QTDA 200 Câu
QTDA 200 Câu
Select one:
a. The daily rate, because if it is incorrect, the total amount of the invoice will be
wrong, which impacts the cash flow.
b. The charge code, name, address, receipt date, pvc code, discount amount,
mail date, and phone number, because they are fairly easy to confirm and
correct, thereby significantly reducing the types of defects.
c. The account number, because if it is incorrect, the invoice may be sent to the
wrong client.
d. The account number and daily rate, because they account for 80 percent of all
defects.
The correct answer is: The account number and daily rate, because they account
for 80 percent of all defects
237. You are a project manager for Dutch Harbor Consulting. Your latest
project involves the upgrade of an organization’s operating system on 236
servers. You performed this project under contract. You are in the Contract
Closure process and have reviewed the contracting process to identify lessons
learned. What is the name of the tool and technique you used to perform this
function?
Select one:
a. Performance reviews
b. Procurement reviews
c. Performance audits
d. Procurement audits
The correct answer is: Performance reviews
238. Assume that your actual costs are $800; your planned value is $1,200;
and your earned value is $1,000. Based on these data, what can be determined
regarding your schedule variance?
Select one:
a. At +$200, the situation is favorable as physical progress is being accomplished
ahead of your plan.
b. At +$400, the situation is favorable as physical progress is being accomplished
at a lower cost than was forecasted.
c. At –$200, the physical progress is being accomplished at a slower rate than is
planned, indicating an unfavorable situation.
d. At –$200, you have a behind-schedule condition, and your critical path has
slipped.
The correct answer is: At –$200, the physical progress is being accomplished at
a slower rate than is planned, indicating an unfavorable situation.
239. Projects are supposed to succeed, not fail. However, termination is an
option to consider when all but which one of the following conditions exist?
Select one:
a. The original purposes for the project have changed.
b. The customer’s strategy has changed.
c. Competition may make the project results obsolete.
d. There are new stakeholders.
The correct answer is: There are new stakeholders.
240. When you are about to terminate a contract, the one place to look for
specific procedures for contract closure is in the—
Select one:
a. Organizational process assets
b. Statement of work in the contract
c. Product description
d. Terms and conditions in the contract
The correct answer is: Terms and conditions in the contract
241. The transition from one phase to another within a project's life cycle (e.g.
design to manufacturing) is typically marked by:
Select one:
a. Constraint
b. Monte Carlo
c. Decision tree
d. Kill point
The correct answer is: Kill point
242. The primary result of effective team development is—
Select one:
a. Enhancement of the ability of stakeholders to contribute as individuals and
team members
b. An understanding by project team members that the project manager is
ultimately responsible for project performance
c. An effective, smoothly running team
d. Improved project performance
The correct answer is: Improved project performance
243. Based on a recent quality audit of your project, your organization’s quality
assurance department is supportive of your approach as it notes the following
characteristics of quality that are being followed consistency. They include all of
the follow EXCEPT—
Select one:
a. Customer satisfaction
b. Management responsibility
c. High-performing team
d. Cost of quality
The correct answer is: High-performing team
244. You are managing a project in which your team members all work in the
same geographic location and have worked together previously on many
projects. Everyone is aware of the various strengths and weaknesses of the
individual team members and their key areas of expertise. As a result—
Select one:
a. A kickoff meeting is recommended
b. You should expect minimal conflicts and changes to occur
c. Rewards and recognition will be handled smoothly throughout the project
d. Team-building activities will not be needed on your project
The correct answer is: A kickoff meeting is recommended
245. You are working on a new project in your city to construct an
environmentally friendly landfill. The existing site is so undesirable that many
residents have moved to other neighboring cities because of their proximity to it.
However, even though the project has the support of the public, you need to
have a number of hearings of the city’s government before you are authorized to
begin work. As you are in the planning phase of the project, you are waiting for
these hearings to be scheduled and held before you can begin site preparation.
These hearings are an example of—
Select one:
a. An external dependency
b. A mandatory dependency
c. A milestone
d. An item to be scheduled as a fragnet
The correct answer is: An external dependency
246. You want to structure your project so that each project team member has
a discrete work package to perform. The work package is a—
Select one:
a. Deliverable at the lowest level of the WBS
b. Required level of reporting
c. Task with a unique identifier
d. Task that can be assigned to more than one organizational unit
The correct answer is: Deliverable at the lowest level of the WBS
247. You are a project manager responsible for the construction of a new office
complex. You are taking over for a project manager who recently left the
company. The prior project manager completed the scope statement and scope
management plan for this project. In your interviews with some key team
members, you conclude which of the following?
Select one:
a. They understand that the scope statement describes how the high-level
deliverables and requirements will be defined and verified.
b. They understand that the scope management plan describes how project
scope will be defined and verified and used to control project scope.
c. They understand that the scope statement assesses the stability of the project
scope and outlines how scope will be verified and used to control changes.
d. They understand that the scope management plan is deliverables oriented and
includes cost estimates and stakeholder needs and expectations.
The correct answer is: They understand that the scope management plan
describes how project scope will be defined and verified and used to control
project scope.
248. Within your company’s portfolio, your project is ranked in the top five in
terms of importance of the 60 projects under way; however, the number of
resources available to you is still limited. You have decided to pilot test the use of
critical chain on your project. You have calculated your critical path. You want to
ensure that your target finish date does not slip in the critical chain method. To
do so you should—
Select one:
a. Put in three feeding buffers
b. Manage the total float of the network paths
c. Add a project buffer
d. Determine the drum resource
The correct answer is: Add a project buffer
249. Most statistical simulations of budgets, schedules, and resource
allocations use which one of the following approaches?
Select one:
a. Decision-tree analysis
b. Present value analysis
c. PERT
d. Monte Carlo analysis
The correct answer is: Monte Carlo analysis
250. You are the project manager for Rivera Gourmet Adventure Vacations.
Rivera combines the wonderful tastes of great gourmet food with outdoor
adventure activities. Your project involves installing a new human resources
software system. Jason, the database analyst working on this project, is
overallocated. Which of the following statements is true?
Select one:
a. You should use fast tracking to resource level the critical path tasks.
b. You should use resource leveling to smooth out resource assignments.
c. You should use resource requirements updates to determine availability and
smooth out resource overallocation.
d. You should use crashing to resource level the critical path tasks.
The correct answer is: You should use crashing to resource level the critical path
tasks.
251. When sequencing project activities in the schedule, all the following are
true EXCEPT —
Select one:
a. Every activity is connected to at least one predecessor and at least one
successor
b. There may be scheduled dates for specific milestones
c. Necessary sequencing of events may be described by the activity attributes
d. Lead or lag time may be required
The correct answer is: Every activity is connected to at least one predecessor
and at least one successor
252. Of the following tools and techniques, which one is NOT used for schedule
control?
Select one:
a. Adjusting leads and lags
b. Fast tracking
c. Three-point estimates
d. What-if scenario analysis
The correct answer is: Three-point estimates
253. All the following are project baselines that are generally part of the project
management plan EXCEPT—
Select one:
a. Cost
b. Scope
c. Time
d. Technical
The correct answer is: Technical
254. Work performance information in control risks means that—
Select one:
a. Templates to the risk management plan and the risk register are
recommended
b. Outcomes of risk reassessments and risk audits are documented
c. Recommended preventive or corrective action is considered through change
requests
d. A mechanism to communicate and support project decision making is provided
The correct answer is: A mechanism to communicate and support project
decision making is provided
255. Your project is using complex, unproven technology. Your team conducted
a brainstorming session to identify risks. Poor allocation of project resources was
the number one risk. This risk was placed on the risk register, which included at
this point a—
Select one:
a. Watch list
b. Known unknown
c. Potential risk response
d. List of other risks requiring additional analysis
The correct answer is: Potential risk response
256. Assigning more talented resources to the project to reduce time to
completion or to provide better quality than originally planned are examples of
which one of the following strategies?
Select one:
a. Exploit
b. Contingent response
c. Share
d. Enhance
The correct answer is: Exploit
257. During the Plan Risk Management process, assigning ___________ will
help you and the project team identify all important risks and work more
effectively during the identification process.
Select one:
a. risk categories
b. risk factors
c. risk mitigation plans
d. blame
The correct answer is: risk categories
258. You are the project manager for Design Your Web Site, Inc. Your
company is designing the website for a national grocery store chain. You have
your activity list in hand and are ready to diagram the activity dependencies using
the PDM technique. Which of the following statements is true?
Select one:
a. PDM is also the AON diagramming method.
b. PDM is also the ADM diagramming method.
c. PDM is also the AND diagramming method.
d. PDM is also the AOA diagramming method.
The correct answer is: PDM is also the AOA diagramming method
259. You have been hired as a contract project manager for Grapevine
Vineyards. Grapevine wants you to design an Internet wine club for its
customers. Customers must register before being allowed to order wine over the
Internet so that legal age can be established. You know that the module to verify
registration must be written and tested using data from Grapevine’s existing
database. This new module cannot be tested until the data from the existing
system is loaded. You are going to hire a vendor to perform the programming
and testing tasks for this module to help speed up the project schedule. Since
they’ll have access to your customer list and potentially other trade secrets, you’ll
asked them to sign a nondisclosure agreement. This is an example of which of
the following?
Select one:
a. Standard form
b. Procurement documents
c. Fixed cost contract
d. Organizational process asset
The correct answer is: Organizational process asset
260. You are the project manager for the Heart of Texas casual clothing
company. It’s introducing a new line of clothing called Black Sheep Ranch Wear.
You will outsource the production of this clothing line to a vendor. Your legal
department has recommended you use a contract that reimburses the seller’s
allowable costs and builds in a bonus based on performance criteria they’ve
outlined in their memo. Which of the following contract types will you use?
Select one:
a. CPF
b. CPFF
c. CPIF
d. CPPC
The correct answer is: CPFF
261. You are the project manager in your organization. You have very little
authority over the projects you manage, and you are mainly engaged in project
coordination activities. You are currently struggling with obtaining the required
human resources for your project during the Acquire Project Team process. Who
you need to negotiate with to obtain these resources?
Select one:
a. The project sponsor
b. The customer
c. The functional managers
d. Your line manager
The correct answer is: The functional managers
262. You are preparing project performance appraisals and have decided you’d
like each team member to get feedback regarding their performance from several
sources, including peers, superiors, and subordinates. Which of the following is
true?
Select one:
a. This is called 360-degree feedback and is considered part of the work
performance information input of the Manage Project Team process.
b. This is called 360-degree feedback and is part of the input to the
organizational project performance appraisals, which is part of the organizational
process assets updates input of the Manage Project Team process.
c. This is called 360-degree feedback and is part of the project performance
appraisals tool and technique of the Manage Project Team process.
d. This is called 360-degree feedback and is considered part of the team
performance assessment input of the Manage Project Team process.
The correct answer is: This is called 360-degree feedback and is considered part
of the team performance assessment input of the Manage Project Team process.
263. As a project manager, you know that the most important activity to ensure
customer and stakeholder satisfaction is which of the following?
Select one:
a. Documenting and meeting the performance measurements
b. Reporting project status regularly and in a timely manner
c. Reporting changes and updating the project plan and other project documents
where appropriate
d. Documenting and meeting the requirements
The correct answer is: Documenting and meeting the performance
measurements
264. The purpose of work performance data in control communications is to
present results
of comparative analysis to the—
Select one:
a. Stakeholder management plan
b. Communications management plan
c. Performance measurement baseline
d. Deliverable status
The correct answer is: Performance measurement baseline
265. According to Herzberg’s Motivator-Hygiene Theory, when achievement,
recognition, responsibility, and advancement, or promotion, are not present,
employees will—
Select one:
a. Become dissatisfied only if they do not receive salary increases
b. Lack motivation but will not be dissatisfied with their work
c. Lack motivation and become dissatisfied with their work
d. Become alienated with the organization and leave
The correct answer is: Lack motivation and become dissatisfied with their work
266. You are a project manager for Bluebird Technologies. Bluebird writes
custom billing applications for several industries. One of your users verbally
requests changes to one of the screen displays. You explain to her that the
change needs to go through the change control system, which is a subset of the
configuration management system. You explain that a change control system
does all of the following except for which one?
Select one:
a. Documents procedures for change requests
b. Determines whether changes are approved or denied
c. Tracks the status of change requests
d. Describes the management impacts of change
The correct answer is: Tracks the status of change requests
267. Configuration management describes procedures for applying technical
and administrative direction and surveillance. Which one of the following tasks is
NOT performed in configuration management?
Select one:
a. Identifying functional and physical characteristics of an item or system
b. Performing an audit to verify conformance to requirements
c. Controlling changes to characteristics
d. Allowing automatic approval of changes
The correct answer is: Allowing automatic approval of changes
268. You do not expect the types of variances that have occurred on the project
to date to continue. If BAC = 800, ETC = 275, PV = 300, ACC = 200, EV = 250,
and CPIC = 1.25, what is the EAC?
Select one:
a. 640
b. 550
c. 600
d. 750
The correct answer is: 750
269. All of the following are outputs of the Integrated Change Control process
except for which one?
Select one:
a. Requested changes
b. Project scope statement updates
c. Validated defect repair
d. Approved corrective actions
The correct answer is: Requested changes
270. The estimate costs process uses all the following tools and techniques
EXCEPT—
Select one:
a. Basis of estimates
b. Reserve analysis (contingency reserves)
c. Three-point estimating
d. Cost of quality assumptions
The correct answer is: Basis of estimates
271. As project manager, you identified a number of acceptable tolerances as
part of your earned value management system. During execution, some
“unacceptable” variances occurred. After each “unacceptable” variance occurred,
you did which one of the following first?
Select one:
a. Adjusted the project plan
b. Prepared a revised cost estimate
c. Documented lessons learned
d. Updated the budget
The correct answer is: Documented lessons learned
272. If you want to calculate the ETC based on your expectations that similar
variances to those noted to date will not occur, you should use which of the
following formulas?
Select one:
a. ETC
b. AC + EAC
c. (BAC – EV)/CPI
d. ETC
e. ETC
f. ETC
g. AC + BAC – EV
h. BAC – EV
The correct answers are: ETC, BAC – EV, (BAC – EV)/CPI, AC + EAC, AC +
BAC – EV
273. Project execution must be compared, and deviations must be measured
for management control according to the—
Select one:
a. Performance measurement baseline
b. Schedule baseline
c. Control system
d. Scope baseline
The correct answer is: Performance measurement baseline
274. You are a project manager for Waterways Houseboats, Inc. You’ve been
asked to perform a cost-benefit analysis for two proposed projects. Project A
costs $2.4 million, with potential benefits of $12 million and future operating costs
of $3 million. Project B costs $2.8 million, with potential benefits of $14 million
and future operating costs of $2 million. Which project should you recommend?
