in the splash zone shall be protected with adapted sealed bolt-caps system filled
with grease (Radolid® or Approved Equivalent). Supplier shall provide the details of above methods
of protection.

4.0 DOCUMENT SUBMITTALS


The Supplier must submit the following documents:
• Written coating procedures for storage, handling, surface preparation, environmental
control, application, touch-up and repair, curing, and inspection along with “Daily
Inspection Report” form for review and approval prior to proceeding with the Work.
• Product Data Sheets (PDS) and Material Safety Data Sheets (MSDS).

Uncontrolled if Printed Page 17 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

• Any Additional Recommendation or instruction not included in PDS, Application


Guideline or MSDS shall be handed over throughout a written technical statement issued
by Coating Manufacturer and Attached to the Coating Procedure.
• Coating procedure shall include a section for personal protective equipment (PPE)
required for this work.
Coating systems and/or products other than those listed in APPENDIX 1, APPENDIX 2, and
APPENDIX 3 require written review and approval prior to use.
Conflicts, if any, between the Coating Manufacturer’s recommendations and this specification, shall
be noted in writing to Purchaser for resolution.

5.0 MATERIALS
Unless otherwise specified, all coating material shall be as specified by the Purchaser in APPENDIX
3, The paint products referenced by trade names within this specification are listed in the APPENDIX
1 to set a standard of quality. Equivalent paint products of other manufacturers will be accepted if
approved in writing by the Contractor.
All coating material in a paint system shall be from the same manufacturer. Material from different
manufacturers shall not be used in conjunction with each other with the exception of carbon/low
alloy steel bulk supplied valves delivered to site already surface prepared and primed with Inorganic
Zinc: Primer top-coating shall be with approved trade-name paints of a manufacturer that might be
different from shop-primer’s.
Inorganic zinc primer shall meet the requirements of SSPC-Paint 20, Type I, Level 1 (minimum 85%
zinc dust by weight in the dry film).
Organic zinc-rich primer shall meet the requirements of SSPC-Paint 20, Type II, Level 1 (minimum
80% zinc dust by weight in the dry film).
Type II zinc powder per ASTM D 520 shall be used in the formulation. Type II zinc powder limits the
total lead content to 0.01% maximum.
Paint Product compliance with either SSPC-Paint 20, Type II, Level 2 and Zinc dust content not less
than 80% (by mass) in the dry film thickness shall be declared in writing by the Paint Manufacturer
unless clearly indicated in the PDS.
Uncoated Machined surfaces shall be protected with a solvent cutback asphalt temporary
preservative (Tectyl 891, Rust Veto 344, or Rust-Ban 392) or Buyer accepted equivalent.
Materials for touch-up of damaged areas of surfaces shall be the same as or equivalent to those
that were originally applied.
Coating material shall be delivered to the place of application in the manufacturer’s unopened,
original containers bearing a legible product designation, batch number, and date of manufacture.
Containers that are damaged shall not be used.
The coating material shall be handled and stored in accordance with the manufacturer’s latest
published instructions and shall be protected from damage, moisture, direct sunlight, and
temperature colder than 5°C (40°F) or warmer than 32°C (90°F). Air-conditioned and/or heated
storage may be required and is the responsibility of the Supplier.
The coating material shall be used within the manufacturer’s published self-life. Containers of
coatings that have exceeded the published self-life shall be segregated from other material and
disposed of in accordance with local regulations.

Uncontrolled if Printed Page 18 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Containers of coatings or components shall not be opened unless they are required for immediate
use.
Thinners, Solvents, and cleaners shall be used as recommended by the manufacturer for each
coating product. The recommended thinners, solvents and cleaners shall be listed on the coating
product data sheets.
Thinner, solvents, cleaning materials, and coating used over stainless steel surfaces shall meet the
following requirements:
• The inorganic halogen content shall be less than 200 ppm by weight.
• The total halogen (inorganic and organic) content shall be less than 1 percent by weight.
• The sulfur content shall not exceed 1 percent by weight.
• Low melting point metals (lead, bismuth, zinc. Mercury, antimony, cadmium, and tin) shall
not be intentionally added to the coating material.
• Inorganic zinc and zinc rich epoxy coatings shall not be applied over stainless steel.
• Temporary Coating on ends-to-weld bulk Stainless Valves, shall be wax-based and
removable by water, alkaline solution or steam cleaning.
MSDS shall be available for review at the job site. The volatile organic compound (VOC) content
shall meet Federal, State and Local or other regulatory requirements.

6.0 COATING PREQUALIFICATION AND TESTING


Before work commences, all the selected systems shall be applied on samples representative of the
surface to be painted (i.e. trial panel or mock-ups). The paints used shall be sampled from the same
batches as these intended for the works.
The system shall be applied in presence of the Applicator and the Purchaser’s representative, under
the climatic conditions that can be foreseen during the works.
Application shall be performed by the blasters and painters who will be responsible for application
during the work, using the normal equipment that will be used during the works.
During Surface preparation and Paint application, all tests described in APPENDIX 5 shall be
performed.
Qualification shall be as reported in APPENDIX 5.
All stainless steel items shall be segregated from carbon steel (Galvanic cell). Attention should be
paid on the earthing loop continuity that could be broken by the segregation (For example by Teflon).
After the system are fully cured, visual inspection and adhesion testing shall be carried out to confirm
that the performance of the painting systems meet those specified for each system.
Paint product Manufacturer(s) shall supplement all the required information in order to support
production setting, when required Qualification Datasheets should contain the minimum data
required in ASTM F 718.

7.0 SURFACE PREPARATION


All welds shall be relatively smooth without sharp edges and surface shall be free of weld slag and
weld splatter prior to blasting.

Uncontrolled if Printed Page 19 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Prior to blasting, the surface shall be cleaned to remove dirt, lose contaminants by brushing,
vacuuming or blowing off with clean dry air. Oil and grease shall be removed by solvent cleaning
per SSPC-SP1.
Abrasive blasting shall produce surface cleanliness and specified anchor profile for the specified
coating system. The anchor profile shall be verified in accordance with ASTM D 4417, Method C,
using replica tape and spring-loaded micrometer.
The particle size shall be capable of producing the specified surface profile.
Silica sand abrasive shall not be used at the job site.
SSPC-VIS 1 shall be used as a visual standard for degree of surface cleanliness.
Defects such as laminations, burrs, and slivers shall be removed after blasting.
Where possible, surfaces to be coated shall be shot or grit blast cleaned. Where abrasive blasting
is impractical, hand or power tool cleaning per SSPC-SP2, SSPC-SP3, or SSPC-SP11 may be used
with the written approval of Purchaser. Power tools used to clean carbon steel shall not be used to
clean stainless steel.
The abrasive for blast cleaning shall comply with SSPC AB1 (for general use), or SSPC AB3 (On
mild steel and carbon steel only). The abrasive mixture and the compressed air shall be clean, dry,
and oil-free. Conductivity of abrasive material shall never exceed 150 µmS/cm when measured
according to standard ISO 11127-6. Traps, in addition to oil and water extractors mounted on the
compressor, shall be used in compressed air lines to remove oil and moisture from the air close to
the point of use. Air supply shall be tested for oil and water contamination in accordance with ASTM
D4285 or applicable parts of ISO 8573.
Carbon steel and iron abrasives shall not be used on stainless steel. Mineral and slag abrasives
shall be used on stainless steel. White corundum (electro-fused aluminum oxide) should be used on
stainless steel surfaces. Among others mineral abrasives like garnet or brown corundum, white
corundum has the lowest % content of Fe2O3. Iron contamination of SS is so that reduced to the
maximum extent.
Use of Sand is Forbidden.
Abrasive blasting shall not be performed when the ambient or the substrate temperature is less than
3°C (5°F) above the dew point temperature. Dew point shall be measured at the location where work
is being performed using sling psychrometer per ASTM E 337.
Blast cleaning shall not be performed in the immediate area where coating or curing of coated
surfaces is in progress. All surfaces and equipment which are not to be coated shall be suitably
protected from blast cleaning.
Blast Cleaned surfaces shall not be left unpainted during night.
Any prepared surfaces which have visible rust or are outside the four hours limit shall be re-prepared.
The time elapsed between surface preparation and primer coat application shall not exceed 4 hours.
In any case, just prior to coating, the surface cleanliness shall be checked.
Machined surfaces shall be solvent wiped in accordance with SSPC-SP 1 before the application of
temporary coating and shall be protected from damage due to cleaning and coating operations.
Surfaces to be coated shall be rendered dust free prior to the application of each coat by blowing
the surface with clean dry air or by using an industrial vacuum cleaner.

Uncontrolled if Printed Page 20 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

The machined portion of pipe flange mating faces shall be masked with plywood or plastic to protect
internal components. The remaining part of the flange face (including bolt-holes) shall then be
cleaned and coated.
Equipment shall have all openings plugged, masked, and/or blinded before abrasive blasting.
Special Attention shall be given to the valves to be abrasive blast cleaned in assembled condition:
• The valve stem and flange facings shall be properly protected to avoid damage from the
abrasive blasting.
• Stuffing Box chambers shall be properly protected to avoid ingress of blasting medium and
subsequent damage of stem during normal operation.
• Valve opening shall be properly closed to avoid ingress of blasting medium and subsequent
damage of stem and/or seat during normal operation.

7.1 Preliminary Operations


Oil, grease, wax, dirt and other foreign matters shall be removed by cleaning and
degreasing from metal surfaces in accordance with SSPC SP1.
Before and after blasting, all welding seams shall be closely inspected for the presence of
welding flux and spatters, slivers, inclusions, all burns, sharp edges, and underlying mill
scales. Imperfections shall be mechanically removed; welding porosity's and welding
pinholes shall be eliminated, and the involved area will be re-blasted to standard. Sharp
edges shall be rounded (R>2mm as minimum).

