Dated: 25/05/2023

Third Party Quarterly Environmental Monitoring Plan

1. Project Background

Dasu Hydropower project is located in district Kohistan of Khyber Pakhtunkhwa Province, on the
Indus River, 7 km upstream of Dasu village, 74 km downstream of Diamer Basha Dam and 350
km away from Islamabad. WAPDA awarded a contract to a joint venture, Dasu Hydropower
Consultants, for preparation of a detailed engineering design and construction supervision of
4,320MW Dasu hydropower project to produce mean annual hydroelectricity of 18440 GWh. The
joint venture of consultants comprises two foreign viz. NIPPON KOEI Co. Ltd (NK), DOLSAR
Engineering Ltd. and three local companies’ viz. Development and Management Consultants
(DMC), National Development Consultants (NDC) & Pakistan Engineering Services Ltd.
consulting (PES). This project is funded by IFC and World Bank.

2. Environmental Monitoring parameters of DASU Hydro Power Project

According to the contract documents (i.e. EIA volume 6, EMAP volume 8, general condition of the
contract and BOQ) for all project components. The contractor is responsible and bound to hire the
services of Third Party Monitor to conduct tests at below different locations. Please see table -01.
Parameter are presented in table -02.

The contractor wants to collect sample from the following locations proposed by the engineer and
employer.
PROPOSED SITE LOCATIONS FOR THE THIRD PARTY MONITORING LAB for MW-01 &02 Sites by CGGC CONTRACTOR

Sr. Air Quality Water Quality Noise & Vibrant


Location of the Activity Remarks
No. Monitoring Monitoring Monitoring
1 Uchar Crusher Plant (90 Ton) √ √ √ The Engineer Reserves the right to Modify./ Change the
2 Thoki Crusher Plant(240 Ton) √ √ √ locations/No of aspects in future as the project (DHPP)
3 CR-02 √ √ √ construction proceeds
4 CR-09 √ √ √
5 Switchyard Camp √ √ √
6 CT-02 √ √
7 Underground Power House √ √
8 Underground Transformer Cavern √ √
9 Seo Crusher Plant √ √
10 Sigloo Batching Plant √ √
11 Main Dam Site & Starter/Coffer Dam √ √ √
Monitoring program during construction presented in various EMP sub plans are summarized and presented in in Table -02

Parameter Parameters Frequency


Surface water Sampling and analysis of river Quarterly
quality water quality and waste water
discharges for the key
parameters given in NEQS
(river water quality – DO, BOD,
COD, Temperature, pH,
Conductivity, TSS, turbidity,
nitrate; ’
Waste water – BOD. TSS,
turbidity, TDS, COD, grease
and oil, iron, ammonia,
sulfates, chlorides)
Air Quality Air quality monitoring for 24 Quarterly
(PM10, NO2, hours for the parameters
SO2, CO2, CO specified in NEQS 2000
Noise and 24 hour noise monitoring Quarterly
vibration