Course Name:
BEQ2103 Professional Practice for Quantity Surveyor
Assignment Title:
Assignment 1
Lecturer:
Ts. Sr. Dr. Nadzirah Binti Zainordin
Table of Contents
1.0 Introduction ....................................................................................................................................... 3
2.0 Procurement Route............................................................................................................................ 3
2.0.1 Traditional Contract ................................................................................................................... 3
2.0.2 Design and Build........................................................................................................................ 3
2.0.3 Management Contracting ........................................................................................................... 4
2.0.4 Construction Management ......................................................................................................... 4
2.1 Chosen Procurement Route............................................................................................................... 4
3.0 Contractual Arrangement .................................................................................................................. 5
3.0.1 Lump Sum.................................................................................................................................. 5
3.0.2 Measurement .............................................................................................................................. 5
3.0.3 Cost Reimbursement .................................................................................................................. 5
3.0.4 Target Cost Plus ......................................................................................................................... 6
3.1 Chosen Contractual Arrangement ..................................................................................................... 6
4.0 Tendering Strategies ......................................................................................................................... 6
4.0.1 Open Tender............................................................................................................................... 7
4.0.2 Selective tender .......................................................................................................................... 7
4.0.3 Negotiated Tender ...................................................................................................................... 7
4.1 Chosen Tendering Strategies ............................................................................................................ 7
5.0 Conclusion ........................................................................................................................................ 7
References ............................................................................................................................................... 9
Appendix ............................................................................................................................................... 11
2|Page
1.0 Introduction
Mr Lim is an entrepreneur, and he is currently 60 years old. Mr Lim plan to build 20-
unit bungalow but he does not have any experience in housing development. Therefore, Mr
Lim ask me as a Professional Quantity Surveyor (QS), to propose a suitable procurement route,
contractual arrangement, and tendering strategies for a 20-unit bungalow housing development.
With that, Mr Lim required us to form a proposal report to present to Mr Lim. Without further
ado, for this report there will be three main topics which in this report include the procurement
route, contractual arrangement, and tendering strategies.
3|Page
2.0.3 Management Contracting
In this instance, the Employer hired experts to prepare the design, and construction has
already begun. In order to split responsibilities across several trade or package contracts, a
"Management Contractor" is appointed in advance (referred to as "works packages"). The
agreements are between the management contractor and the work contractors. “Client will only
communicate with the management contractors, and the client’s risk will be transferred to
management contractors” (Raoneqs, 2021). The exact cost cannot be ascertained until the last
package has been granted, much as in construction management.
4|Page
3.0 Contractual Arrangement
An agreement between two or more parties that imposes legal obligations on them and
authorises or forbids them from taking certain acts is known as a contractual arrangement, or
simply a contract. Laws may impose financial fines, community service requirements, or even
jail time as penalties for violating these responsibilities. We sign contracts every day, whether
it's authorising cookies on a website or accepting a bank loan. “Any company or brand needs
these legally enforceable contracts since they clearly describe the fundamental activities”
(Juang, 2021). Due to the multiple processes and intricacies involved, maintaining contractual
agreements can occasionally be difficult.
3.0.2 Measurement
Measurement contract also referred to as re-measurement contract. On projects when
the vital work's nature may be accurately described in pertinent detail when they are offered,
but the quantity cannot, a measurement contract may be necessary. “Rates are offered in the
contractor's tender rather than a set price, either in accordance with the price estimate or the
price schedule” (“Why Remeasurement Contracts Are Risky - 5 Pros &Amp; Cons Re Mea,”
2021). The tender prices are then applied to the data after determining the actual amount of
work accomplished. The contractor receives payment in accordance with the volume of work
completed. The benefit of employing a measurement contract is that time is saved by not having
to prepare a whole bill because quantity is only an estimate at the tender stage.
5|Page
be used when the nature or scope of the work to be done cannot be precisely stated at the outset
and the risks associated with the assignment are considerable, such as emergency work” (“Cost
Reimbursable Contract,” n.d.). Based on a general specification, any pertinent drawings, and
an estimated cost, the tendering process may go on. One advantage of this structure is the
flexibility it provides.
6|Page
4.0.1 Open Tender
Open tendering is the main procurement method utilised by both the governmental and
commercial sectors. Under an open bidding procedure, anybody may make a proposal to
provide the required products or services, giving every organisation an equal opportunity to do
so. The industries that use this sort of tender the most commonly are engineering and
construction.
5.0 Conclusion
In a nutshell, the traditional contract is Mr. Lim's best option for a procurement channel
in this circumstance. This is so because traditional contracts are appropriate for all clients,
including novice clients. For the most part, contractors are familiar with this approach and the
related process. The architect frequently serves as the project's primary consultant, evaluating
7|Page
the contractor's work and ensuring that the project's emphasis on the calibre of the end product
is maintained. Furthermore, the lump-sum contract is best for Mr. Lim. This is because the
project's budget was known and made public before any actual work had started. Additionally,
maintaining contracts is simpler when there are few or no changes. Last of all, the selection
process used for this project was selective tendering. Selective tendering is frequently quicker
than open tendering and can be perceived as less wasteful because there is no pre-qualification
procedure as part of the tender system itself and only suppliers who are known to be appropriate
for the proposed contract are invited to submit offers.
8|Page
References
3 Main Procurement Routes Explained | Vita Architecture. (2020, April 19). Retrieved
routes-explained/
https://www.designingbuildings.co.uk/wiki/Cost_reimbursable_contract
Ellis, G. (2022, September 16). 8 Main Types of Construction Contracts. Retrieved February
Jain, V. (2020, May 8). Types of Construction Contracts and their Comparison [PDF].
construction-contracts-comparison/14268/
https://ironcladapp.com/journal/contracts/contractual-agreement/
https://www.designingbuildings.co.uk/wiki/Procurement_route
https://quantitysurveyor.blog/2019/08/05/procurement-methods-in-construction/
https://www.designingbuildings.co.uk/wiki/Selective_tendering
What are the Most Common Types of Tender and Tendering. . . (2020, March 11). Retrieved
common-types-of-tender-and-tendering-process/
9|Page
Why remeasurement contracts are risky - 5 Pros & cons Re mea. (2021, January 9). Retrieved
contract-unit-price/
10 | P a g e
Appendix
11 | P a g e
12 | P a g e