7.2 Environmental Conditions


Surface preparation and painting work shall not proceed under any of the following
conditions:
• When air temperature is below 5°C;
• When Steel surface temperature less than 3 °C above ambient air dew point.
• When Relative humidity is greater than 85%. In the case of inorganic zinc rich
primer, application shall be done when relative humidity is between 50-90%.
• In condition of strong or gusty winds or poor visibility or raining.
• When the surface temperature is above 50°C.
Assessment for probability of condensation on steel substrates shall be done in compliance
with ISO 8502-4.

7.3 Cleaning Precautions for Stainless Steel and special Alloy


Stainless steel structures and components shall be carefully inspected before their
installation and before any surface preparation.
Any damages noticed on the structures and components shall be immediately notified by
the Supplier to the Contractor, which shall provide instructions for repairs or disposal of the
damaged structures and components.
In particular, handling shall be carried out with particular care and precautions shall be
implemented to avoid ferrous contamination of the stainless steel structures and
components.
Furthermore, the handling shall be accomplished using suitable equipment to avoid
damages and contaminations of the surfaces.

Uncontrolled if Printed Page 21 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

The surface preparation of stainless steel and special alloys shall be performed when
these surfaces have to be coated. In this case, abrasive blasting will be executed with the
only purpose to rough the metallic surface according to the requirements of the provided
paint system.
In no case, steel-grit and/or shot material shall be used for abrasive blast cleaning of
stainless steel and special alloys. The only use of non-metallic abrasive is mandatory to
perform abrasive blast cleaning on stainless steel.
Use of mild-steel brushes, or brushes previously used on carbon-steel or other ferrous,
such as zinc or copper alloy material for brushing of stainless steel surfaces is not allowed.

7.4 Cleaning Precautions for Galvanized Steel


All hot-dip galvanized steel surfaces, before being coated with the specified paint system,
shall be cleaned as follows:
a) Cleaning and de-greasing according to standard SSPC-SP 1
b) Galvanizing defects and anomalies shall be removed by power and/or hand tooling
paying attention to not remove the zinc layer, and suitably repairing them, according
to referenced standard or applicable design codes;
c) Measurement of galvanizing thickness according to standard ASTM A 123 or ASTM
A 153. Any item falling below the required zinc thickness shall be repaired
according to standard ASTM A 780
d) The galvanized surface shall be roughened by abrasive sweep or brush blasting (to
ensure no removal of zinc layer) according to ASTM D 6386 or, with other method
specified SSPC SP16, or as otherwise approved by Contractor.

7.5 Power Tool Cleaning


Where an abrasive blast cleaning is impractical or could damageable for the vicinity, or the
surfaces are inaccessible to the blasting nozzle, manual and mechanical (power tool)
cleaning shall be used.
In this process, dirt, rust, loose mill scales shall be removed, and the metal surface
prepared by hand chipping, scrapping or wire brushing or abrading. Mechanical
preparation shall be carried out by powered hand tools such as powered wire brushes or
needle guns as far as practical, to achieve the standard ISO 8501-1 grade St 3. On
completion the surface should have a pronounced metallic sheen.
For limited surfaces and after Contractor approval, handheld cleaning power tools (i.e.,
power discing, needle gun, “Scotch-Brite”™ or Carborundum disking, bristle blasting or
vacuum blasting) can be performed according to standards SSPC-SP 3 or SSPC-SP 11
and in accordance with surface preparation grade required by the Paint System and
compatible with the substrate being treated. Tools used on Carbon Steel or galvanized
surfaces shall never be used on stainless steel surfaces.

8.0 APPLICATION

8.1 General
Painting shall not take place during inclement weather. Ambient, substrate and coating
material temperature shall be within the range specified by the manufacturer.

Uncontrolled if Printed Page 22 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Coating application shall not take place when the ambient or substrate temperature is less
than 3°C (5°F) above dew point temperature. The substrate temperature during coating
application and curing shall be maintained between a minimum of 10°C (50°F) and a
maximum of 43°C (109°F).
Coating application shall be suspended during rain, snow or fog. Spray application of
coating shall be suspended during strong gusty wind.
All solvent and thinners and their mix ratios shall be per coating manufacturer’s
recommendation, thinner usage shall not exceed the maximum recommended value in
Paint Product Datasheet.
When multiple component units are mixed, each component shall be mixed separately
prior to the mixing of the combined materials. Only complete kits shall be mixed, no partial
kits will be allowed at any time.
Coating materials shall be thoroughly mixed until they are smooth and free from lumps, if
necessary, strain the material and follow paint manufacturer instructions. Material shall be
agitated to keep the solids in suspension if necessary. Inorganic zinc coatings shall be
applied using an agitated pot.
The cleaned surface shall be coated before any visible rust forms on the surface.
Paint shall be applied strictly in accordance with the Paint Manufacturer recommendations
and the requirements of this specification. Particular attention shall be paid to thinning,
mixing and curing times between subsequent coats.
Prior to apply a succeeding coat, all previous coatings shall be allowed to dry for at least
the minimum time specified by the Paint Manufacturer. Special care must be taken not to
exceed the maximum overcoating time allowed by the Paint Manufacturer. The Paint
Manufacturer's advice regarding the influence of the applied coating thickness, steel
temperature, relative humidity, % of thinner added, shall be considered in determining the
correct over coating intervals.
Coating shall not be conducted When the steel surfaces temperatures is less than 3°C
above the air dew point, When the relative humidity of the air is above 85 % for epoxy
coatings and 90 % for zinc silicate coating (subjected to Paint Manufacturer's
recommendation / requirements compliance).
Prior to apply the following coat, previous coat shall be rendered free of dust, grease and
other foreign matters.
During application of paint containing Zinc powder, attention shall be paid to avoid zinc
spraying on Stainless steel.
The quality of coating application shall be inspected in accordance with section 9 of this
specification to confirm that the Contractor's requirements have been met in full.

8.2 Environmental Conditions


Relative humidity shall be 85 percent or below, depending on the type of paint being used.
When relative humidity falls below 50 percent, the inorganic zinc primers shall be cured
using a fine mist of clean water after one-hour application of the coating and damp
condition shall be maintained on zinc surface for approximately twelve hours or as
recommended in paint application instruction provided by paint manufacturer.
Environmental conditions shall be monitored and kept within the usage limits specified by
the Paint Product Manufacturer in the Product Datasheet or Application Instruction, prior to,
during application and curing.

Uncontrolled if Printed Page 23 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

If full curing of inorganic zinc is suspect, the curing of zinc film shall be checked in
accordance with ASTM D 4752 by use of MEK solvent rub test.
Indoor coatings or enclosures to permit coating of surfaces during inclement weather may
be used, provided the environmental restrictions specified are maintained throughout the
coating and curing periods.
For painting application in indoor environment, the location where the works are performed
shall be appropriately ventilated, and all Safety aspects shall be strictly followed.
For application and curing of epoxy below 10°C (50°F) surface or ambient temperature,
winter formulation or force curing may be used with the written approval of Purchaser.
Primer shall have a uniform thickness over edges, corners, and welds and shall be free
from mud cracking.

8.3 Stripe Coat


In addition to coats described in specified systems, a “Stripe Coat” of materials shall be
applied to weld seams, bolts, flanged edges, and similar areas including edges, external
corners, welds, bolts, nuts and interstices prior to the general application of the coating.

8.4 Complementary Requirements


In general all bolts shall be painted with the same coating system to which they are mated
to, unless factory pre-coated. All Stainless Steel bolts for equipment in coastal areas shall
be painted after final tightening with the paint system applied on the surface the bolt are
mounted to.
Primer shall not be applied within 150 mm (6 inches) of surface or 50 mm (2 inches) from
the edges to be field welded.
Each coat of multiple coat system shall be allowed to cure prior to top-coating.
Overcoats/Topcoats shall be applied within the manufacturer's minimum and maximum
recoat times. The dry film thickness of each coating shall be in accordance with APPENDIX
3.
Coatings to be applied over inorganic zinc primer shall first be applied as a mist coat
followed by a full coat of the specified material.
Coating shall be applied using clean equipment.
Runs, sags, voids, drips, overspray; loss of adhesion, blistering, peeling, mud cracking,
inadequate cure, or rusting of the substrate shall not be permitted.
The color of succeeding coats shall vary slightly from the color of the preceding coat to
permit easy identification without affecting finish color. Damaged coatings shall be
retouched before succeeding coats are applied.
Paints containing metallic aluminium, lead or zinc shall not be used to overcoat stainless
steel materials (formulations containing oxidized aluminium are however acceptable). Also,
these paints shall not be applied in proximity to stainless steel where the stainless steel
could be contaminated with molten, elemental aluminum, lead, or zinc as a result of
welding or fire.
For items having dissimilar materials of construction, paintings containing zinc shall not
overlap onto stainless steels or non-ferrous metals.
Wet film thickness shall be checked during the application of each coat. The DFT of each
coat shall be checked in accordance with the procedure defined by SSPC-PA2 using
properly calibrated magnetic gauge.

