Professional Documents
Culture Documents
Unit 8 Subcontracting
Unit 8 Subcontracting
UNIT: SUBCONTRACTING
An increasing number of contractors do less work by direct labour and they rely to a great extent on
subcontractors for the execution of the work. It is perhaps for this reason (at least in part) that
contractors are sometimes unable to provide adequate particulars and substantiation in support of their
claims.
At tender stage, contractors may rely on subcontractors' quotations for large sections of the works. The
tender may be based on the lowest of all the subcontractors' quotations. Once the contract has been
awarded, the contractor will then seek to get better quotations (by negotiation with the original tendering
subcontractors or by looking for alternative quotations).
In many cases, the contractor will not award the various subcontracts until it is necessary to do so. For
example, the subcontract for painting may not be awarded until a few weeks before the painting is due
to commence. The contractor runs the risk of price increases in these circumstances. If there has been
delay to the project, prior to placing the order for painting, it will be difficult for the contractor to establish
a claim for an increase in the cost of the work. Is the increase in the subcontract price due to the delay
to the project, or is the market for painting buoyant at the time of subcontracting (whereas it may have
been depressed at the time of tender)?
If the painting had been ordered at tender stage, the subcontractor may well have had a claim for
increased costs due to executing the work at a later date, but this would have been determined by
contractual provisions based on conditions at tender stage.
This practice makes it difficult for the contractor to justify a claim for additional payment. The
subcontractor will have no interest in providing particulars (because the extra cost is in his price). The
employer will not expect to reimburse the contractor for the extra cost caused by a buoyant market.
Nevertheless, the contractor may have grounds for a claim.
If all subcontracts were placed at tender stage, based on the same programme and other contractual
provisions, the contractor ought to be able to deal with subcontractors' claims as if they were his own
(subject to the practical difficulty of getting subcontractors to give the same notices and particulars to
the contractor as the contractor is required to give under the principal contract). In practice,
subcontracts are placed progressively during the course of the project. If delays occur throughout the
project, as the magnitude of the cumulative delay increases, various subcontracts will be placed on
different programmes and base costs. Very often subcontracts will be placed when the contractor's
current programme is out of date (sometimes the programme may be obsolete to the extent that the
programme shows completion of the subcontract works before the date of placing the order for the
subcontract). These problems are not imaginary.
They occur regularly in real life and are a constant source of contractual disputes. It is often a problem
to establish the subcontractor's obligations regarding progress and completion of the subcontract works
when the order, or subcontract, states that the subcontract works shall be carried out 'in accordance
with the contractor's programme'.
Which programme? Was it the programme which was in existence at the time of making the
subcontract (even if the programme shows the subcontract works to be complete before the time of the
subcontract)? Is it to be the next revision of the programme?
Is it to be any future revision of the programme?
What is the situation if the contractor never produces a revised programme?
The dangers which may arise from the above practices are:
The period for completion of the subcontract works may be impossible to determine from the
subcontract documents, in which case the subcontractor may have an obligation to complete within a
reasonable time. A reasonable time for the subcontractor may not be within the time allowed for the
principal contract.
The subcontractor may take on board the obligation to execute the works in accordance with any
programme of the contractor.
Even more uncertain and onerous provisions (from the subcontractor's point of view) arise when the
terms of the subcontract require the subcontractor to proceed with the subcontract works in accordance
with the contractor's reasonable requirements.
Domestic Subcontractors
A "domestic subcontractor" is one in whose selection and appointment the Employer traditionally plays no
part other than simply giving consent when that is required under the terms of the main contract. The
appointment of the subcontractor is treated as something entirely for the benefit of Main Contractor (MC) -
a purely "domestic matter." Although MC delegates performance of a part of the works to his domestic
subcontractors, MC nonetheless remains fully responsible to the Employer with respect to these works.
The Employer in no way underwrites the risk of subcontractor default. MC also is directly responsible to
the domestic subcontractor for payment and for their fundamental co operation.
Nominated Subcontractors
Nominated subcontractors have been used in building contracts for over one hundred years. They
appeared in the RIBA Model Form of Contract at the beginning of the last century. They have a useful
and important function where the employer has a genuine requirement to select a subcontractor to
execute specialist work. However, the provisions and procedures surrounding their selection and use
have become unnecessarily complicated.
PC Sums (Prime Cost Sums) in contracts are intended for work to be done by nominated
subcontractors or for materials or goods to be supplied by nominated suppliers.
