Minutes of Construction Quality Meeting #011

Venue: Block-07, New Project office, KPO


Date & Time: 20-03-2014 & 12.30pm

Members Present: (43/54)


As per enclosed List

S.No. Points Discussed Action by Date by

1 Previous MOMs has been displayed and reviewed. Info

Mr. SC displayed and explained a PPT on “Enabling & Infra”.


2 Info
(Copy enclosed)

Mr. ALN present a PPT on general quality violations observed


3 Info
at site for HSM-STR zone. (Copy enclosed)

Mr. RS present a PPT on general quality violations observed at


4 Info
site for HSM-ELE zone.

Mr. RP displayed and discussed about check points/hold points


5 Info
as per QAP/ITP.

Hold points/Check points to be prepared for CVL/STR/PIP


6 SC/CB/RS 22-03-14
indicating the responsibility of CQC team members.

Mr. CHRB suggested that, one common Technical specification


7 PrC 22-03-14
should be available/accessible to all.
Format of record maintained at site to be present in next CQC
8 MK 21-03-14
meeting. (i.e: Surface Preparation & Painting)
Tracking log displayed in CQC meeting in the format as
9 suggested by Mr.CHRB. MK 21-03-14
Details of CVL & ELE to be incorporated in the same.
List of names among the CQC team members mentioning the
10 MK 21-03-14
“Specialization” is to be prepared.
ALN  AL.Narasimham (TSL)