Uncontrolled if Printed Page 24 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Where it is necessary to apply more than one coat of a particular product to obtain a
specified dry film thickness, then the first coat shall be selected sufficiently different in
color, in order to distinguish from the subsequent coats.
DFT measurement of each paint coat shall be performed and it shall not be outside of the
specified range.
Air compressor shall not deliver air at temperatures in excess of 110°C (230°F)

8.5 Galvanized Steel


Where galvanized steel is to be coated (for safety color or under fireproofing), the surface
shall be cleaned to remove dust, mud, and other loose contaminants followed by solvent
cleaned per SSPC SP-1 first to remove oil and grease (if any).
The cleaned surface shall be sweep blasted per SSPC SP 16 (Brush off Blast Cleaning)
with very light air pressure. The cleaned surface shall be top coated with the specified
system and, where needed, intermediate and finish color as per APPENDIX 2 and
APPENDIX 3.
The galvanized surface to be top-coated shall not receive chromate treatment after
galvanizing.
The damaged area shall be cleaned per SSPC SP-3. Cleaned surfaces shall be touched
up with metallic Zinc Rich Epoxy Paint. Minimum DFT shall be 75 μm (3 mils).
“Cold Galvanizing” products applied using aerosol cans are not acceptable. Products for
reinstatement shall be furnished by Supplier and shall be as recommended by Galvanizer.
All hot-dip galvanized steel surfaces, before being coated with the specified paint system,
shall be cleaned as follows:
a) Cleaning and de-greasing according to standard SSPC-SP 1
b) Galvanizing defects and anomalies shall be removed by power and/or hand tooling
paying attention to not remove the zinc layer, and suitably repairing them,
according to referenced standard or applicable design codes;
c) Measurement of galvanizing thickness according to standard ASTM A 123 or ASTM
A 153. Any item falling below the required zinc thickness shall be repaired
according to standard ASTM A 780
d) The galvanized surface shall be roughened by abrasive sweep or brush blasting (to
ensure no removal of zinc layer) according to ASTM D 6386 or, with other method
specified SSPC SP16, or as otherwise approved by Contractor.

9.0 INSPECTION AND TESTING

9.1 General
The following steps shall be subject to inspection by Purchaser's representative:
• Following surface preparation and immediately prior to the coating application,
• Following the application and curing of each coat,
• After final inspection and sign-off, in accordance with the project requirements.
The Supplier shall furnish the necessary testing and inspection instruments, properly calibrated and
maintained. Such equipment shall be available for use by Purchaser in conducting surveillance of
the work.

Uncontrolled if Printed Page 25 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Prior to using compressed air, the quality of the air downstream of the separator shall be tested in
accordance with ASTM D 4285 (or applicable Parts of ISO 8573). The test shall be performed at the
beginning of each shift and at not less than 4-hour intervals.
The test shall also be performed after any interruption of the air compressor operation or as required
by Purchaser. The air shall be used only if the blotter test indicates no visible contamination, oil, or
moisture. If contaminants are evident, the equipment deficiencies shall be corrected and the air
stream shall be retested. Separators shall be bled continuously. All lines shall be tested individually
prior to use. Surfaces which are determined to have been blasted or blown down with contaminated
air must be cleaned of that contamination and re-blasted with clean air and abrasive.
Reading or Continuous Monitoring data-log and printouts shall be recorded on, and attached to,
quality daily reports.
Any defects disclosed by inspection shall be re-inspected after correction.
The Coating Applicator shall prepare and submit to Contractor a Quality Control Plan (QCP),
detailing all coating activities. Details of Test Requirements are provided in APPENDIX 5 and shall
be used as reference in the planning.
The Coating Applicator shall notify the Contractor before work of part of the work commences.
All personnel involved in the coating works shall have adequate experience of the coating process.
Contractor may decide to send a coating inspector during, or at the end of work, to check paint work.
The Manufacturer shall prepare a paint work planning and shall advice the Contractor before the
date of blasting operation.

9.2 Abrasive / Paint Material Storage


Storage conditions of abrasives and Coating material shall be as recommended by the Material
Manufacturer. Abrasive and Paint shall be stored Indoor. Abrasives shall be packaged in sealed,
moisture proof containers and stored in a clean and dry location. The storage conditions of all paint
materials shall be adequate and properly maintained as required by the paint manufacturer and
Where necessary, the temperature is set and properly maintained. Containers and packages shall
not be placed nor stored on wet or damp surfaces, nor in areas where a flood can occur.
Paint Materials shall be stored and disposed in accordance with local regulations and the relevant
instructions from paint manufacturer. Materials shall be kept in their original sealed and labelled
containers or package. Storage conditions shall not be detrimental to the material. Coating materials
shall be protected from direct sun, and rain, heat sensible material shall be stored in a thermally
controlled store with constant temperature set to the written instructions of Paint Manufacturer.
Solvents and thinners shall be provided by the paint manufacturer and shall be as required in the
relevant paint datasheet.
Shelf-life of the materials shall not be exceeded, nor the material be expired.
The coating materials shall be located at a proper distance from any significant heat source and
from any area where free flames, welding works and tools causing sparks are used.
All products that become altered for any reason or show the container and/or package partially or
totally destroyed and/or damaged shall be removed from the store, not used for the coating work
and properly disposed of.
Materials must be stored, until the time of use, in their original packaging in a sheltered and if
possible enclosed place, and must be protected from sunlight, rain, moisture and kept away from
sources of heat.

9.3 Environment Conditions


Surface preparation shall not be carried out when the steel temperature is less than 3°C above dew
point or when the relative humidity of the air is greater than 85%.
No coatings shall be applied when the steel temperature is less than 3°C above air dew point, when
the air temperature is less than 10°C excluding those product grades that are suitable for application
at low temperature. Estimation of the probability for condensation shall be made in accordance with

Uncontrolled if Printed Page 26 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

ISO 8502-4. In outdoor application, no coating materials shall be applied when there is a likelihood
of a detrimental weather change within two hours of application.

9.4 Ventilation
When the abrasive blast cleaning is carried out in confined spaces, the Applicator shall install
suitable and sufficient ventilation and extraction system, such shall allow good visibility to the
operators. The ventilation system and trunking should be arranged to minimize or eliminate “dead
spaces”.
Suitable and sufficient ventilation shall be maintained during the application of paint and shall
continue whilst solvent release during curing/drying. The ventilation system shall assure the correct
drying of the paint film and shall prevent the vapor concentration to exceed 10% of the Lower
Explosive Limit (LEL).

9.5 Surface Preparation Inspection


The temperature, dew point, and relative humidity shall be determined with a sling psychrometer
and contact thermometer or equal following procedures in ASTM E 337.
Readings are required at the start of work and every four hours or at other time intervals approved
in writing by Purchaser. Alternatively, continuous monitoring shall be performed using systems
established and/or accepted by Purchaser.
Blast cleaned surfaces shall be compared with SSPC-VIS 1 (ISO 8501-1) visual standards. The
anchor pattern profile depth shall be verified in accordance with ASTM D 4417 (ISO 8503-5).
Replica Tape (e.g. Testex Press-O-Film) coupons shall be attached to the quality daily reports.
Re-circulated shot and grit used for abrasive cleaning shall be tested for the presence of oil by
immersing in water and checking for oil flotation. Tests shall be made at the start of blasting, every
four hours thereafter, and at the end of blasting. If the oil is evident, contaminated abrasive shall be
replaced with clean abrasive and retested before proceeding. All steel blasted since the last
satisfactory test shall be inspected and all contaminated steel shall be re-blasted.
Re-circulated abrasive shall be checked for angularity of shape and fines in the mix. Rounded worn
material shall be removed after every shift and the pot replenished with a new charge.

9.6 Coating Inspection


Surface temperature and humidity readings shall be taken prior to the application of each coat. The
work shall not proceed if the ambient temperature parameters are outside the requirements of this
Specification. If more stringent, the Coating Manufacturer's requirements shall dictate. The substrate
temperature shall be at least 3°C (5°F) above the dew point temperature.
Wet Film Thickness (WFT) shall be checked during the application of each coat to assure the
specified dry film thickness (DFT) will be met.
The dry film thickness (DFT) shall be tested with an accepted magnetic gauge instrument, The
testing method shall be in accordance with SSPC-PA 2 (ISO 2178 or ISO 2360, as applicable).
Measuring method (DFT gauge readings number, DFT acceptance criteria, etc) including
measurement results shall be recorded on the daily reports.
The film shall be visually inspected for defects such as overspray runs, sags, mud cracking,
inadequate cure, and lack of adhesion. Mud cracking must be removed by re-blasting. The Supplier
shall repair all defects according to the touch-up and repair procedures accepted by Purchaser.
When coating adhesion or inter-coat adhesion is of suspect quality, the adhesion shall be checked
by means of pull-off adhesion tester in accordance with ASTM D4541/ ISO 16276 Part 1. Adhesion
pull strength shall meet or exceed the value recommended by the coating manufacturer.
Paints systems on which testing cannot be performed by Pull-Off method (e.g. Silicone Paints, HB
Inorganic Copolymer, IO Zinc) shall be tested by “X-Cut” or “Cross-Cut” method (ASTM D 3359
Method A/B or ISO 16276 Part 2). Adhesion Tests results shall be recorded on daily reports.

Uncontrolled if Printed Page 27 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

For the list of Test Items to be performed during coating work execution refer to APPENDIX 5

10.0 REPAIR AND COMPLETION


Coated surfaces within the scope of this specification that are damaged during assembly or handling
shall be repaired in accordance with procedures accepted by Purchaser.
The Applicator shall repair all coating defects and damages that will occur during the construction
or at its completion until the final coating works written acceptance has been signed among parties.
Paint products used for the repair of defects and damages shall be supplied by the same paint
manufacturer of the original paint system.
Any repair shall be performed according to the instructions listed in the product data sheet published
by the paint manufacturer. Failing, or for better explain the instructions, the criteria reported in the
following sections shall be followed.
Written repair procedure for coating works shall be provided by the applicator and shall be submitted
to the Purchaser for approval, which shall conform to the requirements of this specification.
All damages occurred to previous coat shall be repaired before application of the next one, and
before the final acceptance of the coating works of the Purchaser.
The surface profile shall be restored to meet the specified surface preparation requirements for
cleanliness and profile. The periphery of a damaged area shall be feathered prior to coating
application.
Precautions shall be taken to protect adjacent coated areas from damage caused by local abrasive
blasting. The use of vacuum blast type equipment is permitted for abrasive blast cleaning.
All tools and materials shall be compatible and not detrimental to the surface being treated during
the repair or touch-ups to eliminate the possibility of cross contamination of the surfaces.
Power tool cleaning shall be done using the requirements of SSPC-SP 11.

