PEKERJAAN JALAN
Lokasi : Meulaboh - Proyek Sumatera utara
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.6 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp.
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp.
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.6 @ Rp. 2.795.732,26 = Rp. 2.795.732,26
Jumlah = Rp. 4.088.692,26
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.8 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.562,50
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.8 @ Rp. 3.659.381,36 = Rp. 3.659.381,36
Jumlah = Rp. 4.978.700,61
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.10 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.562,50
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.10 @ Rp. 4.328.514,90 = Rp. 4.328.514,90
Jumlah = Rp. 5.647.834,15
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.6 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.6 @ Rp. 2.795.732,26 = Rp. 2.795.732,26
Jumlah = Rp. 4.115.564,01
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.8 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.8 @ Rp. 3.659.381,36 = Rp. 3.659.381,36
Jumlah = Rp. 4.979.213,11
Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.10 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.10 @ Rp. 4.328.514,90 = Rp. 4.328.514,90
Jumlah = Rp. 5.648.346,65