Established in terms of Section 92(1) of the National Water Act, 1998 (Act No
36. of 1998)
Contract No:
The works are
Purchase Request no
.
Contractor name:
ADDRESS
Email:
Contact Number:
Date
Document Number:
Clause 61.1
Compensation events arise from the Project Manager giving an instruction
or changing an earlier decision which the Contractor is required to put into
effect.
Part Contents
Part - You are instructed not to submit a quotation as this event arises from a fault of the Contractor.
1
- You are instructed not to submit a quotation as I already have your quotation(s).
- You are instructed to submit quotations for the event as soon as possible but in any case within three
weeks of this instruction.
- Option B: Defined Cost and the resulting Fee for changed rates and new priced items for work not yet
done, and new lump sums for work already done.
- Option C: Defined Cost and the resulting Fee using the Schedule of Cost Components.
- Option D: Defined Cost and the resulting Fee using the Schedule of Cost Components for changed rates
and new priced items for work not yet done, and new lump sums for work already done.
- Option E: Except that per Clause 63.15 the Shorter Schedule of Cost Components has been used for
assessing items per the agreement between the Project Manager and the Contractor.
- A notification that the Project Manager will be making his own assessment because the Contractor has
not complied with the requirements stated in the contract.
Part - Implementation is different for each of the main Options. Please refer to the document for specific
4 instructions.
Part 1: - Project Manager’s notification and request for quotation
In terms of Clause 61.1 I hereby notify you of compensation event(s) stated in Clause 60.1(2)1
This arises from an instruction or changed decision which you are required to put into effect given
by the Project Manager on
The details of the event are:
This compensation event is denoted CE No.
Contractor are instructed to submit quotations for the event as soon as possible but in any case
within two weeks of this instruction, per Clause 62.3, by not later than
Please complete Part 2 of this form and return all parts to me together with your quotation.
Project Manager:
1
Change the clause reference if the event arises from a compensation event in one of the Option clauses.
Part 2: - Contractor’s submission of quotations
In terms of Clauses 62.1 and 62.2 we submit our quotation for the above described
compensation event. If you requested alternative quotations or we have decided to submit
quotations for other methods of dealing with the event these are clearly identified as such.
Each quotation comprises proposed changes to the Prices and any delay to the Completion
Date(s) and Key Dates where they are used and if they are affected.
Each quotation includes full details of our assessment carried out in accordance with Clause 63.
Option A Defined Cost (clause 11.2(22))and the resulting Fee. (Complete or delete 2nd
sentence if it does not apply & delete this note)
Except that per Clause 63.14 rates and lump sums have been used in place of
Defined Cost and the resulting Fee for items per the agreement between the
Project Manager and the Contractor reference dated 2
Option B Defined Cost (clause 11.2(22))and the resulting Fee for proposed changed rates and
new priced items for the proposed work.
(Complete or delete 2nd sentence if it does not apply & delete this note)
Except that per Clause 63.13 rates and lump sums (NOT from the bill) have been
used in place of Defined Cost for items per the agreement between the
Project Manager and the Contractor reference dated 3
Option C Defined Cost (clause 11.2(23)) less Disallowed Cost (clause 11.2(25)and the
resulting Fee using the Schedule of Cost Components.
(Complete or delete 2nd sentence if it does not apply & delete this note)
Except that per Clause 63.15 the Shorter Schedule of Cost Components has been
used for items per the agreement between the Project Manager and the
2
This arrangement only used when it is impractical to assess a Subcontractor’s costs using the Shorter
Schedule of Cost Components.
3
This arrangement only used when it is impractical to assess a Subcontractor’s costs using the Shorter
Schedule of Cost Components.
Contractor reference dated .4
Option D Defined Cost (clause 11.2(23)) less Disallowed Cost (clause 11.2(25)and the
resulting Fee using the Schedule of Cost Components for proposed changed rates
and new priced items for the proposed work.
(Complete or delete 2nd sentence if it does not apply & delete this note)
Except that per Clause 63.13 rates and lump sums (NOT from the Bill) have been
used in place of Defined for items per the agreement between the Project
Manager and the Contractor reference dated 5
(Complete or delete 3rd sentence if it does not apply & delete this note)
Except that per Clause 63.15 the Shorter Schedule of Cost Components has been
used for assessing items per the agreement between the Project Manager and
the Contractor reference dated .
Option E Except that per Clause 63.15 the Shorter Schedule of Cost Components has been
used for assessing items per the agreement between the Project Manager and
the Contractor reference dated .
The Contractor:
4
This may be preferable where a large number of small compensation events have to be assessed.
5
This arrangement only used when it is impractical to assess a large number of low value compensation
events using the full Schedule of Cost Components.
Part 3: - Project Manager’s response to the Contractor’s quotations
In terms of Clause 62.3 the Project Manager’s reply to the Contractor’s quotation is:
[Select one of the three statements below which apply then delete the other two and this note]
Project Manager:
In terms of clause 65, the Project Manager implements this compensation event as follows:
4.1 The changes to the Completion Date and the Key Dates are as follows:
(Delete references to Key Dates if they have not been used then delete this note)