10.1 Repair of Defects


All defective coatings shall be repaired using the same materials and thicknesses as the original
coating system. Initial repairs shall be carried out if failures occur during inspection and testing per
Inspection and Testing requirement.
Surface damage to coated surfaces caused by welding or cutting shall be avoided by protection of
adjacent areas with non-flammable cloth. In addition, the coating around any heat-affected area
shall be removed 150 mm past the affected area to sound coating surface and feathered edges.
The affected areas include areas of discoloration.
Damaged areas shall be cleaned by abrasive blasting or power tool cleaning as required by the
original grade of cleaning for the coating system.
The coating around the damaged area shall be feathered using sand-papering or rotary flap-discs.
The re-cleaning shall be extended, not less than 50mm, to undamaged surrounding surfaces in
order to assure film continuity. The complete specified paint system shall then be applied on the
cleaned area.

10.1.1 Small Dimension Damage


Any damaged areas less than 200x200mm shall be cleaned by power tooling to SSPC-SP11 and
coated with the original paint system. Surface preparation shall be extended not less than 50mm to
the surrounding sound coating and the edges, properly feathered.

Uncontrolled if Printed Page 28 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

10.1.2 Medium Dimension Damage


Any damaged areas less than 1 m2 shall be cleaned by abrasive blasting according to degree of
cleanliness required for the parent paint system then coated with the original specified paint system,
Surface preparation shall be extended not less than 50mm to the surrounding sound coating and
the edges properly feathered. (medium dimension damage).

10.1.3 Extensive Damage


The damaged areas shall be considered extensive in the following instances, in such circumstances
the complete areas shall be re-blasted and re-coated as originally provided by the specification:
1. When the surface affected by damages is greater than 1 m2
2. when the extension of the damages of small and/or medium dimension, is greater than 5%
scattered or greater than 10% localized of the total coated area.
Where corrosion is present, the area shall be initially power tool cleaned to remove the corrosion
prior to surface preparation by approved surface preparation methods (i.e. blast cleaning) and
coating reapplication according to the relevant requirements given in this document.
All areas with inadequate coating thickness shall be thoroughly cleaned, if necessary, abraded and
additional compatible coat(s) applied until they meet the specified thickness. Additional coat(s) shall
not be visible on the final (finish) coating and on adjoining areas.
For steel that has shop primer only, after erection and/or installation, but before top-coating, items
previously primed shall be examined for damage and for un-primed areas.
All oil and grease shall first be removed in accordance with SSPC-SP 1. Following solvent cleaning,
all loose dirt, chalk, and soluble salts or other contaminants shall be removed by high-pressure water
wash or other Purchaser approved techniques. Un-primed and damaged areas shall be power tool
cleaned in accordance with SSPC-SP 11 and recoated prior to application of all finish coat(s)
required for the complete system.
IO Zinc primer shall be touched-up with epoxy zinc rich primer such as for operative temperature up
to 200°F (93°C); above 200°F operating temperature, use silicone zinc pigmented primer paint. If IO
Zinc primer is touched-up once still not over-coated with modified silicone or aluminium silicone
topcoat, touch ups can also be made with High Build Inorganic Copolymer Paint Compatible with
modified silicone or aluminium silicone topcoat. Compatibility with regards to modified silicone or
aluminium silicone top-coating shall be declared in writing by the HB inorganic copolymer coating
manufacturer.
Hot dipped galvanizing shall be repaired using two coats of a Zinc Rich Epoxy coating having zinc
dust not less than 80% zinc (by mass) in dry film, and in any case in accordance with the methods
provided by galvanizer, Refence to MZ-000-CCX-MC-SPC-00017 shall be made for the specific
requirements.

10.2 Completion of Zinc ethyl-silicate primed surfaces


Exposed areas of bare steel that were originally primed with inorganic zinc rich primer shall, after
cleaning and preparation, be primed with one coat of zinc rich epoxy primer. The undercoat and
finish shall be in accordance with the original coating schedule.

10.3 Partially Coated Items


Items requiring significant handling during installation, such as large valves, may be supplied part
coated, that is without the finishing coat, at the Contractor’s discretion. In this case any damage to
the factory coatings shall be made good at site before applying the final coat. On no account shall

Uncontrolled if Printed Page 29 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

items be supplied in zinc rich primer only, due to the formation of zinc salts, the difficulties associated
with their removal and their effect upon the adhesion of any further coats of paint applied
subsequently.

11.0 HANDLING OF COATED ITEMS


Coated items shall not be handled or moved until all coatings have been dried and cured per coating
manufacturer’s instructions.
Coated items shall be protected on non-abrasive supports during storage.
Care shall be taken to avoid damage to coating systems during loading, transport, unloading and
storage. All slings, ropes and chains shall be rubber sheathed or otherwise suitably protected.
Synthetic belt slings are preferred. Adequate timbers blocking shall be provided when stacking
coated items, and no items shall be stacked directly on the ground. Small pieces of equipment shall
be packaged (or crated) to avoid coating damages.
Coated Surfaces shall be protected from damage during lifting or handling, the following are
applicable also for field works:
a. All shop coated piping equipment and steel shall be handled using wide belt slings, web
belts, and wide padded skids or other approved lifting methods to prevent damage to the
coating.
b. Proper dunnage during transport, storage and job site erection shall be used to minimize
damage to the coating. Coated steel shall not be stored directly on the ground.

12.0 REPORTING AND SUBMITTAL


Quality controls, batch number records, meteorological conditions records, coating reports etc. shall
be issued by the Quality Control Department of Supplier.

12.1 Reporting Documents


A blasting and coating report for each item or group of items issued by the Coating QC shall be
added to the painting report, this shall enclose the following minimum information:
• The Paint and Abrasive Manufacturer's certificates for all material used to perform the
painting work.
• Extent of and condition of all surfaces prepared
• Air temperature, dew point and substrate temperatures at the start, during and at end of
work.
• Characteristics of paint used (e.g. shelf life, mixing ratio, thinning ratio, pot life. etc.)
• Surfaces preparation achieved and surface profile.
• DFT of primer, intermediate and finish coats.
• Total dry film thickness.
• Other Inspection Records.

12.2 Submittals
When required and with Enquiry response a painting procedure shall be provided, in accordance
with the requirements of this specification. The document shall enclose the following minimum
information:
• Type, Manufacturer and Quality of all abrasive to be used.
• Paint System Schedule
• Technical Data Sheet of Painting Materials (Product, application and Material Safety
Datasheet) for each system selected

Uncontrolled if Printed Page 30 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

• The Typical Inspection Form, which should include the following minimum information:

o Environmental conditions
o Means of cleaning
o Method of surface preparation and standard achieved Surface profile
o Degree of cleanliness Means of paint application Dry film thickness per coat
o Results of zinc silicate cure tests
o Overcoating intervals
o Thickness of finished coating system
o Completion of test panels
o Repair form for each discrepancy Results of adhesion test
• Means of loading, transport and storage

12.3 Final Documentation


At the completion of the painting work the following information shall be provided:

• Inspection report for each item/group of items coated


• Guarantee forms

13.0 GUARANTEE
The Applicator and Supplier of the painted item must guarantee quality of the paints, correct
application and the expected duration of the painting systems applied.
- Quality of the paints means that the materials applied have no manufacturing defects, are
suitable for the purpose for which they have been designated and comply with the specifications of
the Paint Manufacturer's technical sheets.
- Correct application means that the coatings are applied in a proper workmanlike manner,
complying scrupulously with the Paint Manufacturer's instructions and/or other contract documents.
- Duration of painting systems applied means that the guarantee commitment by the
Subcontractor or Supplier of the painted item, binds this Subcontractor or Supplier for the duration
indicated in the contract both to supply materials and to carry out all repairs to painting systems free
of charge, in the event of degradation of the work performed and of intrinsic defects of painting
systems, i.e. deriving from failure to fulfil the commitments of quality and of correct application.
All defects such as blistering, disbonding, peeling, etc., even without the presence of rusting, are
not allowed during the guarantee period, as they promote corrosion, insufficient bonding and
degradation of painting works.
Declarations of conformity such as technical statements or laboratory test results documentation
shall be attached to paint working procedures as proof of compliance for accelerated lab test
performances to the requirements of ISO 12944-6 for such paint systems used to protect non-
insulated carbon/low alloy steel and hot dip galvanized surfaces. Supplier of the paint must
guarantee quality of the paints, applicator shall guarantee for correct application and duration of the
painting systems applied.
Quality of the paints means that the materials applied in a workmanlike manner have no
manufacturing defects, are suitable for the purpose for which they have been designated and comply
with this specification and prescriptions given in the Paint Manufacturer's technical sheets.
Correct Application means that the coatings are applied by the Supplier’s Applicator in a proper
workmanlike manner, complying scrupulously with the Contract documents, Paint Manufacturer's
instructions, Current standards, Material Safety Datasheets and proper working techniques.

