No Uraian Jumla ( Rp )

1 Biaya Langsung Personil 25,850,000.00

2 Biaya Langsung Non Personil 5,965,000.00

Real Cost 31,815,000.00


PPN 10 % 3,181,500.00
Total 34,996,500.00
Di bulatkan 35,000,000.00

Terbilang : Tiga Puluh Lima Juta Rupiah

Pinrang, 26 September 2018


Pejabat Pembuat Komotmen CV. TOLENGO LA PALETEANG ART DESIGN

A. Pahlevi, ST MUHAMMAD NAWAWI, ST


NIP :19760303 200604 1 007 Direktur
81.250982241081 16,350,000.00

18.749017758919 10,900,000.00

(3,500.00)

CV. TOLENGO LA PALETEANG ART DESIGN


Cempa, Kec.RINCIAN KEGIATAN
Batu Lappa. Kec. Mt. Sompe, Kec.
Paleteang)

Harga Satuan Jumlah


No Uraian Sat. Vol.
( Rp ) ( Rp )

I. Biaya Langsung Personil


I.1. Biaya Tenaga Ahli
1 Ketua Tim/ Site Engineering org/bln 1 x 1.00 7,000,000.00 7,000,000.00
I.2. Biaya Ass. Tenaga Ahli/Sub.Prof.
1. Surveyor/Juru Ukur org/bln 3 x 3.00 3,750,000.00 11,250,000.00
2. Operator Autocad/ Juru gambar org/bln 1 x 1.00 5,000,000.00 5,000,000.00
I.3. Biaya Tenaga Pendukung
1 Operator Komputer / Tenaga Administrasi org/bln 1 x 1.00 2,600,000.00 2,600,000.00

Jumlah I 25,850,000.00

II. Biaya Langsung Non Personil


II.1. Biaya Operasional Kantor
1 Sewa Komputer Ls 1.00 750,000.00 750,000.00
2 Sewa Printer Ls 1.00 500,000.00 500,000.00
3 ATK Ls 1.00 215,000.00 215,000.00
II.2. Biaya Transportasi
1 Sewa Kendaraan Roda 4 Hari 1 3.0 300,000.00 900,000.00
2 Sewa Kendaraan Roda 2 Hari 2 13.0 100,000.00 2,600,000.00
II.3. Biaya Pelaporan
1 laporan Ls 2.00 500,000.00 1,000,000.00

Jumlah II 5,965,000.00
16,350,000.00

10,900,000.00

35,000,000.00 31,815,000.00
48,165,000.00
REKAPITULASI BIAYA
Pekerjaan jasa Perencanaan III

No Uraian Jumla ( Rp )

1 Biaya Langsung Personil 24,850,000.00

2 Biaya Langsung Non Personil 6,965,000.00

Real Cost 31,815,000.00


PPN 10 % 3,181,500.00
Total 34,996,500.00
Di bulatkan 35,000,000.00

Terbilang : Tiga Puluh Juta Rupiah

Pinrang, 4 Juli 2018


Pejabat Pembuat Komotmen CV. HM BROTHER ENGINEERING

A. Pahlevi, ST AMRAN, ST
NIP :19760303 200604 1 007 Direktur
78.107810781078 16,350,000.00

21.892189218922 10,900,000.00

(3,500.00)

CV. TOLENGO LA PALETEANG ART DESIGN


RINCIAN KEGIATAN
Pekerjaan jasa Perencanaan III

Harga Satuan Jumlah


No Uraian Sat. Vol.
( Rp ) ( Rp )

I. Biaya Langsung Personil


I.1. Biaya Tenaga Ahli
1 Ketua Tim/ Site Engineering org/bln 1.00 6,000,000.00 6,000,000.00
I.2. Biaya Ass. Tenaga Ahli/Sub.Prof.
1. Surveyor/Juru Ukur org/bln 3.00 3,750,000.00 11,250,000.00
2. Operator Autocad/ Juru gambar org/bln 1.00 5,000,000.00 5,000,000.00
I.3. Biaya Tenaga Pendukung
1 Operator Komputer / Tenaga Administrasi org/bln 1.00 2,600,000.00 2,600,000.00

Jumlah I 24,850,000.00

II. Biaya Langsung Non Personil


II.1. Biaya Operasional Kantor
1 Sewa Komputer Ls 1.00 750,000.00 750,000.00
2 Sewa Printer Ls 1.00 500,000.00 500,000.00
3 ATK Ls 1.00 315,000.00 315,000.00
II.2. Biaya Transportasi
1 Sewa Kendaraan Roda 4 Hari 3.00 300,000.00 900,000.00
2 Sewa Kendaraan Roda 2 Hari 25.00 100,000.00 2,500,000.00
II.3. Biaya Pelaporan
1 laporan Ls 2.00 1,000,000.00 2,000,000.00

Jumlah II 6,965,000.00
16,350,000.00

10,900,000.00

35,000,000.00 31,815,000.00
48,165,000.00
HPS
Pekerjaan jasa Pengawasan I

Harga Satuan Jumlah


No Uraian Sat. Vol.
( Rp ) ( Rp )

