DAFTAR ANALISA

PEKERJAAN JALAN
Lokasi : Meulaboh - Proyek Sumatera utara

Pekerjaan Lapisan Sirtu+Pemadatan Memakai Alat / M3


1,2000 M3 Batu Sirtu @ Rp. 66.000,00 = Rp. 79.200,00
0,0160 Jam Motor Grader-CAT 126 12G @ Rp. 245.000,00 = Rp. 3.920,00
0,0180 Jam Vibrator Compactor-SV.90 @ Rp. 195.000,00 = Rp. 3.510,00
0,0120 Jam Water Tank Trime @ Rp. 220.000,00 = Rp. 2.640,00
0,9250 Upah Pekerja @ Rp. 75.000,00 = Rp. 69.375,00
0,0080 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 158.645,00

Pekerjaan Lapisan Sirtu Tidak Memakai Alat / M3


1,2000 M3 Batu Sirtu @ Rp. 66.000,00 = Rp. 79.200,00
0,9250 Upah Pekerja @ Rp. 75.000,00 = Rp. 69.375,00
0,0080 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 148.575,00

Pekerjaan Lapisan Batu 1/2 & 2/3 / M3


0,6000 M3 Batu Pecah 1/2 @ Rp. 250.000,00 = Rp. 150.000,00
0,6000 M3 Batu Pecah 2/3 @ Rp. 250.000,00 = Rp. 150.000,00
0,0180 Jam Tandem Roller @ Rp. 195.000,00 = Rp. 3.510,00
0,0120 Jam Water Tank Trime @ Rp. 220.000,00 = Rp. 2.640,00
0,0080 Orang Pekerja @ Rp. 75.000,00 = Rp. 600,00
0,0240 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 306.750,00

Pekerjaan Lapisan Batu 2/3 & 5/7 / M3


0,6000 M3 Batu Pecah 2/3 @ Rp. 250.000,00 = Rp. 150.000,00
0,6000 M3 Batu Pecah 5/7 @ Rp. 250.000,00 = Rp. 150.000,00
0,0180 Jam Tandem Roller @ Rp. 195.000,00 = Rp. 3.510,00
0,0120 Jam Water Tank Trime @ Rp. 220.000,00 = Rp. 2.640,00
0,0080 Orang Pekerja @ Rp. 75.000,00 = Rp. 600,00
0,0240 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 306.750,00

Pekerjaan Kanstin 15x45x100 / M'


0,1550 M3 Galian Tanah @ Rp. 41.250,00 = Rp. 6.393,75
1,0000 Bh Kanstin Beton Pre Cast @ Rp. 40.000,00 = Rp. 40.000,00
0,0116 M3 Adukan Plesteran 1:3 @ Rp. 1.495.000,00 = Rp. 17.342,00
Jumlah = Rp. 63.735,75
70.109,33
Pekerjaan Paving Block / M2
42,0000 Bh Paving Block @ Rp. 2.000,00 = Rp. 84.000,00
0,1000 Upah Tukang @ Rp. 85.000,00 = Rp. 8.500,00
0,0020 Upah Kepala Tukang @ Rp. 100.000,00 = Rp. 200,00
0,0500 Upah Pekerja @ Rp. 75.000,00 = Rp. 3.750,00
0,0025 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 96.450,00

