Professional Documents
Culture Documents
CSI-Format
CSI-Format
2
ELEMENTAL COST SUMMARY
SQM
Elemental Amount
Element Ratio to GFA Quantity Unit Unit Rate, Php
A Substructure
A1010 Standard Foundations 0.331893166 67.6 lm 4,500.00
A1020 Column Foundations 0.063825609 13 No. 4,500.00
A1030 Slab-on-Grade 0.786527887 160.2 sqm 3,500.00
B Shell
B1010 Floor Construction 1 203.68 sqm 600.00
B1020 Roof Construction 0.547918303 111.6 sqm 900.00
B2010 Exterior Walls 1.048409269 213.54 sqm 2,600.00
B2020 Exterior Windows 0.204732914 41.7 sqm 2,950.00
B2030 Exterior Doors 0.059799686 12.18 sqm 2,400.00
B3010 Roof Covering 0.547918303 111.6 sqm 600.00
C Interior
C1011 Fixed Partitions 0.435192459 88.64 sqm 1,900.00
C1020 Interior Doors 0.034367636 7 No. 2,100.00
C2010 Stair Construction 0.078554595 16 Flt 5,000.00
C3010 Wall Finishes 1.505793401 306.7 sqm 300.00
C3020 Floor Finishes 0.785545954 160 sqm 240.00
C3030 Ceiling Finishes 0.943686174 192.21 sqm
D Services
D2010 Plumbing and Drainage 0.065543991 13.35 sqm 3,200.00
D3030 HVAC 0 0 sqm
D50 Electrical Systems
D5010 Service and Distribution 0.785545954 160 sqm 350.00
D5020 Lighting, Devices, & Heating 0.785545954 160 sqm 700.00
E Equipment and Furnishings
E2010 Fixed Casework 0.058915947 12 lm 3,600.00
F Special Construction
F1030 Special Construction Systems 0 sqm
G Building Sitework
G1030 Demolition 0 sqm
G2010 Rough Grading 0.736449332 150 sqm 100.00
G2012 Asphalt Paving 0 sqm
G1050 Landscaping 0.13256088 27 sqm 1,450.00
Z General
Z1010 General Conditions 0.786527887 160.2 sqm 150.00
Z1050 Fee 0.786527887 160.2 sqm 100.00
Z20 Contingencies
Z2010 Design Contingency 1 lot 100,000.00
Z2020 Escalation Contingency 1 lot 20,000.00
Z2030 Construction Contingency 1 lot 35,000.00
Gross Floor Area (GFA), SQM 203.68 Total Cost
Report Date:
COST SUMMARY Proj. Ref:
Sheet No.:
Elemental Amount Rate per SQM, %
Subtotal Total Subtotal Total
923,400.00 32.77833095
304,200.00 10.79832
58,500.00 2.0766
560,700.00 19.90341
997,059.00 35.39303647
122,208.00 4.33807
100,440.00 3.565362
555,204.00 19.70832
123,015.00 4.366717
29,232.00 1.037661
66,960.00 2.376908
393,526.00 13.96916338
168,416.00 5.978336
14,700.00 0.521812
80,000.00 2.839795
92,010.00 3.266119
38,400.00 1.363101
- 0
42,720.00 1.516450399
42,720.00 1.51645
- 0
168,000.00 5.963568983
56,000.00 1.987856
112,000.00 3.975713
43,200.00 1.533489167
43,200.00 1.533489
- 0
- 0
54,150.00 1.922186074
- 0
15,000.00 0.532462
- 0
39,150.00 1.389725
40,050.00 1.421672249
24,030.00 0.853003
16,020.00 0.568669
155000 5.502102336
100,000.00 3.549743
20,000.00 0.709949
35,000.00 1.24241
Total Cost 2,817,105.00 100
MATERIALS DESCRIPTION UNIT QTY PRICE MATERIALS LABOR TOTAL AMOUNT
AMOUNT AMOUNT
1.0 EARTHWORKS
Layout/staking
2x3 Coco Lumber pcs 80 220.00 17,600.00 1,760.00 19,360.00