Uncontrolled if Printed Page 31 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Duration of painting systems applied means that the guarantee commitment by the Supplier for the
duration indicated in the contract both to supply materials and to carry out all repairs to painting
systems free of charge, in the event of degradation of the work performed due to intrinsic defects of
paint formulation deriving from failure to fulfil the commitments of workmanlike of correct application
and/or Paint Product Manufacturing defects;
Paint manufacturer shall Assure that products provided to the Supplier and/or Applicator are of a
good quality, able to prevent corrosion of the surface on which are applied for the guarantee time
indicated below, are provided in their original containers, un-expired and shipped in traceable lots,
compliant to the technical requirements and properties in the available technical datasheet, fulfilling
the performances specified for the Project as well for the veridicity of data and information provided
in its documentation: any application mixing ratio, processing methodology, storage conditions
including disposal and safe handling (including MSDS data), curing time and application times,
serviceability limit stated in its relevant printed documents (product/system/application datasheet
and official instructions) are valid and correct.
In any case the Applicator shall guarantee for the correct surface preparation, the most suitable
method to achieve the required protective properties of a System specified as well as any particular
requirement made by the manufacturer in its printed documentation; Applicator shall guarantee for
the correct execution with respect to the environmental conditions limitations as well as the proper
inter-coating and curing time, as well that the application has been committed within a time-frame
not higher than six (6) month form the paint product production. The applicator shall guarantee that
the products are applied using suitable tools, properly maintained and in good working conditions,
for their settings so to ensure the correct preparation mixing use and application of the Paint
Products Specified. Applicator shall guarantee that prescribed paint products will be applied without
any thinner or additive different from the type provided by the Paint Manufacturer and in any case
in compliance with Written Manufacturer’s Instructions for their correct and safe use (which shall be
reported in the Inspection Documents as agreed with Paint Manufacturer).
Applicator shall produce quality records to track surface preparation and paint system application
activities on a daily basis and store it for the guarantee period.
Applicator shall guarantee all paintings are not exceeding Ri 2 within a period of five (5) year, starting
from work completion acceptance, according to ISO 4628-3.
Applicator at site of the entire coating system or any coat such primer, intermediate or finish shall
guarantee a Rusting Degree from work completion at site, of Ri 2 after five (5) years as per ISO
4628-3.
All defects such as blistering, disbonding, peeling, Cracking, even without the presence of rusting,
are not allowed during the guarantee period, as they promote corrosion, this include insufficient
bonding and degradation of painting works.
At the end of the guarantee period the maximum degree of cracking, blistering, or flaking shall be
3S3 according to ISO 4628-1, ISO 4628-2, ISO 4628-4 and ISO 4628-5.
If during the above-mentioned period painting defects would be ascertained, the Supplier shall, bring
back the faulty surfaces to the required acceptable degree using the product provided as warranted
by Paint Manufacturer without any additional Cost for the Customer or Contractor.
Hot service painting systems are excluded from the duration guarantee.
Degradation of painting works resulting from: mechanical damage done by third party, force majeure
(fire event, war), contact with corrosive substances differing from the usual atmospheric
environment, heat input, failure to perform normal maintenance and mechanical completion as well
as color variation of paints sensitive to ultraviolet radiation and related defects such as chalking are

Uncontrolled if Printed Page 32 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

not covered by the guarantee obligations. In addition to limitations set forth in other provisions
guarantee is limited to the corrosion protection, corrosion is intended as the corrosive alteration of
the metallic substrate, the warranty period will not be extended for any event or occurrence,
including, but not limited to repairs done by others and will start from the day of acceptance of the
works at supplier premises or designated work location, as defined in the contract conditions.
Under no circumstance the Company approval of a coating system shall be considered a guarantee
from the Company related to the coating materials and repair products and they performance, but
just as an approval to use it by experienced, reputable and qualified users.

14.0 DURABILITY
Durability is a technical consideration/planning parameter that can help the owner set up a
maintenance programme. The information set forth in this section is indicative only and based on
the general assumption that the systems are applied correctly throughout the various process stages
and ordinary maintenance is executed by the Company throughout the lifetime of the structures,
from time to time. Reference to ISO 12944 series should be made for details in maintenance
planning of the coating systems applied on the structures.
PAINT
AREA Durability (ISO 12944-1)
SYSTEM
1 Not insulated CS HIGH (15 to 25 years)
1A Not insulated CS Structures HIGH (15 to 25 years)
11 Galvanized Steel Surfaces HIGH (15 to 25 years)
19 Splash Zone VERY HIGH (more than 25 years)
20 Immersion VERY HIGH (more than 25 years)
Above Table considers the Average thickness of each coating system applicable to the structures,
once exposed to “C5” Conditions.
Durability is not a Guarantee time.

15.0 APPENDICES
Appendix 1 Paint Products
Appendix 2 Painting Schedule
Appendix 3 Paint System Descriptions
Appendix 4 Final Coat Colors
Appendix 5 Test Items

Uncontrolled if Printed Page 33 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

APPENDIX 1 PAINT PRODUCTS


Typical Manufacturers and Products (note 1)
Generic
Product PPG International Sherwin-
Hempel Carboline Jotun
Amercoat Paint Williams

Inorganic Zinc Dimetcote 9


Galvosil Zinc Clad II Carbozinc
Series / Interzinc 22 Resist 86
(IO Zinc) 15700 Series 11 Series
Sigmazinc 9
Sigmazinc 109
Zinc Rich Hempadur Zinc Clad Carbozinc
/ Sigmazinc 68 Interzinc 52 Barrier
Epoxy Zinc 17360 IV 859
SP
Hempaprime
Amercoat 385 Multi 500 / Penguard
High Build (HB) Intergard Macropoxy Carboguard
/ Sigmacover Hempadur Pro /
Epoxy 475HS 646 890 / 893
385 Mastic Express
45880/1
Amercoat
8230 / Intertherm Hempadur Thermaline Tankguard
Novolac Epoxy Epo-Phen
Sigmatherm 228HS 85671 450 Storage
230
Heat Flex
Silicone
Modified SigmaTherm Intertherm Hi-Temp Thermaline Solvalitt
Acrylic
Silicone 350 875 500 / Heat- 4900 Series Midtherm
56940
Flex M505

Silicone Heat Flex


Amercoat
Aluminium Hi-Temp
High Heat 8540 / Thermaline
Intertherm 50 56910 / 1000 / Solvalitt
Silicone Sigmatherm 4700 Series
Heat-Flex
540 56914 M505
Amercoat 450 Hempathane Acrolon
Series / Interthane Topcoat 218HS / Carbothane Hardtop
Polyurethane
Sigmadur 550 990 / 990HS 55210 / HS Acrolon 134 Series XP
Series 55610 7300
High Build (HB) Amerlock 2 / Interseal 670
HS Hempadur Macropoxy Carboguard Tankguard
Epoxy to NSF Phenguard
35560 646 PW 891 VOC 412
61 930/940 (Buff/White)
Amercoat Bitumastic
Coal Tar Epoxy Intertuf 708 --- TarGuard ---
78HB 300M
Amerlock
2/400 GFK Interseal
Epoxy (Coal Hempadur Macropoxy Carbomastic Jotamastic
670HS
Tar Free) / Sigmashield 85531 646 (Black) 18BT 80
(Black)
400
ALU
Heat Flex
Pigmented HB Interbond Versiline Jotatemp
-- Hi Temp --
Inorganic 1202 UPC 56990 (Alu) 1000 (Alu)
1200 (Alu)
Copolymer

Uncontrolled if Printed Page 34 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Typical Manufacturers and Products (note 1)


Generic
Product PPG International Sherwin-
Hempel Carboline Jotun
Amercoat Paint Williams
Self Priming
Epoxy Mastic Amerlock 2 / Interseal Hempadur Macropoxy Carboguard Jotamastic
(Immersion Sigmacover 2 670HS 45880/1 646 890 80
Grade)
HT Epoxy (IZ Interbond Carboguard Jotatemp
--- --- ---
Compatible) 2340 UPC 690 250
Heat Flex
GREY HB Versiline Jotatemp
Hi Temp Thermaline
Inorganic Hi-Temp 1027 -- 56990 1000
1200 Heat Shield
Copolymer (Grey) (Grey)
(Grey)
Typical Manufacturers and Products (note 1)
Generic
Product Fuchs
Valvoline Shell Cortec
Lubricants
Temporary
Anticorit
Protective Tectyl 506 EH Ensis TX VPCI 368
BW 366
Compound

Note 1: Typical manufacturers and products are listed. Others may be used with approval
from the Purchaser. Paint Product Manufacturer to provide datasheet

Uncontrolled if Printed Page 35 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

APPENDIX 2 PAINT SCHEDULE


All temperatures noted in this schedule shall be actual operating conditions, not steam out or
design conditions. Paint system(s) selection for supports (skirts, pipe hangers, etc.) shall be
based on the actual skin temperature during operation. Equipment and piping requiring
regeneration shall be painted with coatings having a heat resistance capable of withstanding
said conditions. Refractory lined items such as heaters and stacks shall be painted in
accordance with calculated cold face temperatures.
Item OPERATING TEMPERATURE PAINT
ITEMS
No. °C (°F) SYSTEM
1.0 STRUCTURAL STEEL
Columns, Beams, Girders, Trusses, Channels,
Walkways, Handrails, Ladders, Grating, and other Hot Dip Galvanized per Project Galvanizing
1.1
Structural Members; Structural Fasteners, Anchor Specification
Rods, and Anchor Bolts
Beneath Intumescent Mastic Fireproofing
1.2 ≤80 (≤176) 13
(non-galvanized)
1.3 Non-galvanized structural steel to be painted ≤93 (≤200) 1
Miscellaneous shop coated carbon steel which
1.4 ≤93 (≤200) 1A
requires spot repair
Galvanized Steel for Safety Color; Items such as
1.5 ≤93 (≤200) 11
ladders, cages, handrail assemblies
1.6 Embed Steel, Plates, etc. ≤93 (≤200) 12
1.7 Stainless Steel Structures ≤93 (≤200) 11
2.0 DRUMS, TOWERS, COLUMNS, EXCHANGERS, AND REACTORS
2.1 CARBON STEEL
Un-Insulated or Non-Fireproofed Supports, Saddles,
2.1.1 ≤93 (≤200) 1
Skirts
2.1.2 Un-Insulated ≤93 (≤200) 1
2.1.3 Un-Insulated >94 to ≤204 (>200 to ≤400) 2
2.1.4 Un-Insulated >204 to ≤400 (>400 to ≤752) 3
2.1.5 Un-Insulated >400 to ≤538 (>752 to ≤1000) 7
Insulated or Cementitious Fireproofed Supports,
2.1.6 ≥-45 to ≤150 (≥-49 to ≤300) 5
Saddles, Skirts
2.1.7 Beneath Intumescent Mastic Fireproofing ≤80 (≤ 176) 13
2.1.8 Insulated ≥-45 to ≤150 (≥-49 to ≤300) 5
2.1.9 Insulated >150 to ≤400 (>301 to ≤752) 6
2.1.10 Insulated >400 to ≤538 (>752 to ≤1000) 4
Insulated: Regeneration
2.1.11 Normal Operating Temp ≤60 (≤140) 5
Regeneration Temp ≤232 (≤450)