Pekerjaan Lapisan Hotmix / M3


0,7030 M3 Agregat Kasar @ Rp. 100.000,00 = Rp. 70.300,00
0,5340 M3 Agregrat Halus @ Rp. 100.000,00 = Rp. 53.400,00
75,0000 Kg Asphalt @ Rp. 11.000,00 = Rp. 825.000,00
139,3000 Kg Bahan Pengisi @ Rp. - = Rp. -
0,0370 Jam Whell Loader-CAT.950 @ Rp. 220.000,00 = Rp. 8.140,00
0,0600 Jam Asphalt Mixing Plant @ Rp. 300.000,00 = Rp. 18.000,00
0,2200 Jam Dump Truck @ Rp. 105.000,00 = Rp. 23.100,00
0,0690 Jam Asphalt Finisher @ Rp. 300.000,00 = Rp. 20.700,00
0,0300 Jam Tandem Roller @ Rp. 195.000,00 = Rp. 5.850,00
0,0280 Jam Tyred Roller @ Rp. 205.000,00 = Rp. 5.740,00
0,0600 Jam Generator @ Rp. 180.000,00 = Rp. 10.800,00
0,2200 Orang Pekerja @ Rp. 75.000,00 = Rp. 16.500,00
0,0220 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 1.057.530,00

Pekerjaan Lapisan Asphalt Goreng / M2


2,8000 Kg Asphalt @ Rp. 11.000,00 = Rp. 30.800,00
0,0130 M3 Pasir Pasang @ Rp. 100.000,00 = Rp. 1.300,00
0,0020 M3 Kayu Bakar @ Rp. 135.000,00 = Rp. 270,00
0,0200 Bh Sapu Lidi @ Rp. 7.000,00 = Rp. 140,00
0,0200 Bh Karung Goni @ Rp. 3.000,00 = Rp. 60,00
0,0100 Jam Walles @ Rp. 195.000,00 = Rp. 1.950,00
0,0040 Ls Alat Bantu @ Rp. - = Rp. -
0,2000 Orang Pekerja @ Rp. 75.000,00 = Rp. 15.000,00
0,0200 Orang Tukang @ Rp. 85.000,00 = Rp. 1.700,00
0,0100 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 51.220,00

Pekerjaan Prime Coat / Liter


0,6420 Kg Asphalt @ Rp. 11.000,00 = Rp. 7.062,00
0,4890 Ltr Karosene @ Rp. 6.000,00 = Rp. 2.934,00
0,0050 Jam Asphalt Sprayer @ Rp. 240.000,00 = Rp. 1.200,00
0,0040 Jam Compressor @ Rp. 145.000,00 = Rp. 580,00
0,0050 Jam Plat Bed Truck @ Rp. 120.000,00 = Rp. 600,00
0,0050 Orang Pekerja @ Rp. 75.000,00 = Rp. 375,00
0,0100 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 12.751,00

Pekerjaan Take Coat / Liter


0,8880 Kg Asphal @ Rp. 11.000,00 = Rp. 9.768,00
0,2540 Ltr Karosene @ Rp. 6.000,00 = Rp. 1.524,00
0,0054 Jam Asphalt Sprayer @ Rp. 240.000,00 = Rp. 1.296,00
0,0083 Jam Compressor @ Rp. 145.000,00 = Rp. 1.203,50
0,0054 Jam Plat Bed Truck @ Rp. 120.000,00 = Rp. 648,00
0,0095 Orang Pekerja @ Rp. 75.000,00 = Rp. 712,50
0,0050 Orang Mandor @ Rp. - = Rp. -
Jumlah = Rp. 15.152,00

Pekerjaan Jalan (BARU) Lapisan Asphalt Hotmix ≤ 8 / M'


0,2200 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.255,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
0,0700 M3 Lapisan Batu 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
0,0500 M3 Lapisan Aspalt Hotmix @ Rp. 1.057.530,00 = Rp. 52.876,50
Jumlah = Rp. 119.527,25

Lebar Perkerasan Jumlah


DMJ 4 2,00 M' = Rp. 239.054,50
DMJ 5 2,00 M' = Rp. 239.054,50
DMJ 5 2,50 M' = Rp. 298.818,13
DMJ 6 2,50 M' = Rp. 298.818,13
DMJ 6 3,00 M' = Rp. 358.581,75
DMJ 7 3,00 M' = Rp. 358.581,75
DMJ 7 3,50 M' = Rp. 418.345,38
DMJ 8 3,00 M' = Rp. 358.581,75
DMJ 8 4,00 M' = Rp. 478.109,00