CWN 4 kgs 6 120.00 720.00 72.00 792.00
Tansi rolls 6 50.00 300.00 30.00 330.00
18,620.00 1,862.00 20,482.00
Excavation Column/Footing
51.84 cu.m Bareta pcs 4 650.00 2,600.00 20,736.00 23,336.00
24 col Pala pcs 4 650.00 2,600.00 2,600.00
5,200.00 20,736.00 25,936.00
Excavation FTB
26.166 cu.m - 10,466.40 10,466.40
174.44 m - -
- 10,466.40 10,466.40
Excavation Septic Tank
5.40 cu.m - 2,160.00 2,160.00
- -
- 2,160.00 2,160.00
Backfill and Compaction
121.92 cu.m Escombro cu.m 121.92 300.00 36,576.00 18,288.00 54,864.00
36,576.00 18,288.00 54,864.00
Soil Poisoning
304.8 sq.m Soil Guard liters 5 1,200.00 6,000.00 900.00 6,900.00
6,000.00 900.00 6,900.00
Gravel Bedding
15.24 cu.m 3/4 Gravel cu.m 15.24 1,950.00 29,718.00 1,219.20 30,937.20
Kartilya pcs 3 3,000.00 9,000.00 9,000.00
38,718.00 1,219.20 39,937.20
TOTAL EARTHWORKS 160,745.60
LABOR COST 55,631.60 52.93%
MATERIALS COST 105,114.00
2.0 CONCRETE WORKS
Column/Footing -
24 col 10.368 cu.m Cement bags 83 300.00 24,883.20 6,594.05 31,477.25
13.824 hrs Sand cu.m 8.957952 1,200.00 10,749.54 2,848.63 13,598.17
3/4 Gravel cu.m 11.19744 2,350.00 26,313.98 6,973.21 33,287.19
Gasoline liters 14 60.00 829.44 219.80 1,049.24
62,776.17 16,635.68 79,411.85
Footing Tie Beam
Perimeter 174.44 Cement bags 112 300.00 33,492.48 8,373.12 41,865.60
VOLUME 13.9552 Sand cu.m 12.05729 1,200.00 14,468.75 3,617.19 18,085.94
18.61 hrs 3/4 Gravel cu.m 15.07162 2,350.00 35,418.30 8,854.57 44,272.87
Gasoline liters 18.61 60.00 1,116.42 279.10 1,395.52
84,495.94 21,123.99 105,619.93
Slab-On-Grade Cement bags 244 300.00 73,152.00 18,288.00 91,440.00
AREA 304.8 Sand cu.m 26.33472 1,200.00 31,601.66 7,900.42 39,502.08
VOLUME 30.48 3/4 Gravel cu.m 32.9184 2,350.00 77,358.24 19,339.56 96,697.80
40.6 hrs Gasoline liters 40.6 60.00 2,438.40 609.60 3,048.00
184,550.30 46,137.58 230,687.88
Columns
Height 4.6 110.4 Cement bags 70.656 300.00 21,196.80 5,299.20 26,496.00
Sand cu.m 7.630848 1,200.00 9,157.02 2,289.25 11,446.27
110.4 3/4 Gravel cu.m 9.53856 2,350.00 22,415.62 5,603.90 28,019.52
Volume 8.832 Gasoline liters 11.8 60.00 706.56 176.64 883.20
11.8 hrs -
53,475.99 13,369.00 66,844.99
Second Floor Beams -
Perimeter Cement bags 0.00 300.00 - - -
200x400 Sand cu.m 0 1,200.00 - - -
Volume 0 3/4 Gravel cu.m 0 2,350.00 - - -
0.0 hrs Gasoline liters 0.0 60.00 - - -
- - -
Roof Beam
Perimeter 172.575 Cement bags 51.77 300.00 15,531.75 5,436.11 20,967.86
150x250 Sand cu.m 5.59143 1,200.00 6,709.72 2,348.40 9,058.12
Volume 6.4715625 3/4 Gravel cu.m 6.989288 2,350.00 16,424.83 5,748.69 22,173.51
8.62875 hrs Gasoline liters 8.62875 60.00 517.73 181.20 698.93
39,184.02 13,714.41 52,898.42
Second Floor Slab
Area Cement bags 0 300.00 - - -
Volume Sand cu.m 0 1,200.00 - - -
3/4 Gravel cu.m 0 2,350.00 - - -
0 hrs Gasoline liters 6 60.00 360.00 126.00 486.00