Select one:
a. Project A, because the cost to implement is cheaper than Project B.
b. Project B, because the potential benefits minus the costs to implement are
greater in value than the same calculation for Project A.
c. Project B, because the potential benefits minus the implementation and future
operating costs are greater in value than the same calculation for Project A.
d. Project A, because the potential benefits plus the future operating costs are
less in value than the same calculation for Project B.
The correct answer is: Project B, because the potential benefits minus the
implementation and future operating costs are greater in value than the same
calculation for Project A.
275. Project deliverables are the outputs that include the product, service, or
result of the project as well as ancillaryresults. These ancillary results should be
in the—
Select one:
a. Requirements management plan
b. Scope management plan
c. Project scope statement
d. Project acceptance criteria
The correct answer is: Project scope statement
276. Which of the following are tools and techniques of the Preliminary Scope
Statement process?
Select one:
a. Project selection methods and expert judgment
b. Project management methodology, project management information system,
and expert judgment
c. Project charter, project management information system, and project selection
methods
d. Constraints, assumptions, and expert judgment
The correct answer is: Project management methodology, project management
information system, and expert judgment
277. Assume you are beginning your project to develop a series of residential
condominiums in your city and are identifying possible stakeholders. A key
organizational process asset you can review is—
Select one:
a. Lessons learned
b. Organizational culture
c. Organizational standards
d. Local trends
The correct answer is: Lessons learned
278. The amount of authority a project manager possesses can be related to
Select one:
a. the organizational structure
b. the amount of authority the manager of the project manager possesses
c. the key stakeholder’s influence on the project
d. the project manager’s communication skills
The correct answer is: the organizational structure
279. Name the ethical code you’ll be required to adhere to as a PMP.
Select one:
a. Project Management Policy and Ethics Guide
b. Project Management Professional Code of Professional Conduct
c. Project Management Code of Professional Ethics
d. Project Management Professional Standards and Ethics
The correct answer is: Project Management Professional Code of Professional
Conduct
280. You are managing a project to introduce a new product to the marketplace
that is expected to have a very long life. In this situation, the concept of being
temporary, which is part of the definition of a project,—
Select one:
a. Recognizes that the project team will outlive the actual project
b. Does not apply because the project will not be short in duration
c. Does not apply because the project will have a lasting result
d. Does not apply to the product to be created
The correct answer is: Does not apply to the product to be created
281. You are in the process of performing quality assurance on your product
and find that some requirements are not as complete as they should be, which
causes rework and adds costs to your overall project. The term for all costs
incurred over the life of the product by investing in appraising and inspecting the
product for conformance and nonconformance to requirements is called—
Select one:
a. Expected value
b. Cost of conformance
c. Cost of quality
d. Life-cycle costs
The correct answer is: Cost of quality
282. Results of quality control measurements are used—
Select one:
a. As an input to plan quality management
b. To prepare a control chart
c. As an input to perform quality assurance
d. To prepare an operational definition
The correct answer is: As an input to perform quality assurance
283. All of the following are objectives of a quality audit—
Select one:
a. Improvement opportunities are identified
b. Root cause analysis has been performed as part of process analysis
c. Defect repairs have been implemented
d. Good practices can be introduced elsewhere
The correct answer is: Root cause analysis has been performed as part of
process analysis
284. Quality assurance promotes quality improvement. A “breakthrough” is the
accomplishment of any improvement that takes the organization to
unprecedented levels of performance by attacking—
Select one:
a. Special causes of variation
b. Specific tolerances
c. Common causes of variation
d. Inspection over prevention
The correct answer is: Common causes of variation
285. Payment bonds are often required by the contract and require specific
actions under the stated conditions. Payment bonds are specifically designed to
ensure that the prime contractor provides payment of—
Select one:
a. Damages for accidents caused
b. Weekly payrolls
c. Subcontractors, laborers, and sellers of material
d. Insurance premiums
The correct answer is: Subcontractors, laborers, and sellers of material
286. Oftentimes when a project is terminated, senior managers will replace the
project manager with an individual who is skilled in closing out projects. If this is
done, the first step for the termination manager should be to—
Select one:
a. Complete the lessons learned report
b. Notify all relevant stakeholders of the termination
c. Review the status of all contracts
d. Conduct an immediate review of the work packages
The correct answer is: Conduct an immediate review of the work packages
287. The CPI on your project is 0.84. This means that you should—
Select one:
a. Reassess the life-cycle costs of your product, including the length of the
lifecycle phase
b. Place emphasis on improving the timeliness of the physical progress
c. Place emphasis on improving the productivity by which work was being
performed
d. Recognize that your original estimates were fundamentally flawed, and your
project is in an atypical situation
The correct answer is: Place emphasis on improving the productivity by which
work was being performed
288. You are a project manager for Dutch Harbor Consulting. Your latest
project involves the upgrade of an organization’s operating system on 236
servers. You performed this project under contract. You are in the Closing
process and know that product verification is for what purpose?
Select one:
a. To verify that all the work was completed correctly and satisfactorily
b. To evaluate all the work of the project and compare the results to project
scope
c. To evaluate project goals and ensure that the product of the project meets the
requirements
d. To verify the goals of the project and ensure that the product of the project is
complete
The correct answer is: To evaluate all the work of the project and compare the
results to project scope
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 What are the five project management process groups, in order?
Not answered
Select one:
Marked out of 1.00
a. Initiating, Planning, Monitoring and Controlling, Executing, and Closing
The correct answer is: Initiating, Planning, Executing, Monitoring and Controlling, and
Closing
Question 2 In organizing a project, a project manager must deal with conflict. Which statement is
Not answered TRUE regarding conflict in projects?
b. A matrix form of organization can produce a lack of clear role definitions and
lead to ambiguous jurisdictions between and among functional leaders and project
managers
c. Strong matrix project managers have few human resource conflicts, because
they can dictate their needs to functional managers
The correct answer is: A matrix form of organization can produce a lack of clear role
definitions and lead to ambiguous jurisdictions between and among functional leaders
and project managers
Question 3 Which of the following theorists stated that people generally are motivated according
Not answered to the strength of their desire either to achieve high levels of performance or to
b. Victor Vroom
c. B. F. Skinner
Hide sidebars
d. David McClelland
Question 4 Assume you have identified your stakeholders and are preparing your stakeholder
Not answered management plan. You are fortunate that your team is a collocated team as you are
working on an internal project to reorganize your IT Department so it is focused more
Marked out of 1.00
on its customers. The project sponsor is the Chief Operating Officer, and the IT
Department Director was surprised as she thought all was well. However, you notice
when planning meetings are held, the Chief Financial Officer never attends. You feel
since IT affects the entire company, all the senior leaders need some type of
involvement. You therefore feel the Chief Financial Officer may be—
Select one:
a. Unaware
b. Resistant
c. Satisfied
d. Uninterested
Question 5 The stakeholder register should not be prepared only one time, but it should be
Not answered updated regularly especially if—
The correct answer is: The stakeholder is not impacted by the project
Question 6 The risk register may need to be updated as an output of which following process:
Not answered
c. Sequence activities
Question 7 Your team is split between two buildings on either side of town. As a result, the team
Not answered isn’t very cohesive because the members don’t know each other very well. The team
is still in the storming stage because of the separation issues. Which of the following
Marked out of 1.00
should you consider?
Select one:
a. Training
b. Co-location
c. Conflict resolution
d. Corrective action
Question 8 Assume that you are working on a new product for your firm. Your CEO learned that a
Not answered competitor was about to launch a new product that has similar features to those of
your project. The competitor plans to launch the product on September 1. It is now
Marked out of 1.00
March 1. Your schedule called for you to launch your product on December 1. Your
CEO now has now mandated that you fast track your project so you can launch your
product on August 1. This fast track schedule is an example of an—
Select one:
a. A risk taken to achieve a reward
b. Unknown risk
d. WBS
Question 10 Project managers should pay attention to critical and subcritical activities when
Not answered evaluating project time performance. One way to do this is to analyze 10
subcriticalpaths in order of ascending float. This approach is part of—
Marked out of 1.00
Select one:
a. Earned value management
b. Simulation
c. Trend analysis
d. Variance analysis
Question 11 If you know expected value is 500 and the standard deviation is 12, you can say with
Not answered approximately a 95 percent confidence rating which of the following?
The correct answer is: The activity will take from 464 to 536 days.
Question 12 Use the following graphic to answer this question. If the duration of activity B was
Not answered changed to 10 days and the duration of activity G was changed to 9 days, which path
Select one:
a. A-B-C-E-H
b. A-D-E-H
c. A-F-G-E-H
d. A-F-G-H
b. Start to Start
c. Finish to Finish
d. Finish to Start
Question 14 On a typical project, when are risks highest and impacts (amount at stake) lowest?
Not answered
Select one:
Marked out of 1.00
a. When the project manager is replaced
Select one:
a. Project management processes selected for the project
The correct answer is: Project management processes selected for the project
Question 16 Accurate and unbiased data are essential for perform qualitative risk analysis. Which
Not answered one of the following should you use to examine the extent of understanding of project
risk?
Marked out of 1.00
Select one:
a. Influence diagrams
c. Sensitivity analysis
Select one:
a. Budget
b. Order-of-magnitude
Hide sidebars
c. Detailed
d. Definitive
Question 19 You are the project manager for a scheduled version release of your company’s
Not answered software tracking product. You have identified resources according to their activities.
You might want to display this information in which of the following?
Marked out of 1.00
Select one:
a. PDM
b. AOA
c. AON
d. RAM
Question 20 You are the project manager for BB Tops, a nationwide toy store chain. Your new
Not answered project involves a creating a prototype display at several stores across the country.
You are using a RACI chart to display individuals and activities. What does RACI
Marked out of 1.00
stand for?
Select one:
a. Responsible, assignment, control, inform
b. Have a meeting
Question 22 The workaround that you used to deal with a risk that occurred should be documented
Not answered and included in which following processes?
d. Direct and manage project work and perform integrated change control
The correct answer is: Monitor and control project work and control risks
Question 23 As a result of a face-to-face meeting you recently had to discuss the items in your
Not answered issues log, you have resolved issues and come away with an approved corrective
action and an update to the project management plan. Which process does this
Marked out of 1.00
describe?
Select one:
a. Manage Project Team
b. Information Distribution
c. Performance Reporting
d. Manage Stakeholders
Select one:
a. Inform the potential partners that you suspect there might be a forbidden
ingredient in the sauce, and you’ll request an investigation to determine whether it
Hide sidebars
b. Don’t tell the potential partners about the ingredient because the sauce they’ll
be using in the stores is shipped to them already prepared in cans. They won’t
know the ingredient is in the sauce.
c. Inform the potential partners that a forbidden ingredient exists in the sauce and
work with them to come up with another ingredient to replace that one.
d. Inform the potential partners that your sauce recipe is secret, but you’re certain
there are no forbidden ingredients in it.
The correct answer is: Inform the potential partners that you suspect there might be a
forbidden ingredient in the sauce, and you’ll request an investigation to determine
whether it exists in the sauce.
Question 25 All of the following are tools and techniques of the Contract Administration process
Not answered except for which one?
The correct answer is: Performance reporting, payment system, and claims
administration
Question 26 Which of the following statements best describes attribute sampling versus variables
Not answered sampling?
The correct answer is: Attribute sampling is concerned with conformance, whereas
variables sampling is concerned with the degree of conformity.
Question 27 Change is inevitable on projects. Uncontrolled changes are often referred to as—
Not answered
Select one:
Marked out of 1.00
a. Rework
b. Scope creep
c. Emergency changes
d. Configuration items
Hide sidebars
The correct answer is: Managing the approved cost baseline and any changes to it
Question 30 If you are influencing factors that create changes to the cost of the project, which
Not answered process are you using?
b. Determine Budget
c. Control Costs
d. Estimate Costs
Select one:
Marked out of 1.00
a. Performance data
The correct answer is: Value delivered by vendors meeting the needs
Question 32 Your project scheduler has just started working with your project and has produced
Not answered defective reports for the past two accounting cycles. If this continues, these defective
reports could provide the potential for customer dissatisfaction and lost productivity
Marked out of 1.00
that is due to rework. You discovered that the project scheduler needs additional
training on using the scheduling tool that is used on your project. The cost of training
falls under which one of the following categories?
Select one:
a. Indirect costs
b. Overhead costs
c. Failure costs
d. Prevention costs
Question 33 Assume that your company is working under a fixed-price-incentive contract. It has a
Not answered target cost of $100,000, a target profit of 10%, a price ceiling of $120,000, and a
share formula of 80/20. Assume that your company completes all of the work but has
Marked out of 1.00
actual costs of $110,000. What is the final value of this procurement?
Select one:
a. $110,000
b. $132,000
c. $118,000
d. $120,000
The correct answer is: Business need, strategic plan, product scope description
Question 35 The project scope baseline should be used in the identify risks process because it—
Not answered
Select one:
Marked out of 1.00
a. Contains information on risks from prior projects
d. Identifies all work that must be done; therefore, it includes all risks on the
project
Question 36 You are a project manager for Zippy Tees. Your selection committee has just chosen a
Not answered project you recommended for implementation. Your project is to manufacture a line of
miniature stuffed bears that will be attached to your company’s trendy T-shirts. The
Marked out of 1.00
bears will be wearing the same T-shirt design as the shirt to which they’re attached.
Your project sponsor thinks you’ve really impressed the big boss and wants you to
skip to the manufacturing process right away. What is your response?
Select one:
a. Require a project charter be written and signed off on by all stakeholders
before proceeding.
c. Suggest that a preliminary scope statement be written because this will outline
the objectives of the project and greatly assist in the development of the scope
statement in the Planning processes.
d. Agree with the project sponsor because that person is your boss and has a lot
of authority and power in the company.
The correct answer is: Require a project charter be written and signed off on by all
stakeholders before proceeding.
Question 37 You are the project manager in charge of developing a new shipping container for
Not answered Globus Ocean Transport, which needs to withstand winds of 90 knots and swells of
Select one:
a. Bill of materials
c. Project charter
d. WBS
b. Procurement
c. Risk
d. Resource
Question 39 You are the project manager for Fun Days Vacation Resorts. Your new project
Not answered assignment is to head up the Fun Days resort opening in Austin, Texas. You are
estimating the duration of the project plan activities, devising the project schedule,
Marked out of 1.00
and monitoring and controlling deviations from the schedule. Which of the Project
Management Knowledge Areas are you working in?
