REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM, DONA MARTA HOSPITAL,
ATIMONAN, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
C.Y. 2022 PROJECT ENGINEERING ASSISTANT I
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR
QUEZON IV DISTRICT ENGINEERING OFFICE JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PREPARED:
GUMACA, QUEZON DONA MARTA HOSPITAL, ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
ATIMONAN, QUEZON
2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PERSPECTIVE ERICK S. EVANGELISTA
C.Y. 2022 PROJECT LOCATION MAP ENGINEERING ASSISTANT I
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR
QUEZON IV DISTRICT ENGINEERING OFFICE KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PREPARED:
GUMACA, QUEZON DONA MARTA HOSPITAL, TABLE OF CONTENTS ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
ATIMONAN, QUEZON
1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PLAN ERICK S. EVANGELISTA
C.Y. 2022 PROJECT ELEVATION ENGINEERING ASSISTANT I
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR
QUEZON IV DISTRICT ENGINEERING OFFICE JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PREPARED:
GUMACA, QUEZON DONA MARTA HOSPITAL, ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
ATIMONAN, QUEZON
2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM, SOUTHERN LUZON STATE UNIVERSITY
(SLSU) CALAUAG EXTENSION CAMPUS
CALAUAG, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
SYSTEM, SOUTHERN LUZON STATE UNIVERSITY PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
(SLSU) CALAUAG EXTENSION CAMPUS 2 2 6
CALAUAG, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SYSTEM, SOUTHERN LUZON STATE UNIVERSITY TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
(SLSU) CALAUAG EXTENSION CAMPUS 1 2 6
CALAUAG, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
SYSTEM, SOUTHERN LUZON STATE UNIVERSITY PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
(SLSU) CALAUAG EXTENSION CAMPUS 2 2 6
CALAUAG, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
GUINAYANGAN EVACUATION CENTER
GUINAYANGAN, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUINAYANGAN EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
GUINAYANGAN, QUEZON PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PERSPECTIVE ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUINAYANGAN EVACUATION CENTER KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
GUINAYANGAN, QUEZON TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PLAN ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUINAYANGAN EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
GUINAYANGAN, QUEZON PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
GUINAYANGAN MEDICARE COMMUNITY HOSPITAL
GUINAYANGAN, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
GUINAYANGAN MEDICARE COMMUNITY HOSPITAL PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUINAYANGAN, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
GUINAYANGAN MEDICARE COMMUNITY HOSPITAL TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUINAYANGAN, QUEZON 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
GUINAYANGAN MEDICARE COMMUNITY HOSPITAL PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUINAYANGAN, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
GUMACA EVACUATION CENTER
GUMACA, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A ENGINEERING ASSISTANT I
CONSTRUCTION OF RAINWATER COLLECTOR
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUMACA EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
PREPARED:
GUMACA, QUEZON GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PERSPECTIVE ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR
LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUMACA EVACUATION CENTER KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PLAN ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR
ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, GUMACA EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
PREPARED:
GUMACA, QUEZON GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM,SOUTHERN LUZON STATE UNIVERSITY
(SLSU) GUMACA CAMPUS, BRGY. TABING DAGAT
GUMACA, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A ENGINEERING ASSISTANT I
CONSTRUCTION OF RAINWATER COLLECTOR
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM,SOUTHERN LUZON STATE UNIVERSITY JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
PREPARED:
GUMACA, QUEZON (SLSU) GUMACA CAMPUS, BRGY. TABING DAGAT ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUMACA, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PERSPECTIVE ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR
LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE KEY PLAN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SYSTEM,SOUTHERN LUZON STATE UNIVERSITY
PREPARED: JENNIFER C. APOHIN