360.00 126.00 486.00
Stairs
Volume Cement bags 300.00 - - -
Sand cu.m 1,200.00 - - -
3/4 Gravel cu.m 2,350.00 - - -
0 hrs Gasoline liters 60.00 - - -
- - -
Canopy
Volume 4.08375 Cement bags 33.67 300.00 10,101.00 4,040.40 14,141.40
4.08375 Sand cu.m 3.63636 1,200.00 4,363.63 1,745.45 6,109.08
3/4 Gravel cu.m 4.54545 2,350.00 10,681.81 4,272.72 14,954.53
Gasoline liters 60.00 - - -
25,146.44 10,058.58 35,205.02
Kitchen Counters
Volume 0.6 Cement bags 4.8 300.00 1,440.00 504.00 1,944.00
0.6 Sand cu.m 0.5184 1,200.00 622.08 217.73 839.81
3/4 Gravel cu.m 0.648 2,350.00 1,522.80 532.98 2,055.78
Gasoline liters 0.6 60.00 36.00 12.60 48.60
3,620.88 1,267.31 4,888.19
TOTAL CONCRETE WORKS 576,042.28
LABOR COST 122,432.53 26.99%
MATERIALS COST 453,609.75
3.0 FORM WORKS
FTB 3/8 Formply pcs 36.34167 800.00 29,073.33 5,814.67 34,888.00
Perimeter 174.44 2x3x10 CCL pcs 228.7738 300.00 68,632.13 13,726.43 82,358.56
200x400 CWN 1 1/2 kgs 3 150.00 450.00 90.00 540.00
10LM/hr 17.444 hrs CWN 3 kgs 3 120.00 360.00 72.00 432.00
98,515.46 19,703.09 118,218.56
Columns 3/8 Formply pcs 29.61 800.00 23,688.00 5,211.36 28,899.36
Height 4.7 67.68 2x3x10 CCL pcs 110.9508 300.00 33,285.25 7,322.75 40,608.00
200x400 CWN 1 1/2 kgs 5 150.00 750.00 165.00 915.00
24 sets 67.68 CWN 3 kgs 7 120.00 840.00 184.80 1,024.80
58,563.25 12,883.91 71,447.16
Second Floor Beams 3/8 Formply pcs 0 800.00 - - -
Perimeter 2x3x10 CCL pcs 0 300.00 - - -
200x400 Scaff 2x3x10 CCL pcs 0 300.00 - - -
CWN 1 1/2 kgs 150.00 - - -
CWN 3 kgs 120.00 - - -
CWN 4 kgs 120.00 - - -
- - -
Roof Beam
Perimeter 172.575 3/8 Formply pcs 75.50156 800.00 60,401.25 15,100.31 75,501.56
150x250 2x3x10 CCL pcs 226.3279 300.00 67,898.36 16,974.59 84,872.95
Scaff 86.2875 2x3x10 CCL pcs 258.8625 300.00 77,658.75 19,414.69 97,073.44
5LM/hr 51.7725 CWN 1 1/2 kgs 2 150.00 300.00 75.00 375.00
Scaff CWN 3 kgs 2 120.00 240.00 60.00 300.00
Concrete Nail 3 kgs 3 180.00 540.00 135.00 675.00
207,038.36 51,759.59 258,797.95
SecondFloor Slab
Area 3/8 Formply pcs 0 800.00 - - -
2x3x10 CCL pcs 0 300.00 - - -
CWN 1 1/2 kgs 150.00 - - -
CWN 3 kgs 120.00 - - -
Concrete Nail 3 kgs 120.00 - - -
- - -
Stairs
3/8 Formply pcs 800.00 - - -
2x3x10 CCL pcs 300.00 - - -
CWN 1 1/2 kgs 150.00 - - -
CWN 3 kgs 120.00 - - -
Concrete Nail 3 kgs 120.00 - - -
- - -
Concrete Ledge Canopy
3/8 Formply pcs 10 800.00 8,000.00 3,200.00 11,200.00
2x3x10 CCL pcs 60 300.00 18,000.00 7,200.00 25,200.00
CWN 1 1/2 kgs 2 150.00 300.00 120.00 420.00
CWN 3 kgs 2 120.00 240.00 96.00 336.00
Concrete Nail 3 kgs 2 120.00 240.00 96.00 336.00
26,780.00 10,712.00 37,492.00
Kitchen Counters
Area 4.06 3/8 Formply pcs 3 800.00 2,400.00 720.00 3,120.00
2x3x10 CCL pcs 10 300.00 3,000.00 900.00 3,900.00
CWN 1 1/2 kgs 2 150.00 300.00 90.00 390.00