Select one:
a. Project Scope Management
Select one:
a. Inform your customer that there is no problem with the additive except for an
extremely small percentage of the population and release the product to them.
Hide sidebars
b. Tell the customer you’ll correct the reaction problems in the next batch, but
you’ll release the first batch of product to them now to begin using.
c. Do nothing because the reactions are so minor that very few people will be
affected.
d. Inform the customer that you’ve discovered this condition and tell them you’ll
research it further to determine its impacts.
The correct answer is: Inform the customer that you’ve discovered this condition and
tell them you’ll research it further to determine its impacts.
Question 41 The project team should have a working knowledge of statistical process control to
Not answered help evaluate control quality outputs. Of all the topics involved, which of the following
is the most important for the team to understand?
Marked out of 1.00
Select one:
a. Tolerances and control limits
b. Tell the friend you will do what you can, but don't actually act on this.
Hide sidebars
c. Don't mention your relationship to anyone involved with the project, but push
for the friend's company during the selection process.
d. This is simply networking. Let the project stakeholders know you have a social
connection to the vendor and recommend they get the business.
The correct answer is: Notify the project stakeholders that you have social ties with
one of the vendors, and excuse yourself from the selection committee.
b. Ensure that goods purchased fit the purposes for which they are to be used
The correct answer is: Provide assurance of the level of quality to be provided
Question 45 All of the following statements are true of the project Closing processes except for
Not answered which one?
The correct answer is: Risk is greatest in the project Closing processes.
Question 46 Contract documentation is an input to both the Close Project and Contract Closure
Not answered processes. Contract documentation might include all of the following except for which
b. Supporting documents
c. Contract changes
Hide sidebars
d. Financial documents
Question 47 Your project was just completed. Because of some unfortunate circumstances, the
Not answered project was delayed, causing cost overruns at the end of the project. Which of the
following statements is true?
Marked out of 1.00
Select one:
d. You should pay particular attention to archiving the financial records for this
project.
The correct answer is: You should pay particular attention to archiving the financial
records for this project.
Question 48 Your project was just completed, accepted, and closed. As is customary for your
Not answered organization, you conduct a post-implementation audit. The purpose of this audit
includes all of the following except for which one?
Marked out of 1.00
Select one:
a. Reviewing successes and failures
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
c. Commercial databases
d. Historical information
Question 2 Having worked previously as a software project manager, you were pleased to be
Not answered appointed as the project manager for a new systems integration project designed to
replace the existing air traffic control system in your country. You found a
Marked out of 1.00
requirements traceability matrix to be helpful on software projects, so you decided to
use it on this systems integration project. Using such a matrix helps to ensure that
each requirement—
Select one:
a. Shows the impact to other organizational areas and to entities outside of the
performing organization
b. Sets forth the level of service, performance, safety, security, and compliance
The correct answer is: Adds business value as it links to business and project
objectives
Question 3 A number of organizational process assets are useful as inputs to the manage
Not answered stakeholder engagement process. Similarly a number of organizational process
Select one:
a. Project records
b. Project reports
Hide sidebars
c. Historical information
d. Stakeholder notifications
Question 4 As project manager, you plan to conduct a “kickoff” meeting at which you will discuss
Not answered all the following EXCEPT—
The correct answer is: Discussing specific legal issues regarding the contract
b. 90
c. 50
d. 75
The correct answer is: Decomposition requires a degree of expert judgment and also
requires close analysis of the project scope statement.
Question 7 You’ve just completed the WBS. Which of the following statements is true?
Not answered
Select one:
Marked out of 1.00
a. The WBS breaks the project deliverables down to a level where project
constraints and assumptions can be easily identified.
b. The WBS breaks the project deliverables down to a level where alternatives
identification can be used to determine how level-two assignments should be
made.
c. The WBS breaks the project deliverables down to the work package level,
where product analysis can be documented.
d. The WBS breaks the project deliverables down to the work package level,
where cost and time estimates can be easily determined.
The correct answer is: The WBS breaks the project deliverables down to the work
package level, where cost and time estimates can be easily determined.
Select one:
a. Corrective action is not necessary in this case because the future project
outcomes aren’t affected.
c. Corrective action is taken here to make sure the future project outcomes are
aligned with the project management plan.
The correct answer is: Corrective action is taken here to make sure the future project
outcomes are aligned with the project management plan.
Question 10 If the imposed finish time is reset to 16 and the duration of Activity H is changed to 3,
Not answered what is the late finish for Activity G?
Select one:
a. 11
b. –13
c. 13
d. –11
Select one:
a. 22
b. 2
Hide sidebars
c. 20
d. 4
Question 12 You are remodeling your kitchen and decide to prepare a network diagram for this
Not answered project. Your appliances must be purchased and available for installation by the time
the cabinets are completed. In this example, these relationshipsare—
Marked out of 1.00
Select one:
a. Start-to-start
b. Finish-to-finish
c. Finish-to-start
d. Start-to-finish
b. Start to Start
c. Start to Finish
d. Finish to Finish
Select one:
a. Residual risk
b. Trigger risk
Hide sidebars
c. Secondary risk
d. Mitigated risk
Question 15 The simplest form of quantitative risk analysis and modelingtechniques is—
Not answered
Select one:
Marked out of 1.00
a. Utility theory
b. Delphi technique
c. Probability analysis
d. Sensitivity analysis
Question 16 A risk response strategy that can be used for both threats and opportunities is—
Not answered
Select one:
Marked out of 1.00
a. Share
b. Avoid
c. Transfer
d. Accept
Select one:
a. Mitigation
Hide sidebars
b. Active acceptance
c. Passive acceptance
d. Transference
Question 18 Sally is a project manager working on a project that will require a specially engineered
Not answered machine. Only three manufacturers can make the machine to the specifications Sally
needs. The price of this machine is particularly critical to this project. The budget is
Marked out of 1.00
limited, and there’s no chance of securing additional funds if the bids for the machine
come in higher than budgeted. She’s developing the evaluation criteria for the bidders’
responses and knows all of the following are true except for which one?
Select one:
a. Sally will base the evaluation criteria on price alone since the budget is a
constraint.
b. Sally will use standard contract forms provided by her procurement department
to write the contract for this machine.
c. Sally will update the contract statement of work with any new information.
d. Sally will review the project management plan, including the risk register, as
inputs to this process.
The correct answer is: Sally will review the project management plan, including the
risk register, as inputs to this process.
Question 19 What is the primary risk with including reserves or contingency allowances in your
Not answered cost estimate?
Select one:
a. CPPC
Hide sidebars
b. CPF
c. CPIF
d. Cost-reimbursable contract
Question 21 If you are working on a project with constantly changing scope, which contract type
Not answered would work best when hiring an outside vendor to complete a portion of the work?
b. Cost reimbursable
d. Lump sum
b. Forecasts
b. One party agrees to accept the offer of the other party but secretly knows they
will bring the issue back up at a later time.
Hide sidebars
c. One party claims to accept the offer of the other party, provided a contract
change request is submitted describing the offer in detail.
d. One party claims the issue under discussion was documented and accepted as
part of Scope Verification.
The correct answer is: One party claims the issue under discussion was documented
and accepted as part of Scope Verification.
Question 24 Your upcoming project includes project team members from a foreign country. To
Not answered make certain that cultural differences don’t interfere with team performance, thereby
affecting the success of the project, your first course of action is to do which of the
Marked out of 1.00
following?
Select one:
a. Perform team-building exercises.
Question 25 You have been asked to submit a proposal for a project that has been put out for bid.
Not answered Prior to submitting the proposal, your company must register so that its firm is on the
qualified seller list. Which of the following statements is true?
Marked out of 1.00
Select one:
a. The qualified seller list provides information about the project and the company
that wrote the RFP and is an output of the Select Sellers process.
b. The qualified seller list provides information about the sellers and is a tool and
technique of the Request Seller Responses process.
c. The qualified seller list provides information about the project and the company
that wrote the RFP and is a tool and technique of the Select Sellers process.
d. The qualified seller list provides information about the sellers and is an output
to the Request Seller Responses.
The correct answer is: The qualified seller list provides information about the project
and the company that wrote the RFP and is an output of the Select Sellers process.
Question 26 The direct and manage project work process truly is important in project
Not answered management. It affects many other key processes and uses inputs from others.
The correct answer is: Provide overall management of the project work
Question 27 The Project Charter formally authorizes a project. Who authorizes the project charter?
Not answered
Select one:
Marked out of 1.00
a. The project manager
The correct answer is: A project sponsor or initiator external to the project
Question 28 Your project progressed as planned up until yesterday. Suddenly, an unexpected risk
Not answered event occurred. You quickly devised a response to deal with this negative risk event
using which of the following outputs of Risk Monitoring and Control?
Marked out of 1.00
Select one:
a. Risk management plan updates
c. Workarounds
d. Corrective action
Select one:
a. A defined integrated change control process
Select one:
a. Multi-disciplinary review teams
c. Analytical techniques
d. Independent estimates
Question 31 You are working on a construction project in a city different from your headquarters’
Not answered location. You and your team have not worked in this city, City B, previously, and you
lack knowledge of the local building codes. You had a team member review the
Marked out of 1.00
codes, and he said they were in far greater detail than those in your city, City A. When
you asked him how much time he would need to spend to gain a complete
understanding of these codes, he estimated that at least five weeks would be needed.
You then decided it would be more cost effective to hire a local person from City B
who specializes in this area. As a result, as you prepare your schedule and estimate
your resource requirements for this project, you should coordinate this work closely
with which of the following processes:
Select one:
a. Estimate costs
b. Develop schedule
c. Determine budgets
d. Define activities
Question 32 Table reporting, spreadsheet analysis, and presentations are examples of—
Not answered
Select one:
Marked out of 1.00
a. Work performance information as an output of control stakeholder engagement
The correct answer is: Tools and techniques used in control stakeholder engagement
Question 33 Control accounts—
Not answered
Select one:
Marked out of 1.00
a. Are charge accounts for personnel time management
The correct answer is: Represent the basic level at which project performance is
measured and reported
Question 34 As a project manager, you recognize the importance of actively engaging key project
Not answered stakeholders on a project. You have prepared an analysis of your stakeholders early
in your project and classified them according to their interest, influence, and
Marked out of 1.00
involvement in your project. You want to now—
Select one:
a. Assess stakeholder legitimacy
c. Determine the urgency that each stakeholder requires when he or she requests
information about the project
Question 35 Updates of organizational process assets that are an output of control scope include
Not answered all the following EXCEPT—
a. Lessons learned
d. Causes of variations
Select one:
Marked out of 1.00
a. To recognize and acknowledge the project sponsor
c. To describe the selection methods used to choose this project over its
competitors
Hide sidebars
The correct answer is: To recognize and acknowledge the existence of the project and
commit organizational resources to the project
Question 37 You are a project manager for the Swirling Seas Cruises food division. You’re
Not answered considering two different projects regarding food services on the cruise lines. The
initial cost of Project Fish’n for Chips will be $800,000, with expected cash inflows of
Marked out of 1.00
$300,000 per quarter. Project Picnic’s payback period is six months. Which project
should you recommend?
Select one:
a. Project Fish’n for Chips, because the costs on Project Picnic are unknown.
b. Project Picnic, because Project Fish’n for Chips’ payback period is four months
longer than Project Picnic’s.
c. Project Fish’n for Chips, because its payback period is two months shorter than
Project Picnic’s.
d. Project Picnic, because Project Fish’n for Chips’ payback period is two months
longer than Project Picnic’s.
The correct answer is: Project Picnic, because Project Fish’n for Chips’ payback
period is two months longer than Project Picnic’s.
Question 38 Defining a new project or a new phase of an existing project relates to:
Not answered
Select one:
Marked out of 1.00
a. Control process
b. Initiating process
c. Planning process
Select one:
Marked out of 1.00
a. The organization is focused on projects and project work.
b. All employees report to two or more managers, but project team members
show loyalty to functional managers.
d. All employees report to one manager and have a clear chain of command.
Hide sidebars
The correct answer is: All employees report to one manager and have a clear chain of
command.
The correct answer is: Project plans are put into action.
Question 41 You are a project manager for residential construction. As a project manager, you
Not answered must be especially concerned with building codes—particularly in the plan quality
management process. You must ensure that building codes are reflected in your
Marked out of 1.00
project plans because—
Select one:
a. They are a cost associated with quality initiatives
The correct answer is: Standards and regulations are an input to plan quality
management
Question 42 You are managing a major international project, and your contract requires you to
Not answered prepare both a project plan and a quality management plan. Your core team is
c. Identify specific quality management roles and responsibilities for the project
The correct answer is: Develop a quality policy for the project
Question 43 If you are measuring the quality of items in a sample on a pass/fail basis, what is that
Not answered called?
a. Attribute sampling
b. Variable sampling
c. Biased sampling
d. Stratified sampling
Question 44 Even though your project is vastly different from a manufacturing operation, you
Not answered believe the principles of kaizenwill work well. The kaizen approach to continuous
improvement emphasizes—
Marked out of 1.00
Select one:
a. Radical changes in operating practices
d. Incremental improvement
Question 45 As of the fourth month on the Acme project, cumulative planned expenditures were
Not answered $100,000. Actual expenditures totaled $120,000. How is the Acme project doing?
c. It is ahead of schedule.
b. Behavioral-oriented reasons
d. Contractual issues
Hide sidebars
Question 48 You are the project manager for a construction company that is building a new city
Not answered and county office building in your city. Your CCB recently approved a scope change.
You know that scope change might come about as a result of all of the following
Marked out of 1.00
except which one?
Select one:
a. Changes to the agreed-upon WBS
b. Schedule revisions
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 You have been assigned to a project in which the objectives are to direct customer
Not answered calls to an interactive voice response system before being connected to a live agent.
You are in charge of the media communications for this project. You report to the
Marked out of 1.00
project manager in charge of this project and the VP of marketing, who share
responsibility for this project. Which organizational structure do you work in?
