REKAPITULASI

PROYEK : PEMBANGUNAN KOSTEL CENDEKIA BANDUNG


PEMILIK : PT. PILAR KREASI MANDIRI
LOKASI : UIN SUNAN GUNUNG JATI, CIBIRU - BANDUNG

NO URAIAN JUMLAH HARGA


1 PEKERJAAN PERSIAPAN 1,264,778,600.00
2 PEKERJAAN TANAH 137,902,131.20
3 PEKERJAAN STRUKTUR -
- PEKERJAAN STRUKTUR BAWAH 3,077,891,588.29
- PEKERJAAN STRUKTUR ATAS 14,334,645,221.61
4 PEKERJAAN ARSITEKTUR -
- PEKERJAAN DINDING 6,548,672,354.72
- PEKERJAAN KUSEN, PINTU DAN JENDELA 2,398,210,000.00
- PEKERJAAN LANTAI DAN PELAPISANNYA 2,366,003,786.25
- PEKERJAAN PLAFON 1,002,824,456.70
5 PEKERJAAN MEKANIKAL ELEKTRIKAL -
- INSTALASI AIR KOTOR DAN AIR HUJAN 851,259,930.00
- INSTALASI AIR BERSIH 469,994,290.00
- PEKERJAAN INSTALASI LISTRIK 3,476,046,260.00
- PEKERJAAN FIRE HYDRAN 814,607,317.20
- PEKERJAAN FIRE ALARM 1,424,252,500.00
- PEKERJAAN LIFT 1,000,000,000.00
- PEKERJAAN SUMUR DAN POMPA 282,800,000.00
- PEKERJAAN GENSET 541,400,000.00
- PEKERJAAN STP GWT SALURAN DAN RESAPAN 260,700,000.00
- PEKERJAAN LANDSCAPE DAN SWIMMING POOL 2,715,000,000.00
6 PEKERJAAN INTERIOR (MEUBEL KAMAR) 3,174,750,000.00
TOTAL 46,141,738,435.97
PAJAK PPN 11% ( By OWNER) -
GRAND TOTAL 46,141,738,435.97
DIBULATKAN 46,141,700,000.00

Depok, 16 November 2022


PT. PILAR KREASI MANDIRI

…...............................
Direktur