In general, it is better to limit nominated subcontractors to a minimum, and then only for work which
cannot reasonably be included in the contractor's own scope of work. Some of the reasons which may
justify the use of nominated subcontractors are:
where the subcontractor is to undertake design responsibility and the features of the subcontractor's
design must be co-ordinated with the principal design of the works;
where it is essential to appoint a nominated subcontractor before appointment of the contractor for the
principal contract (for example, there may be long delivery periods for plant and equipment to be
provided by the subcontractor);
where the subcontract works are an extension of work done previously by a particular subcontractor
and the same equipment and standards are required to be used in the new works;
where the subcontract works are the main requirements of the employer and the building, or civil works,
are secondary (for example, in process plants);
where the employer, or its designers, have a particular preference for a subcontractor based on
previous performance and standard of work.
Having regard to the increasing amount of sophisticated mechanical and electrical installations,
including lifts, escalators, heating and ventilating and air conditioning (HVAC), building automation
systems (BAS), security systems (such as closed circuit television - CCTV) and a host of new additions
to the field of building services, it is not surprising to find these in the form of PC sums which, in total,
may make up more than fifty per cent of the total building cost. In these circumstances, if PC sums are
used properly, it may be appropriate to nominate subcontractors to do this type of work.
In this context, 'used properly' means that, for a lump sum contract (such as JCT80), the scope of the
works to be done by nominated subcontractors should be fully defined at tender stage (of the principal
contract). That is to say, the design of the subcontract works should be complete in all of the essential
Selection Procedures
A person executing work or supplying goods may be a Nominated Sub-Contractor if the work or supply
is the subject of a provisional sum or he is "nominated" or "selected" or "approved" by the Employer or
the Engineer. This means such a person can be a NSC if he is identified in an "agreed" list of proposed
subcontractors.
Subcontractors' Programmes
In most cases, the contractor's programme will indicate overall periods for work to be done by each
subcontractor. The programme may show separately, first, second and final king and various sections
of the subcontract work. Whatever the level of detail shown on the contractor's programme, many
subcontractors will need to subdivide their work into several activities when preparing their own
programmes. If the contractor has been given sufficient design information when tendering for the work,
he will have been able to prepare his programme taking into account many of the factors which govern
the sequence of the subcontractor's work. Assuming that the contractor's programme is still valid
(based on progress and the current contractual completion date), the contractor and the subcontractor
ought to be able to agree a realistic programme which is consistent with the overall programme. It
would be unusual if some minor reprogramming of the principal works and/or the subcontract works
was not necessary at the timeof subcontracting. A competent contractor, given sufficient information at
tender stage, ought to be able to accommodate such reprogramming without raising an objection or
subsequent claim.
In some cases, the subcontract works may be on the critical path, in which case the subcontractor's
programme and the overall programme need to be given careful attention, preferably before the
subcontractors submit their tenders for the subcontract works. This can be facilitated by ensuring that
the contractor and all tendering subcontractors have detailed discussions at pre-tender stage. Where
the subcontract works are not critical, the subcontract period may be open to negotiation.
In the case of a domestic subcontractor, the contractor can use the optimum solution to arrive at the
best tender for the main works or (if arising after award of the principal contract) to obtain a saving on
its original estimate for the works.
In the case of a nominated subcontractor, the employer may enjoy the benefit of the optimum solution.
Another difficulty arises where the subcontract is executed on or about the date of commencement of
the main works, but the subcontract works are due to commence several months later. Delays to the
main works which occur prior to the date of commencement of the subcontract works may qualify for an
extension of time (for completion of the main works).
However, the progress of the subcontract works has not been delayed (since the subcontractor has not
yet commenced work) and there may be no provision to adjust the completion date of the subcontract
works. It is therefore important to make provision in the subcontract for the commencement and
completion dates of the subcontract works to be adjusted in such circumstances. This may be
overcome by stating a period for completion of the subcontract works and providing for the
subcontractor to commence work within a specified period of the contractor's written notice. This may
be ideal for contractors, but subcontractors may require provisions to enable them to recover any
additional costs which may arise from delayed commencement.
If the subcontract work is on the critical path, a qualifying delay which affects the subcontract works will
have equal effect to the completion periods for the subcontract works and the main works. If the
subcontract work is not on the critical path, delays which occur may have different effects on the
relevant completion dates. For example, delay on the critical path may give rise to an extension of time
for completion of the main works, but no extension of time may be necessary for completion of the
subcontract works. Alternatively, a qualifying delay to the progress of subcontract works may justify an
extension of time for completion of the subcontract works, but no extension may be necessary for
completion of the main works (subject to the contractor subsequently needing an extension).