Select one:
a. Balanced matrix organization
b. Projectized organization
c. Functional organization
Question 2 You have been a project manager for seven years. You now are managing the
Not answered construction of a new facility that must comply with the government’s newly issued
environmental standards. You want to ensure that your team members are able to
Marked out of 1.00
select methods to complete various activities on the project without needing to involve
you in each situation. As you prepare your human resource management plan, you
should document this information in which of the following—
Select one:
a. Resource breakdown structure
Question 4 You are the project manager for a two-year project that is now beginning its second
Not answered year. The mix of team members has changed, and there is confusion as to roles and
responsibilities. In addition, several of the completed work packages have not
Marked out of 1.00
received the required sign-offs, and three work packages are five weeks behind
schedule. To gain control of this project, you need to—
Select one:
a. Work with your team to prepare a responsibility assignment matrix
d. Create a new division of labor by assigning technical leads to the most critical
activities
The correct answer is: Work with your team to prepare a responsibility assignment
matrix
Question 5 You have decided to organize a study group of other project managers in your
Not answered organization to help prepare for the PMP® exam. What type of communication activity
are you employing in your efforts to organize this group?
Marked out of 1.00
Select one:
a. Horizontal
b. External
c. Vertical
d. Official
The correct answer is: Final output of creating the WBS is described in terms of
verifiable products, services, or results.
Question 7 You are in the process of translating project objectives into tangible deliverables and
Not answered requirements. All the following are techniques used in the product analysis tool and
technique of the Scope Definition process, except for which one?
Marked out of 1.00
Select one:
a. Product configuration and specification analysis
Question 8 On the WBS, the first level of decomposition may be displayed by using all the
Not answered following EXCEPT—
b. Subcomponents
d. Major deliverables
Select one:
a. The information learned from these meetings concerns processes and
activities that have already occurred, so it should be documented because the
information is only useful for future projects.
d. These meetings are called lessons learned meetings and they’re a tool and
technique of the Information Distribution process. They’re also a good team-
building activity.
The correct answer is: These meetings are called lessons learned meetings and
they’re a tool and technique of the Information Distribution process. They’re also a
good team-building activity.
Question 10
Not answered
Select one:
a. 15
b. 14
c. 10
d. 12
Select one:
a. computerized modeling techniques
Question 12 You have been hired as a contract project manger for Grapevine Vineyards.
Not answered Grapevine wants you to design an Internet wine club for its customers. One of the
activities for this project is the installation and testing of several new servers. You
Marked out of 1.00
know from past experience it takes about 16 hours per server to accomplish this task.
Since you’re installing 10 new servers, you estimate this activity to take 160 hours.
Which of the estimating techniques have you used?
Select one:
a. Analogous estimating
b. Reserve analysis
c. Bottom-up estimating
d. Parametric estimating
b. Develop Schedule
c. Create WBS
d. Sequence Activities
Question 15 Your project team has identified all the risks on the project and has categorized them
Not answered as high, medium, and low. The “low” risks are placed on which one of the following for
monitoring?
Marked out of 1.00
Select one:
a. Watch list
d. Threat list
Question 16 What is the primary difference between a risk audit and a risk reassessment?
Not answered
Select one:
Marked out of 1.00
a. Project stakeholders conduct risk audits; management conducts
reassessments.
The correct answer is: Risk reassessments are regularly scheduled; risk audits are
performed as defined in the project’s risk management plan.
Question 17 You are working on identifying possible risks to your project to develop a nutritional
Not answered supplement. You want to develop a comprehensive list of risks that can be addressed
b. Documentation reviews
Hide sidebars
d. Checklist analysis
Question 18 You are the project manager for an upcoming outdoor concert event. You’re working
Not answered on the procurement plan for the computer software program that will control the
lighting and screen projections during the concert. You’re comparing the cost of
Marked out of 1.00
purchasing a software product to the cost of your company programmers writing a
custom software program. You are engaged in which of the following?
Select one:
a. Creating the procurement management plan
b. Make-or-buy analysis
c. Procurement planning
Question 19 You are the project manager for the Heart of Texas casual clothing company. It’s
Not answered introducing a new line of clothing called Black Sheep Ranch Wear. You will outsource
the production of this clothing line to a vendor. The vendor has requested a contract
Marked out of 1.00
SOW. All of the following statements are true except for which one?
Select one:
a. The SOW contains the objectives of the project.
b. The vendor requires a SOW to determine whether it can produce the clothing
line given the detailed specifications of this product.
The correct answer is: As the purchaser, you are required to write the SOW.
Question 20 Which of the following is not an organizational process asset that is used during the
Not answered Plan Human Resource Management process?
Question 21 What is the primary risk with including reserves or contingency allowances in your
Not answered cost estimate?
Question 22 There are likely to be team loyalty issues in a matrixed environment. All of the
Not answered following are true regarding this situation as it pertains to the Manage Project Team
process except for which one?
Marked out of 1.00
Select one:
a. The project manager is generally responsible for managing this relationship.
b. Two of the tools and techniques you might use to manage these relationships
effectively are communications methods and issue logs.
The correct answer is: Two of the tools and techniques you might use to manage
these relationships effectively are communications methods and issue logs.
Question 23 You are a project manager working on contract. You’ve performed earned value
Not answered analysis and discovered that the project will be completed on time and under the
b. Bill the customer for the full amount of the contract because this was the
Hide sidebars
c. Add activities to the project to increase the cost enough to meet the original
estimated amount.
d. Upon completion, inform the customer the project has come in under budget.
The correct answer is: Tell the customer you’re adding requirements to the project
that were originally cut because of cost constraints.
Question 24 You are working on a project and discover that one of the business users responsible
Not answered for testing the product never completed this activity. She has written an email
requesting that one of your team members drop everything to assist her with a
Marked out of 1.00
problem that could have been avoided if she would have performed the test. This
employee reports to a stakeholder, not to the project team. You estimate that the
project might not be completed on time as a result of this missed activity. All of the
following are true except for which one?
Select one:
a. You should recommend a preventive action to reduce the possibility of future
project performance veering off track because of this employee’s failure to
perform this activity.
b. You’ve created a forecast, an output of the Monitor and Control Project Work
process, using past performance to predict what the project’s future condition
might look like.
c. You might have to request a change to the project schedule as a result of this
missed activity.
d. You should recommend a corrective action to bring the expected future project
performance back into line with the project management plan because of this
employee’s failure to perform this activity.
The correct answer is: You should recommend a preventive action to reduce the
possibility of future project performance veering off track because of this employee’s
failure to perform this activity.
Question 25 You are the project manager on a project to improve traffic flow in the company’s
Not answered parking garage. You decide to use flowcharting to—
Question 26 As you work on your project to update its software training classes to focus on an
Not answered agile approach, you have a number of key stakeholders. As many students and their
managers are requesting these classes, your CEO has taken a special interest in
Marked out of 1.00
your project and has asked you to accelerate your schedule to complete it in two
months rather than in your planned six months but still have quality offerings. This
means as you work to monitor overall project stakeholder relationships, you should—
Select one:
a. Provide presentations to each stakeholder group
d. Ask your stakeholders for regular feedback as you work on your project
The correct answer is: Determine how changes will be monitored and controlled
Question 27 You are implementing a project management methodology for your company that
Not answered requires you to establish a change control board. Which one of the following
statements best describes a change control board?
Marked out of 1.00
Select one:
a. Managed by the project manager, who also serves as its secretary
The correct answer is: Used to review, evaluate, approve, delay, or reject changes to
the project
Question 28 You plan to hold a series of meeting as you execute the project plan. While different
Not answered attendees will attend each meeting, a best practice to follow is to:
each meeting
d. Be sensitive to the fact that stakeholders often have very different objectives
and invite them to determine the meeting’s agenda
The correct answer is: Not mix the types of meetings on your project
Question 29 Your customer signed off on the requirements document and scope statement of your
Not answered video game project last month. Today she stated she would like to make it an
interactive game that can be played on a television and on a computer. This
Marked out of 1.00
represents a requested scope change that, at a minimum—
Select one:
a. Should be reviewed according to the perform integrated change control
process
The correct answer is: Should be reviewed according to the perform integrated
change control process
Question 30 The performance measurement baseline consists of all the following EXCEPT—
Not answered
Select one:
Marked out of 1.00
a. Scope baseline
b. Cost baseline
c. Schedule baseline
d. Requirements baseline
Question 32 Assume that your actual costs are $1,000; your planned value is $1,200; and your
Not answered earned value is $1,500. Based on these data, what can be determined regarding your
schedule variance?
Marked out of 1.00
Select one:
a. At +$500, the situation is favorable, as physical progress is being
accomplished at a lower cost than was forecasted.
b. At –$300, you have a behind-schedule condition, and your critical path has
slipped.
The correct answer is: At +$300, the situation is favorable, as physical progress is
being accomplished ahead of your plan.
Question 33 Contract type selection is dependent on the degree of risk or uncertainty facing the
Not answered project manager. From the perspective of the buyer, the preferred contract type in a
low-risk situation is—
Marked out of 1.00
Select one:
a. Fixed-price-incentive
b. Cost-plus-fixed fee
c. Firm-fixed-price
d. Cost-plus-a-percentage-of-cost
c. Use a single prime contractor and have this contractor award any subcontracts
Question 35 Each project can benefit from stakeholder involvement; however, it is in both the
Not answered project manager’s and the teams’ best interest to ensure that all project
stakeholdershave positive attitudes toward the project and its goals and objectives.
Marked out of 1.00
Working as a project manager, you have a number of key stakeholders on your
project. The stakeholder that identifies potential conflicts between organizational
strategies and project goals is the—
Select one:
a. Director of the project management office
c. Program manager
Question 36 You are the project manager for a major logistics installation project and must obtain
Not answered specific services from local sources external to your project. Your subcontracts
administrator has told you to prepare a product or service description, which is
Marked out of 1.00
referenced in a—
Select one:
a. Project statement of work
b. Contract
b. Communications plan
d. Stakeholder register
Hide sidebars
Question 38 The VP of marketing approaches you and requests that you change the visitor logon
Not answered screen on the company’s website to include a username with at least six characters.
This is considered
Marked out of 1.00
Select one:
a. project execution
b. ongoing operations
c. project initiation
d. a project
Question 39 Your company manufactures small kitchen appliances. It is introducing a new product
Not answered line of appliances in designer colors with distinctive features for kitchens in small
spaces. These new products will be offered indefinitely starting with the spring catalog
Marked out of 1.00
release. To determine the characteristics and features of the new product line, you will
have to perform which of the following?
Select one:
a. Consulting with the stakeholders
c. Progressive elaboration
d. Fast tracking
Question 40 Which of the following brings together a set of tools and techniques used to describe,
Not answered organize, and monitor the work of project activities?
b. Project management
c. Stakeholders
The correct answer is: Separate quality assurance and quality control departments
reporting to senior management
Question 44 Recently your company introduced a new set of “metal woods” to its established line
Not answered of golfing equipment. However, in the past weeks many of the clubs have been
d. Evaluate failure modes and causes associated with the design and
manufacture of a new product to replace the clubs
The correct answer is: Evaluate failure modes and causes associated with the design
and manufacture of a new product to replace the clubs
Question 45 If operations on a work package were estimated to cost $1,500 and finish today but,
Not answered instead, have cost $1,350 and are only two-thirds complete, the cost variance is—
b. –$350
c. –$500
d. –$150
The correct answer is: The contract administration process from Solicitation Planning
through Contract Administration
Question 47 Before considering a project closed, what document should be reviewed to ensure
Not answered that project scope has been satisfied?
Question 48 You have collected the work performance information for your project to be included in
Not answered the project archives. What is the purpose of the work performance information?
The correct answer is: The work performance information is used to determine the
status of project activities and make certain the project goals and objectives are met.
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 The VP of customer service has expressed concern over a project in which you’re
Not answered involved. His specific concern is that if the project is implemented as planned, he’ll
have to purchase additional equipment to staff his customer service center. The cost
Marked out of 1.00
is substantial and was not taken into consideration in the project budget. The project
sponsor insists that the project must go forward as originally planned or the customer
will suffer. Which of the following is true?
Select one:
a. The conflict should be resolved in favor of the project sponsor.
b. The VP of customer service is correct. Since the cost was not taken into
account at the beginning of the project, the project should not go forward as
planned. Project initiation should be revisited to examine the project plan and
determine how changes can be made to accommodate customer service.
The correct answer is: The conflict should be resolved in favor of the customer.
Question 2 You have been appointed project manager for a new project in your organization and
Not answered must prepare a project management plan. You decide to prepare a WBS to show the
magnitude and complexity of the work involved. No WBS templates are available to
Marked out of 1.00
help you. To prepare the WBS, your first step should be to—
Select one:
a. Determine the cost and duration estimates for each project deliverable
The correct answer is: Identify and analyze the deliverables and related work
Question 3 You have assembled a core team to develop the project management plan for the
Not answered next generation of fatigue fighting drugs. The science is complex, and the extended
Select one:
a. Project complexity and the capability of resources
Question 4 Assume on your project you have identified 250 stakeholders located in three
Not answered continents and of these 250, you have determined that 200 of them will be actively
involved and interested in your project. Therefore, as you determine an appropriate
Marked out of 1.00
communication method, your best approach is—
Select one:
a. E-mails
c. Knowledge repositories
Question 5 You have a conflict on your team but have enough time to resolve it, and you want to
Not answered maintain future relationships. Thankfully, there is mutual trust, respect, and confidence
among the parties involved. You decide to use confronting to resolve this conflict. In
Marked out of 1.00
using this approach, your first step should be to—
Select one:
a. Establish ground rules
b. Explore alternatives
The correct answer is: There are 28 channels of communication, and this should be a
consideration when using the communications requirements analysis tool and
technique.
Question 7 Which of the following is true regarding the project scope statement?
Not answered
Select one:
Marked out of 1.00
a. The project scope statement describes how the team will define and develop
the work breakdown structure.
b. The project scope further elaborates the Initiating processes and serves as a
basis for future project decisions.
c. The project scope statement assesses the reliability of the project scope and
describes the process for verifying and accepting completed deliverables.
d. The project scope statement includes a change control system that describes
how to make changes to the project scope.
The correct answer is: The project scope further elaborates the Initiating processes
and serves as a basis for future project decisions.
Question 8 You are the project manager for a subcontractor on a major contract. The prime
Not answered contractor has asked that you manage your work in a detailed manner. Your first step
is to—
Marked out of 1.00
Select one:
a. Follow the WBS that the prime contractor developed for the project and use the
work packages you identified during the proposal
b. Develop a subproject WBS for the work package that is your company’s
responsibility
The correct answer is: Develop a subproject WBS for the work package that is your
company’s responsibility
Question 9 You work for a furniture manufacturer. Your project is going to design and produce a
Not answered new office chair. The chair will have the ability to function as a regular chair and also
Select one:
Hide sidebars
a. DOE
b. Benchmarking
c. COQ
d. Quality metrics
Question 10 You are the project manager working on a research project for a new drug treatment.
