Perhitungan Volume Gedung MTA Cabang Sukolilo

No Item Pekerjaan Panjang Lebar Tinggi Jumlah Luas/Total Satuan Harga Satuan Total Harga

1 Perancangan Gambar 1.00 Ls 7,500,000.00 7,500,000.00


dan Pengawasan

2 Pembersihan Lokasi 1.00 Ls 2,000,000.00 2,000,000.00

3 Uitzet/ Bouwplang 62.00 0.00 0.00 62.00 m' 50,000.00 3,100,000.00

4 Strous 0 30 cm 5.00 0.30 19.00 26.60 M3 2,300,000.00 61,180,000.00


( isi 4 Bh / Poer)
0,35 M3
5 Galian Poer 1.25 1.25 1.00 19.00 29.69 M3 50,000.00 1,484,375.00

6 Galian Sloof 123.15 0.30 0.50 18.47 M3 50,000.00 923,625.00

7 Rabat Bawah Poer 1.25 1.25 19.00 29.69 M2 500,000.00 14,843,750.00

8 Rabat Bawah Sloof 123.15 0.30 36.95 M2 500,000.00 18,472,500.00

9 Poer K 250 1.00 1.00 0.40 19.00 7.60 M3 3,500,000.00 26,600,000.00

10 Sloof K 250 123.15 0.20 0.40 9.85 M3 3,500,000.00 34,482,000.00

11 Kolom 25x 40 0.25 0.40 3.50 9.00 3.15 M3 3,500,000.00 11,025,000.00

12 Kolom 30 x 40 0.30 0.40 3.50 4.00 1.68 M3 3,500,000.00 5,880,000.00

13 Kolom 25 x 25 0.25 0.25 3.50 2.00 0.44 M3 3,500,000.00 1,531,250.00

14 Kolom 20 x 20 0.20 0.20 3.50 2.00 0.28 M3 3,500,000.00 980,000.00

15 Kolom Bulat 0.40 0.40 3.50 2.00 2.20 M3 3,500,000.00 7,700,000.00


Perhitungan Volume Gedung MTA Cabang Sukolilo
No Item Pekerjaan Panjang Lebar Tinggi Jumlah Luas/Total Satuan Harga Satuan Total Harga

16 Pondasi Batu Kali 123.00 0.45 1.00 55.35 M3 385,000.00 21,309,750.00

17 Urugan Sirtu 20.00 11.00 0.50 110.00 M3 175,000.00 19,250,000.00

18 Rabat Beton 10 cm 20.00 11.00 0.10 22.00 M3 1,750,000.00 38,500,000.00

19 Balok 20 x 70 11.00 0.20 0.59 2.00 2.60 M3 3,500,000.00 9,086,000.00

20 Balok 20 X 50 11.00 0.20 0.39 3.00 2.57 M3 3,500,000.00 9,009,000.00

21 Plat atap/Dak 11 cm 20.00 11.00 0.11 24.20 M3 3,500,000.00 84,700,000.00

22 Lisplank Beton 10/50 11.00 0.10 0.50 0.55 M3 3,500,000.00 1,925,000.00

23 Pas Bata merah 123.15 3.00 369.45 M2 385,000.00 142,238,250.00

24 Plesteran + Acian 250.00 M2 52,500.00 13,125,000.00

25 Benangan 250.00 250.00 M' 15,000.00 3,750,000.00

26 Pas Keramik Lantai 16.00 11.00 176.00 M2 90,000.00 15,840,000.00

27 Pas Keramik Dinding 15.00 2.00 30.00 M2 95,000.00 2,850,000.00

28 Cat Dinding 250.00 M2 15,000.00 3,750,000.00

29 Cat Plafond Expose 250.00 M2 15,000.00 3,750,000.00

30 Screet/plester atap 20.00 11.00 220.00 M2 26,000.00 5,720,000.00

31 Stek Tangga 1.00 10.00 5.00 Kg 10,000.00 50,000.00


Perhitungan Volume Gedung MTA Cabang Sukolilo
No Item Pekerjaan Panjang Lebar Tinggi Jumlah Luas/Total Satuan Harga Satuan Total Harga

32 Instalasi Listrik 1.00 Ls 9,000,000.00 9,000,000.00

33 Instalasi Air 1.00 Ls 6,200,000.00 6,200,000.00

34 Tandon Air atas & bwh 1.00 Ls 4,500,000.00 4,500,000.00

35 Septictank 2 Bh 1.00 Ls 5,500,000.00 5,500,000.00

36 Closet Jongkok 4 Bh 4.00 Bh 300,000.00 1,200,000.00

37 Saluran Air Kotor 46.00 46.00 M' 25,000.00 1,150,000.00

38 Got Depan 11.00 11.00 m' 250,000.00 2,750,000.00

39 Pintu + Kusen PVC 4.00 Bh 300,000.00 1,200,000.00

40 Pintu jend Aluminium 1.00 Ls 9,000,000.00 9,000,000.00

41 Pengadaan PDAM 1.00 Ls 6,000,000.00 6,000,000.00

42 Almari Dapur 1.00 Ls 2,000,000.00 2,000,000.00

43 Ongkos angkut dari 1.00 Ls 25,000,000.00 25,000,000.00


jalan raya masuk lokasi

44 Perlengkapan + 1.00 Ls 10,000,000.00 10,000,000.00


Instalasi
656,055,500.00