The interpretation of the various subcontracts ought to run in parallel with the main contracts (back to
back). That is to say, all provisions in the main contract which are in connection with the subcontractor's
obligations, rights and remedies are required to work together as if the main contract provisions were
set out in the subcontract. For example, clause 4.1 of the FIDIC Subcontract (1994) provides for an
unpriced copy of the main contract to be made available for the subcontractor to inspect and the
subcontractor is deemed to have full knowledge of it. In addition, clause 12.1 states:
'The provisions of Clause 54 of the Conditions of Main Contract in relation to Contractor's Equipment,
Temporary Works, or materials brought on to the Site by the Subcontractor are hereby incorporated by
reference into the Subcontract as completely as if they were set out in full herein.'
It is important that the subcontractor's obligations to give notice should be consistent with the
contractor's rights to give notice in such a way that neither the contractor nor the subcontractor are
disadvantaged. The FCEC (Federation of Civil Engineering Contractors - now CECA - Civil Engineering
Contractors' Association) blue subcontract form for use with the ICE main contract and the FIDIC
subcontract (1994) for use with the 1987 fourth edition do not quite achieve this. Subclause 7.2 of the
1994 FIDIC subcontract provides for the subcontractor to be entitled to an extension of time (inter alia)
for reasons for which the contractor would be entitled to an extension under the main contract. The
subclause goes on to say:
'Provided that the Subcontractor shall not be entitled to such extension unless he has submitted to the
Contractor notice of the circumstances which are delaying him within 14 days of such delay first
occurring . . . and in any case to which [the Contractor may obtain an extension under the Main
Contract] the extension shall not exceed the extension to which the Contractor is entitled under the
Main Contract.'
These provisions may be difficult if not impossible to reconcile in some circumstances.
Firstly, clause 44 of the FIDIC main contract requires the contractor to give notice within twenty-eight
days after such event has arisen and the engineer has the discretion to grant an extension if notice is
not given within twenty-eight days.
Clause 7.2 of the subcontract provides for the requisite notice to be a condition precedent to the
subcontractor's rights to an extension, whereas Clause 44 of the main contract is not a condition
precedent. If a subcontractor gives notices of a delaying event, which would justify an extension of time,
fifteen days after the event had first arisen and the contractor gave notice under the main contract
before the expiry of the twenty-eight day period, the contractor would be entitled to an extension and
the subcontractor would not be entitled to an extension. This could lead to absurd results. The main
contractor and the subcontractor would have different programmes and other subcontractors would not
know which programme they had to work around.
What happens if the subcontractor's work is not on the critical path for the main contract?
Assume that the period for completion of the subcontract works is six weeks commencing in the fourth
week. There is six weeks' float in the main contractor's original programme.
Notwithstanding the provisions of clause 25.4.7 of JCT80, the subcontract provisions (clause 11.2.2.1
of NSC/4a) preclude an extension of time for completion of the subcontract works in the event of delay
by the subcontractor. The contractor may therefore avoid liability for liquidated damages under the
principal contract and the subcontractor may become liable directly to the employer.
Liquidated Damages
Most subcontracts do not have an express provision for liquidated damages (one of the exceptions
being the FIDIC subcontract, Part 11). If a subcontractor causes delay which results in the main
contractor being liable for liquidated damages, then the main contractor will seek to recover the amount
The Subcontract is drafted very much on the basis of a "total pass down of risk" although there are
some interesting features (particularly from an English law perspective). For example, the payment
provisions are effectively tied to payment under the Main Contract and include "pay when paid" clauses
(Sub-Clause 14.6 (c)) in that the Contractor can withhold monies where "the Employer has failed to
make payment in full to the Contractor in respect of those amounts…" Of course, this protection will not
Whilst common in subcontracts in Europe, any construction contract signed in England and Wales
would be subject to the UK Housing Grants, Construction and Regeneration Act and this prohibits pay
when paid provisions. It will be interesting to see how this plays out in the market, particularly in light of
the harsher conditions for Contractors generally; this may be more palatable to subcontractors in these
straitened times. What it means in practice is that subcontractors will have to take a good deal more
notice of what the main contract says about payment and certification of payments to ensure they are
comfortable with these risks flowing down into their subcontracts.