Pekerjaan Jalan (BARU) Lapisan Asphalt Hotmix ≥ 10 / M'


0,2700 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.767,50
0,2000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 31.729,00
0,0700 M3 Lapisan Batu 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
0,0500 M3 Lapisan Aspalt Hotmix @ Rp. 1.057.530,00 = Rp. 52.876,50
Jumlah = Rp. 127.972,00
Lebar Perkerasan Jumlah
DMJ 10 5,00 M = Rp. 639.860,00
DMJ 10 6,00 M = Rp. 767.832,00

DMJ 12 6,00 M = Rp. 767.832,00


DMJ 12 7,00 M = Rp. 895.804,00
DMJ 14 7,00 M = Rp. 895.804,00
DMJ 14 8,00 M = Rp. 1.023.776,00
DMJ 16 7,00 M = Rp. 895.804,00
DMJ 16 8,00 M = Rp. 1.023.776,00
DMJ 18 8,00 M = Rp. 1.023.776,00
DMJ 18 9,00 M = Rp. 1.151.748,00
DMJ 20 9,00 M = Rp. 1.151.748,00
DMJ 20 10,00 M = Rp. 1.279.720,00

Pekerjaan Jalan (PERBAIKAN) Lapisan Asphalt Hotmix ≤ 8 / M'


- M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. -
- M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. -
0,0700 M3 Lapisan Batu 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
0,0500 M3 Lapisan Aspalt Hotmix @ Rp. 1.057.530,00 = Rp. 52.876,50
Jumlah = Rp. 93.475,50

Lebar Perkerasan Jumlah


DMJ 4 2,00 M' = Rp. 186.951,00
DMJ 5 2,00 M' = Rp. 186.951,00
DMJ 5 2,50 M' = Rp. 233.688,75
DMJ 6 2,50 M' = Rp. 233.688,75
DMJ 6 3,00 M' = Rp. 280.426,50
DMJ 7 3,00 M' = Rp. 280.426,50
DMJ 7 3,50 M' = Rp. 327.164,25
DMJ 8 3,00 M' = Rp. 280.426,50
DMJ 8 4,00 M' = Rp. 373.902,00

Pekerjaan Jalan (PERBAIKAN) Lapisan Asphalt Hotmix ≥ 10 / M'


- M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. -
- M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. -
0,0700 M3 Lapisan Batu 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
0,0500 M3 Lapisan Aspalt Hotmix @ Rp. 1.057.530,00 = Rp. 52.876,50
Jumlah = Rp. 93.475,50

Lebar Perkerasan Jumlah


DMJ 10 5,00 M = Rp. 467.377,50
DMJ 10 6,00 M = Rp. 560.853,00
DMJ 12 6,00 M = Rp. 560.853,00
DMJ 12 7,00 M = Rp. 654.328,50
DMJ 14 7,00 M = Rp. 654.328,50
DMJ 14 8,00 M = Rp. 747.804,00
DMJ 16 7,00 M = Rp. 654.328,50
DMJ 16 8,00 M = Rp. 747.804,00
DMJ 18 8,00 M = Rp. 747.804,00
DMJ 18 9,00 M = Rp. 841.279,50
DMJ 20 9,00 M = Rp. 841.279,50
DMJ 20 10,00 M = Rp. 934.755,00

Pekerjaan Jalan (BARU) Lapisan Asphalt Goreng ≤ 8 / M'


0,2200 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.255,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
0,0700 M3 Batu Pecah 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
1,0000 M2 Lapisan Asphalt Goreng @ Rp. 51.220,00 = Rp. 51.220,00
Jumlah = Rp. 117.870,75