GUMACA, QUEZON (SLSU) GUMACA CAMPUS, BRGY. TABING DAGAT TABLE OF CONTENTS ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUMACA, QUEZON 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS PLAN ERICK S. EVANGELISTA
DETAILED ENGINEERING DESIGN PLAN FOR
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR
ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM,SOUTHERN LUZON STATE UNIVERSITY JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
PREPARED:
GUMACA, QUEZON (SLSU) GUMACA CAMPUS, BRGY. TABING DAGAT ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
GUMACA, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM, LAGUNA STATE POLYTECHNIC
UNIVERSITY(LSPU) LOPEZ SATELLITE CAMPUS
LOPEZ, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
SYSTEM, LAGUNA STATE POLYTECHNIC PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
UNIVERSITY(LSPU) LOPEZ SATELLITE CAMPUS 2 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SYSTEM, LAGUNA STATE POLYTECHNIC TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
UNIVERSITY(LSPU) LOPEZ SATELLITE CAMPUS 1 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
SYSTEM, LAGUNA STATE POLYTECHNIC PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
UNIVERSITY(LSPU) LOPEZ SATELLITE CAMPUS 2 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM
MAGSAYSAY DISTRICT HOSPITAL
LOPEZ, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
SYSTEM MAGSAYSAY DISTRICT HOSPITAL PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
LOPEZ, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SYSTEM MAGSAYSAY DISTRICT HOSPITAL TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
LOPEZ, QUEZON 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
SYSTEM MAGSAYSAY DISTRICT HOSPITAL PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
LOPEZ, QUEZON 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM,TECHNOLOGY UNIVERSITY OF THE
PHILIPPINES(TUP) LOPEZ, QUEZON EXTENSION,
LOPEZ, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
SYSTEM,TECHNOLOGY UNIVERSITY OF THE PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
PHILIPPINES(TUP) LOPEZ, QUEZON EXTENSION, 2 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SYSTEM,TECHNOLOGY UNIVERSITY OF THE TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
PHILIPPINES(TUP) LOPEZ, QUEZON EXTENSION, 1 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
SYSTEM,TECHNOLOGY UNIVERSITY OF THE PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
PHILIPPINES(TUP) LOPEZ, QUEZON EXTENSION, 2 2 6
LOPEZ, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
PLARIDEL EVACUATION CENTER
PLARIDEL, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, PLARIDEL EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
PLARIDEL, QUEZON PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, PLARIDEL EVACUATION CENTER KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
PLARIDEL, QUEZON TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES C.Y. 2022 PROJECT
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR PLAN ERICK S. EVANGELISTA
REGION IV-A CONSTRUCTION OF RAINWATER COLLECTOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, PLARIDEL EVACUATION CENTER JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
PLARIDEL, QUEZON PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
MARIA L. ELEAZAR GENERAL HOSPITAL
TAGKAWAYAN, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
C.Y. 2022 PROJECT SUMMARY OF QUANTITIES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR
ERICK S. EVANGELISTA
REGION IV-A ENGINEERING ASSISTANT I
CONSTRUCTION OF RAINWATER COLLECTOR G 2
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, MARIA L. ELEAZAR GENERAL HOSPITAL PREPARED:
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO
GUMACA, QUEZON TAGKAWAYAN, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
C.Y. 2022 PROJECT PERSPECTIVE
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR
ERICK S. EVANGELISTA
REGION IV-A LOCATION MAP ENGINEERING ASSISTANT I
CONSTRUCTION OF RAINWATER COLLECTOR WS - A 3
QUEZON IV DISTRICT ENGINEERING OFFICE KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO
SYSTEM, MARIA L. ELEAZAR GENERAL HOSPITAL PREPARED:
GUMACA, QUEZON TAGKAWAYAN, QUEZON TABLE OF CONTENTS ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 1 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
C.Y. 2022 PROJECT PLAN
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DETAILED ENGINEERING DESIGN PLAN FOR
ERICK S. EVANGELISTA
REGION IV-A ELEVATION ENGINEERING ASSISTANT I
CONSTRUCTION OF RAINWATER COLLECTOR WS - A 4
QUEZON IV DISTRICT ENGINEERING OFFICE SYSTEM, MARIA L. ELEAZAR GENERAL HOSPITAL PREPARED:
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO
GUMACA, QUEZON TAGKAWAYAN, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2 2 6
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-A
QUEZON IV DISTRICT ENGINEERING OFFICE
GUMACA, QUEZON

