PLN Enjiniring Contractor PLTMG BIAK
Consortium PT. WIKA (Persero) - WRK
Disetujui:
PT. PLN (Persero)
UPP Papua
JOHANES ARI
PIC Proyek PLTMG Biak 15 MW
Project Name GAS ENGINE POWER PLANT BIAK 15 MW
PT PLN (PERSERO) Contract No 0177.PJ/DAN.02.01/DIR/2017 Tanggal 18 Mei 2017
EPC Contractor KSO PT. WIKA (Persero) & WRK
UNIT INDUK PEMBANGUNAN MALUKU DAN PAPUA Cliect PT. PLN (Persero)
Contract Price IDR Rp 296.261.251.905
PLTMG BIAK 15 MW Contract Price DOLLAR
Document No.
MONTHLY PROGRESS REPORT Period Jan-23
Date 26 Dec 22 - 25 Jan 23
PLTMG BIAK 15 MW Total Sheet 3
I ENGINEERING (Detail Design) 1,203% 94,365% 1,135% 5,011% 0,060% 100,000% 1,203%
A CIVIL Lot 1 0,481% 94,591% 0,452% 5,409% 0,026% 100,000% 0,481%
B MECHANICAL Ls 1 0,361% 95,508% 0,342% 4,492% 0,016% 100,000% 0,361%
C ELECTRICAL Ls 1 0,241% 95,000% 0,227% 5,000% 0,012% 100,000% 0,241%
D INSTRUMENT & CONTROL Ls 1 0,120% 95,000% 0,114% 5,000% 0,006% 100,000% 0,120%
II.4 MARINE FREIGHT & INSURANCE 2,743% 100,000% 2,743% 0,000% 0,000% 100,000% 2,743%
A POWER GENERATION UNIT Ls 1 2,382% 100,000% 2,382% 0,000% 0,000% 100,000% 2,382%
B LUBE OIL SUPPLY &DRAIN SYSTEM Ls 1 0,192% 100,000% 0,192% 0,000% 0,000% 100,000% 0,192%
C EQUIPMENT COOLING WATER MAKE UP SYSTEM Ls 1 0,168% 100,000% 0,168% 0,000% 0,000% 100,000% 0,168%
II.5 INLAND TRANPORT 3,180% 99,391% 3,160% 0,609% 0,019% 100,000% 3,180%
A MECHANICAL Ls 1 2,049% 99,055% 2,030% 0,945% 0,019% 100,000% 2,049%
B ELECTRICAL Ls 1 0,762% 100,000% 0,762% 0,000% 0,000% 100,000% 0,762%
C INSTRUMENT Ls 1 0,369% 100,000% 0,369% 0,000% 0,000% 100,000% 0,369%
Page 1 of 4
PREV MONTH THIS MONTH UP TO THIS MONTH
NO DESCRIPTION UNIT QTY WF
PROGRESS WF PROGRESS WF PROGRESS WF
III.3 ELECTRICAL
A COMPLETE GENERATOR AND MAIN OUTPUT SYSTEM Ls 1 0,093% 100,000% 0,093% 0,000% 0,000% 100,000% 0,093%
B COMPLETE PLANT ELECTRICAL EQUIPMENT Ls 1 1,139% 100,000% 1,139% 0,000% 0,000% 100,000% 1,139%
C COMPLETE POWER TRANSFORMER Ls 1 0,099% 100,000% 0,099% 0,000% 0,000% 100,000% 0,099%
D 20 Kv SWITCHGEAR Ls 1 0,022% 100,000% 0,022% 0,000% 0,000% 100,000% 0,022%
B THE CUBICLE AND ACCESSORIES, I/O MODULES Ls 1 0,005% 100,000% 0,005% 0,000% 0,000% 100,000% 0,005%
C POWER PLANT OPERATION CONTROL DESKS Ls 1 0,010% 100,000% 0,010% 0,000% 0,000% 100,000% 0,010%
D SUPERVISORY AND PLANT MANAGEMENT SYSTEM Ls 1 0,016% 100,000% 0,016% 0,000% 0,000% 100,000% 0,016%
Page 2 of 4
PREV MONTH THIS MONTH UP TO THIS MONTH
NO DESCRIPTION UNIT QTY WF
PROGRESS WF PROGRESS WF PROGRESS WF
E DIAGNOSTIC SOFTWARE Ls 1 0,010% 100,000% 0,010% 0,000% 0,000% 100,000% 0,010%
F INSTRUMENT VALVE Ls 1 0,018% 90,000% 0,016% 10,000% 0,002% 100,000% 0,018%
G FIELD INSTRUMENTS Ls 1 0,049% 90,000% 0,044% 10,000% 0,005% 100,000% 0,049%
INSTRUMENT CABLE, CABLE TRAY, JUNCTION BOX, GLAND,
H
AND ACCESSORIES
Ls 1 0,090% 100,000% 0,090% 0,000% 0,000% 100,000% 0,090%
III.7 COMMISSIONING
A FIRST FIRING Ls 1 0,037% 100,000% 0,037% 0,000% 0,000% 100,000% 0,037%
B LOAD TEST Ls 1 0,037% 100,000% 0,037% 0,000% 0,000% 100,000% 0,037%
C LOAD REJECTION Ls 1 0,037% 100,000% 0,037% 0,000% 0,000% 100,000% 0,037%
D RELIABILITY RUN Ls 1 0,037% 100,000% 0,037% 0,000% 0,000% 100,000% 0,037%
E PERFORMANCE TEST Ls 1 0,018% 100,000% 0,018% 0,000% 0,000% 100,000% 0,018%
F ENVIRONMENTAL MEASUREMENT Ls 1 0,018% 100,000% 0,018% 0,000% 0,000% 100,000% 0,018%
Diperiksa: Dibuat:
PLN Enjiniring Contractor PLTMG BIAK
Consortium PT. WIKA (Persero) - WRK
OCTAVIANUS Disetujui:
RIBUT BUDYANTO
Supervisi Konstruksi PLTMG PT. PLN (Persero)
Project Manager PLTMG Biak 15 MW
UPP Papua
Page 3 of 4
PREV MONTH THIS MONTH UP TO THIS MONTH
NO DESCRIPTION UNIT QTY WF
OCTAVIANUS PROGRESS WF PROGRESS WF PROGRESS
RIBUT BUDYANTO WF
Supervisi Konstruksi PLTMG PT. PLN (Persero)
Project Manager PLTMG Biak 15 MW
Biak 15 MW UPP Papua
JOHANES ARI
PIC Proyek
PLTMG BIAK 15 MW
Page 4 of 4