CWN 3 kgs 1 120.00 120.00 36.00 156.00
Concrete Nail 3 kgs 1 120.00 120.00 36.00 156.00
5,940.00 1,782.00 9,504.00
TOTAL FORM WORKS 495,459.67
LABOR COST 96,840.60 24.40%
MATERIALS COST 396,837.07
4.0 REINFORCING BARS
Footing
24 1.20m x 1.20m W=9.468 kgs 16mm x 6.0 gr.33 pcs 68.2 420.00 28,644.00 5,728.80 34,372.80
Total wt 645.7176 W=5.328 kgs 12mm x 6.0 gr.33 pcs 350.00 - - -
W=3.696 kgs 10mm x 6.0 gr.33 pcs 220.00 - - -
work time 34.1 W=3.50 kgs 9mm x 6.0 gr.33 pcs 180.00 - - -
W= 25 kgs GI Tie Wire #16 kgs 16.14294 100.00 1,614.29 322.86 1,937.15
Hacksaw Blade pcs 13.64 90.00 1,227.60 245.52 1,473.12
31,485.89 6,297.18 37,783.07
Column
15 16mm x 6.0 gr.33 pcs 132 420.00 55,440.00 11,088.00 66,528.00
Height 4.7 112.8 12mm x 6.0 gr.33 pcs 2 350.00 700.00 140.00 840.00
10mm x 6.0 gr.33 pcs 127.3333 220.00 28,013.33 5,602.67 33,616.00
112.8 9mm x 6.0 gr.33 pcs 180.00 - - -
Total wt 1731.056 GI Tie Wire #16 kgs 32.5108 100.00 3,251.08 650.22 3,901.30
work time 39.35649327 Hacksaw Blade pcs 26.8 90.00 2,412.00 482.40 2,894.40
89,816.41 17,963.28 107,779.70
SOG
Area 304.8 16mm x 6.0 gr.33 pcs 420.00 - - -
Pieces/m² 0.962 12mm x 6.0 gr.33 pcs 350.00 - - -
Total wt 1171.040333 10mm x 6.0 gr.33 pcs 316.8399 220.00 69,704.78 10,455.72 80,160.50
work time 10.56133056 9mm x 6.0 gr.33 pcs 180.00 - - -
GI Tie Wire #16 kgs 29.27601 100.00 2,927.60 439.14 3,366.74
Hacksaw Blade pcs 31.68399 90.00 2,851.56 427.73 3,279.29
75,483.94 11,322.59 86,806.53
2nd Floor Slab
Area 16mm x 6.0 gr.33 pcs 420.00 - - -
12mm x 6.0 gr.33 pcs 350.00 - - -
10mm x 6.0 gr.33 pcs 220.00 - - -
9mm x 6.0 gr.33 pcs 180.00 - - -
GI Tie Wire #16 kgs 100.00 - - -
Hacksaw Blade pcs 90.00 - - -
- - -
2F Beam
Perimeter 16mm x 6.0 gr.33 pcs 0 420.00 - - -
200x400 12mm x 6.0 gr.33 pcs 0 350.00 - - -
10mm x 6.0 gr.33 pcs 220.00 - - -
9mm x 6.0 gr.33 pcs 0 180.00 - - -
GI Tie Wire #16 kgs 0 100.00 - - -
Hacksaw Blade pcs 0 90.00 - - -
- - -
Roof Beam
Perimeter 172.575 16mm x 6.0 gr.33 pcs 420.00 - - -
150x250 12mm x 6.0 gr.33 pcs 350.00 - - -
Total wt 1404.5304 10mm x 6.0 gr.33 pcs 380.0136 220.00 83,603.00 20,900.75 104,503.75
work time 21.11186869 9mm x 6.0 gr.33 pcs 180.00 - - -
GI Tie Wire #16 kgs 35.11326 100.00 3,511.33 877.83 4,389.16
Hacksaw Blade pcs 38.00136 90.00 3,420.12 855.03 4,275.15
90,534.45 22,633.61 113,168.06
Stairs 16mm x 6.0 gr.33 pcs 420.00 - - -
12mm x 6.0 gr.33 pcs 350.00 - - -
10mm x 6.0 gr.33 pcs 220.00 - - -
9mm x 6.0 gr.33 pcs 180.00 - - -
GI Tie Wire #16 kgs 100.00 - - -
Hacksaw Blade pcs 90.00 - - -
- - -
CHB Wall
Firewall 10mm x 6.0 gr.33 pcs 160.9273 220.00 35,404.00 7,080.80 42,484.80
GF-Wall 132.765 m 10mm x 6.0 gr.33 pcs 140.8114 220.00 30,978.50 6,195.70 37,174.20
2F-Wall 25.02 10mm x 6.0 gr.33 pcs 39.42545 220.00 8,673.60 1,734.72 10,408.32