Not answered Your preliminary project schedule runs past the due date for a federal grant
application. The manager of the R&D department has agreed to release two
Marked out of 1.00
resources to work on your project in order to meet the federal grant application date.
This is an example of ___________________.
Select one:
a. resource leveling
b. fast tracking
c. crashing
Select one:
a. A, B, E, and F
b. A, B, D, and F
c. A, C, E, and F
d. C, A, F, and G
Question 12 Your lead engineer estimates that a work package will most likely require 50 weeks to
Not answered complete. It could be completed in 40 weeks if all goes well, but it could take 180
weeks in the worst case. What is the PERT estimate for the expected duration of the
Marked out of 1.00
work package?
Select one:
a. 70 weeks
b. 140 weeks
c. 90 weeks
d. 45 weeks
b. Analogous estimating
c. Reserve analysis
Hide sidebars
d. Expert judgment
Question 14 You are a project manager for Fountain of Youth Spring Water bottlers. Your project
Not answered involves installing a new accounting system, and you’re performing the risk-planning
processes. You have identified several problems along with the causes of those
Marked out of 1.00
problems. Which of the following diagrams will you use to show the problem and its
causes and effects?
Select one:
a. Decision tree diagram
b. Benchmark diagram
d. Fishbone diagram
Question 15 Each one of the following statements about risk avoidance is true EXCEPT that it—
Not answered
Select one:
Marked out of 1.00
a. Accepts the consequences of the risk event should it occur
The correct answer is: Accepts the consequences of the risk event should it occur
Question 16 You are using the interviewing technique of the Quantitative Risk Analysis process.
Not answered You intend to use normal and lognormal distributions. All of the following statements
d. Interviewing techniques are used to quantify the probability and impact of the
risks on project objectives.
The correct answer is: Normal and lognormal distributions use mean and standard
deviation to quantify risks.
b. Project management tools are generally unavailable at the project team level
Question 18 You are the project manager for an upcoming outdoor concert event. You’re working
Not answered on the procurement plan for the computer software program that will control the
lighting and screen projections during the concert. You’re comparing the cost of
Marked out of 1.00
purchasing a software product to the cost of your company programmers writing a
custom software program. You are engaged in which of the following?
Select one:
a. Procurement planning
c. Make-or-buy analysis
Question 20 You are the project manager for Design Your Web Site, Inc. Your company is
Not answered designing the website for a national grocery store chain. You have your activity list in
hand and are ready to diagram the activity dependencies using the PDM technique.
Marked out of 1.00
Which of the following statements is true?
Select one:
The correct answer is: PDM is also the AOA diagramming method.
Question 21 If you are working on a project with constantly changing scope, which contract type
Not answered would work best when hiring an outside vendor to complete a portion of the work?
b. Lump sum
c. Cost reimbursable
d. Fixed price
Question 22 Which of the following statements most accurately describes a project scenario?
Not answered
Select one:
Marked out of 1.00
a. The influence of the stakeholders is the same all through the project.
b. The next phase of a project should never start until the deliverables for the
previous phase have been completely reviewed and approved.
c. Changes in project scope during the initial phases of the project are very
expensive.
The correct answer is: Staffing peaks up during the execution phase of a project.
Question 23 Your project is progressing as planned. The project team has come up with a demo
Not answered that the sales team will use when making presentations to prospective clients. You will
b. Preview the demo for stakeholders, and obtain their approval and sign-off.
Hide sidebars
c. Report that the demo has been noted as a completed task in the information
retrieval system.
d. Report on the progress of the demo, and note that it’s a completed task.
The correct answer is: Report on the progress of the demo, and note that it’s a
completed task.
Question 24 Schedule control is one important way to avoid delays. While planning and executing
Not answered schedule recovery, one tool available to you for control schedules is—
d. Immediately rebaselining
b. Control communications
c. Report performance
d. Manage risks
Question 28 You want to minimize the impact of changes on your project, yet you want to ensure
Not answered that change is managed when and if it occurs. This can be done through each of the
following ways EXCEPT—
Marked out of 1.00
Select one:
a. Approving changes and incorporating them into a revised baseline
d. Ensuring that project scope changes are reflected in changes to product scope
The correct answer is: Ensuring that project scope changes are reflected in changes
to product scope
Select one:
a. Bottom-up estimating techniques, because this is a form of expert judgment
that uses historical information from similar projects
The correct answer is: Analogous estimating techniques, because this is a form of
expert judgment that uses historical information from similar projects
Question 31 The cumulative cost curve for planned and actual expenditures—
Not answered
Select one:
Marked out of 1.00
a. Helps to monitor project performance at a glance
Question 32 You have decided to award a contract to a seller that has provided quality services to
Not answered your company frequently in the past. Your current project, although somewhat
different from previous projects, is similar to other work the seller has performed. In
Marked out of 1.00
this situation, to minimize your risk you should award what type of contract?
Select one:
b. Cost-plus-award-fee
d. Firm-fixed-price
c. Mandate that the team follow the vision and mission statement of his or her
organization
d. Ensure that every member of the project team uses e-mail as a form of
communication
b. The project charter should be published under the project sponsor’s name.
c. The project charter should be published under the name of the project
manager.
d. The project charter should be published under the name of a manager external
to the project.
The correct answer is: The project charter should be published under the name of a
manager external to the project.
Question 36 The Requirements Traceability Matrix helps in tracing all of the following except:
Not answered
Select one:
Marked out of 1.00
a. Requirements to project scope
Question 37 Your company is embarking on a project to launch a new product delivery service.
Not answered You are the project manager for this project and have just finished the concept phase.
The various outputs/deliverable(s) for this phase include—
Marked out of 1.00
Select one:
a. Roles and responsibilities of the project manager
Question 38 Project managers have the highest level of authority and the most power in which
Not answered type of organizational structure?
b. Projectized
c. Balanced matrix
d. Strong matrix
b. Iterative elaboration
c. Progressive elaboration
d. Waterfall development
Select one:
Marked out of 1.00
a. Control process
b. Planning process
c. Initiating process
b. Customer satisfaction
c. Percent complete
d. Scope creep
Question 42 Rank ordering of defects should be used to guide corrective action. This is the
Not answered underlying principle behind—
b. Inspections
c. Trend analysis
d. Control charts
Question 43 The area where the project manager can have the greatest impact on the quality of
Not answered his or her project is in—
a. Quality assurance
b. Quality planning
c. Quality improvement
d. Quality control
The correct answer is: Procedures used to conduct trade-off analyses among cost,
schedule, and quality
Question 45 Which of the following tools and techniques is used in the close project or phase
Not answered process?
d. Expert judgment
b. Specifications
Question 47 Which of the following processes are performed in the Closing process group and in
Not answered what order?
The correct answer is: Scope Verification and then Close Project
Question 48 During the closing phase of the project, the top-ranked source of conflict is—
Not answered
c. Schedule
d. Human resources
Hide sidebars
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 As a PMP, one of your responsibilities is to ensure integrity on the project. When your
Not answered personal interests are put above the interests of the project or when you use your
influence to cause others to make decisions in your favor without regard for the
Marked out of 1.00
project outcome, this is considered which of the following?
Select one:
a. Culturally unacceptable
b. Conflict of interest
Question 2 All the following elements must be evident in a written contract for it to be legally
Not answered enforceable EXCEPT—
b. Legal capacity
c. Appropriate form
d. Mutual assent
b. (n*n-1)/n
c. (n*n-1)/2
d. n*(n-1)/2
Hide sidebars
Question 4 A communications management plan includes which one of the following sample
Not answered contents?
b. Issues
d. Dimensions
The correct answer is: Escalation processes, including time frames and the
management chains
Question 5 You work for a telecommunications company, and when developing a project
Not answered management plan for a new project, you found that you must tailor some company
processes because the product is so different than those products typically produced
Marked out of 1.00
by your company. To tailor these processes, you will follow—
Select one:
a. Stakeholder risk tolerances
c. Expert judgment
Question 6 Each WBS component should be assigned a unique identifier from a code of
Not answered accounts to—
The correct answer is: Sum costs, schedule, and resource information
Question 7 Which conflict resolution technique do project managers use most often?
Not answered
c. Smoothing
d. Forcing
Hide sidebars
Question 8 Which of the following defines the total scope of the project and represents the work
Not answered specified in the current approved project scope statement?
b. Project Charter
Question 9 Your company, which operates one of the region’s largest chemical processing plants,
Not answered has been convicted of illegally dumping toxic substances into the local river. The court
has mandated that the required cleanup activities be completed by February 15. This
Marked out of 1.00
date is an example of—
Select one:
a. A discretionary dependency
b. An external dependency
c. A milestone
d. A key event
The correct answer is: There is approximately a 68 percent chance of completing this
activity in 98 to 122 days.
Question 11 Which of the following statements is true regarding the critical path?
Not answered
Select one:
Marked out of 1.00
a. It allows for looping and branching.
Question 12 If a project planner imposes a finish time of 14 on the project with no change in the
Not answered start date or activity durations, what is the total float of Activity E?
Select one:
a. Cannot be determined
b. 2
c. –1
d. 0
b. You should use Rolling Wave Planning to help you organize team member's
activities within a large project group.
c. You should use Rolling Wave Planning to help you achieve the appropriate
Hide sidebars
d. You should use Rolling Wave Planning to help you determine which activities
are more important and should be done first.
The correct answer is: You should use Rolling Wave Planning to help you achieve the
appropriate level of detail in each work package at the right time.
Question 14 All of the following are true regarding the Qualitative Risk Analysis process except
Not answered which one?
d. Probability and impact and expert interview are used to help correct biases that
occur in the data you’ve gathered during this process.
The correct answer is: The probability and impact matrix is used during this process
to assign red, yellow, and green conditions to risks.
Question 15 Your team is developing the risk management plan. Which tool and technique of this
Not answered process is used to develop risk cost elements and schedule activities that will be
included in the project budget and schedule?
Marked out of 1.00
Select one:
a. Strategies for both threats and opportunities
Select one:
Marked out of 1.00
a. Assign a relative value to the impact on project objectives if the risk in question
occurs
d. Rank order risks in terms of very low, low, moderate, high, and very high
Hide sidebars
The correct answer is: Assign a relative value to the impact on project objectives if the
risk in question occurs
Question 17 You’ve identified a risk event on your current project that could save $100,000 in
Not answered project costs if it occurs. Which of the following is true based on this statement?
(Choose the best answer.)
Marked out of 1.00
Select one:
a. This is a risk event that should be accepted, because the rewards outweigh the
threat to the project.
b. This a risk event that should be shared to take full advantage of the potential
savings.
The correct answer is: This risk event is an opportunity to the project and should be
exploited.
Question 18 You receive a frantic phone call from your vice president who says she is going to
Not answered meet with a prospective client in 15 minutes to discuss a large and complex project.
She asks you how much the project will cost. You quickly think of some similar past
Marked out of 1.00
projects, factor in a few unknowns, and give her a number. What type of estimate did
you just provide?
Select one:
a. Order-of-magnitude
b. Definitive
c. Budget
d. Detailed
Question 20 Sally is a project manager working on a project that will require a specially engineered
Not answered machine. Only three manufacturers can make the machine to the specifications Sally
needs. The price of this machine is particularly critical to this project. The budget is
Marked out of 1.00
limited, and there’s no chance of securing additional funds if the bids for the machine
come in higher than budgeted. She’s developing the evaluation criteria for the bidders’
responses and knows all of the following are true except for which one?
Select one:
a. Sally will use standard contract forms provided by her procurement department
to write the contract for this machine.
b. Sally will update the contract statement of work with any new information.
c. Sally will review the project management plan, including the risk register, as
inputs to this process.
d. Sally will base the evaluation criteria on price alone since the budget is a
constraint.
The correct answer is: Sally will review the project management plan, including the
risk register, as inputs to this process.
Question 21 You are the project manger for Xylophone Phonics. This company produces children’s
Not answered software programs that teach basic reading and math skills. You are ready to assign
project roles, responsibilities, and reporting relationships. Which project Planning
Marked out of 1.00
process are you working on?
Select one:
a. Resource Planning
d. Acquire Staff
Select one:
a. You are in the Perform Quality Assurance process and have performed a
Hide sidebars
quality audit.
b. You are in the Contract Administration process and have completed a contract
audit to ensure that the subcontractor’s performance meets the contract
requirements.
d. You are in the Perform Quality Assurance process and have performed a
process analysis.
The correct answer is: You are in the Perform Quality Assurance process and have
performed a process analysis.
Question 23 You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your
Not answered company is competing with another retail store for the option of opening two new
stores in a foreign country. You have been invited to dinner with the prospective
Marked out of 1.00
foreign business partners and their spouses upon your arrival. You know that all of the
following statements are generally true except for which one?
Select one:
a. You should spend time building relationships with your prospective foreign
business partners before getting down to business.
b. You should respect the cultural differences you’ll encounter when working with
your prospective foreign business partners.
c. You should explain your company’s rules, standards, and operating policies at
your first meeting with the prospective foreign business partners.
The correct answer is: You should explain your company’s rules, standards, and
operating policies at your first meeting with the prospective foreign business partners.
Question 24 You are a project manager for an engineering company. Your company won the bid to
Not answered add ramp-metering lights to several on-ramps along a stretch of highway at the south
Select one:
a. You agree to meet with the subcontractor to see whether a satisfactory solution
Hide sidebars
can be reached.
b. You document the poor performance in written form and send the
correspondence to the subcontractor.
c. You terminate the contract for poor performance and submit a change request
through Contract Administration.
The correct answer is: You terminate the contract for poor performance and submit a
change request through Contract Administration.
Question 25 One way to determine how to best update and communicate project performance and
Not answered respond to stakeholder information requests is to—
c. Set up a portal
d. Hold meetings
Question 26 You are responsible for ensuring that your seller’s performance meets contractual
Not answered requirements. For effective contract control, you should—
The correct answer is: Implement the contract change control system
Question 27 Which performance measurement tells you what the projected total cost of the project
Not answered will be at completion?
b. EAC
c. SPI
d. ETC
Hide sidebars
Question 28 A number of tools and techniques are helpful in the perform integrated change control
Not answered process. If you want to implement an integrated change control process, you should
use—
Marked out of 1.00
Select one:
a. Configuration management software
b. PV equals 1.
Question 30 Which of the following types of contracts has the least risk to the seller?
