NO DESCRIPTION SEPTEMBER OKTOBER NOVEMBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 PREPARATION

2 CIVIL WORKS

- Removal Existing Wall Partition & Plafond 1st & 2nd Floor

- Removal Existing Tile Floor 1st & 2nd Floor

- Repair Leaking Roof

- Install New Tile Floor & Toilet 1st & 2nd Floor

- Brick Wall ( ALC Block ) 1st Floor

- Install New Wall Partition 1st & 2nd Floor

- Install New Plafond 1st & 2nd Floor


Fabrication at Workshop Install & Setting
- New Door & Window

- Emulsion Paint for Wall & Plafond


Fabrication at Workshop Install & Setting
- Interior ( Backdrop Wall, Cashier Table, Café Table, Mirror etc. )

3 MECHANICAL & ELECTRICAL WORKS

- Wiring Device Installation 1st & 2nd Floor


Wiring Installation Install Unit
- Panel, Cable Tray, Receptacle & Lighting Fixture
Wiring Installation Install Unit
- Public Addres
Wiring Installation Install Unit
- LAN & Telephone
Wiring Installation Install Unit
- CCTV & MATV
Wiring Installation Install Unit
- Fire Alarm
Wiring Installation
- AC
Setting Pipe Installation
- Water Supply & Drainage

- Install Wastafel & Accessories


Removal Unit AC Reinstall Unit AC Install Unit
- Removal, Repair & Reinstall AC Existing, Install New AC

4 REPAIRING & REPAINTING EXTERIOR WALL

5 TEST COMMISIONING & HAND OVER