C.Y. 2022 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF RAINWATER COLLECTOR
SYSTEM, SOUTHERN LUZON STATE UNIVERSITY
(SLSU) TAGKAWAYAN CAMPUS
TAGKAWAYAN, QUEZON

SUBMITTED: RECOMMENDED: APPROVED:

MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO


CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
DATE: DATE: DATE:
SUMMARY OF QUANTITIES

NOTE:

1. THE STAKE-OUT SURVEY BETWEEN THE CONTRACTOR AND


THE GOVERNMENT SHALL BE CONSIDERED AS THE FINAL PLAN.

2. THE ITEMS OF WORK IDENTIFIED WITH CORRESPONDING


COMPUTED QUANTITIES IN THE APPROVED JOINT AS-STAKE
SURVEY PLANS WILL BE BASIS OF PAYMENT.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT SUMMARY OF QUANTITIES ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO G 2
SOUTHERN LUZON STATE UNIVERSITY (SLSU) PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
TAGKAWAYAN CAMPUS 2 2 6
TAGKAWAYAN, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
TABLE OF CONTENTS Republic of the Phillipines
Department of
GENERAL Public Works and Highway
OFFICE OF THE BUILDING OFFICIAL
G1 COVER PAGE

G2 SUMMARY OF QUANTITIES

ARCHITECTURAL
A1 PERSPECTIVE
LOCATION PLAN District/City/Municipality
KEY PLAN
TABLE OF CONTENT LAND USE & ZONING
A2 PLAN
ELEVATION

LINE & GRADE

STRUCTURAL
S1 FOUNDATION PLAN
FRAMING PLAN
SECTION DETAIL
PI-FI DETAIL
FTB-1
ARCHITECTURAL

PERSPECTIVE ELECTRICAL

STRUCTURAL

N PROJECT SITE PROJECT SITE


LUZON

QUEZON-ALABAT-PEREZ

LOPEZ-HONDAGUA PLUMBING SANITARY


QUIRINO HIGWAY

OLD ZIGZAG

VISAYAS

ELECTRICAL

MECHANICAL
TALABA-SUMMIT-PANAON

GUMACA-PITOGO-SAN
NARCISO

MINDANAO
LOPEZ-CATANAUAN LOPEZ-BUENAVISTA

MECHANICAL

PROJECT BILLBOARD

LOCATION MAP KEY PLAN PB1 PROJECT BILLBOARD

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PERSPECTIVE ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR LOCATION MAP ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, KEY PLAN JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 3
SOUTHERN LUZON STATE UNIVERSITY (SLSU) TABLE OF CONTENTS PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
TAGKAWAYAN CAMPUS 1 2 6
TAGKAWAYAN, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE:
1 2
.
4.00 1 2
1.85 4.00

1.85

1.22

VERIFY
A
4.00

1.85

2.21
1.33
B

1.33

4.00
PLAN
SCALE 1:40

0.50
ELEVATION
SCALE 1:40

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS C.Y. 2022 PROJECT PLAN ERICK S. EVANGELISTA
REGION IV-A DETAILED ENGINEERING DESIGN PLAN FOR ELEVATION ENGINEERING ASSISTANT I
QUEZON IV DISTRICT ENGINEERING OFFICE CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM,
JENNIFER C. APOHIN MELINDA R. ABANILLA ROMEL S. PUCHERO RODEL O. FLORIDO WS - A 4
SOUTHERN LUZON STATE UNIVERSITY (SLSU) PREPARED:
GUMACA, QUEZON ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
TAGKAWAYAN CAMPUS 2 2 6
TAGKAWAYAN, QUEZON
JOSHUA FHIL P. ANGCANA
ENGINEER II DATE: DATE: DATE: DATE: