CRONOGRAMA DE VALORIZADO DE OBRA

¤ PARCIAL MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 PARCIAL


ITEM. DESCRIPCION DE PARTIDA
(S/.)
### 01 OBRAS PROVISIONALES, TRABAJOS 444,088.63
PRELIMINARES, SEGURIDAD Y SALUD
OBRAS PROVISIONALES Y TRABAJOS
### 01.01 280,934.58 S/ 158,574.58 S/ 52,440.00 S/ 17,480.00 S/ 17,480.00 S/ 17,480.00 S/ 17,480.00 S/ 280,934.58
PRELIMINARES
### 01.02 SEGURIDAD Y SALUD 13,784.00 S/ 13,784.00 S/ 13,784.00
MEDIDAS DE MITIGACION DE IMPACTO
### 01.03 54,479.48 S/ 12,961.05 S/ 16,343.84 S/ 5,447.95 S/ 5,447.95 S/ 5,447.95 S/ 8,830.74 S/ 54,479.48
AMBIENTAL
PLAN PARA LA VIGILANCIA, PREVENCION Y
### 01.04 48,731.77 9746.35 9746.35 9746.35 9746.35 4873.18 4873.18 S/ 48,731.77
CONTROL DE COVID-19 EN EL TRABAJO
### 01.05 PLAN DE MONITOREO ARQUEOLÓGICO (PMA). 46,158.80 46158.80
### 02 ESTRUCTURAS 2,300,865.03 575216.26 460173.01 345129.75 345129.75 460173.01 115043.25 S/ 2,300,865.03
### 03 ARQUITECTURA 1,173,864.02 58693.20 293466.01 293466.01 234772.80 176079.60 117386.40 S/ 1,173,864.02
### 04 INSTALACIONES SANITARIAS 204,802.96 10240.15 51200.74 51200.74 51200.74 30720.44 10240.15 S/ 204,802.96
### 05 INSTALACIONES ELECTRICAS 668,146.17 33407.31 167036.54 167036.54 167036.54 100221.93 33407.31 S/ 668,146.17
### 06 INSTALACIONES MECANICAS 151,922.73 7596.14 37980.68 37980.68 37980.68 22788.41 7596.14 S/ 151,922.73
### 07 COMUNICACIONES 495,142.67 198057.068 198057.068 99028.534 S/ 495,142.67
### 08 EQUIPAMIENTO MEDICO 939,589.00 281,876.70 657,712.30
COSTO DIRECTO 926377.8375 1088387.174 1125545.0945 1066851.8935 1198689.747 972569.4635 S/ 6,378,421.21
% DE AVANCE MENSUAL 15% 17% 18% 17% 19% 15% 100%
% DE AVANCE ACUMULADO MENSUAL 15% 32% 49% 66% 85% 100% 100%