Uncontrolled if Printed Page 36 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Item OPERATING TEMPERATURE PAINT


ITEMS
No. °C (°F) SYSTEM

Insulated: Regeneration
2.1.12 Normal Operating Temp >60 to ≤232 (>140 to ≤450) 4
Regeneration Temp ≤552 (≤1026)
2.2 STAINLESS STEEL (NOTE 1)
2.2.1 Insulated ≤150 (≤300) 8
2.2.2 Insulated >150 (>300) 17
2.2.3 Uninsulated ≤93 (≤200) 11
2.2.4 Uninsulated >93 to 204 (>200 to 400) 16
2.2.5 Uninsulated >200 to 538 (>400 to 1000) 17
3.0 PIPING, PIPING SUPPORTS, AND FITTINGS
3.1 CARBON STEEL
3.1.1 Un-Insulated ≤93 (≤200) 1
3.1.2 Un-Insulated >94 to ≤204 (>200 to ≤400) 2
3.1.3 Un-Insulated >204 to ≤370 (>400 to ≤700) 3
3.1.4 Un-Insulated >370 to ≤538 (>700 to≤1000) 7
3.1.5 Insulated ≥-45 to ≤150 (≥-49 to ≤300) 5
3.1.6 Insulated >150 to ≤400 (>300 to ≤750) 6
3.1.7 Insulated >400 to ≤538 (>750 to ≤1000) 4
Insulated: Regeneration
3.1.8 Normal Operating Temp ≤60 (≤140) 5
Regeneration Temperature ≤232 (≤450)
Insulated: Regeneration
3.1.9 Normal Operating Temp >61 to ≤232 (>141 to ≤450) 4
Regeneration Temperature ≤552 (≤1026)
3.2 STAINLESS STEEL (NOTE 1)
3.2.1 Insulated ≤150 (≤300) 8
3.2.2 Insulated >150 (>300) 4S
3.2.3 Uninsulated ≤93 (≤200) 11
3.2.4 Uninsulated >93 to 204 (>200 to 400) 16
3.2.5 Uninsulated >204 to 538 (>400 to 1000) 17
4.0 MACHINERY
4.1 Pumps, Compressors, and Rotating Equipment 9
5.0 CONTROL VALVES, MOTORS, AND MISCELLANEOUS ITEMS (CARBON STEEL) (NOTE 2)
Control Valves, Actuated On/Off Valves, Pressure Relief
5.1 9
Valves & Shut Off Valves including Actuators (all types)

Uncontrolled if Printed Page 37 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Item OPERATING TEMPERATURE PAINT


ITEMS
No. °C (°F) SYSTEM
Electric Motors & Electrical Equipment (Transformers,
5.2 9
Resistors, etc.)
Instrument and Control Panels / Boards, Pushbutton
5.3 9
Stations and Switches, HIPPS
Analyzers & Analyzers Shelters, Pressure
&Temperature Transmitters, Flow Meters & Flow
5.4 9
Instruments, Level Gauges & Level Instruments,
Displacement Meters
5.5 JBs, Cable Trays, Cable Ladders 9
5.6 Earthing and Lightning Material 9
6.0 TANKS AND SPHERES (INCLUDING SHOP FABRICATED) (NOTE 3)
6.1 CARBON STEEL
6.1.1 Un-Insulated ≤93 (≤200) 1
6.1.2 Un-Insulated >93 to ≤204 (>200 to ≤400) 2
6.1.3 Insulated ≥-45 to ≤150 (≥-49 to ≤300) 5
6.1.4 Externally Insulated >150 to ≤400 (>300 to ≤750) 7
6.1.5 The underside (soil/basement side) of Tank Bottom ≤93 (≤200) 14
6.2 STAINLESS STEEL (NOTE 1)
6.2.1 Insulated ≤150 (≤300) 8
6.2.2 Insulated >150 (>300) 17
6.2.3 Uninsulated ≤93 (≤200) 11
6.2.4 Uninsulated >93 to 204 (>200 to 400) 16
6.2.5 Uninsulated > 204 to 538 (>400 to 1000) 17
7.0 FURNACES, STACKS, BREECHING, DUCTS, AND BOILERS (CARBON STEEL)
7.1 Uninsulated ≤93 (≤200) 1
7.2 Un-Insulated ≤204 (≤400) 2
7.3 Un-Insulated >204 to ≤400 (>400 to ≤752) 3
7.4 Un-Insulated >400 to ≤538 (>752 to ≤1000) 7
7.5 Insulated ≥-45 to ≤150 (≥-49 to ≤300) 5
7.6 Insulated >150 to ≤400 (>300 to ≤752) 6
UNDERGROUND PIPING (ISO 12944 Im 3 – Soil
8.0
Condition)
FBE external Coating Refer to MZ-000-CCX-MC-SPC-00004
POTABLE WATER TANK (ISO 12944 Im 1 – Fresh
9.0
Water)
Internal Lining Refer to MZ-000-CCX-MC-SPC-00003

Uncontrolled if Printed Page 38 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Item OPERATING TEMPERATURE PAINT


ITEMS
No. °C (°F) SYSTEM
10.0 BOLLARDS, WALKING AREAS
10.1 Emerged Uninsulated Carbon Steel ≤80 (≤200) 1
Decks, Working Floors and Continuous Platforms,
10.2 ≤80 (≤200) 18
Walkways, Escape Routes
10.3 Splash Zone (Extended Tidal Zone) ≤80 (≤200) 19
BREASTING AND MOORING DOLPHINS, JETTY PILES (CARBON STEEL PILES), SHEET
11.0
PILES
11.1 Atmospheric part of immersed item (i.e. Pile) ≤80 (≤200) 19
11.2 Splash Zone (Extended Tidal Zone) ≤80 (≤200) 19
11.3 Permanent Immersion zone / Buried ≤80 (≤200) none
SEAWATER INTAKE AND OUTFALL
12.0
STRUCTURES
12.1 Structures, including Caissons and Conduits ≤80 (≤200) 20

Notes:
<1> No coating is required on the following uninsulated materials subject to the following temperature
conditions:
- 22% Cr Duplex Stainless Steel at a temperature below 100°C;
- 25% Cr Duplex Stainless Steel at a temperature below 110°C;
- 6% Mo Super Austenitic Stainless Steel at a temperature below 120°C.
<2> No coating is required on the non-pressure retaining parts made of Stainless Steel (316/316L
grade minimum)
<3> The underside (soil/basement side) of Field erected Tank Bottom coating system shall not be
repaired on weld seams, Soil corrosion will be managed by cathodic protection.

Uncontrolled if Printed Page 39 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

APPENDIX 3 PAINT SYSTEM DESCRIPTION


SURFACE PREP - SSPC Anchor Profile - SSPC PA2
TOTAL DFT,
PAINT µm (mils) Acceptance
Remark
SYSTEM Primer / Intermediate / Finish DFT- µm
µm (mils) Level
(mils)
SP 10 (Sa 2.5) 38–63 (1.5-2.5)
IO Zinc 62.5-87.5 (2.5-3.5) 200-325
1 Level 4
HB Epoxy 100-162.5 (4.0-6.5) (8.0-13.0)
Polyurethane 37.5-75 (1.5-3.0)
SP 11 min 25 (1.0)
Zinc Rich Epoxy 62.5-87.5 (2.5-3.5) 200-325
1A Level 4
HB Epoxy 100-162.5 (4.0-6.4) (8.0-13.0)
Polyurethane 37.5-75 (1.5-3.0)
SP 10 (Sa 2.5) 25–50 (1.0-2.0)
IO Zinc 50-75 (2.0-3.0) 137.5-175
2 Level 4
Modified Silicone 37.5-50 (1.5-2.0) (5.5-7.0)
Modified Silicone 37.5-50 (1.5-2.0)
SP 10 (Sa 2.5) 38–63 (1.5-2.5)
IO Zinc 50-75 (2.0-3.0) 100-150
3 Level 4
High Heat Silicone 25-37.5 (1.0-1.5) (4.0-6.0)
High Heat Silicone 25-37.5 (1.0-1.5)
SP 10 (Sa 2.5) 1.5-2.5 (38–62.5) Use ALU color
HB Inorganic Copolymer 100-150 (4.0-6.0) version for un-
HB Inorganic Copolymer 100-150 (4.0-6.0) 200-300 insulated surfaces,
4 Level 3
(8.0-6.0) Use GREY or ALU
color version for
Insulated surfaces
SP 16 (Corundum) 2-3 (50–75) Use ALU color
HB Inorganic Copolymer 100-150 (4.0-6.0) version for un-
HB Inorganic Copolymer 100-150 (4.0-6.0) 200-300 insulated surfaces,
4S Level 3
(8.0-6.0) Use GREY or ALU
color version for
Insulated surfaces
SP 10 (Sa 2.5) 38–62.5 (1.5-2.5)
200-300
5 Novolac Epoxy 100-150 (4.0-6.0) Level 4
(8.0-12.0)
Novolac Epoxy 100-150 (4.0-6.0)
SP 10 (Sa 2.5) 25–50 (1.0-2.0) 62.5-87.5
6 Level 4
IO Zinc 62.5-87.5 (2.5-3.5) (2.5-3.5)
SP 10 (Sa2.5) 37.5–62.5 (1.5-2.5)
IO Zinc 50-75 (2.0-3.0)
75-112.5
7 High Heat Silicone 25-37.5 (1.0-1.5) Level 4
(3.0-4.5)

