Daily Report - 20220926
Daily Report - 20220926
Work started at 6:00 WITA. After toolbox meeting was conducted, ADCP equipment was checked. There was no damage to the equipment. The team
then headed for transect 10 and conducted survey on transects 10 through 12. The survey duration for a single transect was around 90 mins. Due to
high waves at 13:00 WITA, ship captain advised to stop survey activities and head to Benete. This caused the survey for the 12 th transect to be halted
in the middle of the transect. This line was the additional line for magnetometer survey.
Strong winds appear to occur starting 12:00 WITA on 27th September. Stationary survey does not appear possible as the waves would rock the vessel
too much rendering the ADCP unable to acquire data.
2.3. PROJECT PROGRESS PERCENTAGE COMPLETE
PREVIOUS TODAY TOTAL TO COMMENTS
DATE
Installation 100% 0% 100%
Survey Transect (ADCP) 45% 17% 62%
Survey Transect (Magnetometer) 56% 38% 94%
Record Tide (GNSS) 36% 26% 62%
0% 0% 0%
0% 0% 0%
0% 0% 0%
0% 0% 0%
0% 0% 0%
Total % of project complete: 0%
3.0. PERSONNEL
PREVIOUS TODAY ON TOTAL
Abubakar Aliyu Alhassan
Barnabas Jamot Tambun
Ben Rogers William
Burhan
Farras Rizqi
Razi
4.0. COMMENTS & APPROVALS
4.1. MANAGEMENT TEAM COMMENTS
4.2. FIELD TEAM COMMENTS
5.0. DOCUMENTATION