Professional Documents
Culture Documents
ABSTRACT
This paper discusses the background of the transition to modern asset management. The Corrective, Period
Based, Condition Based and Risk Based maintenance styles are discussed with the circumstances where these are
applicable. Redundancy plays an important role in grids to safeguard security of supply. With the tendency to delay
replacement and to harvest as much as possible operational life of assets, this redundancy is also put to its limits. The
paper pays particular attention to the quality loss of redundancy if the service life of assets is prolonged. An important
conclusion is that even in the absence of failures an unwanted situation may build up where redundancy is not
effective anymore. Strategies towards strengthening redundancy are recommended to be developed. A measure for
redundancy quality is presented.
KEYWORDS: Asset Management, Corrective Maintenance, Period Based Maintenance, Condition Based Maintenance, Risk
Based Maintenance, Redundancy, Repair, Replacement, Health Index, Combined Health Index, Risk Index, Redundancy
quality
1 INTRODUCTION
Utility grids can consist of large numbers of components and many connections that form their network serving
to supply energy. In the nineteenth century electric light and power supply started out as separate installations and in
the early 1880s the first public or multi-client grids appeared in various countries almost simultaneously. In the
twentieth century the electricity grids in Europe became state owned or controlled and were regarded a public service at
almost any required cost. The grids tended to be overdesigned, over-serviced and often deployed in a national context. By
the end of the twentieth century energy was recognized as strategic. However not at any price since energy costs
became a significant part of production costs and had to be better controlled in order to face international competition.
Therefore in addition to reliability, the demand for cost-efficiency became a high priority.
Components and connections in the grid and must meet the requirements in power supply. As most grid assets wear
due to mechanisms driven by temperature, electro-magnetic fields, mechanical forces and (other) ambient conditions
like salt fog and acidity, preventive and corrective maintenance actions are often necessary. Ultimately replacement
will be necessary. Cost, human resources, materials as well as planned outage form efforts and risks for utilities. Not
undertaking the efforts also forms risks. Therefore maintenance strategies require due consideration. The present
paper discusses several maintenance strategies and which conditions favor which approach. The paper leans on
statistical techniques which are largely discussed in [1], but even if data lack making data analysis impossible, the
principles may still be applicable and may be used in the motivation of methods to repair or replace assets.
2 BACKGROUND OF PRESENT ASSET MANAGEMENT
In Europe the need for cross-border electricity trade grew as a way to secure energy supply and cost-efficiency. This
internationalization was one of the consequences of the drive towards securing energy supply, keeping energy affordable,
protecting the environment, reducing climate change and improving electricity grids. The European Community policy was
summarized in the phrase: sustainable, secure and affordable energy.
This policy had far-reaching consequences. The traditional electricity grids were organized as a chain consisting of
power plants interconnected to a high voltage transmission network, a distribution network, while the electric sales to
end-users such as industry and consumers also belonged to the utility service. By the end of the twentieth century this
utility chain was broken up where electricity production and sales were privatized (see Fig. 1).
Figure 1: Breaking up the electricity supply chain. Production and sales (supply) are privatized, whereas transmission and
distribution kept a monopoly but under supervision of a government installed Regulator. The transition that ended state monopolies on
electricity supply was accompanied by the implementation of modern asset management.
Grids are so capital intensive and had such an impact on spatial planning that neither investments nor right of way
were available to build competing parallel infrastructures. As a consequence there is usually just one electric grid shared
by all providers. As a result the network utilities kept a monopoly on electricity transmission and distribution. In pursue of
cost efficiency and affordability many countries installed a Regulator to supervise and set market prices and quality
standards. This assured that the grid owners / operators could not drive up their prices for their transmission and
distribution services.
Although the utilities kept a physical monopoly, they were compared to world-wide best practice and faced penalties
if underperforming by either poor power quality or excessive expenses. Precise tasks and formulations may differ per
country, but typically the responsibilities of Distribution System Operators (DSOs) and Transmission Operators (TSOs)
comprise maintaining an electricity network, providing connections between producers and consumers. Furthermore TSOs
have a task of maintaining the balance between supply and demand of electric power.
In this context the asset management of utilities aims at providing a resilient, secure and cost-efficient infrastructure.
This leads to solutions that differ from those in the main part of the twentieth century where technical quality of reliable
electrical energy supply faced much less constraints on financial and workforce resources that come with public services.