Lebar Perkerasan Jumlah


DMJ 4 2,00 M' = Rp. 235.741,50
DMJ 5 2,00 M' = Rp. 235.741,50
DMJ 5 2,50 M' = Rp. 294.676,88
DMJ 6 2,50 M' = Rp. 294.676,88
DMJ 6 3,00 M' = Rp. 353.612,25
DMJ 7 3,00 M' = Rp. 353.612,25
DMJ 7 3,50 M' = Rp. 412.547,63
DMJ 8 3,00 M' = Rp. 353.612,25
DMJ 8 4,00 M' = Rp. 471.483,00

Pekerjaan Jalan (BARU) Lapisan Asphalt Goreng ≥ 10 / M'


0,2700 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.767,50
0,2000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 31.729,00
0,0700 M3 Batu Pecah 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
1,0000 M2 Lapisan Asphalt Goreng @ Rp. 51.220,00 = Rp. 51.220,00
Jumlah = Rp. 126.315,50

Lebar Perkerasan Jumlah


DMJ 10 5,00 M = Rp. 631.577,50
DMJ 10 6,00 M = Rp. 757.893,00
DMJ 12 6,00 M = Rp. 757.893,00
DMJ 12 7,00 M = Rp. 884.208,50
DMJ 14 7,00 M = Rp. 884.208,50
DMJ 14 8,00 M = Rp. 1.010.524,00
DMJ 16 7,00 M = Rp. 884.208,50
DMJ 16 8,00 M = Rp. 1.010.524,00
DMJ 18 8,00 M = Rp. 1.010.524,00
DMJ 18 9,00 M = Rp. 1.136.839,50
DMJ 20 9,00 M = Rp. 1.136.839,50
DMJ 20 10,00 M = Rp. 1.263.155,00

Pekerjaan Jalan (PERBAIKAN) Lapisan Asphalt Goreng ≤ 8 / M'


- M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. -
- M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. -
0,0700 M3 Batu Pecah 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
1,0000 M2 Lapisan Asphalt Goreng @ Rp. 51.220,00 = Rp. 51.220,00
Jumlah = Rp. 91.819,00

Lebar Perkerasan Jumlah


DMJ 4 2,00 M' = Rp. 235.741,50
DMJ 5 2,00 M' = Rp. 235.741,50
DMJ 5 2,50 M' = Rp. 294.676,88
DMJ 6 2,50 M' = Rp. 294.676,88
DMJ 6 3,00 M' = Rp. 353.612,25
DMJ 7 3,00 M' = Rp. 353.612,25
DMJ 7 3,50 M' = Rp. 412.547,63
DMJ 8 3,00 M' = Rp. 353.612,25
DMJ 8 4,00 M' = Rp. 471.483,00

Pekerjaan Jalan (PERBAIKAN) Lapisan Asphalt Goreng ≥ 10 / M'


- M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. -
- M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. -
0,0700 M3 Batu Pecah 3/5,5/7 @ Rp. 306.750,00 = Rp. 21.472,50
1,5000 Ltr Prime Coat @ Rp. 12.751,00 = Rp. 19.126,50
1,0000 M2 Lapisan Asphalt Goreng @ Rp. 51.220,00 = Rp. 51.220,00
Jumlah = Rp. 91.819,00

Lebar Perkerasan Jumlah


DMJ 10 5,00 M = Rp. 631.577,50
DMJ 10 6,00 M = Rp. 757.893,00
DMJ 12 6,00 M = Rp. 757.893,00
DMJ 12 7,00 M = Rp. 884.208,50
DMJ 14 7,00 M = Rp. 884.208,50
DMJ 14 8,00 M = Rp. 1.010.524,00
DMJ 16 7,00 M = Rp. 884.208,50
DMJ 16 8,00 M = Rp. 1.010.524,00
DMJ 18 8,00 M = Rp. 1.010.524,00
DMJ 18 9,00 M = Rp. 1.136.839,50
DMJ 20 9,00 M = Rp. 1.136.839,50
DMJ 20 10,00 M = Rp. 1.263.155,00
Pekerjaan Pembesian Wire Mash M.6 / M3
35,2219 M3 Besi Wire Mash M.6 @ Rp. 78.862,41 = Rp. 2.777.682,26
0,2000 Kg Kawat Beton @ Rp. 25.000,00 = Rp. 5.000,00
0,0675 Upah Tukang @ Rp. 85.000,00 = Rp. 5.737,50
0,0225 Upah Kepala Tukang @ Rp. 100.000,00 = Rp. 2.250,00
0,0675 Upah Pekerja @ Rp. 75.000,00 = Rp. 5.062,50
0,0007 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 2.795.732,26

