Professional Documents
Culture Documents
Solar Project Poster
Solar Project Poster
• Yemen’s electricity is less than 50% of the minimum demand. PV Panel - Trina Solar TSM-DEG14(II)
• Junction box – connection with The 3-phase output of 7 units
Configuration A and 1 unit of Configuration B
• The solar technical potential is 2000 TWh/Year, and if only %1 • One of the top ten brands which ensure the product quality
• 3-phase transformer - 440V/33kV with capacity of 6.2 MVA
of that potential would supply double Yemen’s minimum • One of the most common existing brands in Yemen
demand. Figure 5. Location of the site and 33kV substation
(RCREEE, 2017)
• The World Bank is funding this proposed solar project (72,600 • Resistant to sand - Double glass frame
Technical Specification for Trina
m2) in a rural area at Ad-Dali (fed to 33KV to surrounding Table 1. Technical Specification
Solar TSM-DEG14(II) for TSM-DEG14(II)
governorates). Test Condition STC NOCT
Power Output (W) 375 279
Module Efficiency (%) 19.1
Vmp (V) 40 37.1
SOLAR MARKET STATUS Imp (A) 9.39 7.54
Figure 1. Electricity generation by fuel in Yemen (IEA, 2019) Voc (V) 47.5 44.1
Isc (A) 9.71 7.84
ECONOMIC ANALYSIS
Figure 2. Assessment of
• Total Capital cost : £ 10,151,763.22
Yemen’s progress in Figure 6. Capital Cost Structure
renewable energy
according to the 4
evaluation categories:
Market Structure, Policy • Non-tracking system
Framework, Finance and
Investment, and - The largest total power rating and annual energy production
Institutional Capacity. in comparison with tracking systems [See Table 2]
(RCREEE, 2016)
Inverter - SMA Sunny Central 720CP Grid Tied Inverter
Economic Incentives
• Centralized
• Yemen lacks the policies needed to incentivize the
• All values of each configurations are fulfilling the inverter
population to promote huge solar energy deployment. Annual Energy Production [kWh] 13,432,225
requirements [See Table 3]
• The current incentive is driven by the severe energy Table 3. Status of each configuration for Inverter Input
Electricity Tariff (LCOE of Diesel Generator) [£/kWh] £ 0.277
Annual Income (tariff x energy) £ 3,725,594.32
poverty under the absence of adequate quantities of gas Inverter Configuration Configuration
Inverter SC 720CP XT
Limitation A B • Result: £ IRR of 32%, NPV of £8,002,107.26, and payback
and oil due to the political instability in Yemen
Max. DC Power [kW] 808 821.25 897.75 period of 4.81 years
Min. DC Voltage [V] 485 522 626 Table 4. Discounted Cash Flow
Economic & Social
Typical PV Voltage [V] 545 654
Impact of Solar Reduce
• Air-pollution Max. DC Voltage (Inverter) [V] 1000 753 904
Energy Expansion in
• Black-outs & fire accidents Max. Operating Input Current per MPPT [A] 1400 1368 1246.2
Yemen • Poverty
• Sanitary system pollution (pumps)
Max. Input Short-circuit Current per MPPT [A] 2500 1442.5 1314
References
• IEA, 2019. The International Energy Agency. [Online] Available at:
Similar Projects https://www.iea.org/countries/Yemen/
• PERCENT, 2018. HALF OF YEMENIS HAVE SOLAR PANELS. [Online] Available at:
http://www.percentyemen.org/ [Accessed 13 March 2019].
All the currently available solar capacity is for small scale off- • RCREEE, 2016. The Arab Future Energy Index , Cairo: Regional Center for
grid projects, this report is for a first-of-its-kind project in Yemen Renewable Energy and Energy Efficiency.
to supply to the grid, making this report of a great interest to • RCREEE, 2017. Assessment of the status of solar PV in Yemen , Cairo: The Regional
Center for Renewable Energy and Energy Efficiency.
the government as well as future investors in the country.
University of Edinburgh
School of Engineering
2019