Not answered
Select one:
Marked out of 1.00
a. Cost-plus-fixed-fee
b. Fixed-price-incentive fee
c. Firm-fixed-price
d. Cost-plus-award-fee
Select one:
Hide sidebars
a. Ask for more money so that you can contract out one of the phases you had
planned to do with in-house resources.
c. Examine the project plan to see whether there are any phases that can be fast
tracked, and then revise the project plan to reflect the compression of the
schedule.
The correct answer is: Examine the project plan to see whether there are any phases
that can be fast tracked, and then revise the project plan to reflect the compression of
the schedule.
Question 32 Which term describes those costs in a contract that are associated with two or more
Not answered projects but are not traceable to either of them individually?
b. Variable
c. Direct
d. Semivariable
Question 33 Overall cost estimates must be allocated to individual activities to establish the cost
Not answered performance baseline. In an ideal situation, a project manager would prefer to prepare
estimates—
Marked out of 1.00
Select one:
a. Using a bottom-up estimating technique
c. Using a parametric estimating technique and model specific for that project
type
The correct answer is: Project A, because Project B’s payback period is 21 months
Question 35 The business needs, strategic plan, and product scope description all describe
Not answered elements of which of the following?
Select one:
a. Comparing power and influence
Question 37 One key reason that the develop project charter process is so important is that it—
Not answered
Select one:
Marked out of 1.00
a. States the methods for acceptance of the project’s deliverables
The correct answer is: Links the project to the ongoing work of the organization
Question 38 You are a project manager working in a foreign country. You observe that some of
Not answered your project team members are having a difficult time adjusting to the new culture.
Select one:
a. This condition is known as global culturalism.
c. This is the result of working with teams of people from two different countries.
Question 39 You’ve decided to try your hand at project management in the entertainment industry.
Not answered You’re working on a movie production, and the team has just completed the
storyboard phase of the project. Which of the following is true?
Marked out of 1.00
Select one:
a. All the phases of this project together make up a program.
b. The division of phases and determining which processes to use in each phase
is called tailoring.
c. The storyboard phase marks the end of the Initiating process group, and the
next phase of the project should begin.
d. The storyboard is a deliverable that marks the end of the phase. The
deliverable must be approved before the next phase begins.
The correct answer is: The storyboard is a deliverable that marks the end of the
phase. The deliverable must be approved before the next phase begins.
Question 40 You are a project manager working on gathering requirements and establishing
Not answered estimates for the project. Which process group are you in?
b. Planning
d. Executing
d. Quality is designed into the product or service, not inspected into it.
The correct answer is: Quality is the concern of the quality assurance staff.
Question 42 The basic approach to quality management in projects is to be compatible with which
Not answered of the following:
c. Six-Sigma, failure mode and effect analysis, and total quality management
The correct answer is: The International Organization for Standardization (ISO)
b. Settle subcontracts
Question 46 Your project was just completed. Because of some unfortunate circumstances, the
Not answered project was delayed, causing cost overruns at the end of the project. This information
might be useful on future projects in all of the following activities except for which
Marked out of 1.00
one?
Select one:
a. Allocating resources
b. Product verification
c. Activity estimating
d. Cost estimating
Question 47 Your project has experienced some changes to the agreed-upon WBS elements. The
Not answered changes were approved through the proper change control process. The WBS
changes might in turn require which of the following?
Marked out of 1.00
Select one:
b. Scope changes
c. Cost changes
d. Schedule revisions
Question 48 Close procurements is a process that involves includes activities for administrative
Not answered closure such as—
The correct answer is: Audit project success or failure and archiving records
◄ Trao đổi về nội dung… Jump to... Thi thử - 01 ►
Copyright © 2020 - Developed by BKElearning - HUST
Hide sidebars
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 You are managing a project to introduce a new product to the marketplace that is
Not answered expected to have a very long life. In this situation, the concept of being temporary,
which is part of the definition of a project,—
Marked out of 1.00
Select one:
a. Does not apply because the project will not be short in duration
b. Recognizes that the project team will outlive the actual project
c. Does not apply because the project will have a lasting result
The correct answer is: Does not apply to the product to be created
Question 2 In the initial stage of the project life cycle, the project’s technical objectives are apt to
Not answered be understood only in a general sense. A major component of project conflict during
this stage of the project is—
Marked out of 1.00
Select one:
a. Confusion of establishing a project in the matrix management environment
d. Schedules
The correct answer is: Confusion of establishing a project in the matrix management
environment
Question 3 You are working on the next generation of software for mobile phones for your
Not answered telecommunications company. While time to market is critical, you know from your
d. Governance plan
Question 4 Your organization has decided to use project management for all of its endeavors. It
Not answered has established a Center of Excellence for Project Management to support the
movement into management by projects and has appointed you as its director. Since
Marked out of 1.00
you work in a matrix environment, which of the following types of communications is
the most essential for success?
Select one:
a. Upward
b. Downward
c. Diagonal
d. Horizontal
Question 5 The team members on your project have been complaining that they do not have any
Not answered sense of identity as a team because they are located in different areas of the building.
To remedy this situation, you developed a project logo and had it printed on T-shirts to
Marked out of 1.00
promote the project, but this action has not worked. Your next step is to—
Select one:
a. Create an air of mystery about the project
c. Issue guidelines on how team members should interact with other stakeholders
d. Initiate a newsletter
Select one:
a. The WBS template from a previous project, a tool and technique of the Create
WBS process, was used to create the WBS for this project. The WBS
encompasses the major deliverables for the project.
b. The WBS should be created next, and it encompasses the full scope of work
for the project. Only the work of the project is listed on the WBS.
c. The WBS encompasses the full scope of work for the project and the technique
in the question is called rolling wave planning.
d. Only the deliverables associated with the work of the project should be listed
on the WBS. Since product number three isn’t being released until a later date it
should not yet be included on the WBS.
The correct answer is: The WBS template from a previous project, a tool and
technique of the Create WBS process, was used to create the WBS for this project.
The WBS encompasses the major deliverables for the project.
Question 7 The WBS represents all product and project work, including project management. It is
Not answered sometimes called the—
b. Integration of scope, cost, and schedule for comparison to the earned value
d. 100% rule
c. Prevention costs
b. They are organizational process assets that are used to help define and
develop the project management plan.
d. They are forms of expert judgment used to help define and develop the project
scope statement.
The correct answer is: They are used to elaborate the product scope description,
which is an element of the output of the Scope Planning process.
Question 10 You are a project manager for Picture Shades, Inc. It manufactures window shades
Not answered that have replicas of Renaissance-era paintings on the inside for hotel chains. Picture
Shades is taking its product to the home market, and you’re managing the new
Marked out of 1.00
project. It will offer its products at retail stores as well as on its website. You’re
developing the project schedule for this undertaking. Looking at the following graph,
which path is the critical path?
Select one:
a. A-F-G-E-H
b. A-D-E-H
c. A-F-G-H
d. A-B-C-E-H
Question 11 Six sigma refers to the aim of setting tolerance limits at six standard deviations from
Not answered the mean, whereas the normally expected deviation of a process is—
c. Cost baseline
d. Schedule baseline
Hide sidebars
Question 13 As you are creating the Activity List, which technique is recommended for subdividing
Not answered the project into smaller components called activities?
b. Deconstruction
c. Expert judgment
Question 14 The information-gathering techniques used in the Risk Identification process include
Not answered all of the following except ___________________.
b. checklist analysis
Question 15 Your stakeholders have asked for an analysis of the cost risk. All of the following are
Not answered true except for which one?
b. A cost breakdown structure can be used as an input variable for the cost
analysis.
c. Monte Carlo analysis is the preferred method to use to determine the cost risk.
d. A traditional work breakdown structure can be used as an input variable for the
cost analysis.
Select one:
Marked out of 1.00
a. Reducing the probability and/or impact of an adverse risk event to an
acceptable threshold
The correct answer is: Reducing the probability and/or impact of an adverse risk
event to an acceptable threshold
Question 17 Each of the following statements is true regarding the risk management plan except
Not answered for which one?
c. The risk management plan includes a description of the responses to risks and
triggers.
The correct answer is: The risk management plan includes a description of the
responses to risks and triggers.
Question 18 You are the project manager for a scheduled version release of your company’s
Not answered software tracking product. You have identified resources according to their activities.
You might want to display this information in which of the following?
Marked out of 1.00
Select one:
a. AOA
b. PDM
c. RAM
d. AON
Select one:
a. CPPC
Hide sidebars
b. CPF
c. Cost-reimbursable contract
d. CPIF
Question 20 All of the following statements describe the activity list except which one?
Not answered
Select one:
Marked out of 1.00
a. The activity list is an output of the Activity Definition process.
The correct answer is: The activity list includes all activities of the project.
Question 21 During the Plan Procurement Management phase, the make-or-____analysis must be
Not answered completed. This technique prompts the project team to determine the source of their
item.
Marked out of 1.00
Select one:
a. ignore
b. find
c. buy
d. lease
Question 22 Which of the following tools and techniques of the Select Sellers process is used to
Not answered check proposed pricing?
c. Independent estimates
Select one:
a. Run chart
b. Variables chart
Hide sidebars
c. Trend chart
d. Attribute chart
Question 24 Assume your project communication management plan has been approved by your
Not answered sponsor and the members of your Steering Committee. You are managing a global
project and have team members working virtually in four continents and stakeholders
Marked out of 1.00
in numerous locations. Your next step is to—
Select one:
a. Determine performance reporting methods
Question 25 You are a contract project manager for a wholesale flower distribution company. Your
Not answered project involves developing a website for the company that allows retailers to place
their flower orders online. You will also provide a separate link for individual
Marked out of 1.00
purchases that are ordered, packaged, and mailed to the consumer directly from the
grower’s site. This project involves coordinating the parent company, growers, and
distributors. You’ve discovered a problem with one of the technical processes needed
to perform this project. You decide to perform root cause analysis to determine the
cause of this problem and recommended preventive actions. Which of the following is
true?
Select one:
a. You are using the process analysis technique.
The correct answer is: You are using the quality audit technique.
Question 26 Change control procedures, configuration management knowledge base, versions,
Not answered and baselines in the develop project management plan process are:
Question 27 You know that BAC = 375, PV = 300, AC = 200, and EVC = 250. Variances that have
Not answered occurred on the project to date are not expected to continue. What is the ETC?
b. 125
c. 75
d. 50
Question 28 You are a project manager for Bluebird Technologies. Bluebird writes custom billing
Not answered applications for several industries. A schedule change has been requested. You know
change is concerned with all of the following except which one?
Marked out of 1.00
Select one:
a. Verifying change
b. Managing change
Question 29 Which performance measurement tells you how much more of the budget is required
Not answered to finish the project?
a. EAC
b. EV
c. ETC
d. AC
Select one:
a. $12,500; the original project budget
c. $12,500; the revised estimate for total project cost (based on performance thus
far)
d. $10,000; the revised estimate for total project cost (based on performance thus
far)
The correct answer is: $12,500; the revised estimate for total project cost (based on
performance thus far)
Question 31 The CPI on your project is 0.44, which means that you should—
Not answered
Select one:
Marked out of 1.00
a. Place emphasis on improving the timeliness of the physical progress
c. Recognize that your original estimates were fundamentally flawed, and your
project is in an atypical situation
d. Reassess the life-cycle costs of your product, including the length of the life-
cycle phase
The correct answer is: Recognize that your original estimates were fundamentally
flawed, and your project is in an atypical situation
b. Task force
c. Matrix management
d. Fast-tracking
b. Benchmarking
c. Control charts
d. Process analysis
Hide sidebars
Question 34 You have been placed in charge of a group of people that is selecting one of three
Not answered possible projects. As you gather in the conference room, many team members
already have decided which project selection technique to use. Some prefer IRR, and
Marked out of 1.00
others argue for BCR. In deciding which method to use, your first step should be to—
Select one:
a. Select the method for which most team members have knowledge
b. Identify the technique used most often in the company and determine if it is
appropriate for this project
d. Compare and contrast selection techniques and identify the advantages and
disadvantage of each
The correct answer is: Determine the philosophy and wishes of management
Question 35 Change requests include a group of potential changes to a project. Types of change
Not answered requests include all the following EXCEPT—
b. Maintenance requests
c. Defect repairs
d. Corrective actions
b. Procedures
Hide sidebars
c. Strategic plans
d. Policies
Question 37 What are the inputs to the Develop Project Charter process?
Not answered
Select one:
Marked out of 1.00
a. Project SOW, project selection methods, and organizational process assets
The correct answer is: Contract, project SOW, enterprise environmental factors, and
organizational process assets
Question 38 The transition from one phase to another within a project's life cycle (e.g. design to
Not answered manufacturing) is typically marked by:
b. Monte Carlo
c. Decision tree
d. Kill point
Select one:
a. The conflict should be resolved in favor of the customer.
Hide sidebars
b. The VP of customer service is correct. Since the cost was not taken into
account at the beginning of the project, the project should not go forward as
planned. Project initiation should be revisited to examine the project plan and
determine how changes can be made to accommodate customer service.
The correct answer is: The conflict should be resolved in favor of the customer.
Question 40 The VP of marketing approaches you and requests that you change the visitor logon
Not answered screen on the company’s website to include a username with at least six characters.
This is considered
Marked out of 1.00
Select one:
a. project execution
b. project initiation
c. ongoing operations
d. a project
Question 41 Recently your company introduced a new set of “metal woods” to its established line
Not answered of golfing equipment. However, in the past weeks many of the clubs have been
returned because of quality problems. You decide to conduct a failure mode and
Marked out of 1.00
criticality analysis to—
Select one:
a. Help management set priorities in its existing manufacturing processes to
avoid failures
b. Evaluate failure modes and causes associated with the design and
manufacture of a new product to replace the clubs
d. Evaluate failure modes and causes associated with the design and
manufacture of this product
The correct answer is: Evaluate failure modes and causes associated with the design
and manufacture of a new product to replace the clubs
Question 42 If you are measuring the quality of items in a sample on a pass/fail basis, what is that
Not answered called?
b. Stratified sampling
c. Biased sampling
d. Attribute sampling
Hide sidebars
Question 43 Deming’s Fourteen Points provide a way for an organization to create and sustain a
Not answered culture of continuous improvement. As such it should be directed by—
b. Top management
d. Stakeholders
The correct answer is: Provide better product definition and product development
Question 45 Inspections are also called each of the following except for which one?