SP 16 37.5–50 (1.5-2.0)
200-300
8 Novolac Epoxy100-150 (4.0-6.0) Level 4
(8.0-12.0)
Novolac Epoxy 100-150 (4.0-6.0)
Requirements of
9 Manufacturer’s Standard Paint System
Chapter 3
SP 10 (Sa 2.5) 25–37.5 (1.0-1.5) 100-150
10 Level 4
Novolac Epoxy 100-150 (4.0-6.0) (4.0-6.0)

Uncontrolled if Printed Page 40 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

SURFACE PREP - SSPC Anchor Profile - SSPC PA2


TOTAL DFT,
PAINT µm (mils) Acceptance
Remark
SYSTEM Primer / Intermediate / Finish DFT- µm
µm (mils) Level
(mils)
Sweep blast using
SSPC SP 16 25-37.5 (1.0-1.5)
175-250 reduced nozzle
11 HB Epoxy 125-175 (5.0-7.0) Level 4
(7-10) pressure and fine
Polyurethane 50-75 (2-3.0)
abrasive
SP11 min. 25 (1.0)
200-300
12 Epoxy Primer 100-150 (4.0-6.0) (zinc free) Level 4
(8.0-12.0)
Epoxy Primer 100-150 (4.0-6.0) (zinc free)

Paint shall be
SSPC SP10 38-75 (1.5-3.0)
50-75 approved by
13 Epoxy Primer under Intumescent Level 3
(2.0-3.0) Intumescent
Fireproofing 50-75 (2.0-3.0)
Manufacturer.

SP 10 min 50-75 (2.0-3.0)


Epoxy (Coal Tar or Coal Tar Free) 165-240
330-480
14 (6.5 - 9.5) Level 4
(13.0 – 19.0)
Epoxy (Coal Tar or Coal Tar Free) 165-240
(6.5 - 9.5)
SP 16 25 to 37.5 (1.0-1.5)
75-100
16 Modified Silicone 37.5-50 (1.5-2.0) Level 4
(3.0-4.0)
Modified Silicone 37.5-50 (1.5-2.0)
Use ALU color
version for
SP 16 25 to 37.5 (1.0-1.5)
uninsulated
High Build Inorganic Copolymer 100-150
200-300 surfaces and Bulk
17 (4.0-6.0) Level 3
(8.0-12.0) Flanged SS valves,
High Build Inorganic Copolymer 100-150
Use ALU/GREY
(4.0-6.0)
color version for
insulated surfaces
Non-Slip Epoxy
Shall be supplied
as a multi-
SP 10 min 50-75 (2.0-3.0) component kit.
1112.5-2225
18 Epoxy Primer 62.5-87.5 (2.5-3.5) Level 4 Addition of Non-
(44.5-86.5)
Non-Slip Epoxy 1000-2000 (40-80) skid aggregate
subject to Coating
Manufacturer
Recommendations.
SP 5 min 75-100 (3.0-4.0) Coating Materials
Epoxy Glass Flake 400-500 (16.0-20.0) 800-1000 shall be suitable for
19 Level 3
Epoxy Glass Flake 400-500 (16.0-20.0) (32.0-40.0) Cathodic Protection
(-1.1V Potential
SP 10 min 50-75 (3.0-4.0)
Epoxy Glass Flake 150-200 (6.0-8.0) 300-400
20 Level 3
Epoxy Glass Flake 150-200 (6.0-8.0) (32.0-40.0)

Uncontrolled if Printed Page 41 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

DFT Acceptance Level


While individual DFT gage readings that are unusually high or low (and cannot be repeated
consistently) can be discarded, there are limitations on the thickness values representing the spot
measurements (the average of minimum three gage readings). For the purpose of final acceptance
of the total dry film thickness, the cumulative thickness of all coating layers in each area must be no
less than the cumulative minimum specified thickness and no greater than the cumulative maximum
specified thickness.
LEVEL Thickness Restriction Level
Gage Reading Spot Measurement Area Measurement
Level 3 Unrestricted 80% of Minimum As Specified
120% of Maximum
Level 4 Unrestricted 80% of Minimum As Specified
150% of Maximum

Uncontrolled if Printed Page 42 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

APPENDIX 4 FINAL COAT COLORS


In this appendix, the basic finish color schedule for the production facility in the scope of the project
is given. Any deviation from this Appendix and table shall be agreed with Purchaser and Client,
through a formal deviation request.
Final coat color of items not clearly indicated into the Table below shall be stipulated among Vendor
and Contractor before the Purchase Order award.
Care must be ensured in the appropriate selection during design to allow a seamless supply and
avoid contrasting requirement in the procurement and uneven and confusing visive environment
once the items are in place. Finish colors here specified are intended applicable to those coating
systems which the finish coat can be produced with the applicable RAL Designation (i.e., System
1/1A, System 11…); different systems are acceptable in “off-white”, “eggshell” or “light gray” as per
standard manufacturer color (i.e., System 5, System 10…). Systems for high temperature with a
color like the specified “White Aluminum” are acceptable, and in any case per paint manufacturer’s
standard aluminum color (i.e., System 2/3, System 7, System 16/17…) suitable for the operating
conditions, production differences are accepted. The colors of the coatings, related to topcoats only,
shall allow the visibility of the coated pipe or component, or it shall satisfy aesthetic and
homogeneousness requirements. RAL Designation does not apply to finish coat of either paint
systems to be applied to surfaces for under insulation service and surfaces to be buried in contact
with soil. The color definition refers to the RAL 840 HR Deutschen Normen Auschuss Standard.
ITEM DESCRIPTION FINAL COLOR
Vessels, Exchangers & Piping Uninsulated Surfaces Light Gray (RAL 7035)
To 149°C (300°F)
Vessels, Exchangers & Piping Uninsulated Surfaces Manufacturer’s Standard Aluminum
Above 149°C (300°F)
Direct Fired Heaters, Stacks Outside Casing Blue Gray (RAL 7031) or
Traffic Black (RAL 9017)
Spheres and Storage Tanks Uninsulated Surfaces Signal White (RAL 9003)
Water Tanks Potable and non-Potable Signal White (RAL 9003)
Cooler Boxes Uninsulated Surfaces Signal grey (RAL 7004)
Structural Steel, including Non-galvanized Surfaces Signal grey (RAL 7004)
Piping Hangers
Stumbling and Tripping Hazards Zinc Yellow (RAL 1018) / Traffic
Black (RAL 9017) <Note 1>
Handrails, ladders, safety Part of access and egress systems. Traffic Yellow (RAL 1023)
cages assembly
Pumps, Compressors, Motors Uninsulated Manufacturer’s Standard Color or
and other Rotating Equipment Medium Gray (RAL 7004)
Lifting Devices Visible surfaces and Moving Pars Pure Orange (RAL 2004)
Tools and lifting Gears Used maintenance and operation, Zinc Yellow (RAL 1018),
i.e. temporary beams and bracings
Electrical Equipment Light Grey (RAL 7035)
Automation / Instruments Panels, Boards, Pushbutton Manufacturer’s Standard Color,
Stations, Switches, Analysers, neutral grey is preferred.
Analyzer Shelters, Transmitters,
Flow Meters, other Instruments

Uncontrolled if Printed Page 43 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

ITEM DESCRIPTION FINAL COLOR


Fire Fighting System Fire Fighting Equipment, Hydrants, Flame Red (RAL 3000)
Monitors, Hose Reels, Firewater
Pumps, Firewater Lines
Safety Equipment Safety Showers, Eye Wash Leaf Green (RAL 6002)
Fountains
Tanks, Equipment Internal Surface (painted) Light Color Shades (white, cream,
light grey, as qualified)
Tanks, Equipment, and Piping Buried Black
Decks, Working Floors and Main Color Grey
Platforms, walkways, escape General Marking Lines Yellow
routes
Plant Labelling Pipe Identification Refer to MZ-000-AM1-OP-SPC-
00001
Mechanical Component
Valves and Instruments

Notes:
1- The layout and meaning of safety marking is defined as follows: use of Yellow and
Contrasting black on potential hazard location of bumping, falling or tripping of load falling.
Bands are of equal width and to be of at an angle of approximately 45° unless specified
differently.