Aw(gf) 23.28 m² 9mm x 6.0 gr.33 pcs 180.00 - - -
Ad(gf) 32.13 m² GI Tie Wire #16 kgs 31.52356 100.00 3,152.36 630.47 3,782.83
Aw(2f) Hacksaw Blade pcs 34.11641 90.00 3,070.48 614.10 3,684.57
Ad(2f) -
81,278.93 16,255.79 97,534.72
Ledge, S.Tank and
Kit. Countertop 10mm x 6.0 gr.33 pcs 6.363636 220.00 1,400.00 350.00 1,750.00
Ledge 0.30 x 2 10mm x 6.0 gr.33 pcs 9.090909 220.00 2,000.00 500.00 2,500.00
S.Tank 1.5x2.40 10mm x 6.0 gr.33 pcs 4.181818 220.00 920.00 230.00 1,150.00
Countertop 0.60x4.0 9mm x 6.0 gr.33 pcs 180.00 - - -
GI Tie Wire #16 kgs 0.490909 100.00 49.09 12.27 61.36
Hacksaw Blade pcs 1.963636 90.00 176.73 44.18 220.91
4,545.82 1,136.45 5,682.27
16mm TOTAL RSB WORKS 448,754.36
12mm LABOR COST 75,608.91 20.26%
10mm MATERIALS COST 373,145.45
9mm
5. STEEL TRUSSES AND ROOFING, TERRACE,STAIR GRILLS
Area 411.36 2x6x1.20mm pcs 112.2667 950.00 106,653.33 31,996.00 138,649.33
Perimeter 99 2x3x1.20mm pcs 165.9 650.00 107,835.00 32,350.50 140,185.50
278.88 10mm x 6 pcs 25 200.00 5,000.00 1,500.00 6,500.00
Days 20.568 Welding Rod kgs 50 160.00 8,000.00 2,400.00 10,400.00
4x4 Tubular pcs 4 3,500.00 14,000.00 2,800.00 16,800.00
1x2 Tubularr pcs 490.00 - - -
2x2 tubular pcs 680.00 - - -
Grinding Disk pcs 30 150.00 4,500.00 900.00 5,400.00
Cutting Disk pcs 30 150.00 4,500.00 900.00 5,400.00
Cut-Off Disk 14 pcs 5 900.00 4,500.00 900.00 5,400.00
Red Oxide gal 15 560.00 8,400.00 1,680.00 10,080.00
P.Brush 2 pcs 15 80.00 1,200.00 240.00 1,440.00
Paint Thinner pcs 8 390.00 3,120.00 624.00 3,744.00
Ga.24 Roof LM 500 700.00 350,000.00 70,000.00 420,000.00
Ridge Roll pcs 45 550.00 24,750.00 4,950.00 29,700.00
Valley gutter 36" S/S pcs 18 3,200.00 57,600.00 11,520.00 69,120.00
Wall Flashing pcs 500.00 - - -
Outside Gutter 36" pcs 48 750.00 36,000.00 7,200.00 43,200.00
Tekscrew pcs 2600 8.00 20,800.00 4,160.00 24,960.00
TUP cans 5 450.00 2,250.00 450.00 2,700.00
Blind Rivets box 15 660.00 9,900.00 1,980.00 11,880.00
769,008.33 176,550.50 945,558.83
TOTAL TRUSSES AND ROOFING WORKS 945,558.83
LABOR COST 176,550.50 22.96%
MATERIALS COST 769,008.33
6. PLUMBING WORKS
Labor 6
1 cu.m/man-day 4.361 days
Labor 2
1 cu.m/man-day 2.7 days
Foreman 600 0 0 8 0
Leadman 1 530 530 66.25 8 530
Mason/Carpenter 2 500 1000 125 8 1000
Labor 2 350 700 87.5 8 700
2,230.00
Foreman 600 0 0 0
Leadman 1 530 530 66.25 24 1590
Mason/Carpenter 2 500 1000 125 24 3000
Labor 2 350 700 87.5 24 2100
6,690.00
Foreman 600 0 0 0
Leadman 530 0 0 0
Mason/Carpenter 1 500 500 62.5 8 500
Labor 2 350 700 87.5 8 700
1,200.00
Foreman 600 0 0 0
Leadman 530 0 0 0
Mason/Steelman 1 500 500 62.5 34.1 2131.25
Labor 2 350 700 87.5 34.1 2983.75
5,115.00
Foreman 600 0 0 0
Leadman 530 0 0 0
Mason/Steelman 2 500 1000 125 39.35649 4919.561658785
Labor 3 350 1050 131.25 39.35649 5165.5397417243
10,085.10
60,000.00
601,560.00
349,933.50