Not answered
Select one:
Marked out of 1.00
a. Audits
b. Walk-throughs
c. Assessment
d. Reviews
b. This project ended due to integration because it was completed and accepted
Hide sidebars
c. This project ended due to extinction because it was completed and accepted.
d. This project ended due to integration because it was completed and accepted.
The correct answer is: This project ended due to integration because it was
completed and accepted and the project manager moved on to a new project.
Question 47 Requirements for formal contract acceptance and closure usually are defined in the—
Not answered
Select one:
Marked out of 1.00
a. Procurement audit report
c. Proposal
d. Statement of work
Question 48 Typically, the seller receives formal written notice that the contract has been
Not answered completed by the—
c. Project manager
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 You are managing a project to install a new postage software system that will
Not answered automatically print labels and administer postage for certified mailings, overnight
packages, and other special mailing needs. You’ve attempted to gain the cooperation
Marked out of 1.00
of the business analyst working on this project, and you need some answers. She is
elusive and tells you that this project is not her top priority. What should you do to
avoid situations like this in the future?
Select one:
a. Establish the business analyst’s duties well ahead of due dates, and tell her
you are expecting her to meet these expectations because the customer is
counting on the project meeting due dates to save significant costs on their annual
mailings.
b. Negotiate with the business analyst’s functional manager during the planning
process to establish expectations, and inform the functional manager of the
requirements of the project. Agreement from the functional manager will assure
the cooperation of the business analyst.
c. Establish the business analyst’s duties well ahead of due dates, and tell her
you’ll be reporting on her performance to her functional manager.
d. Negotiate with the business analyst’s functional manager during the planning
process to establish expectations and request to participate in the business
analyst’s annual performance review.
The correct answer is: Negotiate with the business analyst’s functional manager
during the planning process to establish expectations and request to participate in the
business analyst’s annual performance review.
Question 2 You and your team are documenting requirements on you project to control fatigue as
Not answered people need to work more hours to keep up with the competition. You decided to set
b. Business requirements
Hide sidebars
c. Transition requirements
d. Stakeholder requirements
Question 3 You are responsible for a project management training curriculum that is offered
Not answered throughout the organization. In this situation, your intangible deliverables are—
The correct answer is: Employees who can apply the training effectively
Question 4 Work completed, key performance indicators, technical performance measures, start
Not answered and finish dates of schedule activities, number of change requests, number of
defects, actual costs, and actual decisions are examples of work performance data
Marked out of 1.00
are an output of—
Select one:
a. Monitor and control project work
d. Risk control
Question 7 You are working on a project that is similar in scope to a project performed last year
Not answered by your company. You might consider which of the following?
c. Reusing the previous project’s product description when writing the scope
statement
The correct answer is: Reusing the previous project’s cost-benefit analysis as
justification for this project
d. Stakeholder register
b. 1 to 5
Hide sidebars
c. 10 to 18
d. 5 to 11
Question 10 You are managing a construction project for a new city water system. The contract
Not answered requires you to use special titanium piping equipment that is guaranteed not to
corrode. The titanium pipe must be resting in the ground a total of 10 days before
Marked out of 1.00
connectors can be installed. In this example, the 10-day period is defined as—
Select one:
a. Slack
b. Lead
c. Lag
d. Float
The correct answer is: Project duration calculations are sometimes approximate.
Question 12 The technique most commonly used by project management software packages to
Not answered construct a project schedule network diagram is:
b. Activity-In-Node (AIN)
c. Node-On-Activity (NOA)
d. Finish-to-Start (FS)
b. Expected float
c. Free float
d. Extra float
Hide sidebars
Question 14 The highest risk impact generally occurs during which one of the following project life-
Not answered cycle phases?
Question 15 All of the following statements are true regarding the RBS except for which one?
Not answered
Select one:
Marked out of 1.00
a. The RBS is similar to the WBS in that the lowest levels of both are easily
assigned to a responsible party or owner.
c. The lowest level of the RBS can be used as a checklist, which is a tool and
technique of the Risk Identification process.
d. It describes risk categories, which are a systematic way to identify risks and
provide a foundation for understanding for everyone involved on the project.
The correct answer is: It describes risk categories, which are a systematic way to
identify risks and provide a foundation for understanding for everyone involved on the
project.
b. Risks that are not identified at the outset of the project but are known before
they occur
c. Risks that cannot be known before they occur because they are external risks
The correct answer is: Any risks that cannot be known before they occur
Question 17 Risk score measures the—
Not answered
Select one:
Marked out of 1.00
a. Reduced monetary value of the risk event
The correct answer is: Product of the probability and impact of the risk
Question 18 You have been hired as a contract project manager for Grapevine Vineyards.
Not answered Grapevine wants you to design an Internet wine club for its customers. Customers
must register before being allowed to order wine over the Internet so that legal age
Marked out of 1.00
can be established. You know that the module to verify registration must be written
and tested using data from Grapevine’s existing database. This new module cannot
be tested until the data from the existing system is loaded. You are going to hire a
vendor to perform the programming and testing tasks for this module to help speed up
the project schedule. Since they’ll have access to your customer list and potentially
other trade secrets, you’ll asked them to sign a nondisclosure agreement. This is an
example of which of the following?
Select one:
a. Standard form
b. Procurement documents
Question 19 Assume you are preparing your procurement management plan. A useful tool and
Not answered technique is to—
d. Have a meeting
The correct answer is: Amount of time before net cash flow becomes positive
Question 21 All of the following statements are true regarding the ADM method except which one?
Not answered
Select one:
Marked out of 1.00
a. The ADA method is rarely used today.
The correct answer is: The ADM method uses one time estimate to determine
durations.
Question 22 You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your
Not answered company is competing with another retail store for the option of opening two new
stores in a foreign country. You know, but have not yet informed your company, that
Marked out of 1.00
you are going to go to work for the competitor, which happens to be bidding for this
same opportunity. What is the most appropriate response?
Select one:
a. You’ve not yet received an official offer from the competing company for your
new job opportunity, so you choose to participate in the initial meetings with the
foreign business partners.
b. You decline to participate in the initial meetings with the foreign business
partners because of a conflict of interest.
c. You inform the foreign business partners that you’re going to be working with a
new company and that you know the deal they’ll receive from the competing
company is better than the one this company is proposing.
d. You decide to participate in the initial meetings with the foreign business
partners because any information you gain now will help you when you make the
move to the new company.
The correct answer is: You’ve not yet received an official offer from the competing
company for your new job opportunity, so you choose to participate in the initial
meetings with the foreign business partners.
Question 23 To anticipate and help develop approaches to deal with potential quality problems on
Not answered your project, you want to use a variety of root-cause analysis techniques including all
c. Ishikawa diagrams
Hide sidebars
d. Fishbone diagrams
Question 24 A structured review of the seller’s progress to deliver projectscope and quality within
Not answered cost and schedule is known as a(n)—
b. Inspection
d. Procurement audit
Question 25 As project manager, you need a relatively fast and informal method addressing
Not answered disagreements with contractors. One such method is to submit the issue in question
to an impartial third party for resolution. This process is known as—
Marked out of 1.00
Select one:
a. Steering resolution
b. Problem processing
d. Mediation litigation
b. Configuration Identification
c. Configuration Verification
d. Change request
This project involves coordinating the parent company, growers, and distributors. You
are preparing a performance review and have the following measurements at hand:
PV = 300, AC = 200, and EV = 250. What is the CPI of this project?
Select one:
Hide sidebars
a. 0.83
b. 1.25
c. 0.80
d. 1.5
Question 28 You know that BAC = 500, PV = 325, ACC = 275, and EVC = 250 and that you are
Not answered experiencing typical variances. What is ETC?
b. 250
c. 227.3
d. 525
Question 29 An intentional activity to ensure future performance of project work is aligned with the
Not answered project management plan is—
b. Corrective action
d. Preventive action
b. Project priorities
c. Schedule
d. Cost
Hide sidebars
Question 31 You are using earned value progress reporting for your current project in an effort to
Not answered teach your software developers the benefits of earned value. You plan to display
project results on the cafeteria bulletin board so that the team knows how the project
Marked out of 1.00
is progressing: PV = $2,200; EV = $2,000; AC = $2,500; BAC = $10,000. The CV for
this project is—
Select one:
a. 500
b. –$500
c. –$300
d. 300
c. Providing quality products will stop, or at least diminish, the number of returned
items
The correct answer is: Beyond a certain point, additional investment in quality has a
negative ROI
Question 33 To meet regulatory requirements, you need to crash your project schedule. Your first
Not answered step is to compute—
b. The cost and time slope for each critical activity that can be expedited
c. The time saved in the overall schedule when tasks are expedited on the critical
path
Hide sidebars
The correct answer is: The cost and time slope for each critical activity that can be
expedited
The correct answer is: The product description is a component of an input of the
Develop Project Charter process. It describes the characteristics of the product,
service, or result and contains less detail in the early phases of the project.
Question 35 The baseline for evaluating whether requests for changes or additional work are
Not answered contained within or outside the project’s exclusion is provided by the—
The correct answer is: Assess how stakeholders probably will respond in various
situations
Question 37 Your nonprofit organization is preparing to host its first annual 5K run/walk in City
Not answered Park. You worked on a similar project for the organization two years ago when it
cohosted the 10K run through Overland Pass. Which of the organizational process
Marked out of 1.00
assets might be helpful to you on your new project?
Select one:
a. Historical information on the 10K run project
b. The strategic plan, because you’ll want to make sure the project reflects the
overall strategic direction of the organization
c. The project SOW, which describes the high-level details of the run/walk
program
The correct answer is: Historical information on the 10K run project
Question 38 You have been assigned to a project in which the objectives are to direct customer
Not answered calls to an interactive voice response system before being connected to a live agent.
You are in charge of the media communications for this project. You report to the
Marked out of 1.00
project manager in charge of this project and the VP of marketing, who share
responsibility for this project. Which organizational structure do you work in?
Select one:
a. Projectized organization
b. Functional organization
c. This is a project because this new product line has never been manufactured
and sold by this company before.
The correct answer is: This is a project because this new product line has never been
manufactured and sold by this company before.
Question 40 During which project management process are risk and stakeholder’s ability to
Not answered influence project outcomes the highest at the beginning of the process?
b. Initiating
d. Executing
b. Control tests
c. Walkthroughs
d. Checklists
Select one:
Marked out of 1.00
a. Quality metrics
b. Quality baseline
Question 43 Assume you wish to provide a process to be more creative in problem solving as on
Not answered your project you have a somewhat complex scenario that possesses intertwined
logical relationships for up to 50 items. The best approach is to—
Marked out of 1.00
Select one:
a. Design an experiment
Question 44 The project team should have a working knowledge of statistical process control to
Not answered help evaluate control quality outputs. Of all the topics involved, which of the following
is the most important for the team to understand?
Marked out of 1.00
Select one:
a. Attribute sampling and variables sampling
Question 45 All the following are processes in project procurement management EXCEPT—
Not answered
Select one:
Marked out of 1.00
a. Terminate procurements
b. Control procurements
c. Close procurements
Select one:
a. Extinction
b. Integration
c. Starvation
d. Addition
Question 47 You are finalizing all the contracts and ensuring that they are closed. The close
Not answered procurements process involves all the following administrative actions EXCEPT—
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
b. Commercial databases
d. Historical information
Question 2 You have been the project manager for your nuclear submarine project for four years.
Not answered While you did not assume this position until the project management plan had been
prepared and approved, you find you spend a significant amount of time collecting
Marked out of 1.00
data and communicating. You also spend time reviewing the impact of project
changes and implementing ones that have been approved. Often you have had to
modify a non-conforming product, which means you are spending time on—
Select one:
a. Updating the traceability matrix
b. Defect repair
d. Corrective actions
b. Quality metrics
d. Cost-benefit analysis
Hide sidebars
Question 4 Your project is now under way, and you are working with your team to prepare your
Not answered requirements management plan. Which of the following strongly influences how
requirements are managed?
Marked out of 1.00
Select one:
a. A set of procedures by which project scope and product scope may be
changed
b. Requirements documentation
Question 5 You are the project manager for Heartthrobs by the Numbers Dating Services. You’re
Not answered working on an updated Internet site that will display pictures as well as short bios of
prospective heartbreakers. You’ve just completed your project staff assignments and
Marked out of 1.00
published the project team directory. Which process are you in?
Select one:
a. Human Resource Planning
b. Deliverables
c. Assumptions
d. Constraints
c. In the project scope statement, which will be used as an input to the Create
WBS process
The correct answer is: In the project scope statement, which will be used as an input
to the Create WBS process
Question 8 If you are creating a new WBS for your project, what should you consider to save time
Not answered during the creation process?
The correct answer is: Use a previous WBS from a similar project as a template
Question 9 Your company, Kick That Ball Sports, has appointed you project manager for its new
Not answered Cricket product line introduction. This is a national effort, and all the retail stores
across the country need to have the new products on the shelves before the media
Marked out of 1.00
advertising blitz begins. The product line involves three new products, two of which
will be introduced together and a third one that will follow within two years. You are
ready to create the WBS. All of the following are true expect for which one?
Select one:
a. Each level of the WBS represents verifiable products or results.
c. Each of the three products should be elaborated to the same number of levels.
This is known as rolling wave planning.
d. The WBS should be elaborated to a level where costs and schedule are easily
estimated. This is known as the work package level.
The correct answer is: The WBS should be elaborated to a level where costs and
schedule are easily estimated. This is known as the work package level.
Question 10 Your lead engineer estimates that a work package will most likely require 50 weeks to
Not answered complete. It could be completed in 40 weeks if all goes well, but it could take 180
b. 90 weeks
Hide sidebars
c. 70 weeks
d. 140 weeks
Question 11 You are remodeling your kitchen and decide to prepare a network diagram for this
Not answered project. Your appliances must be purchased and available for installation by the time
the cabinets are completed. In this example, these relationshipsare—
Marked out of 1.00
Select one:
a. Start-to-start
b. Start-to-finish
c. Finish-to-start
d. Finish-to-finish
b. Create WBS
c. Define Activities
d. Sequence Activities
Question 13 You are managing a construction project for a new city water system. The contract
Not answered requires you to use special titanium piping equipment that is guaranteed not to
corrode. The titanium pipe must be resting in the ground a total of 10 days before
Marked out of 1.00
connectors can be installed. In this example, the 10-day period is defined as—
Select one:
a. Lead
b. Float
c. Lag
d. Slack
c. Inconsequential
d. Finite
Hide sidebars
Question 15 As project manager, you have assembled the team to prepare a comprehensive list of
Not answered project risks. Which one of the following documents would be the most helpful in this
process?