I. Biaya Langsung Personil


I.1. Biaya Tenaga Ahli
1 Site Engineer Ls 1.00 6,000,000.00 6,000,000.00
2 Quality Engineer Ls 1.00 4,750,000.00 4,750,000.00
I.2. Biaya Ass. Tenaga Ahli/Sub.Prof.
1. Inspector Ls 1.00 3,750,000.00 3,750,000.00
I.3. Biaya Tenaga Pendukung
1 Operator Komputer / Tenaga Administrasi Ls 1.00 2,600,000.00 2,600,000.00

Jumlah I 17,100,000.00

II. Biaya Langsung Non Personil


II.1. Biaya Operasional Kantor
1 Sewa Komputer Ls 1.00 750,000.00 750,000.00
2 Sewa Printer Ls 1.00 500,000.00 500,000.00
3 ATK Ls 1.00 315,000.00 315,000.00
4 Foto Dokumentasi Ls 1.00 273,000.00 273,000.00
II.2. Biaya Transportasi
1 Sewa Kendaraan Roda 4 Hari 4.00 300,000.00 1,200,000.00
2 Sewa Kendaraan Roda 2 Hari 30.00 100,000.00 3,000,000.00

II.4. Biaya Pelaporan


1 laporan set 1.00 1,000,000.00 1,000,000.00

Jumlah II 7,038,000.00
Real Cost 24,138,000.00
PPN 10 % 3,181,500.00
Total 27,319,500.00
Di bulatkan 35,000,000.00

Terbilang : Tiga Puluh Lima Juta Rupiah

Pejabat Pembuat Komotmen

A. Pahlevi, ST
NIP :19760303 200604 1 007
16,350,000.00

10,900,000.00

24,138,000.00
24,138,000.00
HPS
Pembangunan Jalan dan Jembatan Perdesaan
Kabupaten Pinrang Tahun Anggaran 2018
Pekerjaan jasa Perencanaan

Harga Satuan Jumlah


No Uraian Sat. Vol.
( Rp ) ( Rp )

I. Biaya Langsung Personil


I.1. Biaya Tenaga Ahli
1 Ketua Tim/ahli Sipil Perencanaan Orang 1.00 6,000,000.00 6,000,000.00
2 Ahli Sipil ( Cost dan Quantity Engineer) Orang 1.00 5,500,000.00 5,500,000.00
I.2. Biaya Ass. Tenaga Ahli/Sub.Prof.
1. Ass. Tenaga Ahli Sipil ( Surveyor/Juru Ukur ) Orang 1.00 4,850,000.00 4,850,000.00

Jumlah I 16,350,000.00

II. Biaya Langsung Non Personil


II.1. Biaya Tenaga Pendukung
1 Operator Komputer Orang 1.00 1,500,000.00 1,500,000.00
2 Operator Auto CAD Orang 1.00 1,750,000.00 1,750,000.00
3 Administrasi Orang 1.00 750,000.00 750,000.00
II.2. Biaya Operasional Kantor
1 Sewa Komputer Ls 1.00 1,000,000.00 1,000,000.00
2 Sewa Printer Ls 1.00 400,000.00 400,000.00
3 Kebutuhan Bahan Gambar Ls 1.00 1,000,000.00 1,000,000.00
4 Foto Dokumentasi Ls 1.00 350,000.00 350,000.00
5 Telpon, Fax, Hp Ls 1.00 250,000.00 250,000.00
II.3. Biaya Transportasi
1 Sewa Kendaraan Roda 4 Hari 3.00 300,000.00 900,000.00
2 Sewa Kendaraan Roda 2 Hari 3.00 100,000.00 300,000.00
II.4. Biaya Survey
1 Pengukuran Ls 1.00 1,700,000.00 1,700,000.00
II.5. Biaya Pelaporan
1 Laporan Pendahuluan Set 1.00 500,000.00 500,000.00
2 laporan Akhir Set 1.00 500,000.00 500,000.00

Jumlah II 10,900,000.00
Real Cost 31,815,000.00
PPN 10 % 3,181,500.00
Total 34,996,500.00
Di bulatkan 35,000,000.00

Terbilang : Tiga Puluh Juta Rupiah

Pejabat Pembuat Komotmen

A. Pahlevi, ST
NIP :19760303 200604 1 007
16,350,000.00

10,900,000.00

27,250,000.00
43,600,000.00
REKAPITULASI BIAYA
Kegiatan Pembangunan Saluran Drainase / Gorong - Gorong
Kabupaten Pinrang Tahun Anggaran 2016
Pekerjaan jasa Perencanaan

No Uraian Jumla ( Rp )

1 Biaya Langsung Personil 14,500,000.00

2 Biaya Langsung Non Personil 10,150,000.00

Real Cost 24,650,000.00


PPN 10 % 2,465,000.00
Total 27,115,000.00
Di bulatkan 27,100,000.00

Terbilang : Lima puluh juta rupiah

Pinrang, 24 Maret 2016


CV. C 97 CONSULTANT

SURIADI, ST
Direktur