Yearly Construction Schedule in 2019-Utility

General status 2018 Finished status Plan


Items
Total(m) TOTAL Completed(m) TOTAL Finish. Perce REMAINING 2018 Schedule Up to 2018-September finished Precentage Oct, Nov, Dec Schedule 2019 Schedule REMARK

OASIS SURF.DRAN 5527 1046 19% 4481 4774 293 6% 2406 2075

FF 34336 33899 99% 437 1966 1529 78% 137 300

FF pressure Test 34337 27754 81% 6583 - - - 2000 4583

IRR 36761 35263 96% 1498 5424 3926 72% 521 977

IRR (OASIS) 4185 2552 61% 1633 3527 1894 54% 200 1433

IRR pressure Test 40946 31324 77% 9622 - - - 9622 -

FUEL TRENCH 14285 12525 88% 1760 3942 2182 55% 495 1265

FUEL TEST 14285 3346 23% 10939 - - - 3796 7143

W.S 17995 17521 97% 474 1501 1027.4 68% 433 -

W.S (OASIS) 2246 1830 81% 416 1805 1389 77% 129 287

W.S TESTING 20241 12618 62% 7623 - - - 2400 5223

TSE 7404 7404 100% - 87 87 100% - -

TSE PRESSURE TEST 7404 6978 94% 426 - - - 426 -

C.W (MAIN LINE) 4189 4189 100% 0 414 414 100% - -

C.W (OASIS LINE) 2216 1798 81% 418 2005 1587 79% 0 418

C.W(Valve Chamber) 31 17 55% 14 31 17 55% 0 14

11KV 13207 12038 91% 1169 4339 3170 73% 400 769

11KV (OASIS) 89 89 100% 0 89 89 100% - -

415V 22302 21349 96% 953 4579 3626 79% 362 591

415V (OASIS) 2680 857 32% 1823 2534 711 28% 588 1235

FBS 21909 20599 94% 1310 3471 2161 62% 320 990

FBS (OASIS) 2200 248 11% 1952 1523 0 0% 341 1611

FBS Sub. Duct Installation 138171 6909 131263

FBS Sub. Duct Installation (OASIS) 11766 11766

TELECOM 17272 15326 89% 1946 4192 2246 54% 357 1589

TELE (OASIS) 2080 343 16% 1737 2080 343 16% 496 1241

TELE. Sub. Duct Installation 50338 2517 47821

TELE. Sub. Duct Installation (OASIS) 5445 5445

SANITARY 9770 9547 98% 223 242 19 8% 107 116

S.W 32712 32429 99% 283 1416 1133 80% 161 122

TRAFFIC PIPE LINE 10065 3965 39% 6100 - 3965 - 3000 3100

TRAFFIC POLE 369 334 91% 35 180 143 79% 15 20

TRAFFIC POLE installation 369 12 36

TRAFFIC MH&HH&TCC&PB 764 540 71% 224 755 529 70% 100 124

All MH& HH Cover 4372 2615 60% 1757 - 2615 - 450 1000