Marked out of 1.00
Select one:
a. CBS
b. WBS
c. OBS
d. RBS
Question 16 You are developing radio frequency (RF) technology that will improve overnight
Not answered package delivery. You ask each stakeholder to estimate the most optimistic package
delivery time using the RF technology, the most pessimistic time, and the most likely
Marked out of 1.00
time. This shows that for your next step you plan to—
Select one:
a. Structure a decision analysis as a decision tree
Question 17 Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest will
Not answered prevent your equipment from arriving on time. You identified a risk response strategy
for this risk and have arranged for a local company to lease you the needed
Marked out of 1.00
equipment until yours arrives. This is an example of which risk response strategy?
Select one:
a. Acceptance
b. Avoid
c. Transfer
d. Mitigate
Select one:
Marked out of 1.00
a. Start-to-start
b. Start-to-finish
c. Finish-to-start
d. Finish-to-finish
Hide sidebars
Question 19 You are the project manager for BB Tops, a nationwide toy store chain. Your new
Not answered project involves a creating a prototype display at several stores across the country.
You are using a RACI chart to display individuals and activities. What does RACI
Marked out of 1.00
stand for?
Select one:
a. Responsible, assignment, control, inform
Question 20 You are the project manager for the Heart of Texas casual clothing company. It’s
Not answered introducing a new line of clothing called Black Sheep Ranch Wear. You will outsource
the production of this clothing line to a vendor. The vendor has requested a contract
Marked out of 1.00
SOW. All of the following statements are true except for which one?
Select one:
a. As the purchaser, you are required to write the SOW.
b. The vendor requires a SOW to determine whether it can produce the clothing
line given the detailed specifications of this product.
The correct answer is: As the purchaser, you are required to write the SOW.
Question 21 Which of the following is not an organizational process asset that is used during the
Not answered Plan Human Resource Management process?
Question 23 In the below path convergence example, if the odds of completing activities 1, 2, and
Not answered 3 on time are 50 percent, 50 percent, and 50 percent, what are the chances of
starting activity 4 on day 6?
Marked out of 1.00
Select one:
a. 40 percent
b. 10 percent
c. 50 percent
d. 13 percent
Question 24 You have been asked to submit a proposal for a project that has been put out for bid.
Not answered First you attend the bidder conference to ask questions of the buyers and to hear the
questions some of the other bidders will ask. Which of the following statements is
Marked out of 1.00
true?
Select one:
a. Bidder conferences are an output of the Select Sellers process.
c. Bidder conferences are a tool and technique of the Request Seller Responses
process.
d. Bidder conferences are a tool and technique of the Select Sellers process.
The correct answer is: Bidder conferences are an output of the Select Sellers
process.
Question 25 You have decided to use a fishbone diagram to identify the relationship between an
Not answered effect and its causes. To begin, you should first—
c. Select an interdisciplinary team who has used the technique before to help
brainstorm the problem
Hide sidebars
Question 26 You are a project manager for Laurel’s Theater Productions. Your new project is
Not answered coming in over budget and requires a cost change through the cost change control
system. You know all of the following statements are true regarding Cost Control
Marked out of 1.00
except for which one?
Select one:
a. Changes are monitored so that inappropriate changes do not get into the cost
baseline.
The correct answer is: Changes are reflected in the cost baseline.
Question 27 You know that BAC = 500, PV = 325, ACC = 275, CPI = .9, and EV = 250 and that
Not answered you are experiencing atypical variances. Variance at completion tells you which of the
following?
Marked out of 1.00
Select one:
a. 52
b. –52
c. –25
d. 25
Question 29 The best approach to resolve the settlement of all outstanding contract changes,
Not answered claims, and disputes is using—
b. Litigation
c. Mediation
Question 30 Your cost control specialist has developed a budget plan for your project to add a
Not answered second surgical center to the Children’s Hospital. As you analyze cash flow
requirements, you notice that cash flow activity is greatest in the closing phase. You
Marked out of 1.00
find this unusual because on most projects the largest portion of the budget spent
during—
Select one:
a. Monitoring and Controlling
b. Controlling
c. Initiating
d. Executing
c. Resource leveling
d. Crashing
The correct answer is: Scope, quality, schedule, budget, and risk
Question 34 Assume you have been working with your sponsor to prepare you charter, and you
Not answered plan to present it to your Steering Committee on Friday. You are managing a software
project, and the business need stated that you should use agile for the first time in our
Marked out of 1.00
company rather than waterfall. In the Develop Project Charter process, this is then—
Select one:
a. Stated in the strategic plan as a tool and technique in this process
d. A high-level requirement
Select one:
Marked out of 1.00
a. Constraints are considered true for planning purposes, and assumptions limit
the options of the project team.
b. Constraints restrict the actions of the project team, and assumptions are
considered true for planning purposes.
c. Constraints and assumptions are inputs to the Initiation process. They should
Hide sidebars
The correct answer is: Constraints restrict the actions of the project team, and
assumptions are considered true for planning purposes.
d. Deliverables
Question 37 Managing change to the scope baseline is the main objectiveof the process of control
Not answered scope. The scope baseline consists of the following components EXCEPT—
b. WBS
b. Risk
c. Procurement
d. Resource
Select one:
Marked out of 1.00
a. Project plans are put into action.
The correct answer is: Project plans are put into action.
Question 40 Project managers have the highest level of authority and the most power in which
Not answered type of organizational structure?
b. Strong matrix
c. Projectized
d. Balanced matrix
Select one:
a. Consensus
b. Coin flip
c. Command
d. Consultation
Question 42 Rank ordering of defects should be used to guide corrective action. This is the
Not answered underlying principle behind—
b. Pareto diagrams
c. Inspections
d. Control charts
Select one:
Marked out of 1.00
a. structured and independent
Question 44 The quality management plan describes all the following EXCEPT the—
Not answered
Select one:
Marked out of 1.00
a. Method for implementing the quality policy
The correct answer is: Procedures used to conduct trade-off analyses among cost,
schedule, and quality
Question 45 You are a project manager for Penguin Software. Your company creates custom
Not answered software programs for hospitals and large dental offices. You have just completed a
project and are gathering the documentation of the product of the project. This might
Marked out of 1.00
include all of the following except ___________________.
Select one:
a. technical specifications
c. electronic files
Question 46 The outputs of the Close Project process include all of the following except for which
Not answered one?
b. Formal acceptance
d. Lessons learned
b. Formal acceptance
Hide sidebars
Question 48 You are the project manager for a top-secret software project for an agency of the
Not answered United States government. Your mission—should you choose to accept it—is to
complete the project using internal resources. The reason is that getting top-secret
Marked out of 1.00
clearances for contractors takes quite a bit of time, and waiting for clearances would
jeopardize the implementation date. Your programmers are 80 percent of the way
through the programming and testing work when your agency appoints a new
executive director. Your programmers are siphoned off this project to work on the
executive director’s hot new project. Which of the following addresses the purpose of
Scope Verification in this case?
Select one:
a. Scope Verification determines whether the project results comply with quality
standards.
d. Scope Verification determines the correctness and completion of all the work.
The correct answer is: Scope Verification documents the level and degree of
completion.
Dashboard My courses
BL-IT4244-132671 - Quản trị dự án CNTT
General
Thi thử
State Finished
Marks 0.00/48.00
Question 1 Your company manufactures small kitchen appliances. It is introducing a new product
Not answered line of appliances in designer colors with distinctive features for kitchens in small
spaces. These new products will be offered indefinitely starting with the spring catalog
Marked out of 1.00
release. To determine the characteristics and features of the new product line, you will
have to perform which of the following?
Select one:
a. Progressive elaboration
b. Fast tracking
Question 2 You are a project manager who has recently held a project team kickoff meeting
Not answered where all the team members were formally introduced to each other. Some of the
team members know each other from other projects and have been working with you
Marked out of 1.00
for the past three weeks during the Planning processes. Which of the following
statements is true?
Select one:
a. Team building begins in the Planning process group. This team is in the
forming stage of team development.
b. Team building begins once all the members of the team are identified and
introduced to each other. This team is in the storming stage of team development.
c. Team building begins in the Planning process group. This team is in the
storming stage of team development.
d. Team building begins once all the members of the team are identified and
introduced to each other. This team is in the forming stage of team development.
The correct answer is: Team building begins in the Planning process group. This team
is in the forming stage of team development.
Question 3 The resource calendar is an output of which following process?
Not answered
Select one:
Marked out of 1.00
a. Manage project team
Question 4 As project manager, you are primarily responsible for implementing the project
Not answered management plan by authorizing the execution of project activities. Because you do
not work in a projectized organization, you do not have direct access to human
Marked out of 1.00
resource administrative activities. Therefore you need to—
Select one:
a. Ensure that your team is sufficiently aware of administrative requirements to
ensure compliance
b. Ask the head of human resources to approve your project human resource
plan personally
c. Prepare a project team charter that is signed off by a member of the human
resources department to delineate responsibilities
The correct answer is: Ensure that your team is sufficiently aware of administrative
requirements to ensure compliance
Question 5 In which of the following methods of resolving conflict will the conflict typically
Not answered reappear again in another form?
b. Smoothing
c. Confronting
d. Compromising
Question 7 Which of the following describes the cost of quality associated with scrapping, rework,
Not answered and downtime?
b. Prevention costs
d. Appraisal costs
Question 8 Four people are responsible for establishing cost of quality theories. Crosby and
Not answered Juran are two them, and their theories respectively are
Question 9 All the following statements are true about the grassroots estimate, EXCEPT—
Not answered
Select one:
Marked out of 1.00
a. It is used primarily for Level 1 of the WBS
The correct answer is: It is used primarily for Level 1 of the WBS
Question 10 Activity A has a duration of three days and begins on the morning of Monday the 4th.
Not answered The successor activity, B, has a finish-to-start relationship with A. The finish-to-start
The correct answer is: Calendar time between the start of A to the finish of B is 11
days
Question 11 You are the project manager for a custom home-building construction company. You
Not answered are working on the model home project for the upcoming Show Homes Tour. The
model home includes Internet connections in every room and talking appliances. You
Marked out of 1.00
are working on the cost budget for this project. All of the following statements are true
except which one?
Select one:
a. This process assigns cost estimates for expected future period operating costs.
c. This process assigns cost estimates to project activities, including risks and
contingency plans.
d. The cost baseline will be used to measure variances and future project
performance.
The correct answer is: The cost baseline will be used to measure variances and
future project performance.
The correct answer is: Review scenarios to bring the schedule in line with the plan
Question 13 If a project planner imposes a finish time of 14 on the project with no change in the
Not answered start date or activity durations, what is the total float of Activity E?
Select one:
a. 0
b. 2
c. Cannot be determined
d. –1
Question 14 After brainstorming potential project risks, what is the recommended method for
Not answered prioritizing these risks and their mitigation plans?
c. Control chart
d. RACI chart
b. The probability and impact matrix multiplies the risk’s probability by the cost of
the impact to determine an expected value of the risk event.
Hide sidebars
c. The probability and impact matrix multiplies the risk’s probability—which fall
from 0.0 to 1.0—and the risk’s impact and then adds them together to determine a
risk score.
d. The probability and impact matrix multiplies the risk’s probability by the
expected value of the risk event to determine a risk score based on a
predetermined threshold.
The correct answer is: The probability and impact matrix multiplies the risk’s
probability—which fall from 0.0 to 1.0—and the risk’s impact and then adds them
together to determine a risk score.
Question 17 You’ve identified a risk event on your current project that could save $500,000 in
Not answered project costs if it occurs. Your organization is considering hiring a consulting firm to
help establish proper project management techniques in order to assure it realizes
Marked out of 1.00
these savings. Which of the following is true based on this statement? (Choose the
best answer.)
Select one:
a. This risk event is an opportunity to the project and should be exploited.
c. This is a risk event that should be accepted, because the rewards outweigh the
threat to the project.
d. This a risk event that should be shared to take full advantage of the potential
savings.
The correct answer is: This risk event is an opportunity to the project and should be
exploited.
Question 18 You are the project manager for an outdoor concert event scheduled for one year
Not answered from today. You’re working on the procurement plan for the computer software
program that will control the lighting and screen projections during the concert. You’ve
Marked out of 1.00
decided to contract with a professional services company that specializes in writing
custom software programs. You want to minimize the risk to the organization, so you’ll
opt for which contract type?
Select one:
a. Cost plus fixed fee
c. Fixed price
c. The staffing management plan created in this process describes how and when
Hide sidebars
d. A RAM (or RACI chart) is an output of this process that allows you to see all
the people assigned to an activity.
The correct answer is: One of the Human Resource Planning outputs includes project
organization charts that show the project’s reporting relationships.
Question 20 You are the project manager in your organization. You have very little authority over
Not answered the projects you manage, and you are mainly engaged in project coordination
activities. You are currently struggling with obtaining the required human resources for
Marked out of 1.00
your project during the Acquire Project Team process. Who you need to negotiate
with to obtain these resources?
Select one:
a. The customer
Question 21 If you are requesting a vendor quote for a defined scope, what is the recommended
Not answered contract type?
b. Cost reimbursable
d. Commission
question later.
b. Thank them, and decline. Explain that this is considered personal gain, which
is unacceptable in your country.
c. Thank them, and decline. Explain that this is considered a conflict of interest,
which is unacceptable in your country.
d. Thank them, and accept. You don’t believe there is a conflict of interest or an
integrity issue at stake.
The correct answer is: Thank them, and accept. You don’t believe there is a conflict of
interest or an integrity issue at stake.
Question 23 Your project has been under way for some time, but indicators show that it is in
Not answered trouble. You have observed all the following symptoms of poor teamwork in your
project team EXCEPT—
Marked out of 1.00
Select one:
a. Lack of trust or confidence in the project manager
b. Unproductive meetings
c. Frustration
d. Excessive meetings
The correct answer is: Ensuring the information needs of stakeholders are met
Question 25 Contested changes are requested changes when the buyer and seller cannot agree
Not answered on compensation for the change. They are also known as all but which one of the
b. Appeals
c. Disputes
Hide sidebars
d. Demands
Question 26 Assume that you are a major subcontractor doing work for a prime contractor on a
Not answered major project. Your change control system should—
Question 27 Which of the following is not an activity of configuration management during the
Not answered Integrated Change Control process?
b. Verification
c. Status accounting
d. Auditing
Question 28 If you apply the configuration management system along with change control
Not answered processes project wide, you will achieve all but one of the which following objectives?
The correct answer is: Document the specific responsibilities of each stakeholder in
the perform integrated change control process