Uncontrolled if Printed Page 44 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

APPENDIX 5 TEST ITEMS


Unless otherwise agreed, the Supplier must carry out and certify the Inspections. Frequency,
application, and entity of the tests shall be submitted for Contractor comments and approval in the
relevant testing schedule prior to the commencement of the works. Selection of the appropriate
inspection items shall suit the protective system being applied and frequency shall account for the
entity of the works.
Tests, Inspections, and Checks carried out in accordance with the applicable standards indicated in
the following table and shall be reported in the QCP, submitted for Contractor Evaluation and
Acceptance.
The surfaces must be accessible until the final inspection has been carried out.
Contractor reserves the right to carry out Inspections, Tests, and Checks before, during and upon
completion of painting works.
Tests, Inspections, and Checks are carried out in accordance with the applicable standards
indicated in the following table and shall be reported in the QCP, submitted for Contractor Evaluation
and Acceptance.
The surfaces must be accessible until the final inspection has been carried out.
Reference to the applicable Company Inspection Test and Plan shall be made to define the
Involvement Level for painting inspection works, inspection crew qualification, inspectors should be
accordingly NACE, FROSIO or equivalently qualified.
Supplier shall establish an adequate organization, able to assure the following minimum tasks:
a) Prepare work procedures describing in detail the various activities to be performed, including
use of the proper equipment and the adequate work environment,
b) Comply with the referenced standards and rules and with the specific requirements in the
specification, as well as specific requirements set out in the Purchase Order,
c) Provide sufficiently trained working personnel, able to perform the executive, administrative
and supervisory tasks required to attain workmanlike and satisfactory protective coating
works. Applicators should be qualified per ASTM D4228 or other industry practice.
d) Be able to coordinate the supply chain, complete with proper planning, and arrange in
coordination with paint manufacturer the proper quality and work documentation.
e) Monitor, check and record the specific characteristics of any coating phase and process.
f) Allow Contractor and Company’s Inspector duties, providing access to its facilities prior,
during and after production and in any case prior to shipment, as defined in the Contract
Test Items
Minimum Solution of the
Item Test Method Acceptance Criteria
Frequency Non-conformity
All coating materials and
Storage of
thinners shall be Provide Suitable
1 Coating Visual All
properly stored in the Storage Area
Materials
Applicator’s facility
All coating materials Provision of Material
shall be supplied to the in sealed containers,
work site in their original properly
marked/labeled to an
Containers unopened and clearly
2 Visual All acceptable level,
Integrity identified containers, completed of shelf
bearing readable labels life, batch production
of the Paint no., date of expiry,
Manufacturer. GHS symbols.

Uncontrolled if Printed Page 45 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Minimum Solution of the


Item Test Method Acceptance Criteria
Frequency Non-conformity
According to Product
Datasheet, Product use Rejection Of Paint
should be within the Material, Correctly
All supplied manufacturing date and Dispose of expired
3 Shelf Life Visual
material the written expiry time material. Provision
marked by paint of new, unexpired,
manufacturer on paint materials.
package
Noble Material is
spatially and phisically Arrange the Work
All items to be
Material separated from Less area to provide
4 Visual painted, prior to
Segregation noble Material or separate area by
work staging.
potentially adequate means
contaminating material
According to Rectify the surface
Steel and
requirements and prior to surface
5 Welding ISO 8501-3 100%
compliant to the grade preparation
Imperfections
specified for the system operations.
No Surface
As Minimum,
When the steel preparation or
ISO 8502-4 Before start of
temperature is at 3°C Painting. Control
Sling each shift and
Environmental above dew point or the working
6 Conditions
Psychrometer, twice a day or
when the relative Environment to suit
Contact whenever
humidity of the air is optimal application
Thermometer suspected
lower than 80%. conditions prior to
conditions
work start, retest.
Welding Flux Any weld left
Distilled Water Remove Welding
Fumes and unclean or
7 + pH “Neutral” (6.5 – 7.5) Fumes Flux
Oxides prepared per Item
Litmus Paper Oxides, retest
Removal 4
Clean the surface,
it shall be free from
Grease, Oils, Dirt &
Cleaning of Dust, Drawing &
8 SSPC-SP 1 100% Free of Contaminants
Material Cutting
Compounds, and
other foreign
matter.
All equipment,
structures and any other
Protection of area subject to damages
Apply all necessary
9 Fragile Visual 100% caused by surface
protections
Materials protection or coating
application shall be
protected
Purge the System,
Compressed Air shall be free from
10 ASTM D4285 Every Shift Clean and Change
Air Quality moisture and oil
the filters, retest
Discard spent
Suitable for the abrasive and
Abrasive Substrate being treated, Provide new
11 ISO 11127-6 Every Shift
Materials Conductivity ≤ 150 abrasive and use
µs/cm @ 20°C Clean Abrasives,
retest

Uncontrolled if Printed Page 46 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Minimum Solution of the


Item Test Method Acceptance Criteria
Frequency Non-conformity
Removal of all
visible oil, grease,
soil, drawing and
cutting
compounds, and
Free from Dirt, Oil, other soluble
Cleaning of
12 SSPC-SP1 100% Grease and other contaminants from
Surfaces
foreign matter steel surfaces with
solvent, vapor,
cleaning
compound, alkali,
emulsifying agent,
or steam.
Blast Clean the
surfaces to the
required level,
retest. The surface
shall be free from
Compliant with final Grease, Oils, Dirt,
Abrasive
SSPC-VIS 1 Grade specified for the and dust, Drawing
13 Blast 100%
ISO 8501-1 particular coating & Cutting
Cleaning
system Compounds, Mill
Scale, Rust,
previously applied
paint, Oxide
Coating, and other
foreign matter.
Compliant with final Power tool Clean
Power Tool Grade specified for the the surfaces to the
14 SSPC-VIS 3 100%
Cleaning particular coating required level,
system. retest
Verify Abrasive
Compliant with final
ASTM D4417 media per Item 10,
15 Roughness Spot Checks grade specified in the
ISO 8503-5 rectify (if needed),
relevant paint system
reblast, retest
In Shop: Maximum
Quantity 1 and dust Blow with fresh dry
Dust Test
dimension 2, air, dedust using
16 after surface ISO 8502-3 Spot Checks
In the field: Maximum vacuum aspirator,
preparation
Quantity 2 and dust retest
dimension 2.
Clean The surface
using fresh, clean
water per SSPC-
Spot Checks, SP1, retest and
Mandatory on According to the reclean until
Water ISO 8502-6
17 permanently specified level for the reaching the
Soluble Salts ISO 8502-9
Immersed and coating System acceptability
Buried Surfaces criteria, the
surfaces shall be
dry. Rinse with
fresh water.

Uncontrolled if Printed Page 47 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Minimum Solution of the


Item Test Method Acceptance Criteria
Frequency Non-conformity
Use the required
Material, any
Conformity of paint label sediment shall be
with specified product easily
description, redispersible,
Paint Visually, Prior and during
18 No skin formation, viscosity
Application ISO 12944-7 the application
No Irreversible settling adjustement per
and usability under the paint Product
site conditions Manufacturer
Instructions and
recorded.
Corner, edges, welds,
bolts, nuts, difficult-to-
Before Starting of
reach-areas, etc. shall
Visually, the painting work
Stripe be pre-coated by brush Do not perform
19 SSPC-PA and in any case
Coating (stripe-coated) to ensure Coating Works.
Guide 11 after surface
that they at least the
preparation and
minimum specified film
thickness
According to Product
Data Sheet for the Rectify for Coating
Wet Film Metallic Methodically any
19 Specified Dry Film Thickness
Thickness “Comb Gauge” during Application
Thickness (considering Deficiency
any added thinner)
Spot checks,
Required for field
Residual dust completion of
Blow with fresh dry
level prior to coating build-up,
Conform to Quantity 1 air, dedust using
20 application of ISO 8502-3 prior to the
and dust size 1 vacuum aspirator,
subsequent commencement
retest
coat. of works, in case
of deferred
operation.
Dry Film
Thickness of Rectify for Coating
Level Specified for Each
21 Each coat SSPC-PA2 As per PA2 Thickness
Coating System
and complete Deficiency.
paint system

Verify Quality of
Applied Materials,
stirring machine,
Temperature,
Curing of Before Painting
Compliant with Levels Humidity and
22 Zinc Silicate ASTM D 4752 over inorganic
4/5 curing Time. Wet
Primer zinc-rich primer
the primed coated
surface or suitably
condition the
surface.

Uncontrolled if Printed Page 48 of 49


Mozambique LNG – 6.44 MTPA
PAINTING REQUIREMENTS FOR
PIPING - EQUIPMENT AND STRUCTURES
Document No. MZ-000-CCX-MC-SPC-00001
Rev. 1 Rev Date: 21-MAY-2020

Minimum Solution of the


Item Test Method Acceptance Criteria
Frequency Non-conformity
Rejection of
painting, Check the
As per Paint Product quality of materials,
As per Paint
Curing of Datasheet and Paint expiry, and shelf-
23 Product Methodically
Paints Manufacturer life. Remove un-
datasheet
Application Instructions cured paint and
allow for proper
curing time.
ASTM D 4541 To be Performed on
Adhesion Type III / ISO Test Panels, one per
Rejection of
24 (Destructive 16276-1 Spot Checks item, minimum 5 MPa
Coating works
Test) ASTM D 3359 Ratings 4/5
ISO 16276-2 Levels 0/1/2
No Sagging,
contaminations, orange Rejection of the
Visual Visual and ISO
25 100% of Surfaces peel, cracking, works, Eliminate all
Examination 4628 1 to 6
blistering, rust, damages defects
and any other defects.
Rejection of the
works, Eliminate all
NACE defects providing a
Holiday SP0274, suitable Repair
Testing of settings as per method in case of
Buried Paint product the localized
Substrates Manufacturer pinhole (size to be
Instructions agreed with
Once in place and
Contractor).
after every repair,
Scattered pin-
on the cured
holing throughout
26 coating system, No Holidays
the area are a
100% of Buried or
proof sign of
Holiday Testing NACE Immersed
improper coating
of Immersed SP0188, Surfaces
Or
application /
settings as per improper surface
Buried Non-
Conductive Paint product preparation.
Coating Manufacturer Coating shall be
Substrates Instructions mapped, a
corrective action
submitted, agreed
and implemented.

Uncontrolled if Printed Page 49 of 49

You might also like