VIJAYAWADA BYPASS BALANCE WORKS STATUS

26.07.2023

Highways Physical Progress (Main Carraiage Way) No work due to Rain


Work done
Available
S. No Description of Work Unit Scope Hindrance Completed Balance(Km) today i.e on Balance Qty(Cum) Remarks
Front
26.07.23

HT Locations (Partially
1 Earthwork up to sub-grade Km 56.637 2.160 54.477 50.37 4.11 41,524
Cleared)-43,500 Cum

2 RE Wall Erection Km 22.81 2.080 20.730 17.56 3.17 6,427 Sqm


3 GSB Km 56.637 2.160 54.477 48.63 5.85 20,400
4 CTB Km 55.709 2.380 53.329 47.05 6.28 17,104
5 WMM Km 55.709 2.380 53.329 45.86 7.47 7,201
6 DBM Km 55.709 2.380 53.329 44.99 8.34 8,724
7 BC Km 59.400 2.380 57.020 32.04 24.98 17,029

Highways Physical Progress (Slip Roads)


Work done
Available
S. No Description of Work Unit Scope Hindrance Completed Balance(Km) today i.e on Balance Qty(Cum) Remarks
Front
26.07.23
1 Earthwork up to sub-grade Km 22.34 0.310 22.03 19.03 2.997 8,223
2 GSB Km 22.34 0.310 22.03 18.63 3.4 4,496
3 WMM Km 22.34 0.310 22.03 17.08 4.95 8,797
4 DBM Km 22.34 0.310 22.03 14.67 7.356 2,134
5 BC Km 22.34 0.310 22.03 0.00 22.03 4,850

Miscellaneous Works
Work done
Available Balance(Km/
S. No Description of Work Unit Scope Hindrance Completed today i.e on Balance Qty(Cum) Remarks
Front No/Rmt)
26.07.23
1 RCC Drain Km 22.4 0.310 22.09 20.73 1.4 850
2 CC Drain(Toe,Median) Km 32.5 0.000 32.5 15.66 16.845 2,531
3 Kerb Km 24.4 0.310 24.09 22.36 1.735 101
4 Thrie Beam Crash Barrier Km 68.83 4.500 64.33 38.84 25.494
5 Turfing with Coir Mat Km 13.874 13.874 9.224 4.650
6 Turfing with Grass Seeds Km 15.73 15.73 1.00 14.73

7 Downtake Pipe 150mm PVC Pipe Rmt 3351 3351

8 Boundary Wall Km 56.53 4.500 52.03 6.27 45.757

9 Road Marking Km 60 2.080 57.92 13.37 44.555

10 Tree Plantation (Median plantation) Nos 18892 756.000 18136 11920 6216
11 Tree Plantation (Avenue Plantation) Nos 6794 540.000 6254 1803.00 4451
12 Overhead Gantry-Foundation Nos 34 1.000 33 21.00 12
13 Cantilever-Foundation Nos 16 0.000 16 12.00 4
14 Sign Boards Nos 797 0.000 797 16.00 781 `
15 Road Studs Nos 14460 0.000 14460 0.00 14460
16 Delineators Nos 62 0.000 62 0.00 62

17 Km & Hectometer Stones Nos 300 0.000 300 0.00 300

18 Luminar Studs Nos 1296 0.000 1296 0.00 1296


19 Chute Drain Nos 236 236 31.00 205
20 Project Facilities : Truck Lay Byes Nos 2 2 2.00 0
23 Highway Lighting
Double Arm
Foundation Nos 228 228 153 75
Pole Erection Nos 228 228 30 198
Single Arm
Foundation Nos 123 123 123
Pole Erection Nos 123 123 123
Differential Arm
Bracket Nos 806 806 451 355
Pole Erection Nos 806 806 415 391
VIJAYAWADA BYPASS BALANCE WORKS STATUS
26.07.2023
Work done
Available
S. No Description of Work Unit Scope Hindrance Completed Balance today i.e on Balance Qty(Cum) Remarks
Front
26.07.23
24 TMS
Chambers for TMS Nos 80 80 80 0
Chambers for Earth Pits Nos 35 35 35 0
Earth Pit Nos 35 35 35 0
Kerb Rmt 840 840 230 610
Bull Nose Nos 13 13 7 6
Tollbooth Foundation Nos 2 2 2
25 ATMS
ATMS Control Room No 1 1 1 Plinth beam completed
PTZ
Foundation Nos 23 23 8 15
Pole Fixing Nos 23 23 23
VIDS (Visual Display)
Foundation Nos 26 26 2 24
Pole Fixing Nos 26 26 26
ECB(Emergency Call Box)
Foundation Nos 30 30 30
Pole Fixing Nos 30 30 30
TTES(Travel Time Estimation)
Foundation Nos 6 6 6
Pole Fixing Nos 6 6 6
VMS(Visual Message Sign)
Foundation Nos 23 23 23
Pole Fixing Nos 23 23 23
VSD(Visual Speed Display)
Foundation Nos 20 20 1 19
Pole Fixing Nos 20 20 20
MRC (Mobile Radio Communication)
Foundation Nos 12 12 12
Pole Fixing Nos 12 12 12
Chambers for ATMS Nos 120 120 120
Chambers for Earth Pit Nos 130 130 130
Earth pit rods Nos 130 130 130