In addition to Corrective Maintenance (CM) and Period Based Maintenance PBM), new maintenance styles like
Condition Based Maintenance (CBM) and Risk Based Maintenance (RBM) came up supported by tools like diagnostics,
condition monitoring, health index and risk index. CBM focusses on the functionality of grid components. RBM also takes
the consequences of dysfunctionality into account measured in terms of a set of business values like safety, power quality,
security of supply etc. However CBM and RBM are not always more feasible nor more cost-efficient than conventional
styles like CM and PBM. A brief overview on the styles is given below in Section 2.1. For further reading a more detailed
introduction and discussion on the pros and cons of these styles is given in section 1.3.5 of [1].
3 ASPECTS OF MAINTENANCE INCLUDING REPLACEMENT
The physical grid components are the tangible assets that together shape the network infrastructure. Asset
Management (AM) is the collective term for the structured decision-making and execution of plans to reach an optimized
balance between performance, efforts and risk with the utilization of the assets. An AM system is an organized set of
systematic and coordinated activities to stay in control. Standards have been developed for common practice in AM such
as PAS 55 [2] and ISO 55000 standards [3], [4], [5]. An important part of asset management is the selection of
maintenance style(s). Maintenance is defined here to comprise the activities of inspections, servicing and replacement.
The longer components can be utilized, the more value is retrieved. However, the more costly the maintenance, the
less profitable the delay of investments. Moreover if the functionality is jeopardized and failures occur with possibly
significant consequences, then business values may be violated severely. Liability and mitigation costs as well as
reputation damage may rise disproportionally and waste all benefits of prolonging the operation life of ageing assets.
How should asset management contribute to a sustainable, secure and affordable energy? This paper discusses some
of the maintenance and configuration optimizing dilemmas. First some basic aspects of maintenance and replacement are
discussed to set the context and definitions. Next the information is applied to diagnosable assets and finally the role of
redundancy is studied.
2b. Hazard rate for PBM with two periods or CBM with two maximum hazard rate levels compared to CM.
Figure 2a and 2b: comparison of maintenance styles by their hazard rates. The coarser vertical scale for h(t) in 2a is to show the ongoing
development of hazard rate for CM. PBM is controlled by time, CBM by maximum allowable hazard rate. The RBM style resembles
CBM. In all cases a Weibull distribution with α=80 yr and β=3 was assumed in the present example. Where CM leads to high hazard
rates and likely failure, the styles PBM and CBM bring the asset back into new state (theoretically) and overall the hazard rate can be
kept low, which results in a significantly longer expected life. The difference between PBM and CBM is that PBM works with the same
maintenance period T for all assets, whereas CBM tunes the maintenance to need of the individual asset.
Though required technology and information may differ between the styles, it cannot be claimed that one style is
generally better or more efficient than the other. It depends on the purpose, on the balance between operational
expenses versus capital expenses (i.e. investment) and on the circumstances which style is more adequate. As an
example, pressurized oil cables can be periodically checked for oil pressure (PBM inspections) and the oil may be
replenished if necessary (CM/CBM servicing). As another example, many polyethylene insulated cables are not inspected
at all typically, but will be repaired after a failure (CM servicing) and if forensics indicate, the cable may be replaced
(CBM/RBM). As a third example, utilities may use periodic replacement schemes, by e.g. replacing cable after 40 or 50
years (PBM replacement). This sacrifices a part of the remaining cable operational life, but may save on costs for
emergency repairs and PBM allows a much easier planning. So, in practice utilities can have various reasons to apply a mix
of these styles [1].
In an RBM approach the risks to utility business values are leading in prioritizing maintenance actions. The probability
of a failure event to occur is multiplied with the impact that such an event may have. This maintenance style provides the
strategy to take threat to safety and other hazards into account. For evaluation of risks so-called risk matrices (or in the
continuous variant: the risk plane) lead to a Risk Index. The risk that a redundant system can go down, is part of the
evaluation with the aspect security of supply.
In the following some examples are elaborated to compare the strategies in practice. First situations will be studied
where the condition may be diagnosed (whether economically efficient or not). Secondly, redundancy is studied while
hardly to no condition information is available. In that case the situation is analyzed by assumed distributions.
4 DIAGNOSABLE ASSETS
If the condition of an asset can be assessed with sufficient confidence the three maintenance styles CM, PBM and
CBM are all feasible in principle. If the impact of failure is known, then also RBM is feasible. The suitability and comparison
between CM, PBM and CBM is discussed in [6], while quantitative examples are elaborated in greater detail in section 9.1
of [1]. Which of the mainteanance styles is most appropriate depends on the cost and posibilities of preventive
maintenance when comparing CM and PBM. Both maintenance styles treat all assets the same. CM lets all asets run to fail
and takes advantage of the full asset operational life, but the impact of unforeseen failure may be high and flexibility is
required to adequately respond to failures. As failures are part of this asset management style, redundancy is commonly
employed to warrant continuous power supply. Part of the gain by employing the full asset life may be cancelled by
increased investments in redundancy. The need for redundancy may be higher for CM than for PBM as PBM sacrifices
asset life in order to prevent unplanned outage. Emergency situations should occur less with PBM than with CM.