Pekerjaan Pembesian Wire Mash M.8 / M3


62,6167 M3 Besi Wire Mash M.6 @ Rp. 58.152,75 = Rp. 3.641.331,36
0,2000 Kg Kawat Beton @ Rp. 25.000,00 = Rp. 5.000,00
0,0675 Upah Tukang @ Rp. 85.000,00 = Rp. 5.737,50
0,0225 Upah Kepala Tukang @ Rp. 100.000,00 = Rp. 2.250,00
0,0675 Upah Pekerja @ Rp. 75.000,00 = Rp. 5.062,50
0,0007 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 3.659.381,36

Pekerjaan Pembesian Wire Mash M.10 / M3


97,8386 M3 Besi Wire Mash M.6 @ Rp. 44.056,92 = Rp. 4.310.464,90
0,2000 Kg Kawat Beton @ Rp. 25.000,00 = Rp. 5.000,00
0,0675 Upah Tukang @ Rp. 85.000,00 = Rp. 5.737,50
0,0225 Upah Kepala Tukang @ Rp. 100.000,00 = Rp. 2.250,00
0,0675 Upah Pekerja @ Rp. 75.000,00 = Rp. 5.062,50
0,0007 Upah Mandor @ Rp. - = Rp. -
Jumlah = Rp. 4.328.514,90

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.6 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp.
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp.
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.6 @ Rp. 2.795.732,26 = Rp. 2.795.732,26
Jumlah = Rp. 4.088.692,26

Tebal Lebar Perkerasan Jumlah


0,1200 DMJ 6 3,00 M' = Rp. 1.471.929,21
0,1200 DMJ 8 4,00 M' = Rp. 1.962.572,28
0,1200 DMJ 10 5,00 M' = Rp. 2.453.215,35
0,1200 DMJ 12 6,00 M' = Rp. 2.943.858,42
0,1200 DMJ 14 7,00 M' = Rp. 3.434.501,50

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.8 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.562,50
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.8 @ Rp. 3.659.381,36 = Rp. 3.659.381,36
Jumlah = Rp. 4.978.700,61

Tebal Lebar Perkerasan Jumlah


0,1500 DMJ 6 3,00 M' = Rp. 2.240.415,28
0,1500 DMJ 8 4,00 M' = Rp. 2.987.220,37
0,1500 DMJ 10 5,00 M' = Rp. 3.734.025,46
0,1500 DMJ ... - M' = Rp. -
0,1500 DMJ ... - M' = Rp. -

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.10 Tebal 15Cm
0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.562,50
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.10 @ Rp. 4.328.514,90 = Rp. 4.328.514,90
Jumlah = Rp. 5.647.834,15

Tebal Lebar Perkerasan Jumlah


0,1500 DMJ 6 3,00 M' = Rp. 2.541.525,37
0,1500 DMJ 8 4,00 M' = Rp. 3.388.700,49
0,1500 DMJ 10 5,00 M' = Rp. 4.235.875,61
0,1500 DMJ ... ... M' = Rp. #VALUE!
0,1500 DMJ ... ... M' = Rp. #VALUE!