When comparing CBM and PBM, the largest gain of CBM lies in utilizing information of the individual assets. Fig. 4
(taken from [6]) shows the distribution of failure times of a group of 10 assets. It is assumed that each failure is preceeded
by a detectable signal that indicates the imminent failure of that particular asset. The failure likelihood per asset is shown
by the percentage markers as a representation of failure time probability after the first indication of imminent failure. E.g.
if the green status line in Fig. 4 defines the moment of evaluation, assets i=1-4 have already signalled that failure is
imminent (i=1, 2 May have failed already), while assets i>5 have not yet given an alert. This is essential in CBM which
allows to timely plan and mitigate the situation with assets i=1-4. In contrast if PBM is applied all assets would be replaced
or serviced well before the first fails (otherwise the managemnt style becomes CM). PBM might therefore dictate
replacement at the moment the cumulative dostribution reaches the e.g. 1% level at t=3 (arbitrary units). CBM would
allow operation on the average until about t=11 (arbitrary units). So on average the lifetime would triple that what is
achieved with PBM in this case. CBM requires adequate diagnostics and adequate expert rules in order to judge the need
for mitigation.
CBM techniques and rules often require more advanced technology than CM or PBM and can be more expensive.
Evaluating whether or not such investments are worthwhile is part of asset management.
Figure 6: The deterioration of MTBF. The connection MTBF collapses faster than the circuit MTBF. Also the ratio of circuit MTBF and the
connection MTBF starts to increase significantly indicating the faster shrinkage of the latter. These results are achieved with the
parameter set (α,β)= (70yr, 5.4).
Fig. 6 also compares the connection and circuit MTBF θ (right-hand vertical axis scale). It underlines the decreasing
quality of redundancy. Furthermore, this ratio may be used to define a quality of redundancy Qr as 1 minus the ratio:
𝜃!"#! 𝑡 ℎ!"## 𝑡
𝑄! 𝑡 = 1 − =1− (14)
𝜃!"## 𝑡 ℎ!"#! 𝑡
The circuit hazard rates are already a factor roughly 10 larger than the average hazard rate over the first 40 years. It is
the decay of the redundancy that is worrying. Table 3 indicates that mitigation is compulsory already or soon will be. The
solution can be replacement of one or both cables, which sacrifices cable operational life. Another strategy is to install a
new, third parallel cable in the connection which changes the configuration and upgrades the redundancy. The new
situation can be analyzed by the Markov chain method (e.g. section 8.6 in [1]). A third circuit requires a bay at the
substations on both sides of the connection.
ACKNOWLEDGEMENTS
The author gratefully acknowledges the financial supports for this research from the Netherlands Ministry of
Economic Affairs (TKI project FIND-GO, ref. TEUE418008).
REFERENCES
[1] R. Ross, Reliability Analysis for Asset Management of Electric Power Grids, Hoboken, NJ: Wiley-IEEE Press|, 2019,
pp. 4-20.
[2] British Standard Institution, “Asset management, Vol. Part 1: Specification for the optimized management of physical
assets,” British Standard Institution, London, 2008.
[3] International Standards Organization, “ISO 55000: Asset Management - Overview, principles and terminology,”
International Standards Organization, Geneva, CH, 2014.
[4] International Standards Organization, “ISO 55001: Asset management - Requirements,” International Standards
Organization, Geneva, CH, 2014.
[5] International Standards Organization, “Asset Management - Guidelines on the Application,” International Standards
Organization, Geneva, CH, 2014.
[6] R. Ross, “Health Index methodologies for decision-making on asset maintenance and replacement,” in Cigré 2017
Colloquium of Study Committees A3, B4 & D1, Winnipeg, Canada, 2017.
[7] Cigré WG B1.10, “TB379 Update of Service Experience of HV Underground and Submarine Cable Systems,” Cigré,
Paris, 2009.
Robert Ross is professor at TU Delft, director of IWO (Institute for Science & Development, Ede). Professor at HAN
University of Applied Sciences and AM Research Strategist at TenneT (TSO in the Netherlands and part of Germany). At
KEMA and the Royal Institute for the Navy he worked on reliability and post-failure forensic investigations. His interests
concern reliability statistics, electro-technical materials, sustainable technology and superconductivity. He was granted a
SenterNovem Annual award for energy inventions and nominated Best Researcher by the World Technology Network.