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.6 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.6 @ Rp. 2.795.732,26 = Rp. 2.795.732,26
Jumlah = Rp. 4.115.564,01

Tebal Lebar Perkerasan Jumlah


0,2000 DMJ 10 5,00 M' = Rp. 4.115.564,01
0,2000 DMJ 12 6,00 M' = Rp. 4.938.676,81
0,2000 DMJ 14 7,00 M' = Rp. 5.761.789,61
0,2000 DMJ 16 8,00 M' = Rp. 6.584.902,41
0,2000 DMJ 18 12,00 M' = Rp. 9.877.353,62

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.8 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.8 @ Rp. 3.659.381,36 = Rp. 3.659.381,36
Jumlah = Rp. 4.979.213,11

Tebal Lebar Perkerasan Jumlah


0,2000 DMJ 6 3,00 M' = Rp. 2.987.527,87
0,2000 DMJ 8 4,00 M' = Rp. 3.983.370,49
0,2000 DMJ 10 5,00 M' = Rp. 4.979.213,11
0,2000 DMJ ... 8,00 M' = Rp. 7.966.740,98
0,2000 DMJ ... - M' = Rp. -

Pekerjaan Jalan Beton Cor Mixer + Wire Mash M.10 Tebal 20Cm
0,3000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 3.075,00
0,1500 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 23.796,75
1,0000 M2 Plastik Geotextile @ Rp. 13.000,00 = Rp. 13.000,00
1,0000 M3 Beton Mixer K.225 @ Rp. 1.031.600,00 = Rp. 1.031.600,00
1,0000 M3 Begesting Beton 5xPakai @ Rp. 248.360,00 = Rp. 248.360,00
1,0000 M3 Wire Mash M.10 @ Rp. 4.328.514,90 = Rp. 4.328.514,90
Jumlah = Rp. 5.648.346,65

Tebal Lebar Perkerasan Jumlah


0,2000 DMJ 6 3,00 M' = Rp. 3.389.007,99
0,2000 DMJ 8 4,00 M' = Rp. 4.518.677,32
0,2000 DMJ 10 5,00 M' = Rp. 5.648.346,65
0,2000 DMJ ... - M' = Rp. -
0,2000 DMJ ... - M' = Rp. -

Pekerjaan Jalan (BARU) Lapisan Paving Block / M'


0,2500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 2.562,50
0,2000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 31.729,00
0,0500 M3 Lapisan Pasir Extra Beton @ Rp. 140.100,00 = Rp. 7.005,00
1,0000 M2 Lapisan Paving Block @ Rp. 96.450,00 = Rp. 96.450,00
Jumlah = Rp. 137.746,50

Lebar Perkerasan Jumlah


DMJ 6 3,00 M' = Rp. 413.239,50
DMJ 8 4,00 M' = Rp. 550.986,00
DMJ 10 5,00 M' = Rp. 688.732,50
DMJ ... - M' = Rp. -
DMJ ... - M' = Rp. -

Pekerjaan Badan Jalan 6 / M' (tebal 25cm)


0,5250 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 5.381,25
0,6000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 95.187,00
Jumlah = Rp. 100.568,25

Pekerjaan Badan Jalan 8 / M' (tebal 20cm)


0,7000 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 7.175,00
0,8000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 126.916,00
Jumlah = Rp. 134.091,00

Pekerjaan Badan Jalan 10 / M' (tebal 20cm)


0,8750 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 8.968,75
1,0000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 158.645,00
Jumlah = Rp. 167.613,75

Pekerjaan Badan Jalan 12 / M' (tebal 20cm)


1,0500 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 10.762,50
1,2000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 190.374,00
Jumlah = Rp. 201.136,50

Pekerjaan Badan Jalan 14 / M' (tebal 2cm)


1,2250 M3 Galian Tanah Pakai Alat @ Rp. 10.250,00 = Rp. 12.556,25
1,4000 M3 Lapisan Sirtu Pakai Alat @ Rp. 158.645,00 = Rp. 222.103,00
Jumlah = Rp. 234.659,25

Aceh Barat, 21 Juli 2023


PT PUTRA PADANG RAJA

T. NOVA IRWAN
Direktur Utama